Loading…
Loading…
Tender Value
₹3.8 L
EMD Value
₹4,800
Closing Date
14 Sept 2026, 5:00 pm2d left
AE (Civil)
Office of The General Manager, Mugma Area, P.O-Mugma, Dist.- Dhanbad, 828204
Repairing of Pandra weighbridge along heightening of boundary wall and fencing with concertina coil wire at Central Pool under Lakhimata Colliery.
2026_ECL_364740_1
ECL/GM/MA/CE/26-27/e-Tender/55 Dt. 02.09.2026
Open Tender
Civil Works - Buildings
Percentage
45 days
Central Pool Railway Siding
Please refer Tender documents.
4 documents required · 4 mandatory
₹4,800
3 Sept 2026
3 Sept 2026
15 Sept 2026
3 Sept 2026
14 Sept 2026
4 Sept 2026
4 Sept 2026 - 11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0 | Based on analysis | - | - | - | - |
| 1 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :Cement mortar 1:6 (1 cement : 6 coarse sand) | 5.23 | cum | 6,973.6 | ₹36,437.06 |
| 2 | 12 mm cement plaster of mix :1:6 (1 cement: 6 fine sand) | 117.5 | sqm | 226.8 | ₹26,649 |
| 3 | Reinforced cement concrete work in beams, suspended foors, roofs having slope up to 15* landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to foor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 0.71 | cum | 8,420.4 | ₹5,995.32 |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form forLintels, beams, plinth beams, girders, bressumers and cantilevers | 5.7 | sqm | 494.05 | ₹2,816.09 |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. | 140.38 | kg | 95.75 | ₹13,441.39 |
| 6 | Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) | 218.4 | sqm | 136.3 | ₹29,767.92 |
| 7 | Providing and fixing concertina coil fencing with punched tapeconcertina coil 600 mm dia 10 metre openable length ( total length90 m), having 50 nos rounds per 6 metre length, upto 3 m height ofwall with existing angle iron 'Y' shaped placed 2.4m or 3.00 m apartand with 9 horizontal R.B.T. reinforced barbed wire, stud tied withG.I. staples and G.I. clips to retain horizontal, including necessarybolts or G.I. barbed wire tied to angle iron, all complete as per directionof Engineer-in-charge, with reinforced barbed tape(R.B.T.) / Springcore (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mmwith tape (0.52 mm thick) and weight 43.478 gm/ metre (cost ofM.S. angle, C.C. blocks shall be paid separately) | 60 | metre | 258.4 | ₹15,504 |
| 8 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 203.58 | kg | 85.5 | ₹17,406.09 |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.64 | cum | 6,007.2 | ₹15,840.99 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 1.76 MB
BOQ_377658.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .