| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.9 LAccepted-AOC | L1 | Accepted-AOC L1 |
Tender Value
₹16.9 L
EMD Value
₹42,370
Closing Date
14 Nov 2024, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EXECUTIVE ENGINEER
O/o Executive Engineer,LSGD,DivisionCivi station
Equotation Annual Plan-Alappuzha District Panchayath Punnapra Division - Kainakary Grama Panchayath - Construction of Smart Anganvady-in ward no 6 of Kainakary GP Angananavady No 118 ALAPPUZHA JP 2023-2024 262-24-General Civil Work
2024_LSGD_702846_2
LIDEW/JP/RE/NOV/24-25
Open Tender
Civil Works - Buildings
Item Rate
330 days
Alappuzha DP
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹42,370
Yes
10 Feb 2025
6 Nov 2024
16 Nov 2024
6 Nov 2024
14 Nov 2024
6 Nov 2024
Amount
Building Work Ground floor
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD323410/2023-2024: Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
OD323388/2023-2024:od1380448/2021_2022 :Driving down coconut piles to lines and levels through soft to medium clay and soil strata including all hire charges and all other appliances necessary for pile driving down after pointing the bottom end details for one post of 60m long 15 numbers per dayb 6x15=90 m deatils for 90 m length
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
16.78.2:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases)
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
6.47:Providing and laying autoclaved aerated cement blocks masonry with 150mm/ 230mm/300 mm thick AAC blocks in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately).
50.18.9.9.1:Providing and fixing PVC pipes includings jointing of pipes with one step PVC solvent cement, trenching, refilling & testing of Joints complete as per direction of engineer in charge.110 mm dia 6Kgf/cm2
50.18.9.22.5:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes including jointing with PVC solvent cement 110x110x110 mm dia Tee
Bidder Name
PRAVEEN K P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1099312.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .