| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.7 LAccepted-Finance 1D 70A NIT FARIDABAD HARYANA 121001 | FARIDABAD | HARYANA | 121001 | ₹16.7 L | L1 | Accepted-Finance being the lowest |
| 2 | L2₹17.6 L+₹84,383.52 (5.05%)Accepted-Finance | ₹17.6 L+₹84,383.52 (5.05%) | L2 | Accepted-Finance Being the second lowest |
Tender Value
₹16.9 L
EMD Value
₹33,753
Closing Date
29 May 2026, 3:00 pmClosed
EE-II (WKS) SVPMC
EE-II (WKS) SVPMC
Construction of RCC Road Side Retaining Wall to Protect Public Motorable Road and Staircase Leading to Kaali Mandir Near Maccan Singh House at Machi Line South Point Ward No 10
2026_PMBC_23099_1
01/EE-II/RW/MC/Estt/2026-27
Open Tender
Civil Works - Roads
Works
180 days
South Point Ward No 10
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹33,753
29 May 2026
21 May 2026
29 May 2026
21 May 2026
29 May 2026
21 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.
a) All kinds of soil | 125.16 | Cum | 250.43 | ₹31,343.82 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.
a) All kinds of soil | 1 | Cum | 367.24 | ₹366.87 |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
a) All kinds of soil. | - | Cum | 9,610.71 | - |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for
a) Foundations, footings, bases of columns, etc. for mass concrete | - | Sqm | 553.26 | - |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for
a)Walls (any thickness) including attached pilasters,butteresses, plinth and string courses etc. | 183.36 | Sqm | 1,188.64 | ₹2,17,949.03 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
a)1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | - | Cum | 11,115.38 | - |
| 7 | Providing and laying cement concrete in retaining walls, return walls,walls (any thickness) including attached pilasters, columns, piers,abutments, pillars, posts, struts, buttresses, string or lacing courses,parapets, coping, bed blocks, anchor blocks, plain window sills, fillets,sunken floor etc., up to floor five level, excluding the cost of centering,shuttering and finishing:
a)1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.1 | Cum | 13,960.64 | ₹29,317.34 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth level.
a)Thermo-Mechanically Treated bars of grade Fe-500D or more. | 19.74 | Cum | 12,762.2 | ₹2,51,925.83 |
| 9 | Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands,copings, bed plates, anchor blocks, plain window sills and the like,including the cost of required centering, shuttering but excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | - | Cum | 15,311.88 | - |
| 10 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
a) Thermo-Mechanically Treated bars of grade Fe-500D or more. | 4,085.48 | Kgs | 152.16 | ₹6,21,646.64 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.15 MB
Tendernotice_2.pdf
PDF • 0.46 MB
BOQ_24488.xls
BOQ • 0.29 MB
corrigendumDateChange.pdf
PDF • 0.20 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .