Loading…
Loading…
Tender Value
₹38.1 L
EMD Value
₹38,052
Closing Date
16 Sept 2026, 6:00 pm
Taluka Development Officer, Dholka
CONSTRUCTING INTEGRATED SETTLER WITH ABR - 4 NOS
338691
2026-2027
Open
Miscellaneous Works
Works
Ahmedabad
3 documents required · 3 mandatory
₹1,500
SBM-G TDO DHOLKA
₹38,052
25 Aug 2026
25 Aug 2026
25 Aug 2026
16 Sept 2026
25 Aug 2026
8 Section -7 Bill of Quantities
9 Section -8 Securities and Other Forms
10 Section -9 Drawings
11 Section -10 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The TALUKA DEVLOPMENT OFFICER, TALUKA PANCHAYAT DHOLKA invites bids
for the construction of works detailed in the table. The bidders may submit bids for
any or all of the following works.
Package Name of work Approximate Bid Cost of Period of #Class of
No. value of security documen completion Registration /
works (Rs.) (Rs.) t (Rs.) Category of
1 Integrated Settler with ABR 38,05,224/- 38,052/- 1500/- 4 months D and Above
For Grey Water Treatment
Plant at Various Villages
Under TALUKA PANCHAYAT
Milestone Dates for Tendering
1 Tender Downloading Date 25/08/2026, 12.00 am
2 Tender Online Submission Date 16/09/2026, 18.00 pm
3 Submission of Tender in Physical form at 16/09/2026, 18.00 pm
Swachh Bharat Mission, Taluka Panchayat
Dholka, Ahmedabad
4 Bid Opening Date 19/09/2026, 12.00 pm Onwards
6 Bid Validity 120 Days after opening of price bid
2. Prospective / Interested bidder may download the Bid Documents from website
https://www.nprocure.com free of cost till the Time and Date as mentioned on online
NIT at website https://www.nprocure.com.
3. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee
/ Tender Fee through Demand Draft only of any Schedule Bank payable at
DHOLKA and in favour of “SBM-G TDO DHOLKA”. Once the Bid is received online, Bid
Document / Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid
Security / EMD shall be submitted in electronic format through online (by scanning)
while uploading the bid, this submission shall mean that bid document / tender fee and Bid
Security / EMD has been received. Accordingly, the offer of only those shall be opened whose
Bid Document / Tender Fee and Bid Security / EMD have been received electronically.
However, for the purpose of realization of Demand Draft, and FDR / Bank Guarantee bidder
shall send the same in original through R.P.A.D. so as to reach to ‘SBM-G TDO DHOLKA’
for Tender Fee and “TALUKA DEVLOPMENT OFFICER DHOLKA” for EMD. within 7 the last day
of bid submission. Penaltative action for not submitting Demand Draft / FDR / Bank
Guarantee in original to ‘TALUKA DEVLOPMENT OFFICER, TALUKA PANCHAYAT
DHOLKA’. / Tender Inviting Authority by bidder shall be initiated.
4. Bids received online, will be opened on the time, date and place as specified in the online
NIT at website https://www.nprocure.com in the presence of the bidders or their
authorized representatives, who wish to remain present.
If the office happens to be closed on the day of opening of the bids as specified, the bids
will be opened on the next working day at the same time and venue.
5. #Bid Security (EMD) is equal to 1% of Estimated Amount put to bid / tender and should
be rounded off to the next thousand rupees.
6. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the
tender submission date and time. After the tender submission date and time, the
bidder cannot modify / edit / withdraw their submitted offer in any case. No written
or online request in this regard shall be granted.
B. Offers in physical form will not be accepted in any case.
C. Demand Draft purchased by the other then bidder and issued after the last date of
submission of Bids, will not be considered or accepted.
D. The cost incurred by the contractor for this offer for clarification or attending
discussion, conferences or site visits will not be reimbursed by the Employer or
Engineer-in-Charge.
E. Conditional tender shall not be accepted.
F. Any changes, addition, alternation made in the prescribed form attached with tender
are liable to be rejected.
G. Any change in format or conditional Bank Guarantee will not be accepted and the
bidder will be considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the
format given in the checklist /qualification document / tender document.
I. It is mandatory for the bidders to supply each and every information as asked strictly
in electronic format at appropriate places only.
J. Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even if the bidder has been qualified in a similar or larger size of project in the past,
it shall not be deemed to be a ground / reason for not giving required information for
this work / bid.
L. Information supplied for earlier projects shall not be considered while evaluation of
this bid. The Government will not ask for any other information, unless it is found
absolutely necessary by the competent authority.
M. If found necessary, the contractor will be intimated for negotiation,
# For the works costing up to 7.5 crore (ROAD), 7.0 crore (BUILDING & BRIDGE)
kindly refer to SSR-10-2015-17-C dated 03-02-2017
For the works costing under 7.5 crore for Road Works and 7.0 crore for Building and
Bridge Works following documents shall be submitted in electronic format only through
online by scanning and the (i) Bid Document Fee / Tender Fee (ii) Bid Security / EMD
should be sent in original to the Tender opening authority through RPAD, so as to reach
the Taluka Development Officer D H O L K A within 7 days from last day of submission
(i) Bid Document Fee / Tender Fee Demand Draft Favour of “SBM-G TDO
(ii) Bid Security / EMD in Form of FDR Favour of “ TALUKA DEVLOPMENT
OFFICER DHOLKA”
(iii) Registration Certificate of Appropriate GST Certificate
(iv) Bank Solvency of the Current Calendar Year i.e.
(vii) Government Registration Certificate of Approved Contractor
(viii) Average annual financial turnover of last 3 years should be at least
Rs.10,00,000/-. Bidder must enclose C.A. certificate along with Bid.
(ix) The bidder must have experience of Civil/Mechanical/fabrication/waste water
treatment plant work will be preferred. The 3A / completion certificates of
Government or Semi – Government Body or Private body for similar
nature of works showing actual work done amount and work completion
date shall be duly signed by concerned authority.
(x) Mandatory valid bank solvency certificate shall be of minimum Rs 2,00,000/- .
The solvency certificate of Nationalized Bank/ Schedule Bank shall only be
(xi) The bidder should finish the work order or completion certificate of similar work
(Water / Waste Water treatment plant etc.) along with the Tender.
All quoted rates must be inclusive of all types of taxes/cess/transport. Only GST will be
paid extra by TALUKA DEVLOPMENT OFFICER, TALUKA PANCHAYAT DH OLK A
on bidders quoted rates
(xii) The decision of TDO will be final and binding to the contractor in case of
INSTRUCTIONS TO BIDDERS
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. General D. Submission of Bids
1. Scope of Bid 10 19. Sealing & Marking of Bids
2. Source of Funds 10 20. Deadline for Submission of
3. Eligible Bidders 10 21. Late Bids
4. Qualification of the 10 22. Modification and
Bidder Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding 10 E. Bid Opening and Evaluation
7. Site Visit 11 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding 12 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding 12 27. Correction of Errors
10. Amendment of Bidding 13 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising 14 F. Award of Contract
13. Bid Prices 14 31. Award Criteria
14. Currencies of Bid and 15 32. Employer’s Right to Accept
Payment any Bid and to Reject any
15. Bid Validity 15 33. Notification of Award and
Signing of Agreement
16. Bid Security 15 34. Performance Security
17. Alternative Proposals By 16 35. Advance Payment and
Bidders Security
18. Format and Signing of Bid 16 36. Dispute Review Expert
37. Correct or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction of works
(as defined in these documents and referred to as ‘the works”) detailed in the table
given in IFB. The bidders may submit bids for any or all of the works detailed in the
table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended
completion date specified in the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their
derivatives (bidder/ tenderer, bid / tender, bidding/ tendering, etc.) are
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Govt. of Gujarat /
Govt. of India for centrally sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
statement that the Bidder is neither associated, nor has been associated, directly or
indirectly, with the consultant or any other entity that has prepared the design,
specifications, and other documents for the Project or being proposed as Project
Manager for the Contract. A firm that has been engaged by the Employer to provide
consulting services for the preparation or supervision of the works, and any of its
affiliates, shall not be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
preliminary description of the proposed work method and schedule, including
drawings and charts, as necessary. The proposed methodology should include a
program of construction backed with equipment planning and deployment duly
supported with broad calculations and quality assurance procedures proposed to be
adopted justifying their capability of execution and completion of work as per
technical specifications, within stipulated period of completion.
5. One bid per bidder
5.1. Each bidder shall submit only one bid for one package. A bidder who submits or
participates in more than one bid (other than as a subcontractor or in cases of
alternatives that have been permitted or requested) will cause all the proposals with
the bidder’s participation to be disqualified.
6. Cost of Bidding
6.1 The bidder shall bear all costs associated with the preparation and submission of his
Bid, and the Employer will in no case be responsible and liable for those costs.
7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and
examine the Site of work and its surrounding and obtain all information that may be
necessary for preparing the Bid and entering into a contract for construction of the
The costs of visiting the site shall be at the Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda
issued in accordance with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2 Volumes I, II, III and IV are available online and documents to be furnished by the
bidder in compliance to section 2 will be prepared by him and furnished as Volume- V
in two parts (refer clause 12).
8.3 The bidder is expected to examine carefully all instructions, conditions of contract,
contract data, forms, terms, technical specifications, bill of quantities, forms, Annexes
and drawings in the Bid Document. Failure to comply with the requirements of Bid
Documents shall be at the bidder’s own risk. Pursuant to clause 26 hereof, bids
which are not substantially responsive to the requirements of the Bid Documents
shall be rejected.
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may
notify the Employer in writing or through E-mail at the Employer’s address
indicated in the invitation to bid. The Employer will respond to any request for
clarification which he received earlier than 15 days prior to the deadline for
submission of bids. Employer’s response will be published on website including a
description of the enquiry but without identifying its source.
9.2 Pre-bid meeting
9.2.1 The bidder or his official representative is invited to attend a pre-bid
meeting which will take place at the address, venue, time and date as
indicated in the appendix.
9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on
any matter that may be raised at that stage.
9.2.3 The bidder shall be required to submit any questions in writing or e-mail to reach
the Employer not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the
source of enquiry) and the responses given will be published without delay on the
tender website i.e. www.nprocure.com. Any modification of the bidding
documents listed in sub-Clause 8.1 which may become necessary as a result of the
pre-bid meeting shall be made by the Employer exclusively through the issue of an
Addendum pursuant to Clause 10 and not through the minutes of the pre-bid
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding
documents by issuing addenda.
10.2 Any addendum thus issued shall be part of the bidding documents. The Employer will
assume no responsibility for the same.
10.3 To give prospective bidders reasonable time in which to take an addendum into
account in preparing their bids, the Employer may, at his discretion, extend as
necessary the deadline for submission of bids, in accordance with Sub-Clause
C. PREPARATION OF BIDS
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents Comprising the Bid
12.1 The bid be submitted by the bidder as Volume V of the bid document (refer Clause
8.1) shall be in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
(i) Bid Security in the form specified in Section
(ii) Qualification Information and supporting documents as specified in Section
(iii) Certificates, undertakings, affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 of these instructions
(v) Undertaking that the bid shall remain valid for the period specified in Clause
Part II shall be named “Financial Bid” and shall comprise
(i) Form of Bid as specified in Section
(ii) Priced Bill of Quantities for items specified in Section
12.2 The Bidder shall submit the details / information pertaining to each part
i.e. technical as well as financial and must be submitted online only.
12.3 Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
Invitation for Bids (IFB)
1 Instruction to Bidders Volume I
3 Conditions of Contract
4 Contract Data
5 Specifications Volume II
9 Drawings Volume IV
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on
the priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for
all items of the Works described in the Bill of Quantities along with total bid price
(Both in figures and words). Items for which no rate or price is entered by the bidder
will not be paid for by the Bill of Quantities.
13.3 All duties, taxes, and other levies except GST payable by the contractor under the
contract, or for any other cause shall be included in the rates, prices and total Bid
Price submitted by the Bidder. (GST will be paid extra)
13.5 The rates and prices quoted by the bidder are subject to adjustment during the
performance of the Contract in accordance with the provisions of Clause 47 of the
Condition of Contract (Irrespective of the time limit and Bid Amount)
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees.
All payments shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date
forbid submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer
may request that the bidders may extend the period of validity for a specified period. A
bidder may refuse the request without forfeiting his bid security. A bidder agreeing to
the request will not be required or permitted to modify his bid, but will be required to
extend the validity of his security for a period of the extension, and in compliance
with Clause 16 in all respects.
16. Bid Security
16.1 The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in
column 4 of the table of IFB for this particular work. This Bid security shall be in
favor of Employer as named in Appendix and may be in one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in
Volume III. (Bank Guarantee is applicable only for Bid Estimated Amount of
Crore and above) and Bank Guarantee of Schedule and Private Banks shall be
considered as per GoG Finance Department’s Circular No. FD/MSM/e-
file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank
approved by the Reserve Bank of India.
# A Valid Bid Security / EMD Exemption Certificate issued by (1) Road & Building
Department of Govt. of Gujarat. Exemption Certificate is applicable only when
Registration Certificate of Appropriate Class and Category of Approved
Contractors is required as eligible criteria of bidder.
16.2 Bank guarantees (and other instruments having fixed validity) issued as surety
for the bid shall be valid for 45 days beyond the validity of the bid i.e. total
validity of 120+45 = 165 Days
16.3 Any bid not accompanied by an acceptable Bid Security and not secured as
indicated in Sub-Clauses 16.1 and 16.2 above shall be rejected by the Employer
as non-responsive.
16.4 The Bid Security of unsuccessful bidders will be returned within 28 days of the
end of the bid validity period specified in Sub-Clause
16.5 The Bid Security of the successful bidder will be discharged when the bidder
has signed the Agreement and furnished the required Performance Security.
16.6 The bid Security may be forfeited
(a) If the Bidder withdraws the bid after Bid opening during the period of Bid
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He will be
intimated maximum three times within the validity period for negotiation, If
contractor does not respond in time, his Bid Security (EMD) will be forfeited and his
tender will be rejected. Punitive action will be taken on such contractors. (As per GoG
17. Alternative Proposals by Bidders.
17.1 Bidders shall submit offers that fully comply with the requirements of the bidding
documents, including the conditions of contract (including mobilization advance or
time for completion), basic technical design as indicated in the drawing and
specifications. Conditional offers or alternative offers will not be considered further in
the process of tender evaluation.
18. Format and Signing of Bid
18.1 The Bidder shall prepare documents comprising the bid as described in Clause 12 of
these Instructions to bidder as the “Technical Bid “and “Financial Bid” in separate
parts to be uploaded.
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1 Complete Bids must be received online by the Employer at the tender website
specified above not later than the date indicated in appendix.
20.2 The Employer may extend the deadline for submission of bids by issuing an
amendment in accordance with Clause 10, in which case all right and obligation of
the Employer and the bidders previously subject to the original deadline will then be
subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their bids online before the deadline prescribed in
Clause 20 or pursuant to Clause
22.3 No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4 Withdrawal or modification of a bid between the deadline for submission of bids
and the expiration of the original period of bid validity specified in Clause
above or as extended pursuant to Clause 15.2 may result in the forfeiture of the Bid
security pursuant to Clause
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant
to Clause 22, in the presence of the Bidders or their representatives who choose to
attend at time, date and the place specified in Appendix in the manner specified in
Clauses 20 and 23.3, In the event of the specified date of Bid opening being declared a
holiday for the Employer, the Bids will be opened at the appointed time and location
on the next working day.
23.3 The “Technical Bid” shall be opened. The amount, form and validity of the bid security
furnished with each bid will be announced. If the bid security furnished does not
conform to the amount and validity period as specified in the invitation for bid (ref.
Column 4 and paragraph 3), and has not been furnished in the form specified in Clause
16, the technical bid will not be opened.
23.4 (i) Subject to confirmation of the bid security by the issuing Bank, the bids
accompanied with valid bid security will be taken up for evaluation with
respect to the Qualification 23.3 information and other information
furnished in part I of the bid pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his Qualification
Documents with respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the clarification
(iv) Immediately (usually within 3 or 4 days), on receipt of these clarification the
Evaluation Committee will finalize the list of responsive bidders whose
financial bids are eligible for consideration.
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found
responsive in accordance with Clause 23.4(iv) will be announced. The bids of only
these bidders will be opened. The responsive Bidders’ names, the Bid prices, the
total amount of each bid, any discount and such other details as the Employer may
total amount of each bid, any discount and such other details as the Employer may
consider appropriate, will be announced by the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found
responsive in accordance with Clause 23.4(iv) will be announced. The bids of only
these bidders will be opened. The responsive Bidders’ names, the Bid prices, the
total amount of each bid, any discount, and such other details as the Employer may
total amount of each bid, any discount, and such other details as the Employer may
consider appropriate, will be announced by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the
“Financial Bid” shall be in order of estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and comparison of
Bids and recommendations for the award of a contract shall not be disclosed to
Bidders or any other persons not officially concerned with such process until the
award to the successful Bidder has been announced. Any effort by Bidder to
influence the Employer’s processing of Bids or award decisions may result in the
rejection of his Bid.
25. Clarification of Financial Bids
25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at
his discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit
rates. The request for clarification and the response shall be in writing or by e- mail,
but no change in the price or substances of the Bid shall be sought, offered, or
permitted except as required to confirm the correction of arithmetic errors
discovered by the Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter
relating to his Bid opening to the contract is awarded. If the Bidder wishes to bring
additional information to the notice of the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation,
bid comparison or contract award decision may result in the rejection of the Bidders’
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether
each Bid (a) meets the eligibility criteria defined in Clause 3 and 4; (b) has been
properly signed; (c) is accompanied by the required securities and; (d) is substantially
responsive to the requirements of the Bidding document. During the detailed
evaluation of the “Financial Bid”, the responsiveness of the bids will be further
determined with respect to the remaining bid conditions, i.e., priced bill of
quantities, technical specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms,
conditions and specifications of bidding documents, without material deviation or
reservation. A material deviation or reservation is one (a) which affects in any
substantial way the scope, quality, or performance of the Works; (b) which limits in
any substantial way, inconsistent with the Bidding documents, the Employer’s rights
or the Bidder’s obligations under the Contract; or (c) whose rectification would affect
unfairly the competitive position of other Bidders presenting substantially
responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the
Employer, and may not subsequently be made responsive by correction or
withdrawal of the non-conforming deviation or reservation.
29. Evaluation and Comparison of Financial Bids
29.1 The Employer will evaluate and compare only the Bids determined to be substantially
responsive in accordance with Sub-Clause 26.2.
29.3 The Employer reserves the right to accept or reject any variation or deviation.
Variation and deviations and other factors, which are in excess of the requirements of
the Bidding documents or otherwise result in unsolicited benefits for the Employer,
shall not be taken in to account in Bid evaluation.
29.4 The estimated effect of the price adjustment conditions under Clause 47 of the
Conditions of Contact, during the period of implementation of the Contract, will not
be taken in to account in Bid evaluation.
29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the
Engineer’s estimate of the cost of work to be performed under the contract the
Employer may require the Bidder to produce detailed consistency of those prices
with the construction methods and schedule proposed. After evaluation of the price
analyses, the Employer may require that the amount of the performance security set
forth in Clause 34 be increased at the expense of the successful /bidder to a level
sufficient to protect the Employer against financial loss in the event of default of the
successful Bidder under the Contract.
29.6 A bid which contains several items in the bill of Quantities which are unrealistically
priced low and which cannot be substantiated satisfactorily by the bidder may be
rejected as non-responsive.
F. AWARD OF CONTRACT
31. Award Criteria
31.1 Subject to Clause 32, the Employer will award the contract to the Bidder whose
Bid has been determined.
(i) to be substantially responsive to the Bidding documents and who has offered
the lowest evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price
which is the lowest evaluation in any of the packages opened earlier than the
one consideration.
In no case, the contract shall be awarded to any bidder whose available bid
capacity is less than the evaluated bid price, even if the said bid is the lowest
evaluated bid. The contract will in such cases be awarded to the next lowest bidder
at his evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any
Bid, and to cancel the Bidding process and reject all Bids, at any time prior to the
award of contract, without thereby incurring any liability to the affected bidder or
Bidder or any obligation to inform the affected Bidder or Bidders of the grounds for
the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1 The Bidder whose Bid has been accepted will be notified of the award by the
Employer prior to expiration of the Bid validity period by cable, telex or facsimile
confirmed by registered letter. This letter (hereinafter and in the condition of
contract called the “Letter of Acceptance”) will state the sum that the Employer will
pay the Contractor in consideration of the execution, completion, and maintenance of
the Works by the Contractor as prescribed by the Contract (hereinafter and in the
Contract called the “Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to
the furnishing of a performance security in accordance with the provisions of Clause.
33.3 The Agreement will incorporate all agreements between the Employer and the
successful Bidder. It will be signed by the Employer and to the successful Bidder,
within 28 days following the notification of award along with the Letter of
Acceptance. Within 21 days of receipt, the successful Bidder will sign the Agreement
and deliver it to the Employer.
33.4 Upon the furnishing by the successful Bidder of the Performance Security, the
Employer will promptly notify the other Bidders that their Bids have been
34. Performance Security
34.1 (A) Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder
shall furnish to the Employer an irrevocable and unconditional guarantee from a
Bank in the form set forth in Section 8 (the “Performance Security”) for an
amount equal to 3% (Three percent) of its Contract Price. In case of bids
mentioned below, the successful Bidder, along with the Performance Security,
shall also furnish to the Authority an irrevocable and unconditional guarantee
from a Bank in the same form given at Section 8 towards an Additional
Performance Security (The “Additional Performance Security”) for an amount
calculated as under:
(a) If the Contract Price offered by the Selected Bidder is lower than 10% but
up to 20% of the Estimated Project Cost, then the Additional Performance
Security shall be calculated @ 20% of the difference in the (i) Estimated
Project Cost (as mentioned in Bid Document) - Minus 10% of the
Estimated Project Cost and (ii) Contract Price offered by the selected
(b) If the Contract Price offered by the Selected Bidder is lower than 20% of
the Estimated Project Cost, then the Additional Performance Security
shall be calculated @ 30% of the difference in the (i) Estimated Project
Cost (as mentioned in Bid Document) - Minus 10% of the Estimated
Project Cost and (ii) Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of the
Performance Security.
(B) The Performance Security shall be valid beyond 60(sixty) days of the Defects
Liability Period and the Additional Performance Security shall be valid
beyond 28 (twenty-eight) days of Project Completion Date.
34.2 If the performance security is provided by the successful Bidder in the form of a
Bank Guarantee, it shall be issued either (a) at the Bidder’s option, by a
Nationalized/Scheduled Indian bank or (b) by a foreign bank located in India and
acceptable to the Employer. As per GoG Finance Department’s Circular No.
FD/MSM/e-file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their latest
34.3 Failure of the successful Bidder to comply with the requirement of Sub-Clause
shall constitute sufficient grounds for cancellation of the award and forfeiture of the
35 Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in completing for the
contract in question and will declare the firm ineligible, either indefinitely or for a
stated period of time, to be awarded a contract with National Highways Authority of
India/ State PWD and any other agencies, if it at any time determines that the firm
has engaged in corrupt or fraudulent practices in completing for the contractor, or in
3.72 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of
the Conditions of Contract.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
2. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
* Fill the name of Consultant
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR
AVAILABILITY OF CREDIT FACILITIES
(CLAUSE 4.5.6 OF ITB)
BANK CERTIFICATE
This is to certify that M/s. is a reputed company
with a good financial standing.
If the contract for the work, namely is awarded to the
above firm, we shall be able to provide overdraft/credit facilities to the extent of
Rs. to meet their working capital requirements for executing the above
during the contract period.
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
_ have not abandoned any work of
Government of Gujarat/Government of India/any Board or Corporation under
Government of Gujarat/Government of India nor any contract awarded to us for
such works have been rescinded, during last five years prior to the date of this
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by
the Department to verify this statement or regarding any (our) competence and
general reputation.
4. The Undersigned understands and agrees that further qualifying information
may be requested, and agrees to furnish any such information at the request of
the Department/ Project implementing agency.
(Signed by an Authorized Officer of the Firm)
Title of Officer
CONDITIONS OF CONTRACT
Conditions of Contract
Table of Contents
A General Page D. Cost Control
1 Definitions 36 37 Bill of Quantities
2 Interpretation 37 38 Changes in the Quantities
3 Language and Law 38 39 Variations
4 Engineer’s Decisions 38 40 Payments for Variations
5 Delegations 38 41 Cash Flow Forecasts
6 Communications 38 42 Payment Certificates
7 Sub-Contractors 38 43 Payments
8 Other Contractors 38 44 Compensations Events
9 Personnel 40 45 Tax
10 Employer’s & Contractor Risk 40 46 Currencies
11 Employers Risks 40 47 Price Adjustment
12 Contractor’s Risk 40 48 Retention
13 Insurance 40 49 Liquidated damages
14 Site Investigations Reports 41 50 Bonus
15 Queries about the Contract 41 51 Advance Payment
16 Contractors to Construct the 41 52 Securities
17 The Works to be Completed By 41 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 41 54 Cost of Repair
20 Discoveries 42 E. Finishing the Contract
21 Possession of the Site 42 55 Completion
22 Access to the Site 42 56 Taking Over
23 Instructions 42 57 Final Account
24 Disputes 42 58 Operating and Maintenance
25 Procedure for Disputes
26 Deleted 43 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 44 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted 44 F.Special Conditions of
30 Delays Ordered by The 44 63 Labour
Engineer 64 Compliance with labour
31 Management Meetings 45 65 Arbitration
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of
Contract but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities
forming part of the Bid
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified by
the Engineer in accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to
execute, complete and maintain the Works till the completion of Defects
Liability Period. It consists of the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which
comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the
Work has been accepted by the Employer.
The Contractor’s Bid is the completed Bidding document submitted by the
Contractor to the Employer and includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and
calculated from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the
The Engineer is the person named in the Contract Data (or any other
competent person appointed and notified to the contractor to act in replacement of
the Engineer) who is responsible for supervising the Contractor, administering the
Contract, certifying payments due to the Contractor, issuing and valuing Variations
to the Contract, awarding extensions of time, and valuing the Compensations
Equipment is Contractor’s machinery and vehicles brought temporarily to
the site to construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s
Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is specified in
the Contract Data. The Intended Completion Date may be revised only by the
Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for
incorporation in the works.
Plant is any integral part of the work which is to have mechanical, electrical,
electronic or chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding
documents and are factual interpretive reports about the surface and subsurface
conditions at the site.
Specifications means the Specifications of the works included in the Contract
and any modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the
Contractor shall commence execution of the works. It does not necessarily coincide
with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the
Contractor to carry out a part of the work in the Contract which includes work on the
Temporary Works are works designed, constructed, installed, and removed
by the Contractor which are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct, install,
and turn over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural,
male also means female or neuter and the other way around. Heading
have no significance. Words have their normal meaning under the
language of the Contract unless specifically defined. The Engineer will
provide instructions clarifying queries about Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in
the Conditions of Contract to the Works, the Completion date, and Intended
Completion Date apply to any Section of the Works (other than references
to the Completion Date and Intended Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the
following order of priority
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming part of the
3. Language and Law
The language of the Contract and the law governing the Contract are stated in
the Contract Data.
4. Engineers Decisions
Except where otherwise specifically stated, the Engineer will decide
contractual matters between the Employer and the Contractor in the role
representing the Employer.
The Engineer may delegate any of his duties and responsibilities to other
people after notifying the Contractor and may cancel any delegation after
notifying the Contractor.
6. Communications
Communications between parties which are referred to in the conditions are
effective only when in writing. A notice shall be effective only when it is
delivered (in terms of Indian Contract Act).
7. Sub-Contracting
The Contractor may subcontract any portion of work, up to a limit specified in
contract data, with the approval of the engineer but may not assign the
Contract without the approval of the Employer in writing. Subcontracting
shall not alter the Contractor’s obligations. Sub-contracting of supply or
specific items of work is not allowed.
The sub-contractor must be registered in appropriate class and category for
the part of work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other
contractors, public authorities, utilities and the Employer between the
dates given in the Schedule of other Contractor. The Contractors shall as
refer to in the Contract Data, also provide facilities and services for them
as described in the Schedule. The employer may modify the schedule of
other contractors and shall notify the contractor of any such modifications.
9.1 The Contractor shall employ the key personnel named in the Schedule of
Key Personnel as referred to in the Contract Data to carry out the functions
stated in the Schedule or other personnel approved by the Engineer. The
Engineer will approve any proposed replacement of key personnel only if
their qualifications, abilities, and relevant experience are substantially
equal to or better than those of the personnel listed in the Schedule.
9.2 If the engineer asks the Contractor to remove a person who is a member
of the Contractor Staff or his work force stating the reasons the Contractor
shall ensure that the person leaves the Site within seven days and has no
further connection with the work in the Contract.
10. Employer’s and Contractors Risks
10.1 The Employer carries the risk which these Contract states are
Employer’s risks, and the Contractor carries the risks which these
Contracts states are Contractors risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far
as they directly affect the execution of the Works, the risks of war,
hostilities, invasion, act of foreign enemies, rebellion, revolution,
insurrection or military or usurped power, civil war, riot commotion or
disorder (unless restricted to the Contractor’s employees), and
contamination from any nuclear fuel or nuclear waste or radioactive toxic
12. Contractor’s Risks
12.1 All risks of loss of or damages to physical property and of personal injury
and death which arise during and in consequence of the performance of the
Contract other than the excepted risks are the responsibility of the
13.1 The Contractor shall provide, in the joint names of the Employer and
the Contractor, insurance cover from the Start date to the end of the
Defects Liability Period, in the amounts and deductibles stated in the
Contract data for the following events which are due to the Contractor’s
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and
Equipment) in connection with the Contract; and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor
to the Engineer for the Engineer’s approval before the Start Date. All such
insurance shall provide for compensation to be payable in the types and
proportions of currencies required to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates
required, the Employer may affect the insurance which the Contractor
should have provided and recover the premiums the Employer has paid
from payments otherwise due to the Contractor or, if no payment is due, the
payment of the premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made without the
approval of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site Investigation
reports referred to in the Contract Data, supplemented by any
information available to the Bidder.
15. Queries about the Contract data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance with
the specification and Drawings.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date
and shall carry out the Works in accordance with the programme
submitted by the Contractor, as updated with the approval of the
Engineer, and complete them by the Intended Completion date
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the
proposed Temporary works to the Engineer, who is to approve them if
they comply with the Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility for
design of the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of
the Temporary works where required.
18.5 All Drawings prepared by the Contractors for the execution of the
temporary or permanent work are subject to prior approval by the Engineer
before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value
unexpectedly discovered on the site is the property of the Employer. The
contractor is to notify the engineer of such discoveries and carry out the
Engineer’s instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the Contractor.
If possession of a part is not given by the date stated in the Contract Data
the Employer is deemed to have delayed the start of the relevant
activities and this will be a Compensation Event.
21.2 If within 25% of the time limit of the project, 80% of possession of the site
is not handed over to the Contractor, then contractor/ Employer may fore-
close the contract. Contractor/Employer has to foreclose the work within
30 days after lapse of 25%-time limit and after 30 days foreclosure
option will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by
the Engineer access to the Site, to any place where work in connection
with the Contract is being carried out or is intended to be carried out and to
any place where materials or plants are being manufactured/ fabricated/
assembled for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining
to works which comply with the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s
accounts and records relating to the performance of the Contractor and
to have them audited by auditors appointed by the Employer, if so required
by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer
was either outside the authority given to the Engineer by the Contract or
that the decision was wrongly taken, the decision shall be
referred to …… (Higher Authority)within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the
matter for conciliation within 15 days from the decision given by the
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with
the decision of ……………………………. both the parties have to refer to
the Chief Engineer concern for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied
with the decision of the ……………………………….. both the parties have to
refer to the #Secretary, Roads & Building Department, Government of
Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process, he may refer
the dispute to Gujarat Public Works Contract Dispute Arbitration Tribunal. If
the Contractor fails to refer a claim / dispute to the Higher Authority within
14 days of the notification of the Engineer's decision, the Contractor shall not
be entitled to any additional payment/claim if he doesn’t follow the above
sequence in stipulated time and he should not stop the work.
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the
arbitration procedure stated in the Special Conditions of Contract.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to
the Engineer for approval a Programme showing the general methods,
arrangements orders, and timing for all the activities in the works along
with monthly cash flow forecast.
27.2 An update of the Programme shall be a programme showing the actual
progress achieved on each activity and the effect of the progress achieved
on the timing of the remaining work including any changes to the
sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated
programme at intervals no longer than the period stated in the Contract
data. If the Contractor does not submit an updated programme within this
period, the Engineer may withhold the amount stated in the Contract data
from the next payment after the date on which the overdue programme has
been submitted.
27.4 The Engineer’s approval of the programme shall not alter the
Contractor’s obligations. The Contractor may revise the programme and
submit it to the Engineer again at any time. A revised programme is to
show the effect of Variations and Compensations events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a
compensation Event occurs or a Variation is issued which makes it
impossible for completion to be achieved by the Intended Completion Date
without the Contractor taking steps to accelerate the remaining work and
which would cause the Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the
Intended Completion Date within 35 days of the Contractor asking the
Engineer for a decision upon the effect of a compensation event or
Variation and submitting full supporting information. If the Contractor has
failed to give early warning of a delay or has failed to cooperate in dealing
with a delay, the delay by this failure shall not be considered in assessing
the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the
contractor for extension of Intended Completion Date refer to the
Employer his decision. The employer shall in not more than 21 days
communicate to the engineer the acceptance or otherwise of the
Engineer’s decision. If the employer fails to give his acceptance, the
Engineer shall not grant the extension and the contractor may refer the
matter under Clause
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of
any activity within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a
management meeting. The business of a management meeting shall be
to review the plans for remaining work and to deal with matters raised in
accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is
to provide copies of his record to those attending the meeting and to the
Employer. The responsibility of the parties for actions to be taken is to
be decided by the Engineer either at the management meeting or after the
management meeting and stated in writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of
specific likely future events or circumstances that may adversely affect the
quality of the work, increase the Contract price or delay the execution of
works. The Engineer may require the contractor to provide an estimate of
the expected effect of the future event or circumstance on the contract
price and completion date. The estimate is to be provided by the
Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and
considering proposals for how the effect of such an event or circumstance
can be avoided or reduced by anyone involved in the work and in carrying
out any resulting instruction of the Engineer.
C. QUALITY CONTROL
# 33. Identifying Defects/ Defect liability period
33.1 : Defect liability period : The contractor shall be responsible to make good and
remedy at his own expense any defect which may develop or may be noticed
before the period mentioned hereunder from the certified date of completion.
The Engineer in charge shall give the contractor a notice in writing about the
defects and the contractor shall make good the same within 15 days of receipt of
the notice. In the case of failure on the part of the contractor, the Engineer- in-
charge may rectify or remove or re-execute the work at the risk & cost of the
contractor. The Engineer-in-charge shall be entitled to appropriate the
whole or any part of the amount of security deposit towards the expenses, if
any, Incurred by him in rectification, removal or re-execution. The Defects
Liability period shall be as under….
(a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall
be 3 Months from the certified date of completion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put
tender), the period shall be 12 (Twelve) months from the certified date of
completion or one monsoon, whichever is later.
(c) For major projects costing more than Rs. 1 crore, the period shall be
Months from the certified date of completion which should include three
(d) For original building works the defect liability period will be 4 years or elapse
of 4 monsoon period following date of possession of building taken over by
user agency following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September shall be
treated as the last date.
Modified vide R & B D Circular No. PAC-11-102008-2076-N dated 31/8/2009,
PRCH/102013(2976) 2759-N, Dated 27/05/2013 and Circular
No.TNC/10/2016/Clause 17A (Correction/(1)C Dated 12/05/2016]
33.2 Free maintenance guarantee period for works of Road/Bridge construction
the contractor shall have to give four years free maintenance guarantee
from the certified date of completion. During this period the contractor
shall visit the site every six months along with the concerned Section
Officer / Deputy Executive Engineer and will examine the work already
carried out in this contract like road work, jungle cutting, side shoulders,
side gutter, road furniture, patta etc. and will prepare Km. wise
inspection report duly signed by all concerned and any defect observed shall
be done within 15 days by the contractor at his risk and cost as per the
direction of Engineer in charge. The contractor needs to do
videography of these visits and require to submit at the time of release of
FMG. If B.T. the surface during the maintenance period of 4 years is worn
out then agency shall have to provide renewal coating as per tender
item as directed by the Engineer-in- charge. The amount equivalent to 5% of
each running bill shall be withheld and will be released after the free
maintenance guarantee period (i.e. 4 years) is over.
However, this amount shall be released against fixed deposit or bank
guarantee pledged in the name of Executive Engineer after completion
certificate of work is issued.
(1) The flakiness and elongation index (combined) for coarse aggregates
under no circumstances shall exceed the allowable limit set forth in the
relevant clause for the material in question.
(2) 2% of the amount eligible for the payment of bituminous items shall be
withheld till the miscellaneous items like earthwork in embankment /
cutting for side shoulders, side gutters, kilometer / indicator / guard
stones, sign boards etc. are completed in all respect by the contractor.
After completion of the miscellaneous items, the above said 2% withheld
amount shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as
per Govt. letter No.: SSR/10/2015-16/26/C, Dtd. 26/11/15 for the work
costing more than Rs. 5.00 Crore.
(4) Setting up of adequate laboratory & deployment of quality engineers.
The contractor shall have to set up the laboratory with adequate
equipment. Till the setting up of adequate laboratory is completed &
reported of this to the engineer (subject to due verification by engineer’s
representative) by contractor in writing, Rs.2,00,000/- shall be withheld.
The qualified quality Engineer shall be deployed exclusively for this
contract by the contractors. If quality Engineer is not deployed by
contractor within one month after the date of work order, the amount
equivalent to Rs.20,000 per month shall be recovered till the actual
deployment of quality engineer. The amount so recovered towards the
deployment of quality engineers shall not be refunded.
(5) Asphalt work will have to be cross checked as per G.R. No.:
RGN/60/2006/35/C, dtd.31/05/07 before final bill is paid.
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall maintain, at his own
risk and cost, the existing lane(s) of the road so that the traffic worthiness
and safety thereof are at no time materially inferior as compared to their
condition 10 (ten) days prior to the date of the Agreement, and shall
undertake the necessary repair and maintenance works for this purpose;
provided that the Contractor may, at his cost, interrupt and divert the flow
of traffic if such interruption and diversion is necessary for the efficient
progress of works and conforms to Good Industry Practice; provided
further that such interruption and diversion shall be undertaken by the
Contractor only with the prior written approval of the Executive Engineer
which approval shall not be unreasonably withheld. For the avoidance of
doubt, it is agreed that the Contractor shall at all times be responsible for
ensuring safe operation of the road.
33.3 The Engineer shall check the Contractor’s work and notify the Contractor
of any defects that are found. Such checking shall not affect the
Contractor’s responsibilities the Engineer may instruct the Contractor to
search for a Defect and to uncover and test any work that the Engineer
considers may have a Defect.
34.1 If the engineer instructs the Contractor to carry out a test not specified in
the Specification to check whether any work has a Defect and the test
shows that it does, the Contractor shall pay for the test and any samples.
If there is no defect the test shall be a Compensation Event.
34.2 #1% of the amount of work done should be deducted from R.A. Bill of
the contractor for testing the quality of material workmanship,
irrespective of actual charges.
34.3 Agency has to establish testing laboratory on site for the various test to
be carried out in the work for this purpose agency shall construct a pukka
laboratory building with all facility on site at location specified by the
engineer in charge.
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects before the
end of the defects Liability Period, which begins at Completion and is
defined in the contract data. The Defects Liability Period shall be extended
for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the
notified defect within the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in
the Engineer’s notice, the Engineer will assess the cost of having the Defect
corrected, and the Contractor will pay this amount.
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions, installation,
testing and commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor
is paid for the quantity of the work done at the rate in the Bill of Quantities
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to
the original specifications , drawings, designs and instructions that may
appear to him to be necessary or advisable during the progress of the
work and the contractor shall be bound to carry out the work in
accordance with any instruction in this connection which may be given to
him in writing signed by the Engineer and such alteration shall not
invalidate the contract and any additional work which the contractor
may be directed to do in the manner above specified as part of the work
shall be carried out by the contractor on the same conditions in all
respects on which he agreed to do the main work and at the same rate as
are specified in the tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the
tender by more than 130%, the contractor will be paid for the quantity in
excess of 130%, at the rate entered in the SOR of the year during which the
excess in quantity is first executed.
39.1 All Variations shall be included in updated programmes produced by the
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no
rate is specified in this contract, then such class of work shall be carried
(i) At the rate derived from the item within the contract which is comparable to
the one involving additional or altered class of work; where there are more
than one comparable items, the item of the contract which is nearest in
comparison with regard to class or classes of the work involved shall be
selected and the decision of the Superintending Engineer as to the nearest
comparable item shall be final and binding on the contractor.
(ii) If the rate cannot be derived in accordance with (i) above, such class of works
shall be carried out at the rate entered in the Schedule of Rates of the division
for the year in which the tender was received, increased or decreased by the
percentage by which the tender amount is more or less as compared to the
amount arrived at the rates in the “Schedule of Rates” of the Division in the
year in which the tender was received. If the Schedule of rates of the Division
does not contain all the items, the percentage increase or decrease of the
tender shall be calculated considering such items which were included in the
“Scheduled Rates” of the division for the year and for materials consumed on
such item the rate to be charged would be the basic rate taken into account
for fixing the rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of
work shall be carried out at the rate decided by the competent authorities on
the basis of detailed rate analysis after hearing the contractor before a
Committee of two Superintending Engineers stationed at the same place or
the nearest place.
40.2 If the additional or altered work, for which no rate is entered in the
“Schedule of Rates” of the Division is ordered to be carried out before the
rate is agreed upon, then the contractor shall within seven days of the date
of receipt by him of the order to carry out the work, inform the Engineer-in-
charge of the rate, which it is his intention to charge for such class of work
and if the Engineer in charge does not agree to this rates, he shall by notice
in writing be at liberty to cancel his order to carry out such class of work
and arrange to carry it out in such manner as he may consider it advisable,
provided always that if the contractor shall commence work or incur any
expenditure in regard thereof before the rates shall have been determined
as lastly herein before mentioned, then in such cases he shall only be
entitled to be paid in respect of the work carried out or expenditure
incurred by him prior to the date of the determination of the rate as
aforesaid according to such rate or rates as shall be fixed by the Engineer-
in-charge. In the event of the dispute, the decision of the Superintending
Engineer of the Circle shall be final.
Where, however, the work is to be executed according to the
designs, drawings and specifications recommended by the contractor and
accepted by the competent authority, the alternation above referred to shall
be within the scope of such designs, drawings and specifications appended to
The time limit for the completion of the work shall be extended in
the proportion that the increase in the cost occasioned by alterations bears
to the cost of the original work and the certificate of the Engineer-in-
charge as to such proportion shall be final and conclusive.
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the
engineer with an updated cash flow forecast.
42. Payment certificates.
42.1 The Contractor shall submit to the Engineer monthly statements of the
estimated value of the work completed less the cumulative amount
certified previously.
42.2 The Engineer shall check the Contractor’s monthly statement within
days and certify the amount to be paid to the Contractor after taking in to
account any credit or debit for the month in question in respect of
materials for the works in the relevant amounts and under conditions set
forth in sub-clause 32.3 of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of
the items in the Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations and
compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate or
reduce the proportion of any item previously certified in any certificate in
the light of later information
43.1 Payments shall be adjusted for deductions for advance payments,
retention, other recoveries in terms of the contract and taxes at source,
as applicable under the law. The Employer shall pay the Contractor the
amounts certified by the Engineer within 28 days of the date of each
43.2 Payment of GST (prevailing rates) on the amount payable under the
contract to the Contractor will be made by the Employer. Hence, it is the
responsibility of the contractor to pay the GST to the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not
be paid by the Employer and shall be deemed covered by other rates and
prices in the Contract.
44. Compensation events
44.1 The following are compensation Events unless they are caused by the
(a) The Employer does not give access to a part of the Site by the site
Possession date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being
completed beyond the Intended Completion Date then Authority will
approve EOT with eligible contractual price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing
on due date of bid submission except GST. However, any subsequent
changes in the tax structure by Government after due date of bid
submission will be compensated (+/-) on availability or submission of
actual documentation. Contractor will have to intimate Engineer regarding
changes occurred in the tax structure after bid submission. If the contractor
fails to provide such information and if any financial obligation may arise
due to change in tax structure, same will be recovered from the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of
the contractor to pay the GST to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
52.1 The performance Security (including additional security for unbalanced
bids) shall be provided to the Employer no later than the date specified
in the Letter of Acceptance and shall be issued in an amount and form and
by a bank or surety acceptable to the Employer, and denominated in Indian
Rupees. The performance Security shall be valid until a date 60 days
from the date of expiry of Defects Liability Period and the additional
security for unbalanced bids shall be valid until a date 28 days from the
date of issue of the certificate of completion.
53. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the
Works between the Start date and the end of Defects Correction periods
shall be remedied by the Contractor at the Contractor’s cost if the loss or
damages arises from the Contractor’s acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of
Completion of the works and the Engineer will do so upon deciding
that the work is completed.
55. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of
the Engineer issuing a certificate of Completion.
56. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of
the total amount that the Contractor considers payable as full and final
the total amount that the Contractor considers payable as full and final
settlement of all claims under the Contract for items before the end of the
Defects Liability Period. The Engineer shall issue a Defect Liability
Certificate and certify any final payment that is due to the Contractor
within 56 days of receiving the Contractor's account if it is correct and
complete. If it is not, the Engineer shall issue within 56 days a schedule
that states the scope of the corrections or additions that are necessary. If
the Final Account is still unsatisfactory after it has been resubmitted, the
Engineer shall decide on the amount payable to the Contractor and issue a
payment certificate, within 56 days of receiving the Contractor’s revised
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of
excesses and savings in final account is observed, the Engineer/Employer
shall be at liberty to restrict the final payment of BOQ items to the lowest
amount evaluated of the bids considering the final quantities and the
rates quoted including the rebates if any. Payment of variation items
shall however be made at the rates approved by the Employer, within
days from the physical completion of work.
57. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals are
required, the Contractor shall supply them by the dates stated in the
58.2 If the Contractor does not supply the Drawings and/or manuals by the
dates stated in the Contract data, or they do not receive the Engineer’s
approval, the Engineer shall withhold the amount stated in the Contract
Data from payments due to the Contractor.
58. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other
party causes a fundamental breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to
1. The contractor stops work for 28 days when no stoppage of work is
shown on the current programme and the stoppage has not been
authorized by the Engineer
2. The Engineer instructs the Contractor to delay the progress of the Works
and the instructions is not withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into liquidation
other than for a reconstructions or amalgamation
4. A payment certified by the Engineer is not paid by the Employer to the
Contractor within 56 days of the date of the Engineer’s certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a
fundamental breach of Contract and the Contractor fails to correct it
within a reasonable period of time determined by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the number of
days for which the maximum amount of liquidated damages can be paid as
defined in the Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged in corrupt
or fraudulent practices in competing for or in executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the
offering, giving, receiving or soliciting of anything of value to influence the
action of a public official in the procurement process or in contract execution.
“Fraudulent practice” means a misrepresentation of facts in order to influence
a procurement process or the execution of a contract to the detriment of the
borrower, and includes collusive practice among Bidders (prior to or after bid
submission) designed to establish bid prices at artificial non-competitive
levels and to deprive the Borrower of the benefits of free and open
59.3 When either party to the Contract gives notice of a breach of contract to
the Engineer for a cause other than those listed under Sub Clause
above, the Engineer shall decide whether the breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for
59. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract
by the Contractor, the Engineer shall issue a Certificate for the value of the
work done less advance payments received up to the date of the issue
of the certificate, less other recoveries due in terms of the contract, less
taxes due to deducted at source as per applicable law and less the
percentage to apply to the work not completed as indicated in the
Contract data. Additional Liquidated Damages shall not apply. If the total
amount due to the Employer exceeds any payment due to the Contractor
the difference shall be a debt payable to the Employer.
60.2 If the Contract is terminated at the Employer’s convenience or because of
a fundamental breach of Contract by the Employer, the Engineer shall
issue a certificate for the value of the work done, the cost of balance material
brought by the contractor and available at site, the reasonable cost of
removal of equipment, repatriation of the Contractor’s personnel employed
solely on the works, and the Contractor’s cost of protecting and securing
the Works and less advance payment received up to the date of the
certificate, less other recoveries due in terms of the contract and less
taxes due to deducted at source as per applicable law.
61.1 All materials on the Site, Plant Equipment, Temporary Works and Works
are deemed to be property of the Employer, if the Contract is terminated
because of a Contractor’s default.
61. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other
event entirely outside the control of either the Employer or the Contractor
the Engineer shall certify that the Contract has been frustrated. The
Contractor shall make the Site safe and stop work as quickly as possible
after receiving this certificate and shall be paid for all work carried out
before receiving it and for any work carried out afterwards to which
commitment was made.
F. SPECIAL C O N D I T I O N S OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make
his own arrangements for the engagement of all staff and labour, local or
other, and for their payment of housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the
Engineer a return in detail, in such form and at such intervals as the Engineer
may prescribe, showing the staff and the numbers of the several classes of
labour from time to time employed by the Contractor on the site and such
other information as the Engineer may require.
63. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his sub-
contractor shall abide at all times by all existing labour enactments and rules
made thereunder, regulations, notification and bye laws of the State or central
Government or local authority and any other labour law (including rules),
regulations, bye laws that may be passed or notifications that may be issued
under any labour law in future either by the State or the Central Government
or the local authority. Salient features of some of the major labour laws that
are applicable to the construction industry are given below. The Contractor
shall keep the Employer indemnified in case any action is taken against the
Employer by the competent authority on account of contravention of any of
the provisions of any Act or rules made thereunder, regulations or
notifications including amendments. If the Employer is caused to pay or
reimburse, such amounts as may be necessary to cause or observe, or for
observance of the provisions stipulated in the notifications/bye
laws/Acts/Rules/regulations including amendments, if any, on the part of the
Contractor, the Engineer/employer shall have the right to deduct any money
due to the Contractor including his amount of performance security. The
Employer/Engineer shall also have the right to recover from the Contractor
any sum required or estimated to be required for making good the loss or
damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be
treated as the employees of the Employer at any point to time.
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS APPLICABLE TO
ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS WORK
A) Workmen Compensation Act 1923 :- The Act provides for compensation in
case of injury by accident arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee under the
Act on satisfaction of certain conditions on separation if an employee has
completed 5 years service or more on death, the rate of 15 days wages for every
completed year of service. The Act is applicable to all establishments employing
10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952:- The Act Provides for
monthly contributions by the employer plus workers @ 10% or 8.33% The
benefits payable under the Act are :
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951 :- The Act provides for leave and some other
benefits to women employees in case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides for
certain welfare measures to be provided by the Contractor to contract labour and
in case the Contractor fails to provide, the same are required to be provided, by
the Principal Employer by Law. The principal Employer is required to take
Certificate of Registration and the Contractor is required to take license from the
designated Officer. The Act is applicable to the establishments or Contractor of
Principal Employer, if they employ 20 or more contract labour.
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the Act, if
the employment is a scheduled employment. Construction of Building, Roads,
Runways are scheduled employment.
G) Payments of wages Act 1936:- It lays down as to by what date the wages are to
be paid, when it will be paid and what deductions can be made from the wages
of the workers.
H) Equal remunerations Act 1979 :- The Act provides for payment of equal
wages for work of equal nature to Male and Female workers and for not making
discrimination against female employees in the matter of transfer, training and
promotions etc.
I) Payments of Bonus Act 1965 :- The Act is applicable to all establishments
employing 20 or more employees. The Act provides for payments of annual
bonus subject to a minimum of 8.33% of wages and maximum of 20 % of wages
to employees drawing Rs. 3500/- per month or less. The bonus to be paid to
employees getting Rs. 2500/- per month or above Rs. 3500/- per month shall be
worked out by taking wages as Rs. 2500/- per month only. The Act does not
apply to certain establishments. The newly set-up establishments are exempted
for five years in certain circumstances. Some of the State Governments have
reduced the employment size from 20 to 10 for the purpose of applicability of
J) Industrial Disputes Act 1947 :- The Act lays down the machinery and
procedure for resolutions of Industrial disputes, in what situations a strike or
lock-out becomes illegal and what are the requirements for laying off or
retrenching the employees or closing down the establishment.
K) Industrial employment (standing Orders) Act 1946 :- It is applicable to all
establishments employing 100 or more workmen (employment size reduced by
some of the State and Central Government to 50). The Act provides for laying
down rules governing the conditions of employment by the Employer on
matters provided in the Act and get the same certified by the designated
L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade
unions of workmen and employers. The Trade Unions registered under the Act
have given certain immunities from civil and criminal liabilities.
M) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits
employment of children below 14 years of age in certain occupations and
process and provides for regulation of employment of children in all other
occupations and processes. Employment of Child labour is prohibited in Building
and Construction Industry.
N) Inter – State Migrant workmen’s (Regulation of Employment & Conditions
of service) Act 1979:- The Act is applicable to an establishment which employs
5 or more inter-state migrant workmen through an intermediary (who has
recruited workmen in one state for employment in the establishment situated in
another state).The inter-state migrant workmen, is an establishment to which
this Act becomes applicable, are required to be provided certain facilities such as
housing, medical aid, traveling expenses from home upto the establishment and
O) The Building and Other Construction workers (Regulation of employment
and Conditions of Service) Act 1996 and the Cess Act of 1996:- All the
establishments who carry on any building or other constructions work and
employ 10 or more workers are covered under this Act.
All such establishments are required to pay cess at the rate not exceeding 2% of
the cost of construction as may be modified by the government. The Employer of
the establishment is required to provide safety measures at the Building or
construction work and other welfare measures, such as canteens, First Aid
facilities, Ambulance, Housing accommodations for workers near the workplace
etc. The Employer to whom the Act applies has to obtain a registration
certificate from the Registering Officers appointed by the Government.
P) Factories Act 1948 :- The Act lays down the procedure for approval of plans
before setting up a factory, health and safety provisions, welfare provisions,
working hours, annual earned leave and rendering information regarding
accidents or dangerous occurrences to designated authorities. It is applicable to
premises employing 10 persons or more with aid of power or 20 or more
persons without the aid of power engaged in the manufacturing process.
Q) Royalty charges-The contractor shall pay the royalty to the competent
authority as per rule. The royalty charges paid shall be borne by the
contractor and shall not be reimbursed by the Employer.
R) Following Pollution control Acts and amendments made thereof
from time to time shall be applicable.
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental
management plan for best energy use, waste management, the reduction
of pollution as in EMS (Environmental Management system)ISO-14001-
64. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the decision
was wrongly taken, the decision shall be referred to…...… (Higher Authority)
within 14 days of the notification of the Engineer's decision. If the issue is
not resolved, any party can refer the matter for conciliation within 15 days
from the decision given by the …………………………………………………………………..
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the …………………………….both the parties have to refer to the
#Chief Engineer concerned for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied
with the decision of the Superintending Engineer, both parties have to
refer to the #Secretary, Roads & Building Department, Government of
Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process,
contractor may refer the dispute to Gujarat Public Works Contract Dispute
Arbitration Tribunal. If the Contractor fails to refer a claim / dispute to the
Higher Authority within 14 days of the notification of the Engineer's
decision, the Contractor shall not be entitled to any additional
payment/claim if he doesn’t follow the above sequence in stipulated time.
However, during such period, he would not stop the work in any case.
Clause Reference With
respect To section
Item marked “N/A” do not apply to this Contract.
1. The Employers is [CL.1.1]
Name: Director, District Rural Development Agency, Ahmedabad
Address: District Rural Development Agency, Anjali char Rasta, Ahmedabad
Name of authorized Representative (will be intimated later)
2. The Engineer is
Name of Authorized Representative
3. The Defects Liability Period is 03 years from the date of [CL.1.1&33]
Completion. (Including Monsoon Period)
4. The Start Date shall be 1st days for the date of issue of the Notice [CL.1.1]
to proceed with the work.
5. The Intended Completion Date for the whole of the works is [CL.1.1,17&2]
4 MONTHS after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period from the start date
Milestone 1 i.e. 25% 15 days
Milestone 2 i.e. 50% 45 days
Milestone 3 i.e. 75% 85 days
Milestone 4 i.e. 100% 120 days
6. The Site is located at DHOLKA TALUKA, VILLAGE - NESDA, TRANSAD, [CL.1.1]
BHETAWADA, AMBALIYARA
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of with items as per [CL.1.1]
B.O.Q. The works shall, inter alia, include the following, as
Specified or as directed:
(C) Other Items [CL.1.1]
Any Other Items as required to fulfill all contractual obligations as per the Bid
10. The following documents also form part of the Contract: [CL.2.3(9)]
As per clause 2-3
11. The law which applies to the Contract is the law of Union of India [CL.3.1]
12. The language of the Contract documents is English [CL.3.1]
13. Limit of subcontracting 25% of the Initial Contract Price [CL.7.1]
14. The Schedule of Other Contractors [CL.8]
15. The Schedule of Key Personnel As per Annex – II to Section I [CL.9]
16. The minimum insurance cover for physical property, injury and death [CL13]
is Rs. 5 lakhs per occurrence with the number of occurrences limited
to four. After each occurrence, the contractor will pay an additional
premium necessary to make insurance valid for four occurrences
17. Site Investigation report [CL.14]
18. The Site Possession dates shall be …………………….. [CL.21]
19. The period for submission of programme for approval of the engineer [CL. 27.1]
shall be ........ days from the issue of Letter of Acceptance.
20. The period between program updates will be …….. days. [CL.27.3]
21. The amount to be withheld for late submission of an updated [CL. 27.3]
programme shall be Rs. …………
22. The following events shall also be Compensation Events [CL. 44]
Substantially adverse ground conditions encountered during the
course of execution of work not provided for in the bidding document.
(i) Removal of underground utilities detected subsequently
(ii) Significant changes in classification of soil requiring
additional mobilization by the contractor, e.g. ordinary soil
to rock excavation,
(iii) Removal of unsuitable material like marsh, debris dumps,
etc. not caused by the contractor.
(iv) Artesian conditions
(v) Seepage, erosion landslide
(vi) River training requiring protection of permanent work
(vii) Presence of historical, archeological or religious structures,
monuments interfering with the works
(viii) Restriction of access to ground imposed by civil, judicial, or
military authority
23. The currency of the Contract is Indian Rupees [CL. 46]
TECHNICAL SPECIFICATION
GENERAL INFORMATION
A. GENERAL: The work under this tender shall be executed strictly in accordance with constructional and material
requirements defined under these specifications. The Contractor shall carefully acquaint himself with these specifications to
determine his contractual obligations for the work. The conditions of these specifications will be binding on the Contractor and
no deviation shall be permissible unless specifically approved by the Consultant / Project-in-charge in writing. In absence of any
detailed Specifications these specification, latest Indian Standard specifications and code of practice shall become applicable.
Wherever the codes and specifications are silent then the same shall be governed by sound engineering practices and the
decision of the Project-in-charge / consultant in matters of interpretation etc., shall be final and binding on the Contractor.
B. DRAWINGS / DIMENSIONS:
Figured dimensions on drawings shall supersede measurements by scale and drawings to a large scale take
precedence over those to a smaller scale. Special dimensions or directions in the specifications shall be checked on
site. Measurements and other information concerning the existing site on the drawings are believed to be correct,
but the Contractor shall verify them for himself and also examine the nature of the
ground as no claim or allowance whatsoever shall be entertained hereinafter on account of any errors or omissions
in the levels or the description of the ground turning out to be different from what was expected or shown on the
C. CORRELATION OF DRAWING:
Before commencement of work, the Contractor shall correlate all relevant structural, Construction and services
drawings and satisfy himself that the information available is complete and unambiguous. The Contractor shall be
responsible for any error / difficulty in execution / damage incurred owing to any discrepancy in the drawings
which has been overlooked by him and has not been brought to the notice of the Project-in-charge / Consultant
before execution.
D. B.I.S CODES OF PRACTICE:
Wherever any reference is made in the specifications to any bureau of Indian Standard (IS) code of practice, it
shall be understood to indicate the latest version of the code of practice in usage at the time of construction.
E. ALL SIMILAR RATES TO HAVE SAME QUOTED RATE
It shall be noted by the bidder that a similar item repeated at various sub heads of the tender, he should quote same
rates. For any reasons different rates are quoted the lowest rate shall be considered for deriving
the substituted / extra item rate if required.
1. SPECIFICATIONS FOR EXCAVATION AND EARTHWORK
The scope of work broadly includes but is not necessarily limited to the following i.e. clearing of the site, excavation
of foundation trenches, back-filling, disposal of surplus earth as required including dewatering, shoring and
strutting. Contractor shall provide all tools, labour, equipment and incidentals necessary, required for completion of
all aspects of work covered in these specifications.
1.2 TYPES OF SOIL
Contractor shall thoroughly acquaint himself with the types of soil in excavation by an inspection of nature of the
ground at site & scrutiny of the investigation details available with the Consultant.
1.3 CLEARING THE SITE
The site on which the structure is to be built shown on the drawing and the area required for setting out and other
operations like road, drains, sheds, etc. should be cleared and all obstructions, loose stones, materials, and rubbish
of all kinds, stump, brush wood and trees removed as directed, roots being entirely grubbed up. All useful materials
obtained will be the property of the Project-in-charges and will be handed over to the Consultant. Rejected
materials will be removed by the contractor to his own dump.
1.4 GROUND LEVELS AND SITE LEVEL PLAN
Before starting the excavations, the requisite block levels of the entire plot shall be taken by the contractor in
consultation with the Consultant and a proper record of these levels to be kept, which shall be jointly signed by the
Contractor and the Consultant. A block level plan showing-all the ground levels of the plot shall be prepared and
shall jointly be signed by the Contractor and the Consultant/Project-in-charge.
1.5 SETTING OUT
After clearing the site, and preparing the site level plan, the Contractor will set out the center lines of the building or
other involved works and get the same approved from the Consultant. It shall be the responsibility of the
Contractor to install substantial reference marks; bench marks etc. and maintain them as long as required by the
Consultant. The Contractor will assume full responsibility for proper setting out, alignment, elevation and
dimension of each and all parts of the work
1.6 EXCAVATION AND PREPARATION OF FOUNDATIONS FOR CONCRETING
1.6.1 General Foundation trenches shall be dug wet or dry to the dimensions as shown on the drawings or as directed by the
Consultant. The excavated materials shall be stacked at a sufficient distance away from the edge of the excavated pit so
as not to endanger the stability of the sides. The soil heap shall not exceed more than 2 m from the ground.
The contractor shall, at his expense and without any extra charge, make provision for all shoring and strutting,
extra excavation in slope, extra excavation in working space, dredging or bailing out water, and the excavation
shall be kept free from water when the foundation work is in progress.
If excavation is carried out to greater width, length or depth than specified, extra depth shall be made up by filling
in lean concrete and extra length or width by filling in with earth rammed hard or by masonry as shall be borne in
full by the contractor.
If required to protect the sides of pits and trenches, timber shoring and strutting shall be erected. The timbering
shall be closed or open depending on the nature of the soil and work, and arrangement of timbering including sizes
and spacing of members used shall be as approved by the Consultant. NO extra charges shall be admissible on this
The bottoms of all excavation shall be trimmed and leveled in accordance with drawings / directions of the
Consultant / Project-in-charge. The bottoms of all excavation shall be rammed and wetted before deposition of
concrete. The contractors shall report to the Consultant / Project-in-charge when the excavation is ready to
receive concrete. NO concrete shall be placed in foundations until the contractor has obtained the approval
of Consultant / Project-in-charge.
1.6.2 PROTECTION
All foundation trenches and similar excavations shall be strong, fenced and marked with red lights at night for
watchmen to avoid accidents. Adequate protective measures shall be taken to see that the excavation does not
affect or damage adjoining structures. All measures required for the safety of the excavation, the people working in
and near the foundation trenches, property and the people in the vicinity shall be taken care by the Contractor at his
own cost, being entirely responsible for any injury and damage to property caused by his negligence or accident
due to his construction operations.
1.6.3 STACKING OF EXCAVATED MATERIALS:
Work for excavation shall include sorting out of useful materials and stacking them on site as directed. Materials
suitable and useful for back-filling, plinth, filling, leveling of the plot or other use shall be stacked at convenient
places, but not in such a way as to obstruct free movement of men, equipment and vehicles or encroach on the area
required for constructional purposes.
1.7 BACKFILLING
1.7.1 Earth obtained from excavation (or approved earth brought from out side for which no extra payment shall be made)
shall be filled in layers as described in 1.7.3 around the foundations and under floors, In case extra earth used for filling
is required under floors, plinth protection including sit outs, courtyards, the contractor will do at their own cost. The
lump sum offer shall be deemed to include the earth filing required under floors and plinth protection with plinth height
shown in Drawing above the bottom of foundation concrete and finished courtyard level shown in Drawing below D PC
/coping level of the main building.
1.7.2 QUALITY OF FILL
Fill shall be of well compacted, well graded earth or sand and shall be free from tree stumps, organic matter, seed
and peat etc Where earth or sand from source other than excavation at site is used, the quality of such earth or
sand shall be the same as that obtained from excavation at site, or superior to it. Fine sand for filling is River Sand.
Black cotton soil shall not be used for back filling or plinth filling.
1.7.3 COMPACTION
The fill shall be spread in layers not exceeding 20 cm thick and each layer shall be watered and thoroughly
consolidated by suitable mechanical rollers, rammers, vibrators or other approved plant or system of compaction.
The fill material shall be pulverized before depositing in place. An optimum moisture content shall be maintained
for the filled materials. Compaction shall be done so as to achieve a dry density of not less than 90% of the
maximum density obtained at optimum moisture content, except for the upper 20 cm layer which shall be
compacted to a density of not less than 95% of the maximum density. In order that the fill shall be reasonably
uniform through out, the material shall be dumped in place in approximately horizontal layers “Edge dumping”, a
process by which the materials is pushed off edge of the fill and allowed to roll down the slope shall not be carried
out. If there is traffic over the fill during construction, either by construction equipment or otherwise, it should be
routed to make the compaction as uniform load shall be maintained and also care shall be taken to prevent any
wedging action.
1.8 SURPLUS EXCAVATED MATERIAL
All excavated material certified as surplus and not useful, shall be removed by the Contractor from the site in an
approved manner at his own cost and risk so as indemnify owner from any claims any time of whatsoever nature.
1. SPECIFICATIONS FOR ANTI-TERMITE TREATMENT
Prevention of termite from reaching the super structure can be achieved by creating a chemical barrier between
the ground and the building by treating the soil beneath the building and around the foundations.The
work shall be carried out as per IS 6313 part II. of 2001 or the latest edition. This shall be provided to sides and
bottom of trenches and footings including treating the backfill of foundations up to ground level and the vertical
surface of wall, and filling of each under floors and treating the surface at ground level 900 mm around the
Anti termite treatment, shall be carried out strictly in accordance with CPWD specifications using Chloropyrifos (CPP) an
Emulsified concentrate @ 1% concentration or any other approved chemical.
2.3 PRE-CONSTRUCTION CHEMICAL TREATMENT
This is a process in which chemical treatment is applied to a building in the early stages of its construction at the
rate specified In IS 6313 part II of 2001 or the latest edition. Hand operated pressure pump shall be used for
uniform spraying of the chemical. To have proper check for uniform spraying of chemical graduated
containers shall be used. Proper check should be kept that specified quantity of chemical is used for the
required areas during the operation.
2.4 TIME OF APPLICATION
Soil treatment shall start when foundation trenches and pits are ready to take lean concrete in foundations. Laying
of lean concrete shall start when chemical emulsion has been absorbed by the soil and the surface is quite dry.
Treatment should not be carried out when it is raining or soil is wet with rain or sub soil water. The foregoing
applies also in the case of treatment to the filled earth surface within the plinth before laying the sub grade for the
2.5 DISTURBANCE
The treated soil barriers shall not be disturbed after they are formed. If by chance, treated soil barriers are
disturbed, immediate steps shall be taken to restore the continuity and completeness of the barrier system.
2.6 TREATMENT OF COLUMN PITS AND WALL TRENCHES
a) The bottom surface and the sides (up to a height of above 300 mm) of the excavation made for column
pits and trenches shall be treated with the chemical at the rate specified in IS 6313 Part II of 2001 or the latest
b) After the column foundation and the wall foundation come up, the back fill in immediate contact with the
foundation structure shall be treated at the rate specified in IS 6313 Part II of 2001 or the latest edition of the
vertical surface of the substructure for each side If water is used for ramming the earth fill, the chemical
treatment shall be carried out after the ramming operation is done by prodding the earth at 150 mm centers
close to the wall surface and spraying the chemical with the above dose. The earth is usually returned in layers
and the treatment shall be carried out in similar stages. The chemical emulsion shall be directed towards the
concrete to masonry surface of the columns and walls so that the earth in contact with these surfaces is well
treated with the chemical.
c) In the case of R.C.C. framed structure with columns and plinth beams and R.C.C basement with concrete, mix is
rich and dense (being 1:2:4 or richer), it is unnecessary to start the treatment from the bottom of excavation
for columns and plinth beams. The treatment shall start at the depth of 500 mm below ground level. , From
this depth the back-fill around the columns, beams and R.C.C. basement wall shall be treated at the rate as
per IS 6313 Part II of 2001 or the latest edition. The other details of treatment shall be as laid down in the
Clause (b) above.
2.7 TREATMENT OF TOP SURFACE OF PLINTH FILLING
The top surface of the filled earth within plinth wall shall be treated with chemical emulsion at the rate as per IS
6313 Part II 2001 or the latest direction (surface area) before the sand/sub-grade is laid. Holes up to 50 to70
mm deep at 150 mm centers both ways shall be made with crow bars on the surface to facilitate
saturation of the soil with chemical emulsion.
2.8 TREATMENT OF JUNCTION OF WALL AND FLOOR
To achieve continuity of the vertical chemical barrier on inner wall surface from the ground level, small channel
X 30 mm shall be made at all the junctions of wall and columns with the floor (before laying the sub-grade) and rod
holes made in the channel up to ground level 150 mm apart and the chemical emulsion poured along the channel as
per rate of application, mentioned in IS 6313 Part II (2001) or the latest edition so as to soak the soil right up to
bottom. The soil shall be tamped back into place after this operation.
2.9 TREATEMENT OF SOIL ALONG EXTERNAL PERMIETER OF BUILDING
During progress of work, provide hole in the soil with iron rods along the external perimeter of the building at
intervals of about 150 mm and depth 300 mm and filling these holes with chemical emulsion at the rate (as per IS
6313 Part II of 2001 or the latest edition) per meter of perimeter of the external wall.
2.10 TREATMENT FOR EXPANSION JOINTS
Anti termite treatment shall be supplemented by treating through the expansion joint after the sub grade has been
laid as per IS 6313 Part II of 2001 or the latest edition.
2.11 TREATMENT OF SOIL SURROUNDING PIPES AND CONDUITS
When pipes and conduits enter the soil inside the area of the foundations, the soil surrounding the points of entry
shall be loosened around each such pipe, or conduit for a distance of 150 mm and up to depth of 75 mm before
treatment is commenced When they enter the soil external to the foundations, they shall be similarly treated unless
they stand clear of the walls of the building by about 75 mm for distance of over 300 mm from ground level.
2.12 SAFETY PRECAUTIONS
All chemicals used for anti-termite treatment are poisonous and hazardous to health. These chemicals can have an
adverse effect upon health when absorbed through the skin, inhaled as vapors or spray mists or swallowed.
Person using or handling these chemicals should be warned of these dangers and advised that absorption through
the skin is the most likely source of accidental poisoning. They should be cautioned to observe carefully the safety
precautions given below.
These chemicals are usually brought to site in the form of emulsifiable concentrates. The containers should be
clearly labeled and should be stored carefully so that children and pets cannot get at them. They should be kept
securely closed.
Special care should be taken to prevent skin contact with concentrates. Prolonged exposure to dilute emulsions
should also be avoided Workers should wear clean clothing and should wash thoroughly with soap and water,
especially before eating or smoking. In the event of severe contamination, clothing should be removed at once and
the skin washed with soap and water, if chemicals splash into the eyes they should be flushed with plenty of fresh
water and immediate medical attention should be sought.
The concentrates are oil solutions and present a fire hazard owing to the use of petroleum solvents. Flames should
not be allowed nearby during the mixing. Care should be taken in the applications and present a fire hazard owing
to the use of petroleum solvents Flames should not be allowed nearby during the mixing.
Care should be taken in the application of chemicals to see that they are not allowed to contaminate wells or
springs which serve as source of drinking water.
The contractor shall guarantee through a guarantee bond, the anti-termite work for 10 years from the date of completion of
the project, and shall indemnify the Project-in-charge against any defects that arise therein during the guarantee period as
aforesaid. They shall immediately rectify, any defects that may occur therein, and repair all other damage occurring to any
part of the structure on account of defect in Anti-termite treatment, during the guarantee period of aforesaid.
3. SPECIFICATION FOR CAST – IN – SITU REINFORCED CEMENT CONCRETE
3.1.1 DESCRIPTION
This section covers the requirements for finishing of cement concrete, proportioning, batching, mixing,
testing, placing, compacting, finishing, jointing, curing and all other work as required for cast in place
reinforced concrete. The contractor shall provide all the materials including cement, steel, labour, equipment, ‘form
work’, scaffolding etc., required for completion of all reinforced concrete works as per drawings and documents.
Cement concrete shall be composed of cement, fine aggregate, coarse aggregate, water, with or without admixture
as approved, proportioned and mixed as specified herein.
3.1.2 RELATED WORK SPECIFIED ELSEWHERE
a) Steel reinforcement
3.1.3 APPLICABLE CODES AND STANDARDS
The codes and standards generally applicable to the work of this section are listed hereinafter. IS
383 Coarse and fine aggregates from natural sources for concrete
IS 456 Code of practice for plain and reinforced concrete IS
516 Methods of testing for strength of concrete
IS 1199 Methods of sampling and analysis of concrete
IS 1838 Performed fillers for expansion joints in concrete non-extruding and resilient type IS
1946 Code of practice for use of fixing devices in walls, ceiling and floors of solid
IS 2389 Methods of testing of aggregate for concrete’s IS
2505 Concrete vibrators, immersion type
IS 2645 Integral cement water proofing compounds
IS 3414 Code of practice for design and installation of joints in buildings
IS 3558 Code of practice for use for immersion vibrators for consolidating concrete IS
4082 Recommendation on stacking and storage of construction materials at
IS 7861 Code of practice for extreme weather concretizing
IS 7861 Recommended practice for hot weather (part I) concretizing IS
8112 Ordinary Portland Cement grade
IS 12269 Ordinary Portland Cement grade
The following clauses are intended to amplify the requirements of the reference document listed above and the
contractor shall comply with these clauses
3.2.1 Material Report
3.2.2 Prior to start of delivery of materials required, the following shall be submitted by the contractor to the
Consultant / Project-in-charge for approval
Suppliers and / or sources of all consumable materials including cement, steel, fine and coarse aggregates, water
additives, bricks and timber etc.
Quality Inspection Plan to ensure continuing quality control of ingredients by periodic sampling, testing and
reporting to the Consultant on the quality of materials being supply
3.3 PLANT AND EQUIPMENT
The contractor shall submit the following to the Consultant well in advance.
The proposed program, methods and details of plant and Equipment for be used to testing of ingredients and
concrete samples.
The proposed programed methods and details of plant & equipment to be used for concrete work.
3.4 REPORTS FOR INSPECTION AND TESTING
During concreting operations, the contractor shall conduct inspection and testing as described under the list of
mandatory tests in this volume and all reports thereon shall be submitted in summary form to the Consultant /
Project-in-charge.
Before commencement of the work the contractor shall prepare working schedules of concreting giving dates and
rate of pour for each item of work and submit the same to the Consultant / Project-in-charge for their approval.
Before bringing to the site, all materials for cement concrete shall be approved by the Consultant / Project-in-
charge. All approved samples shall be deposited in the office of the Consultant / Engineer-in-charge before placing
orders for the materials with suppliers The materials brought on to the work shall
Conform in every respect to their approved samples.
Fresh samples shall be deposited with the Consultant / Project-in-charge whenever type or source of any material
changes The contractor shall check each fresh consignment of materials as it is brought on to the works to ensure
that they conform to the specification and / or approved samples.
The Consultant / Project-in-charge shall have the option to have any of the materials tested to find whether they
are in accordance with specifications at the contractor‘s expense. All bills vouchers and test certificates which in
the opinion of the Consultant / Project-in-charge are necessary to convince him as to the quality of materials or
their suitability shall be produced for his inspection when required.
Any materials which have not been found to the specification and not approved by the Consultant / Project- in-
charge shall be rejected forthwith and shall be removed from the site by the Contractor’s at his own cost within the
time stipulated by the Consultant / Project-in-charge. The Consultant / Project-in-charge shall have the powers to
cause the contractors to purchase and use materials from any particular source, as may in their opinion be
necessary for the proper execution of work.
Cement shall be provided by the Contractor. On the following types of cement as specified shall be used
a. Ordinary Portland Cement 43 grade confirming to BIS 8112-1987
b. Ordinary Portland Cement 53 grade confirming to BIS 12269-1987
Cement at site shall be stored in dry weather proof go-downs (or shed) built by the Contractor at his own costs in
stacks which are not higher than 10 bags. The cement go-down shall be constructed as per CPWD specifications.
The contractor shall conduct all necessary tests as specified in the IS, at his own cost to ascertain himself on quality
of the material.
3.6.2 AGGREGATES
a) Aggregates from natural sources shall be in accordance with IS:383. The contractor shall submit to the
Consultant / Project-in-charge certificates of grading and compliance from the suppliers for all consignments of
aggregate. In addition at site from time to time, the contractor shall test the aggregates in accordance with IS:
2386 parts I, II, III and IV. The contractor shall allow for and provide all necessary apparatus for carrying out each
test and for supplying test records to the Consultant.
b) For fair faced concrete, the contractor shall ensure that aggregates are free from iron pyrites and impurities which may
cause discoloration.
c) The fine aggregates shall be river sand, stone dust or other approved sand. It shall be free from clay, loam, earth or
vegetables matter and from salt or other harmful chemical impurities It shall be dean sharp, strong angular and
composed of hard siliceous material.
The grading of sand as determined by the method prescribed in IS: 2386 part I shall be within the limits of grading
zone III given in Table 1. When the grading falls outside the percentage limits given for sieves other than
micron, 300 micron, and 150 micron (I.S) sieves by not more 5 percent, it shall be regarded as falling within this
zone. The 5 percent can be excess submission on one more sieves.
I. S. Sieve Percentage passing for Grading
IV ZONEI ZONEII ZONEIII ZONE
The maximum quantity of silt as determined by the method prescribed in IS: 2386 Part II shall not exceed 8%.
Stone dust shall be within the limits of Grading Zone III given in table 1. When the grading falls outside the
percentage limits given for the sieves other than 600 micron and 300 micron (IS) sieves by not more than 5 percent
and on 150 micron sieves by not more than 20 percent it shall be regarded as falling within this zone. The 5 percent
can be excess summation on one or more sieves.
COARSE AGGREGATE
The coarse aggregate shall be crushed stone or broken stone. Coarse aggregate obtained from crushed or broken
stone shall be angular, hay, strong, dense, durable clean and free from soft, friable, thin, flat, elongated flaky
pieces. The coarse aggregate should be from the approved source/quarry. Coarse aggregate River shingle or pit
gravel shall be rounded, sound hard, clean, non-porous, suitably graded in size with or without broken fragments
and free from flat particle of shale, clay, silt, loam and other impurities.
Except where it can be shown to the satisfaction of the Consultant than a supply of properly graded aggregate of
uniform quality can be maintained over the period of the obtaining the coarse aggregate in different sizes &
blending them in correct proportions as and when required.
The maximum size of coarse aggregate shall be such that the concrete can be placed without difficulty so s to
surround all reinforcement thoroughly and fill the comers of form work.
Water used in the works shall be potable water and free from deleterious materials. Water used for mixing and
curing concrete as well as for cooling and/or washing aggregate shall be fresh and clean, free from injurious
amounts of oil, salts, acids, alkali, other chemicals and organic matter.
Water shall be from the source approved by the Consultant / Project-in-charge and shall be in accordance with
Clause 4.3 of IS:
Before starting any concreting work and whenever the source of water changes, the water shall be tested for its
chemical and other impurities to ascertain its suitability for use in concrete for approval of the Consultant. No
water shall be used until tested and found satisfactory. Cost of all such tests shall be borne by the contractor.
3.6.4 ADMIXTURES AND ADDITIVES
Chemical admixtures are not to be used until permitted by the Consultant/Project-in-charge in case their use is
permitted, the type, amount and method of use of any admixture proposed by the contractor shall be
submitted to the Consultant for approval
The contractor shall further provide the following information concerning each admixture to the
Consultant/Project-in-charge.
a) Normal dosage and detrimental effects, if any, of under dosage and over dosage.
b) The chemical names of the main ingredients in the admixture.
c) The chloride ion content, if any, expressed as a percentage by weight of admixture.
d) Whether or not the admixture leads to the entertainment of air when used in the manufacturer’s
recommended dosage.
e) Where two or more admixtures are proposed to be used in any one mix, the manufacturer’s written
confirmation of their compatibility.
In reinforced concrete, the chloride ion of any admixture as determined in accordance with IS: 6925 and the total
chloride ion in all admixtures used in concrete mix shall not exceed 0.30n percent by weight of cement. The
admixtures when used shall conform to IS: 9103. The suitability of all admixtures shall be verified by trial mixes.
The addition of calcium chloride to concrete containing embedded metal will not be permitted under any
Regarding admixtures when used shall be based on lingo-sulphonates with due consideration to clause 5.2 and
Waterproofing admixtures shall comply with IS:
The contractor shall obtain the approval of the Consultant/Project-in-charge for all plant items he proposes to use
for the manufacture and placing of concrete.
The arrangement shall maintain all items of plant at all times in a clean and efficient working condition.
All goods and products covered by these specifications shall be procured well in advance and stored as specified
Cement shall be stored on a raised floor in dry weather proof & dust free but well ventilated shed.
Cement bags shall be stacked close together away from external walls and in stacks of not more than ten bags to
avoid lumping under pressure.
Cement stored during monsoons or cement expected to be in store for more than eight weeks shall be completely
enclosed in 700 micron polyethylene sheet so arranged that the flap closes on the top stack. The contractor shall
ensure that protective polyethylene sheet is not damaged at any time during use.
Consignments of cement shall be used in order of delivery A record shall be kept of the batch numbers of cement
deliveries in such a form that the part of the works in which the cement is used can be readily identified. If during
delivery or by test, the cement is found to be defective, the same shall be returned back forthwith.
The contractor shall be responsible for the storage of cement at the site and no claim will be entertained in the
event of any damage occurring to cement due to faulty storage by the contractors or on account of his negligence.
Cement stored on site for a period longer than eight weeks shall be tested to the satisfaction of the
Consultant/Project-in-charge before it is used in the works. Cement that has failed the tests conducted shall not
be used in the works and shall be removed from the site immediately without fail.
3.8.2 STORING OF AGGREGATE
Aggregates shall be stored on a suitable well drained raft of concrete, timber, metal or other approved
material. The storage of aggregates on the ground will not be permitted.
Each size of aggregate shall be stored separately in such a manner as to prevent spillage and mixing of one
aggregate with an adjacent aggregate The dividing walls of any bin shall be of sufficient height and the aggregate
shall be so deposited that a distance of 100 mm shall be left between the top of the division wall and any
part of the aggregate stack
When stack piling, the aggregate shall not form pyramids resulting in segregation of different size particles. The
stacks shall be regular and of a height not exceeding two meters.
3.9 GRADES OF CONCRETE
The grades of concrete shall be in accordance with the following table. The grade of concrete to be used in each
section of work will be shown in the drawings or in the Bill of Quantities:
Grade of Grade of Concrete Characteristic Nominal maximum
Concrete strength i.e. compressive strength of aggregate size (mm)
15 cm. Cubes at 28 days (N/mm2)
Unless otherwise specified in the drawings, the maximum nominal size of coarse aggregates for different
grades of concrete shall be as under:
a) For concreting in very narrow space or in very small thickness 12 mm
b) For all reinforced concrete work except in massive foundations 20 mm
c) For all ordinary plain concrete and massive reinforced foundations 10 mm
All mix design grades viz., M10, M15, M20, M25, M30 etc., shall be designed and have a minimum cement
content as follows:
Grade Qty (in kg)
Minimum content of cement remaining unchanged, as specified above for each type of concrete mix, the
proportion and quantities of local sand and aggregate are to be worked out and determined in the
field/laboratory as per Road Research Note No.4, Department of Scientific and Industrial Research, United
Kingdom for design of concrete mixes or as per ACI 613 with the approval of the Engineer. Any change in the
source of aggregates will require the re-designing of the concrete mix for the Engineer's approval.
3.10 Mix Design
At the commencement of the contract, the Contractor shall make preliminary tests to determine the proportions by
weight of cement, fine aggregates, coarse aggregates and water necessary to produce required grades of concrete.
The mix proportions shall be selected to ensure that workability of the fresh concrete is suitable for the conditions
of handling and placing and when concrete hardens, it shall have the required strength, durability and surface
finish. The Contractor shall get approval of the Engineer to such proportions before start of concreting. However,
such approval shall not relieve the
Contractor of his responsibility to produce concrete having compressive strengths as laid down in the foregoing
No departure from the approved proportions will be permitted during the works unless and until the Engineer
gives written authorization for any change in proportion. The Engineer shall have authority at any time to check
whether the mixing of concrete is being carried out according to the approved proportions.
For the major and important RC works and for all special works, the design of mixes shall be made by the
Contractor at his own cost, for each grade of concrete as well as for various workability. The design of mixes shall
be made according to relevant I.S. codes or to approved standard methods.
The concrete made by designing the mix is termed hereinafter as "Design Mix Concrete".
3.11 Water/Cement Ratio
Where a particular water/cement ratio is stipulated in the design or drawing along with the characteristic grade
of concrete, the design of mix shall be carried out by adjusting the other variable factors to obtain characteristic
strength of concrete with stipulated water/cement ratio.
In the structures where the impermeability and shrinkage of concrete have an important bearing on the durability
and serviceability of the structures, such as water retaining structures, basements, underground premises, tunnels,
pump houses, exposed structures near sea side or deserts, pre-stressed structure, thin precast members etc., the
water/cement ratio shall be kept low and preferably not exceeding 0.45.
The water cement ratio as achieved in the mix design or as specified in the drawings shall be adhered to strictly
and shall not be varied without the permission of the Engineer.
3.12 Workability
The workability of fresh concrete shall be such that the concrete is just suitable for the conditions of handling and
placing so that after compaction, it becomes completely consistent and homogeneously surrounds all the
reinforcement and completely fills the formwork.
The workability of fresh concrete at the place of batching/mixing shall be measured by compacting factor test and
at the place of disposition by means of slump test. During the finalization of trial mixes, the relationship between
compacting factor and slump test shall be established for each grade of concrete as well as for various levels for
Normally, in the condition of low water cement ratio as well as for medium/high workability, the workability shall
be achieved by increasing the cement content.
In cases where the cement content is to be limited to reduce the heat of hydration, and the water / cement ratio is
also to be kept low to reduce the permeability or due to other requirements the desired workability may be
achieved with the use of limited doses of plasticizer or air entraining agent. In such cases, the method of mixing and
dosage of the plasticizer / air entraining agent shall be according to the manufacturer's specification and with the
approval of the Engineer.
Consistency and workability of concrete shall be checked by measuring the slump of a truncated cone of concrete
straight from the mixer under normal working conditions. The conical mold shall be of metal, 300 mm high and
100 mm and 200 mm in diameter at top and base respectively.
Moulds shall be prepared by the Contractor. The slump range of concrete shall be as per the tabulation given below,
as well as standards.
Slump tests shall be performed as per IS:1881 at intervals established by the Engineer at the Contractor's cost
in such a way as to check that the degree of consistency established by the Engineer for work in progress is
maintained. The table below gives the general slump range to be followed for various types of construction unless
otherwise shown on drawings or instructed by the Engineer.
Various types of construction ....Slump (in mm)... Max. Min.
Reinforced foundation walls and footings 80
Plain footings, caissons and structure walls 75
Compressor foundations and for heavy mass constructions 50
Pumps and other misc. equipment foundations 75
Columns, slabs, beams and reinforced walls 100
3.13 Durability
The durability of concrete, depending on the exposure condition, is to be taken into account while designing the
mix. For given aggregates, the cement content should be sufficient to make sufficiently low water/cement ratio and
Appendix A of IS: 456 shall be taken as guideline for durability considerations.
3.14 Trial Mixes
After approval of the mix design by the Engineer, the Contractor shall make in presence of the Engineer the trial
mixes for each grade of concrete as well as for required workability.
Before starting the trial mixes, necessary preparatory works like determination of sieve analysis of the aggregates,
densities of different ingredients, moisture contents in the aggregates, shall be completed according to the relevant
Each trial mix shall be handled and compacted by the method which the Contractor proposes to use for that mix in
the works and the mixes shall not show tendency of inadequate compaction by the method proposed.
The compacting factor and the slump of each trial mix shall be determined immediately after mixing and the values
shall not exceed the maximum value obtained in the mix design.
Five (5) 150 mm test cubes shall be made from each trial mix. These shall be cured and tested in accordance with
relevant BIS codes. In order to have the specified characteristic strength in the field, the concrete mix as designed in
the design mix shall have higher average compressive strength depending on the degree of quality of control at site.
Before commencement of the concreting works of particular grade of concrete, the Contractor must complete the
work of trial mixes and subsequent testing of the test cubes obtained there from and the desire of the approved mix
for that particular grade of concrete.
The entire cost of all the trial mixes including all the preparatory works for trial mixes, preparation of test cubes
and their testing shall be borne by the Contractor.
3.15 Nominal Mix Concrete
Nominal mix concrete may be used for all concrete of grade M-10 and below. If design mix concrete cannot be
used for any reason for grade M-15 and M-20, nominal mix concrete may be used with the permission of the
Engineer. Nominal mix concrete shall be in accordance with Table-3 of clause 8.3 of I S 456. The stipulations of
clauses 8.3.1 and 8.3.2 of IS: 456 shall also be taken into consideration..
3.16 Volumetric Mix Concrete
Where concrete is specified in volumetric proportions such as 1:4:8, 1:3:6, 1:2:4, 1:1.5:3, 1:1:2 etc., in the Bill of
Quantities, coarse & fine aggregates shall be measured by volume & cement by weight. The water cement ratio shall be
within 0.45 & 0.70 depending upon the workability.
3.17 Batching of Concrete
Cement shall always be batched by weight. A separate weighing device shall be provided for weighing
cement. Where the weight of cement is determined by accepting the weight per bag, a number of bags shall be
weighed separately to determine the average net weight of cement per bag and the same shall be checked regularly.
3.17.2 Aggregates:
For both design mix concrete and nominal mix concrete, the aggregates,(coarse and fine) shall be batched by
In particular cases, or where weight-batching is not possible, proportioning by volume batching may be allowed by
the aggregates throughout the period of construction. For this purpose, the Contractor shall submit to the Engineer
sufficient data indicating the weight/volume relationship of the aggregates shall be made by the Contractor to the
satisfaction of the Engineer. Where aggregates are moist and volume batching is adopted, allowance shall be
bulking in accordance with IS (Part III).
Suitable adjustments shall be made for the variation in the weight of aggregates due to variation in their moisture
Water may be measured either by weight or by volume. When measured by volume, it shall be by well calibrated
conical shaped jar or vessel or from a calibrated tank filled to the mixer.
Adjustment of Water Due to Moisture Contents in Coarse and Fine Aggregates It is very important to maintain the
water cement ratio constant at its correct value. For the correct determination of the amount of water to be added
in the concrete mix, to maintain the water cement ratio constant, the amount of moisture content in both coarse
and fine aggregates shall be taken into consideration, be checked as frequently as possible, the frequency for a
given job being determined by the Engineer according to weather condition.
Determination of Moisture Content in the Aggregates
Determination of moisture content in the aggregates shall be according to IS 2386 (Part-III). Where tests are not
conducted, the amount of surface water may be estimated from the following table:
Aggregates Surface water Carried by Aggregates
% by weight l/m3
Very wet sand 7.50
Moderately wet sand 5.00
Moist gravel stone chips* 125.25 20-40
• coarser the aggregate, less the water it will carry
3.18.2 Admixtures
Any solid admixture, to be added, shall be measured by weight, but liquid or semi-liquid admixture may be
measured by weight or volume.
The Bidder shall indicate the brand name, the Manufacturer and the properties of any admixture to be used for
the concrete as per Bill of Quantity items or on his own initiative.
3.18.3 Accuracy of Batching
The accuracy of batching shall be within the following tolerance:
1 Cement within + 2% by weight
2 Aggregate within + 5% by weight
3 Water within + 0.5% by weight.
3.19 Mixing of Concrete
3.19.1 Machine Mixing
Concrete shall always be mixed in mechanical mixer. Water shall not, normally, be charged into the drum of the
mixer until all other ingredients are already in the drum and mixed for at least one minute. Mixing shall be
continued until there is uniform distribution of materials and the mass is uniform in colour and consistency. The
mixing time from the time of adding water shall be in accordance with IS 1791, but in no case less than 2 minutes or
at least 40 revolutions.
3.19.2 Hand Mixing
When hand mixing is permitted by the Engineer, it shall be carried out on a water tight platform and care shall
be taken to ensure that mixing is continued until the mass is uniform in colour and consistency. In case, of hand
mixing, 10% extra cement shall be added to each batch at no extra cost to EMPLOYER,
3.20 Transportation of Concrete
Concrete shall be transported from the place of mixing to the place of placing concrete as rapidly as practicable by
any means, which will prevent the segregation or loss of any of the ingredients and maintain the required
workability. No water shall be mixed with the concrete after it has left the mixer.
Where concrete is transported over long distances, the Contractor shall provide suitable means by which different
grades of concrete are readily identifiable at the place of final deposit.
3.21 Preparatory Works/Surface Preparation
3.21.1 For Concrete Directly on Earth Foundation
Earth foundation on which direct placement of concrete is specified, shall be rammed and consolidated as directed
by the Engineer such that it does not crumble and get mixed with concrete during or after placement. If the
foundation is quite wet, the same shall be kept dry and then sufficiently consolidated, if necessary, a thin top layer
of the wet soil shall be removed and replaced by sand or other suitable materials as directed by the Engineer
without extra cost to EMPLOYER, Care shall also be taken that earth from the sides also does not get mixed with
the concrete, during or after placement, before it has sufficiently set and hardened.
The earth foundation, over which concrete is to be placed directly, shall not be kept abandon at the specified level
and concrete shall be placed immediately following otherwise suitable measures shall be taken, as directed by the
Engineer without extra cost to EMPLOYER.
3.21.2 For Construction Joints
Concrete shall be cast, as far as possible, continuously until the parts of structure to be built are finished. Should
this not be feasible, the type, number and location of construction joints shall be approved by the Engineer prior to
placing concrete.
All such joints shall have continuous square bond grooves to produce substantial and water-tight-key and the
exposed faces of joints shall be monolithic with the main mass of concrete formed and completed under
substantially shattered faces. The Contractor shall take all the necessary steps by means of timber edgings etc. to
ensure an exact horizontal straight finish to outside edge of any lift of concrete. Subject to the approval of the
Engineer, the Contractor is at liberty to arrange his own construction joints but the following restrictions are to be
1. There shall be no vertical construction joints
2. No longitudinal joints shall be made in the walls and floors of trenches and pits unless otherwise shown in
3. Concrete pouring shall be reasonably large, but in no case shall the height of
pouring concrete exceed 1.5 m without the Engineer's firm approval. Such approval of the Engineer shall
not in any way relieve the Contractor of his responsibility to ensure that the construction is water tight
and that no segregation takes place.
4. Laitance shall be removed from the surface of concrete before it has set hard by washing and wire brushing so
as to expose the stones of the top layer without undue erosion of the mortar or damage to the under laying
All beds and joints in concrete faces, which have become set, are to be picked all over and all loose materials
removed before fresh concrete is deposited thereon. The indentations shall be at least 12 mm deep and not less
than seventy five percent of the area of the existing concrete face to be covered over.
Immediately before depositing fresh concrete, the exposed surface shall be cleaned of foreign matter by further
wire brushing, if necessary. It shall then be thoroughly washed and surplus water removed. The surface, while still
moist, shall be covered with layer of 1:1 cement mortar which must be vigorously stippled into the surface by
means of a stiff brush, the depositing of the fresh concrete following on closely. Pockets to form keys shall be left in
the surface of the concrete at constructional joints, 75 mm deep and approximately equal to 20% of the exposed
All costs in connection with the forming of construction joints shall be to the account of the Contractor and shall be
deemed to be included in the rates for concreting and formwork and shall not be separately paid for. In a column,
the joint shall be formed 75 mm below the lowest soffits of the beams, including haunches, if any.
Concrete in a beam shall be placed throughout without a joint but if the provision of a joint is unavoidable, then the
joint shall be vertical and at the center of, or within, middle third of the span, unless otherwise shown on the
3.21.3 On Vertical Surfaces of Masonry
When the concrete is placed on the vertical surface of masonry (as in the case of thin concrete fins projected from
the vertical masonry surface), a groove of dimension as directed by the Engineer shall be cut in the masonry to
ensure a proper bond and the surface shall be cleaned thoroughly. Before the placement of concrete, the surface
shall be kept moist by spraying water at least for the period of 2 hours and a thick coat of cement slurry shall be
applied immediately before the placement of concrete.
Inside the Form Works (Cleaning, Surface Preparation etc.)
The interior of the form works, where the concrete is to be placed, shall be thoroughly washed by high pressure
water jet or air jet to completely clean the entire volume from the dirt’s, grease/oil foreign and deleterious
materials etc. The reinforcements shall be completely cleaned and free from all sorts of dirt’s grease/oil, rust,
foreign/deleterious materials etc. Before placement of concrete, the form works coming in contact with concrete,
shall be coated highly with form oil or raw linseed oily material or provided with any approved material to prevent
adhesion of concrete to the form work, but utmost care shall be taken so that such oily material does not come in
contact with the reinforcement.
3.22 Placing and Compaction of Concrete
Before placing the concrete, the Contractor shall ensure that:
1. All mixing and placing equipment is thoroughly cleaned
2. All concreting space is free from debris and rubbish
3. All forms have been thoroughly wetted or oiled and firmly installed in line and plumb to the Engineer's
4. All reinforcement is cleaned of loose rust, scales and other injurious adherents and is firmly bound and
correctly placed and has been so approved by the Engineer.
5. All inserts, sleeves, foundation bolts and embedded parts have been correctly and firmly installed to conform
to the Engineer's drawings and have been carefully checked to comply with the drawings. Special care shall be
taken to locate and check sleeves or inserts, which may not be symmetrically placed with respect to center
The Contractor and Engineer shall separately inspect and check the above mentioned points and record and sign
the results in a register which shall be maintained by the Contractor in a approved form. No concrete shall be
placed without the Engineer having inspected and approved in writing. In spite of ensuring the above requirements,
the Contractor shall fill pour cards furnishing the necessary details of the job, duly signed by the Engineer. This,
however, will not absolve the Contractor from his responsibility to correctly execute the work. Pour cards shall
contain the following information:
- Work test specimen
- Type of finishing and admixtures used (if any)
- Period of removal of shuttering/props/forms.
a. The concrete pouring method shall be submitted to the Engineer for approval and shall always be such as to
avoid any possibility of segregation of the components or shifting of the reinforcement.
b. Special grout or mix shall be used for difficult and intricate locations as specified by the Engineer. During
placing, the concrete shall be thoroughly worked around reinforcement, embedded parts and corners of the
c. Greatest possible care shall be taken by the Contractor that reinforcement and embedded parts, particularly
foundation bolts and sleeves are not displaced during placement of concrete. While concreting mats and other
such locations where top and bottom reinforcement are adopted, top reinforcement shall be thoroughly
cleaned of all slurry and mortar sticking to them at the time of concreting top layers.
d. The concrete shall be placed and compacted before setting commences and should not be subsequently
disturbed. No water shall be mixed with the concrete after it has left the mixer. Method of placing should be
such as to preclude segregation. Approved mechanical vibrator shall be used for compacting concrete, and
concrete shall not be non-vibrated or under vibrated. No concrete shall be placed until the place of deposit has
been thoroughly inspected and approved by the Engineer, all inserts and embedment properly secured in
position and checked and forms properly oiled. No concrete shall be placed in the absence of the Engineer.
e. Concrete shall be placed on clean bed having the designed level. The bed shall be cleaned of all debris and
other objectionable materials. Seepage water, if any, shall be controlled or diverted.
f. Concreting shall not be carried on during rains unless all precautions have been taken by the Contractor and
necessary permission has been given by the Engineer. Suitable measures shall be taken to control the
temperature of concrete.
g. Where plums are permitted in massive concrete, they shall be washed and carefully placed. No stone shall be
closer than 30 cm to an exposed face, nor nearer than 15 cm to an adjacent stone.
h. Concrete shall not be dropped from a height of more than 2 m except through a chute, the design and type of
which shall be subjected to approval of the Engineer.
i. The concrete shall be placed, spread and compacted by approved mechanical vibrator. Vibrators shall not be
used for pushing concrete to adjoining areas.
j. For members involving vertical placing of concrete (e.g. columns, walls etc.), each lift shall be deposited
in horizontal layer extending for the full width between shuttering and of such depth that each layer can be
easily and effectively vibrated and incorporated with the layer below by means of compaction being employed.
k. For members involving horizontal placing of concrete (e.g., slabs, beams etc.), the concrete shall be placed
along the line of starting point in such quantities as will allow members to be cast to their full
depth along the full width between side shuttering and then gradually brought towards the finishing
point along its entire front parallel to the starting line. Vibration and surface finish shall follow behind the
placement as closely as possible.
l. Utmost care shall be taken to avoid the displacement of reinforcements/ embedded parts or
movement of form work or damage to faces of the form work or transmission of any harmful
vibration/shocks to the concrete which has not yet hardened sufficiently.
m. All members shall be concreted at such a rate that no cold joint is formed and fresh concrete is placed
always against green concrete, which is still plastic and workable.
n. Should any unforeseen occurrence result in a stoppage of concreting for one hour or such other time as might
allow the concrete, already placed, to begin to set before the next batches can be placed, the Contractor shall
make at his own cost, suitable tongue, and groove construction joint, as approved by the Engineer. Any
additional reinforcement required as directed by the Engineer shall also be provided by the Contractor at his
own cost. Before placement of new batches of concrete over that construction joint, the surface preparation
according to this specification stipulated earlier, shall be done by the Contractor.
o. The concrete shall be worked well up against whatever surface it adjoins and compacted to such a degree
that it reaches its maximum density as a homogeneous mass, free from air and water holes and penetrates
to all corners of molds and shuttering and completely surrounds the reinforcement. All measures shall be
taken to make the shape, size, and location of the finished concrete including its embedment, holes, openings
etc., well within the accepted tolerance limit.
3.23 Construction Joints
Normally, the construction joints including crack inducing joints shall be constructed as per locations and details
indicated on the drawings. Where the location of the joint is not specified in the drawings, it shall be in accordance
with the following guidelines. In all construction joints, the reinforcements shall pass through as per drawings and
the same shall not be disturbed in any way.
i) In case of Projection from Basement Slab, 300 mm from the top of base slab or 75 mm from the top of the
haunches whichever is higher.
ii) In framing the beam at different elevation, 75 mm below the lowest soffit of the beam and in case of
projection from beams and slabs 75 mm from the top surface of the beam/slab or at the top surface of
beam/slab whichever facilitates formwork.
iii) For columns below flat slabs, 75 mm below the lowest soffit of the slab.
b) In Walls (Horizontal Construction Joints)
i) For Walls Projecting From Base Slab, 300 mm from top of base slab.
ii) For Walls supporting the suspended slab, 75 mm from the lowest soffit of the slab.
Note: In the case of water retaining structures and structures under the influence of ground water, approved water
bars of suitable size shall be provided to make the joint completely watertight.
Beams shall be cast, as a rule, without a joint. But if provision of a joint is unavoidable, the joints from simply
supported beam shall be vertical and at the middle of the span; in continuous beam, the same shall be at the
point of minimum shear force.
d) In Suspended Slabs
i) In slab of small span, there shall be reconstruction joints.
ii) In slabs of large span and continuous slabs, the Construction joint, if allowed by the Engineer, shall be vertical at
the middle of span and at right angles to the principal reinforcement.
e) In Walls (Vertical Construction Joint)
As a rule, walls shall be cast monolithically without any vertical construction joint, unless specified in the drawing.
However, for a long wall, Engineer may allow vertical construction joint and the same shall be at the place of
minimum shear force.
f) In Slabs Resting on Ground
i) For Plain Concrete
Concreting shall be done in alternate panels not exceeding 10 m2 in area. The largest panel
dimension shall be 5 m.
ii) For Nominally Reinforced Slab The area of pour shall not exceed 40 m2 and the
maximum panel dimension shall not exceed 8m.
iii) For the Basement Slabs Which Act as Structural Member There shall be no
construction joint.
g) In Ribbed Beams The beams shall be monolithic with the slab in one continuous
3.24 Cold Joints:
An advancing face of pour, which could not be covered before expiry of initial setting time for unexpected reasons,
is called a cold joint. The Contractor shall remain always vigilant to avoid cold joints. If however, a cold joint is
formed due to unavoidable reasons, the following procedures shall be adopted for treating it:
1. If the concrete is so green that it can be removed manually and if vibrators can penetrate the surface without much
effort, fresh concrete can be placed directly over the old surface and the fresh concrete along with the old concrete
shall be vibrated systematically and thoroughly.
2. In case the concrete has hardened a bit more than (1), but can still be easily removed by a light hand pick, the surface
shall be raked thoroughly and the loose concrete removed completely without disturbing the rest of the concrete in
depth. Then a rich mortar layer of 12 mm thickness shall be placed on one cold joint and then the fresh concrete shall be
placed on the mortar layer and vibrated thoroughly penetrating deep into the layer of concrete.
3. In case the concrete at the joint has become so stiff that it cannot be remolded and mortar or slurry does not rise in
spite of extensive vibration, a tongue and groove joint shall be made by removing some of the older concrete and the
joint shall be left to harden at least for 12-24 hours. It will then be treated as regular construction joint and the surface
preparation of the same, before placement of concrete, shall be as described in the appropriate clauses of these
specifications.
3.25 Sub-standard concrete
Should the work strength of controlled concrete fall below the specified strength, Engineer shall decide:
1. To reject the work, in which case the Contractor shall replace the defective work with concrete of required
strength and bear all costs for dismantling and replacing including cost of associated form work, reinforcement,
embedded parts & all associated works.
2. To accept the work at a reduced rate, in which case the unit rate payable for sub-standard work will be
reduced by EMPLOYER, directly in proportion to the work strength as compared to the specified strength. The
Engineer may, in addition, require other tests performed on the respective structural member so accepted
period to its acceptance with or without necessary corrective measures and in each such case, the Contractor
shall bear all costs for all such tests or corrective measures, besides the reduction in the unit rates as specified
3. Concrete of strength below fifteen (15) percent of the specified strength will not be
4. The test load shall be 125% of the maximum superimposed load for which the structure was designed. Such
test load shall not be applied before 56 days after the effective hardening of concrete. During the test, struts
strong enough to take the whole load shall be placed in position leaving a gap under the members. The test
load shall be maintained for 24 hours before removal.
5. If, within 24 hours of the removal of the load, the structure does not show a recovery of at least 75% of the
maximum deflection shown during the 24 hours under load, the test loading shall be repeated after a lapse of
At least 72 hours. The structure shall be considered to have failed to pass the test if the recovery after the
second test is not at least 75% of the maximum deflection shown during the second test. If the structure is
certified as failed by the Engineer, the cost of the load test shall be borne by the Contractor.
3.26 Optional Tests
The Engineer, if he so desires, may order tests to be carried out on cement, sand, coarse aggregate, water in
accordance with the relevant Indian Standards.
Tests on cement shall include
1. Fineness test
2. Test for normal consistency
3. Test for setting time
4. Test for soundness
5. Test for tensile strength
6. Test for compressive strength
7. Test for heat of hydration (by experiment and by calculation) in accordance with IS:269.
Tests on sand shall include
2. Test for organic impurities.
3. Decantation test for determining clay and silt content.
4. Specific gravity test.
5. Test for unit weight and bulk age factor.
6. Test for sieve analysis and fineness modulus.
Tests on coarse aggregates shall include
1. Sieve analysis.
2. Specific gravity and unit weight of dry, loose and rodded aggregate.
3. Soundness and alkali aggregate reactivity.
4. Petrographic examination.
5. Deleterious materials and organic impurities.
6. Test for aggregate crushing value.
Any or all these tests would normally be ordered to be carried out only if the Engineer feels the materials are not in
accordance with the specifications or if the specified concrete strengths are not obtained and shall be performed by
the Contractor at an approved test laboratory at the cost of the Contractor. If the work cubes do not give the
stipulated strengths, the Engineer reserves the right to ask the Contractor to dismantle such portions of the work
which, in his opinion, are unacceptable and re-do the work to standards stipulated, at the Contractor's cost. The
unit rate for concrete shall be all inclusive, including making preliminary mix design and test cubes works, cubes,
testing them as per specification, slump tests, optional tests etc.,
3.27 Concrete for Equipment or steel structures foundations:-
Concrete for equipment foundation, whether principal or auxiliary, shall be poured continuously so that the
structure becomes monolithic, particular care being exercised to see that the base slabs, if any, are of compact
impervious construction. Tunnels, passages, apertures and so forth shall be provided in accordance with the
drawings for the installation of mechanical and electrical equipment, pipes or cables. The top elevation of the
equipment foundations or parts shall be accurately cast to 20/50 mm (or more as may be specified on the
drawings) above the level required for grouting and it shall be pneumatically chiseled off and well roughened just
prior to the erection of the equipment concerned. All embedded anchor bolts or bolt sleeves shall be accurately and
firmly set with the aid of approved templates, steel supports and/or other accessories. For holding the embedded
bolts or sleeves in the correct position during concreting, template shall have to be of steel of suitable section
approved by the Engineer. Two sets of templates shall have to provided, one to hold the bottom and the other the
top of the bolts or sleeves. The bottom template shall be securely and rigidly fixed by providing anchorage
arrangement and by welding to the lowest part of the steel reinforcement and other structural supports. The top
templates shall be securely fixed by tying with guy wires and turn buckle arrangements to firm and rigid adjoining
structures and staging. The bottom template that is embedded in concrete will be measured and paid for as
embedded steel. Bolt pockets, where required, shall be cast with wooden taper wedges. These shall be
withdrawn at an appropriate time when the concrete has set, the pockets cleaned, roughened and then covered
or blocked thoroughly to prevent debris getting into these. The exposed portions of bolts and embedded parts shall
be kept well-greased and adequately protected from damage throughout construction. Any damages found shall
have to be corrected at the Contractor's cost. EMPLOYER, shall have the right to use the foundations, pads, piers,
slabs, floors and all concrete work as needed for other works or equipment erected prior to its "Taking Over".
3.28 Requirements for Concreting in Special Cases
3.28.1 Concreting in Deep Lifts
3.28.2 Concreting Under Water
3.28.3 Cold Weather Concreting
3.28.4 Hot Weather Concreting
3.28.5 Concreting in Large Pours (Mass Concrete)
3.29 Finishes to Exposed Surface of Concrete
The Contractor is to include his quoted rate for concrete, the provision of normal finishes in both formed and
unformed surfaces as and where required by the Engineer without any extra cost to EMPLOYER, Some
common finishes are indicated below:
3.29.1 Surfaces which do not Require Plastering
Surface in contact with casing shall be brought to a fair and even surface by working the concrete smooth
against casings with a steel trowel while it is being deposited and also by working over the surface with a trowel
immediately after the removal of the casings or centering, removing any irregularities and stopping air holes, etc.
Use of mortar plaster is not permissible for correcting levels, removing unevenness etc. However, if in the opinion
of the Engineer, such plastering is unavoidable, then the thickness of plaster shall in no case exceed 5 mm and the
plastering shall be in CM (1:3).
3.29.2 Faces of Foundations which will be Back Filled
Neither the smoothness of the surface not the positions of the joints in the form work are important. Small
blemishes caused by entrapped air are permitted. No special surface finish is required.
3.29.3 Exposed Surfaces
Surface of beams/columns flushing with the block work or other structures where it is intended to plaster, shall be
backed adequately as soon as the shuttering is stripped off so that proper bond with the plaster can develop.
3.29.4 Surface for Non-integral Finish
Where a non-integral finish such as floor finish is specified or required, the surface of the concrete shall be struck
off at the specified levels shall be furnished and finished rough.
3.29.5 For Monolithic Finish
Where no more finishing course is to be supplied as in the case of basement floor, industrial flooring or the screed
concrete flooring etc., the concrete shall be completed and struck off at the specified levels and slopes in a screed
board and then floated with a wooden float. Steel trowel ling is then started after the concrete has hardened enough
to prevent the excess of fines and water to rise to the surface but not hard enough to prevent proper finishing.
Trowelling shall be such that the surface is flat, smooth and neatly finished.
3.30 Curing of Concrete
The purpose of curing is either to provide sufficient water at optimum temperature or to prevent loss of moisture
from the concrete itself so that the cement inside the concrete is sufficiently hydrated which, of course, is a slow
and prolonged process. As soon as the concrete has hardened sufficiently, the curing shall be started.
3.30.2 Different Methods of Curing
Any one of the following may be used for curing as approved by the Engineer.
a) Curing by Direct Water
This is done either by pounding or spraying water.
Ponding is widely used for curing slabs and pavement. Earth bands are formed over the slabs and water is pumped
or poured into them and the same is replenished at interval to make up for the loss of evaporation. As this type of
curing is one of the best methods, 10 days of curing after final setting is sufficient.
By Spraying Water Curing is done by spraying water by suitable means at approved time intervals. While spraying,
it shall be ensured that the complete area is covered. In order to avoid cracking, cold water shall not be applied to
massive members immediately after striking the form work, while the concrete is still warm.
Alternative wetting and over drying shall be avoided.
Curing by spraying water shall be continued atleast for 18 days.
a) Curing of Concrete with Absorbent Material Kept Damp The entire concrete surface is covered either with hessian,
burlap, sawdust, sand, canvas or similar material and kept wet continuously for at least 12 days after final settings.
b) Curing by Covering Concrete Surface with an Impressive Sheet This is achieved by covering the entire concrete
surface with water proof paper or plastic sheets specially manufactured for this purpose. The waterproof papers are
stuck together by adhesive compound and the plastic sheets can be welded at site. Such type of covering shall be
kept at least for 24 days after the final setting. It is preferable to have sheet as white in appearance since the white
colour will reflect hot sunrays and keep the concrete temperature at reasonable level.
c) Curing by Providing Protective Membrane by Applying curing compound This is achieved by applying a membrane
forming compound (curing compound) over the concrete surface. Generally, these are available in the emulsion
form. The application of the curing compound should be started immediately after stripping off the shuttering in
case of formed surface and after the surface has hardened in case of unformed surface.
The curing compound membrane forming emulsions dry up within 3 to 4 hours after application and forms a
continuous coherent adhesive membrane over the concrete surface. Such membrane serves as a physical
barrier to prevent the loss of moisture from the concrete itself. Membrane forming emulsions are generally
coloured black or white to improve visibility for ensuring uniform application. Black colour shall never be used
for curing in very hot weather. In order to prevent glare, a colouring pigment may be added to white
compounds. Black curing compounds are either Bituminous or Asphaltic emulsions and shall be used to
surfaces which are to be covered by back filling or on the floor which is to be covered with tiles and linoleum.
White curing compound shall be used for the surfaces of tall structures under exposure of hot sun where
other method of curing can not be properly ensured.
d) Curing by Chemical Coating For chemical curing, sodium silicate or calcium chloride is used. The use of calcium
chloride shall be done with the approval of the Engineer. Normally, the sodium silicate mixed with water is applied
over concrete surface and, when it dries up, it forms a thin varnish like film, which fills up the pores, and surface
voids and prevents evaporation of water. This also acts like curing compound but only difference is that curing
compounds are available in ready mixed emulsion forms while sodium silicate is to be mixed with water at site.
3.30.3 Limitation to Use of Different Methods of Curing
i) Curing by the processes as indicated in Section B – Clause 3-24 and more specifically as per sub-clause 2(b) of
the above clause gives very good results in normal warm climate for maturity of concrete. ii) In cold weather, the
process as indicated in sub-clause 2(b) of clause 3-24 gives very good result for maturity of concrete. iii)
Where water cement ratio is less than 0.5, the methods indicated in sub-clause 2(d) and 2(e) of clause 3-24 of
Section B, shall not be used. iv) In warm climate also, where the methods of curing as indicated in sub-
clauses 2(a) and 2(b) of clause 3-24 cannot be properly ensured, any suitable method of curing as indicated
in subclasses 2(c) to 2(e) of clause 3-24 of Section B, as approved/directed by the Engineer, shall be
3.31 Testing of Concrete
The Contractor shall carry out, entirely at his own cost, all sampling and testing in accordance with the
relevant IS standards and as supplemented herein. The Contractor shall get all tests done in an approved
laboratory and submit to the Engineer, the test result in triplicate within 3 days after completion of the test.
3.31.2 Consistency Test (Tests of Fresh Concrete)
At the place of deposition/pouring of the concrete, to control the consistency slump tests and/or compacting
factor tests shall be carried out by the Contractor in accordance with IS 1199 as directed by the Engineer.
The results of the slump tests/compacting factor tests shall be recorded in a register for reference duly signed by
both the Contractor and the Engineer. That register shall be considered as the property of EMPLOYER, and shall be
kept by the Contractor at site in safe custody.
The results of the slump tests/compacting factor tests shall tally, within accepted variation of 12%, with the results
in the respective design mix, in case of mix design concrete and with the values indicated in the table under clause
6.1 of IS:456 in case of nominal mix concrete. For any particular batch of concrete, if the results do not conform to
the requirements as specified in IS 456, the Engineer has the right to reject that batch and the Contractor shall
remove the same immediately from the site, at no cost to EMPLOYER,.
3.31.3 Strength Test of Concrete
While placing concrete, the Contractor shall make six (6) 150 mm test cubes from particular batches of
concrete as desired by the Engineer. The frequency of taking test cubes shall be either according to clause
14.2 of IS:456 or as directed by the Engineer.
The cubes shall be prepared, cured and tested according to IS 516. Out of the six (6) test cubes, 3 shall be tested for
compressive strength at 7 days after casting and the remaining 3 at 28 days after casting A register shall be
maintained at site by the Contractor with the following details entered and signed by both the Contractor and the
Engineer. That register shall be considered as the property of EMPLOYER,
a) Reference to the specific structural member
b) Mark on cubes
c) The grade of concrete
d) The mix of concrete
e) Date and time
f) Crushing strength at 7 days
g) Crushing strength at 28 days
h) Any other information directed by the Engineer.
3.31.4 Acceptance Criteria for Test Cubes
The acceptance criteria of concrete on strength requirement shall be in accordance with the stipulations under clause
3.31.5 Non-destructive Tests on Hardened Concrete
If there is doubt about the strength or quality of a particular work or the test results do not comply with the
acceptance criteria as stipulated under clause 15 of IS:456, non-destructive tests on hardened concrete like core
tests and/or load tests or other type of non destructive tests like ultrasonic impulse test etc. shall be carried out, as
may be directed by the Engineer, by the Contractor at entirely his own cost.
The core tests and load tests shall comply with the requirements of clause 16.6 of IS:
3.31.6 Concrete Below Specified Strength
In case of failure of test cubes to meet the specified requirements, the Engineer may take one of the following
1. Reject the work and instruct that section of the works to which the failed cubes relate shall be cut out
and replaced at the Contractor's expense.
2. Instruct the Contractor to carry out additional tests and/or works to ensure the soundness of the structure at the
Contractor's expense.
3. Accept the work with reduction in the rate in appropriate item.
3.31.7 Concrete failed in Non-destruction Tests
In case test results of the core tests or load tests in a particular work do not comply with requirements of respective
clause (16.3 for core test and 16.5 for load tests) of IS 456, the whole or part of the work concerned shall be
dismantled and replaced by the Contractor as may be directed by the Engineer at no extra cost to EMPLOYER, and
to the satisfaction of the Engineer. No payment for the dismantled concrete including relevant form work,
reinforcement, embedded fixtures etc. shall be made. In the course of dismantling if any damage occurs to the
adjacent structure or embedded item, the same shall be made good, free of charge by the Contractor, to the
satisfaction of the Engineer.
3.32 EXPANSION JOINTS
Expansion joints shall be provided where shown on the drawings or as directed by Consultant. They shall be
constructed with an initial gap between the adjoining parts of the works of the width specified in the
The contractor shall ensure that no debris is allowed to enter expansion joints Expansion joints shall be provided as
per drawings. Contractor shall ensure that expansion joints are made water-tight and that no leakage occurs
through these joints for which he shall be responsible to redo at his own cost.
3.32.2 OPEN JOINT FILLERS
Where shown on the drawings, open joints in the structure shall be filled with joint fillers.
The joint filler shall be easily and uniformly compressible to its original thickness, tampable, easily cut or sawn,
robust, durable, resistant to decay due to termite or weathering, unaffected by water and free of any constituent
which will bleed into or stain the concrete.
The joint filler shall be of same thickness of the joint width, it shall extend through the full thickness of the concrete
unless otherwise specified and shall be sufficiently rigid during handling and placing to permit the formation of
straight joints
3.32.3 JOINT SEALING COMPOUNDS
Joints sealing compounds shall seal joints in concrete against the passage of water prevent the ingress of grit or
other foreign material and protect the joint filler. The compound shall have good extensibility and adhesion to
concrete shall have good extensibility and adhesion to concrete surfaces and shall have resistant to flow and
weathering. Polysulphide joints where specified on the drawings shall be seated with polysulphide liquid polymer,
stored, mixed handled, applied and cured strictly in dimensions, thoroughly cleaned and treated with
recommended primer strictly in accordance with the manufacturer’s written instructions prior to sealing. The
Contractor shall use only competent personnel experienced in the application of polysulphide for such work.
Where specified in the drawings, rubber/bituminous based sealant shall be of an approved manufacturer. The
treatment of the joint and the use of sealing compound shall be strictly in accordance with the manufacturer’s
written instructions.
3.32.4 WATER BARS
Where water bars are shown on the drawings, the joints shall incorporate an approved PVC external type
water-bar complete with all necessary molded or prefabricated intersection pieces assembled in accordance with
the drawings with bends and butt joints in running lengths made by heat welding in an electrically heated
Jointing and fixing of water-bars shall be carried out strictly in accordance with the manufacturers written
The water-bars shall be installed so that they are securely held in their correct position during the placing and
compacting of the concrete.
Where reinforcement is present adjacent to water-bars, adequate clearance shall be left between the
reinforcement and water-beds to facilitate of the concrete.
If any cracks develop in the reinforced cement concrete construction which in the opinion of the Consultant may be
detrimental to the strength of the construction, the contractor at his own expense shall test the structural
element in question If under these test loads the cracks shall develop further the contractor at his own expense
shall dismantle the construction, cart away the debris, replace the construction and carry out all consequential
work there to at no extra cost.
If the cracks are not detrimental to the stability of the construction in the opinion of the Consultant, the contractor
at his own expense shall grout the cracks with pneumatically applied mortar. At his own expense and risk he shall
also make good all other building works such as plaster, molding, surface finish of floods, roofs, ceiling etc. which in
the opinion of the Consultant have suffered damage either in appearance or stability owing to such cracks.
The repair work shall be carried out to the satisfaction of the Consultant/Project-in-charge. The decision of the
Consultant/Project-in-charge as to the extent of the liability of the contractor in the above matter shall be final and
binding on the contractor.
3.34 SUPERVISION
All concreting work shall be done under strict supervision of the qualified and experienced representatives of the
Contractor as well as those of the Consultant The contractor’s Engineer and supervisor who are incharge of
concreting work shall be skilled in this class of work and shall personally supervise all the concreting operations.
Special attention shall be paid to the following:-
(a) Proportioning, mixing and quality testing of the materials with particular control on the water cement
(b) Laying of material in place and thorough compaction of the concrete to ensure solidity and freedom from
voids and honey combing.
(c) Proper curing for the requisite period.
(d) Reinforcement and inserts/embodiments position are not disturbed during concreting and
consolidation by vibration.
3.35 QUALITY CONTROL
The Consultant/Project-in-charge reserves the right to make changes in the mix proportions including the
increased cement content or/and a change in the Contractor’s control procedure, should the quality control during
progress of the works prove to be inadequate in his opinion. All the concrete work shall be true to level, plumb
and square within the acceptable tolerance. The corners, edges and rises in all cases shall be unbroken and finished
properly and carefully.
3.36 TOLERANCES
The acceptable tolerances for formed concrete surfaces shall be given below: -
a) Variation from plumb for -
i. Columns and walls to be rendered 6 mm in 3 meters
ii. Exposed columns and walls 3 mm in 3 meters
b) Variation in cross sectional dimensions of columns and beams and in the thickness of slabs and walls: -
All the works executed beyond the tolerance limits are liable to be rejected and no extra cost shall be paid to the
contractor for reconstructing the same as desired by the Consultant/Project-in-charge.
3.37 TESTING ROOM
A testing room of not less than 10 sq.m. equipped with the following apparatus and qualified concrete technician,
labor and materials required for carrying out tests therein shall be provided by the contractor at his own cost:
1. Sieve Set (For aggregate 20 mm down)
40 mm, 20 mm, 16 mm, 12.5 mm, 10 mm, 4.75 mm, 600 micron, 300 micron, and 75 micron having
diameter of 45 cms.
a) Physical balance cap. 200 gms with weigh box (accuracy 0.5 gm)
b) Counter Scale cap 20 Kg
5 kg 1 No 500 gms 1 No.
2kg 2 Nos. 200 gms 1 No.
1 kg 1 No. 100 gms 1 No.
3. Slump Cones 2 Nos
4. 15 cms moulds 18 no.
5. Electric/Kerosene Heater
6. Pans etc. as directed by the Consultant
7. Measuring Cylinders of 1000 ml., 500 ml and 100ml.
8. Wash bottles of the Capacity of 500 ml., 2 Nos.
10. Work benches, shelves, desks and any other furniture and lighting as required by the
11. Spring balance dial type cap. 100 kg
12. Liter measures
a) 10 Lit 1 No.
e) 1/2 Lit 1 No.
13. Cube Testing Machine 100 Tons.
15. Cores/ Apparatus for conducting Proctor Density Tests.
3.38 CO-ORDINATION OF WORK
The contractor is fully responsible for coordinating with the other agencies for sanitary, electrical work, etc. to
ensure execution of their work related to commencement of concreting. Nothing extra shall be payable to the
contractor, if the works pertaining to concreting have to be dismantled and redone due to lack of co-
ordination on the part of the contractor in ensuring completion of works of such agencies before concreting had
been undertaken.
4 SPECIFICATIONS FOR STEEL REINFORCEMENT
4.1.1 DESCRIPTION
This section covers the requirements for fabricating, delivering and placing of steel reinforcement in position for
casting all types of concrete work
4.1.2 RELATED WORK SPECIFIED ELSEWHERE
Applicable Codes and Standards:
The codes and standards generally applicable to the work in this sections are listed below: - IS:
280 Mild wire for general engineering purpose
IS: 432 Part I Mild steel and medium tensile steel bars Part II Hard drawn steel wire IS:
456 Code of practice for plain and reinforced concrete
IS: 1139 Hot rolled mild steel, medium tensile steel and high yield strength steel deformed bars for
concrete reinforcement
IS: 1566 Hard drawn steel wire fabric for concrete reinforcement
IS: 2502 Code of Practice for bending and fixing of bars for concrete reinforcement
The following clauses are intended to amplify the requirements of the reference documents listed above and the
contractor/Project-in-charge shall comply with these clauses.
4.2.1. BAR BENDING SCHEDULE
The Contractor shall prepare Bar Bending Schedule for reinforcement before fabrication
4.3.1 STEEL REINFORCEMENT
Steel reinforcement to be procured by the Contractor for works shall be either of the following types:-
(a) Mild steel of Grade 1 tested quality conforming to IS: 432-Part-
(b) 3370 Code of practice for concrete structures for (Part I to IV) the storage of liquids
(c) High yield strength cold worked deformed steel bars of tested quality conforming to IS: 1786 or hot rolled high
tensile deformed steel bars of tested quality conforming to IS:
(d) Hard drawn steel fabric conforming to IS:
(e) Where galvanized reinforcement is specified in the drawings, the bars or mesh shall be hot-dip galvanized after
bending generally in accordance with IS: 2629 and IS: 4759. Galvanized reinforcement shall be coated with a layer of zinc
no where less than 0.05 mm in thickness.
All reinforcement shall be stored horizontally above ground level on supports, skids or other approved supports,
clear of any running or standing water. Contact with soil should be avoided. Proper drainage and protection from
the elements shall be provided to minimize corrosion.
Before steel reinforcement is placed in position, the surface of the reinforcement shall be cleaned of rust, dust,
grease and other objectionable substances. In order to confirm the quality periodical tests as specified as the
relevant IS shall be conducted by the contractor at his own cost.
4.3.2. BINDING WIRE
Binding wire shall be black annealed steel wire conforming to IS: 280 and of minimum 18 gauge.
4.3.3. WELDING ELECTRODES
Electrodes used for welding of steel bars shall be of ordinary mild steel grade electrodes conforming to IS: 814 and
shall be of the best quality approved by Consultant/Project-in-charge.
Reinforcement steel shall be handled and stored in a manner that bending or distortion of the bars is avoided and
contamination of steel is prevented.
All reinforcement shall be stored horizontally above ground level on supports, skids or other approved supports,
clear of any running or standing water Contact with soil should be avoided. Proper drainage and protection from
the elements shall be provided to minimize corrosion Bars of different classifications and diameters shall be stored
separately A record shall be kept of the batch numbers of reinforcement deliveries in such a form that the part of
the works in which particular reinforcement is used can be readily identified. Welding electrodes shall be stored in
moisture control-led environment in accordance with the manufacturer’s recommendations.
4.5 FABRICATION
Reinforcement steel shall be carefully and accurately cut, bent or formed to the dimensions and configurations
shown on the drawings and as per bar bending schedules approved by the Consultant / Project- in-charge. All
reinforcement shall be bent cold using appropriate pin size. Bars may be preheated only on approval of the
Consultant. Quenching shall not cool hot bars. Bends shall be in accordance with IS:
It shall be ensured that the bars are not straightened in any manner that will injure the material. Any bars
incorrectly bent shall be used only if means for straightening and rebinding be such as not to affect adversely the
material. Reinforcement shall not be re-bent or straightened without prior review by the Consultant. No
reinforcement shall be placed in position on the works without approval of the Consultant, whether or not i t is
partially embedded in hardened concrete.
Reinforcement steel having a reduced section, visible transverse cracks in bends, or otherwise damaged in anyway
shall not be used.
Spiral reinforcement shall be accurately fabricated to the diameter and pitch shown on the drawings. One and one
half finishing turns shall be provided at both top and bottom unless shown otherwise. Cut ends of galvanized rods
shall be given a protective coat of an approved zinc paint immediately after cutting.
As far as possible bars of maximum length available shall be used. All bars shall be in one length unless otherwise
shown on the drawings or agreed with the Consultant/Project-in-charge.
Laps shown on the drawings or otherwise specified by the Consultant shall be based on the used of bars of
maximum length by the contractor. In case the Contractor wishes to use shorter bars, laps shall be provided at the
Contractor’s cost in the manner and locations approved by the Consultant /Project-in-charge.
Not more than 1/3 rd of the bars or as specified in the drawings shall be lapped at one section.
Reinforcement bars shall not be welded unless shown on the drawings or instructed by the Consultant / Project-in-
All reinforcement shall be placed accurately and maintained in the position indicated on the drawings. The
contractor shall provide approved type of supports for maintaining the bars in position and ensuring required
spacing and correct cover of concrete to the reinforcement as called for in drawings. Pre-cast cement concrete
blocks of required shapes and size, MS. chairs and spacers bars shall be used in order to ensure accurate
positioning of reinforcement. Pre-cast concrete blocks shall be cast well in advance and shall be at least equal in
quality to the class of concrete specified in the work.
In fair faces of concrete, temporary spacers only shall be used and removed or withdrawn as compaction of
concrete proceeds. Spacers will not be permitted to be left in fair faces of concrete.
All intersections of the reinforcements shall be securely tied with two strands of binds wire twisted tight to make
the skeleton or net work rigid so that the reinforcement is not displaced during placing of concrete.
Tack welding of crossing bars shall not be done except as authorized or directed by the Consultant / Project- in-
charge. Nothing extra will be paid for tack welding.
The contractor shall take all responsible precautions to ensure that when handling or erecting reinforcement no
damage shall be done to finished concrete . Bars that are partially embedded in concrete shall not be filed bent
unless concurrence has been obtained from the Consultant / Project-in-charge.
Walkways and borrow runs for placing and compacting the concrete shall be independent of the reinforcement.
Loose binding wire and other extraneous metal shall be removed from inside the form work prior to concrete
Without relieving the Contractor of the responsibilities for the correctness thereof, the reinforcement shall be
inspected and approved by the Consultant in writing before any concrete is placed and the contractor shall allow
sufficient time for such inspecting and any subsequent remedial action to be carried out No part of the
reinforcement shall be used for conducting electrical currents.
4.8 COVER TO REINFORCEMENT
Unless shown otherwise on the drawings, minimum cover for all reinforcement shall be provided as per IS:
care shall be taken to maintain the correct cover to reinforcement.
For concrete members exposed to weather, earth, action of harmful chemicals, acid vapor, saline atmosphere,
sulphurous smoke etc minimum cover for reinforcement shall be increased by 15 cm to 40 mm as directed by the
Consultant / Project-in-charge.
The maximum cover for reinforcement shall not be greater than that specified above or shown on the drawings
plus 10 mm except for bundled bars.
For bundled bars, minimum, concrete cover shall be equal to the equivalent diameter of the bundle but need not be
greater than 50 mm.
Exposed reinforcement intended for binding with future extensions shall be protected from corrosion as shown in
After placing, the reinforcement shall be maintained in a clean condition until the concrete is placed. On no account
the bars shall be oiled or painted or mould oil used on the formwork be allowed to come in contact with the bars.
Before concreting is commenced, the bars shall be thoroughly cleaned with dry gunny bags if they are coated lightly
with rust or other impurities.
4.10 WORK WILL INCLUDE
a) All cutting to lengths, labour in bending and cranking, forming hook ends, handling, hoisting and all that is
necessary to fix reinforcement in work as per Drawings and specifications This shall also include all that is fairly
intended and is necessary for completion of work.
b) Cost of pre-cast concrete cover blocks to maintain cover and holding reinforcement in position, chairs, spaces,
dowels, pins, laps, etc.
c) For fabricating and fixing reinforcement in any structural member irrespective of its location, dimension and
d) Work at all levels.
e) All the above mentioned works shall be included in the quoted rates Nothing extra shall be payable to the
contractor on this account
f) Reinforcement Steel procurement shall be done by the Contractor.
5 SPECIFICATIONS FOR FORMWORK
5.1.1 DESCRIPTION
This section covers the requirements for providing, fabricating and erecting of form work including propping,
bracing, shoring, strutting, rising, bolting, wedging and all other temporary and all other temporary supports to
the concrete during the process of setting subsequent removal of forms.
5.1.2 RELATED WORK SPECIFIED ELSEWHERE
a. Cast-in-place Reinforced Concrete
5.1.3 APPLICABLE CODES AND STANDARDS
The codes and standards generally applicable to the work of this section are listed hereinafter IS:
456 Code of practice for plain and reinforced concrete.
IS: 4990 Ply wood for concrete shuttering work.
5.2.1 TYPE OF FORM WORK
Prior to start of delivery of material for formwork, the contractor shall prepare samples of different types of
formwork for about 10 sqm and obtain approval of the Consultant/Project-in-charge.
5.2.2 DESIGN OF FORMS
Before fabricating of forms, the contractor shall submit design calculations for proposed form work to
Consultant/Project-in-charge for his approval However, the approval of his responsibility for adequately
constructing and maintaining the forms so that they will function properly.
5.2.3 TIE BOLTS
In case the contractor proposes to use tie bolts running through the concrete, the location and size of such tie bolts
shall be submitted to the Consultant/Project-in-charge for his Approval.
5.3.1 Formwork shall be timber, plywood, steel or any other material capable of resisting damage to the contact faces under
normal conditions of erecting forms, fixing steel and placing concrete. The selection of materials suitable for formwork
shall be made by the Contractor based on the maximum quality consistent with the specified finished and safety.
Timber used for formwork shall be easily workable with nails without splitting. It shall be stable and into liable to
warp when exposed to sun and rain or wetted during concreting.
Plywood used for formwork shall be 12 mm thick shuttering quality plywood complying with IS: 4990 and of make
approved by the Consultant
Steel form work shall be made of minimum 2 mm thick or more as required black sheets stiffened with angle iron
frame made out of M S angles 40 mm X 6mm.
5.4 DESIGN CRITERIA
Formwork shall be designed for the loads and lateral pressures due to dead weight of concrete, superimposed live
loads of workmen, materials and plants and for other loads as indicated on the drawings. Forms shall be designed
to have sufficient strength to carry on the hydrostatic head of concrete as a liquid without deflection tolerances
exceeding the acceptable limits.
Where necessary to maintain the tolerances indicated on the drawings. The formwork shall be cambered to
compensate for anticipated deflections due to the weight and pressure of the fresh concrete, and also due to any
other construction loads. Unless otherwise shown or specified, the camber shall be provided as below:-
Types of member Compression Steel Camber
As % of tensile steel Co-efficient
Continuous Restrained 50%
span Cantilever Cantilever 0%
Camber in cms Where (K X L X 2.54)/D
K= Camber coefficient
L= Length of member in meter
D= Depth of member in meter
5.5 ERECTION OF FORMWORK
Forms shall be used wherever necessary to confine the concrete during vibration and to shape it to the required
line. The formwork shall conform to shapes, lines, levels and dimensions of the concrete sections shown on the
Forms shall have sufficient strength to withstand the pressure resulting from placement and vibration of concrete
and shall be maintained rigidly in position. Form work shall be adequately supported by adequate number and size
of struts, braces, ties and props to ensure rigidity of forms during concreting. Where props rest on natural or filled
up ground, to avoid any settlement, the soil shall be thoroughly compacted and bases of props shall be sufficient
size so as to restrict the bearing on the ground to 50 t/ sqm Forms shall be tight enough to prevent loss of mortar
from the concrete and to produce dense, homogenous and uniformly coloured concrete completely free from
honeycombing or surface roughness. Joints in formwork shall be designed to prevent leakage, not only between
individual elements forming the panels but also from the horizontal and vertical junction between the panels
If form work is held together by bolts or wires, those shall be so fixed that no reinforcement bar is exposed on
surface against which concrete is to be laid. The Consultant may at his discretion allow the contractor to use tie
bolts running through the concrete at his own cost.
Hole left in the concrete by these tie-bolts shall be filled as specified by him at the Contractor’s expense. Formwork
shall be constructed so as to facilitate loosening and permit removal without jarring the concrete Wedges, clamps
and bolts shall be used wherever practicable instead of nails. All formwork erected shall be approved by the
Consultant/Project-in-charge before concreting is started.
5.6 CLEANING AND OILING OF FORMS
At the time concrete is placed in the forms, the surface of the forms in contact with the concrete shall be free from
encrustations of mortar, grout or other foreign materials. Temporary openings shall be left at the bottom of
formwork to enable, sawdust, shavings, wire cuttings and other foreign material to be worked out form the interior
of the forms before the concrete is placed.
The surface of the forms to be in contact with the concrete shall be coated with an approved coating that will
effectively prevent sticking and will not stain the concrete surfaces. After each use the surfaces of forms in contact
with concrete shall be cleaned, well settled and treated with form oil approved by the Consultant Project-in-charge.
Lubricating (machine) oils shall not be used.
Oiling shall be done before reinforcement has been placed and care shall be taken that no oil comes in contact with
the reinforcement while it is being placed in positions.
Immediately before concreting is commenced the formworks shall be carefully examined to see that all dirt,
shavings, sawdust and other refuse have been removed and the formwork shall be wetted thoroughly to prevent
absorption of water from concrete. The formwork shall be kept wet during concreting and for the whole time that it
is left in place.
5.7 REMOVAL OF FORM WORK
Form works shall be removed carefully so as to prevent damage too the concrete. Wooden wedge only shall be
used between the concrete surface and the form where force is necessary to separate the form from the
concrete. Metal wedge, bars or tools shall not be used for this purpose. Any concrete damaged in the process of
removing the forms shall be repaired in accordance with the provision of concrete specifications.
Unless otherwise permitted by the Consultant, the forms shall not be stripped in less than the minimum periods
specified in IS: 456. However the Consultant may increase the above period if he considers it necessary for
structural stability
All non-supporting forms shall be loosened and removed during regular working hours, and as soon as the concrete
has hardened sufficiently to prevent damage from the removal of the forms All false work and forms supporting
concrete beam and slabs, or other members subject to direct bending stress, shall not be removed or released until
the concrete has attained sufficient strength to ensure structural stability and to carry both the dead and live loads
including any construction loads which may be placed upon it.
No construction loads exceeding the combination of superimposed dead load plus specified live load shall be
supported on any unshared portion of the structure under construction, unless analysis indicates adequate
strength to support such additional loads Form work shall be removed in such a manner so as not to impair safety
and serviceability of the structure It shall be removed gradually to prevent sudden application of loads to the
concrete All concrete to be exposed shall have sufficient strength to prevent any damage caused by removal of
5.7.1. HACKING:
Immediately after removal of forms, the concrete surface intended to be either plastered or finished, shall be
roughened with brush hammer or with chisel and hammer as directed by the construction manager to make the
surface sufficiently coarse and rough to provide a bonding key for plaster.
No extra payments shall be made to the Contractor for such work on concrete surface after removal of the form
work. No payment shall be made for temporary formwork used in concreting, or for form work required for joints
or bulk-heads, in floor or elsewhere, whether such joints are to be covered later with concrete or mastic or other
5.7.2. POCKETS AND OPENINGS:
Where boxes, pockets or openings are required (not exceeding 0.1 sqm) to be formed in the concrete. No
deduction shall be made for the area of box or pockets in measuring the area of concrete surface shuttered. In other
words the area of shuttering shall be reckoned as if box of pocket or openings were not present.
However, on measuring the concrete quantity, the volume of the box or pocket shall be deducted. If the area of box
or pocket or openings against the shuttered faces exceeds 0.1 sqm. It shall be paid not as a box or pocket or opening
but as formwork at the rates for formwork.
No extra payment shall be made for holes to be made in the form work for inserting electrical conduits hooks for
5.8 REUSE OF FORMS
Immediately after the forms are removed, they shall be cleaned with jet of water and a soft brush before they are
The contractor shall not be permitted reuse of any forms which in the opinion of the Consultant has worn out and
has become unfit for formwork.
The Consultant/Project-in-charge may in his absolute discretion, order rejection of any forms he considers unfit for
use in the works, and order their removal from the site.
6 SPECIFICATIONS FOR BRICK MASONRY WORK:-
The Contractor shall provide all labour, materials, scaffolding operations, equipment and incidentals necessary
required for the completion of all brickwork called for in the drawings and documents and that which is fairly
intended for smooth completion of the work.
6.1.1 BRICKS (CLASS 50):-
The bricks shall be well burnt locally available from good brick earth and shall be of uniform size (9”x
4.5”x3”) unless otherwise specified They shall be of uniform deep red, cherry or copper colour, thoroughly well
burnt without being verified and regular in shapes.
6.1.3 MORTARS:-
All brick work shall laid with specified mortar of good workable consistency.
6.1.4 SOAKING OF BRICKS:-
All bricks required for masonry in cement or composite lime mortars shall be thoroughly soaked in clean water
for at least one hour in advance of sufficient quantity size for immediate use. The cessation of bubbles when the
bricks are immersed in water is an indication of thorough soaking of bricks.
a) Bricks shall be laid in English bond, unless otherwise specified. Half or cut bricks shall not be used except where
necessary to complete the bond. Closers in such cases shall be cut to the required size and used near the ends of the
b) The walls shall be taken up truly plumb. All courses shall be laid truly horizontal and all vertical joints join shall be truly
vertical. Vertical joints in alternate courses shall come directly one over the other. The thickness of brick courses shall be
kept uniform and for this purpose straight edge with graduations showing the thickness of each brick course including
joint shall be used. Bricks shall be laid with frogs upwards.
c) The walls of a structure shall be carried up regularly and nearly at one level and no portion of the work shall be left more
than 3 ft. below the rest of the work. Where this is not possible the work shall be raked back according to bond (and not
left toothed) at an angle not exceeding 45°.
d) All iron fixtures pipes, outlets of water, holdfasts of doors and windows, etc., which are required to be built in walls, shall
be embedded in cement mortar or in cement concrete as specified, in their correct positions as the work proceeds.
Nothing extra shall be paid for such extra cement mortar or of the nature stated above.
6.1.6. JOINTS:-
Bricks shall be so laid that all joints are quite full of mortar. The thickness of the bed joints shall in no case exceed
3/8”, unless otherwise specified. The face of joints shall be raked to a minimum depth of 0.5” by raking tool daily
during the progress of work when the mortar is still green, so as to provide proper key for the plaster or pointing to
be done. Where plastering or pointing is not required to be done, the joints shall be struck flush and finished at the
time of laying. The face of brick work shall be cleaned daily and all mortar droppings removed.
6.1.7 BRICK-IN-EDGE COPING
The top course of all plinths, parapets, steps and tops of walls below R C.C. slabs or beams shall be laid with brick
on edge, unless otherwise specified Proper care shall be taken that the bricks forming the top corners and ends of
walls shall be properly radiate and keyed in to position.
6.1.8. CURING:-
Green Work shall be protected from rain by suitable covering Brick Masonry with cement or composite mortar
shall be kept constantly moist on all faces for a minimum period of 7 (Seven) days. In case of fat lime mortar,
curing shall commence two days after the laying of masonry and shall continue for 7 (seven) days
6.1.9 SCAFFOLDING:
Double scaffolding having two sets of vertical supports shall be provided The supports shall be sound and strong
Tied together with horizontal pieces over which the scaffolding planks shall be fixed. In building up to two stories,
single scaffolding shall be allowed In this case, the inner end of the horizontal scaffolding pole shall rest in a hole
provided in the header course only. Only one header or each pole shall be left out. The holds left in masonry work
for supporting the scaffoldings shall be filled and made good, before plastering. The Contractor shall be
responsible for providing and maintaining sufficiently strong scaffolding so as to withstand all loads likely to come
6.2 HALF BRICK AND THREE INCH THICK MASONRY:-
6.2.1. The work shall be done exactly similar to the specification ‘BRICK WORK’ except that all courses shall be laid with
6.2.2 Cement Mortar 1:4 (1 cement: 4 sand) shall be used unless otherwise specified in the description of the item.
6.2.3 The description of the item shall mention whether or not, reinforcement is to be provided, when the brick work is to
be reinforced, hoop iron band 1” x 1/16” (2.5 c.m. x 1.6. mm) shall be embedded in the cement mortar at every fourth
course or as described in the description of the item. The hoop iron shall be hooked (given a double lap) with minimum
of 9” hooks at all angles and junctions. At either end of the wall, 2” (5 c.m.) lengths of the hoops shall be bent up or
down so as to take a firm grip of the brick work. When hoop iron is not available. The Consultant may allow equivalent
reinforcement in the form of mild steel.
6.3 RUBBLE MASONRY:-
7. SPECIFICATION FOR DOORS & WINDOWS :
7.1.1.1 TEAK WOOD
Teakwood shall be second class Indian Teakwood conforming to IS: 4021 of good quality, well seasoned and free
from defects such as cracks, dead knots, sapwood etc. No individual and sound knot shall be more than 15 sq.cm
in size and the aggregate area of such knots shall not exceed 2% of the areas of the piece. The timber shall be
fairly close grained having not less than 2 growth rings per cm. Width in cross – section.
7.1.1.2 Hard Wood:
Hard wood shall be first class conforming to IS 4021 of good quality, well seasoned and free from defects such as
dead knots, cracks, sapwood etc. No individual hard and sound knot shall exceed 6 sq.cm in size with no dimension
more than 50 mm and the aggregate area of such knots shall not be more than 1% of the area of the piece. There
shall not be less than 5 growth rings per cm. Width in cross-section.
7.1.1.3.1 Moisture content in timber
The maximum permissible percentage of moisture content for well seasoned timber shall be as per IS
7.1.1.4 Workmanship of wood work
Workmanship for wood and joinery shall be as per IS 1200 and IS
7.1.1.5 Painting / Polishing of wood work
Painting / polishing of wood work shall be in accordance with clause Nos. of specification No.6.9.2 to 6.11.3.
7.2 WOODEN DOOR / WINDOW FRAME
Wooden door / window frame shall be made of specified wood as per item description and shall be in accordance
with detailed drawings.
The wooden members of the frame shall be planed smooth and accurate to the full dimensions. Rebats,
rounding, moulding etc., shall be done before the members are jointed into frames.
Joints in the frame work shall be perfect with square edges and shall be pinned with hard wood / bamboo pins of
10 to 15 mm dia.
Wood work shall be painted / polished or otherwise treated as specified. All exposed portions shall be coated with
wood primer and concealed surface by bituminous paints as per clause No.
Before any surface treatment is applied, the wood work shall be got approved by the Project-in-charge. The frames
shall be fixed only after acceptance by the Project-in-charge. The frames shall be fixed to the masonry by 300 mm x
25 mm x 6mm MS hold fasts embedded in M-15 grade concrete block of 350 mm x 100mm x 100 mm in the hole
of the masonry. In case of concrete, frames shall be fixed by 96mm long 12 mm dia metallic dash fasteners.
7.3.1. Particle Board flush shutter:
Particle board flush shutter shall in general conform to IS:
7.3.1.1 Materials
7.3.1.1.1 Particle Board
Particle board shall conform to IS 3097 and shall be three layer flat pressed teak wood based
and of exterior grade (Grade –1), type – 1, BWP type, bonded with phenol Formaldehyde
synthetic resin conforming to IS:
7.3.1.1.2 Veneers
Veneers shall conform to class – 1 of IS 303 and (BS 476 Part – 7)
7.3.1.1.3 Teak wood
Specification of Teak wood shall same as specified in clause 9.1.1.1
7.3.1.1.4 Hinges
Hinges shall be of brass and butt type conforming to IS: 205. Size of hinges shall be in accordance
with shutter width and as per IS:
7.3.1.2.1 Workmanship
The particle board of required size and thickness shall be lipped on all the edges with T- type,
teak wood lipping. The overall board lipping composition shall be uniform and specified
thickness and shall be properly sized in view of the operation of shutter.
All the four edges of the door shutter shall be square. The shutter shall be free from twist or
warp in its plane. In case of double leaf shutters, the meeting of the stiles shall be rebated by
one third the thickness of shutter. The rebating shall be splayed.
The shutter then shall be veneered on both faces by gluing approved shade and textured
commercial type 0.5 mm thick veneering conforming to class 1 of IS 303. The veneering shall be
done by gluing the veneer with BWP type, phenol formal dehyde synthetic resin conforming to IS
848 by not press process on the shutter. Workmanship and finish of the veneering shall conform
to IS 303. The exposed surfaces of the lipping of the edges, shall be french polished in
accordance with clause No. 6.9.2.4.2 of specification No.6. The shutter shall be fixed to the door
frame, by means of hinges @ minimum 3 hinges per leaf, maximum spacing of hinges being
mm or as per drawing with suitable sized screws.
The shutter when fitted to the frame shall satisfy all operational aspects of the door like smooth
movement, proper closing against the door frame etc.
7.3.2 Glazed Wooden Door shutter
7.3.2.1 Materials
Teakwood for various members like stiles, rails etc., shall be as specified in clause No.9.1.1.1.
7.3.2.1.1 GLAZING
Glass sheets for glazing shall be
i. 4 mm thick plain glass (wt. 7.2 kg/m2) conforming IS : 2835, or
ii. 5.5 mm thick wired glass conforming to IS: 5437 or
iii. 6.3 mm thick laminated glass conforming to IS: 2553 as case may be as per item description or
iv. 5.5 mm thick toughened glass.
Glass sheets shall be free from flaws, scratches, cracks, bubbles etc.
7.3.2.1.3 WORKMANSHIP
Teakwood stiles and rails of size as specified in item description shall be cut accurately and planned smoothly to
required dimensions as per drawings. The stiles and rails shall be provided with rebates for fixing the glazing and
shall be jointed together to form the profile of the shutter as per drawings. The joinery work shall be as approved
by Project-in-charge. Only after such approval, the joints shall be coated with white lead,
pressed and secured by hardwood pins of about 6 mm dia. All the four edges of the shutter shall be square. In case
of double leaf doors, rebates shall be provided at the meeting of stiles. Rebates shall be splayed type and one third
the thickness of the stiles.
The glass sheets for glazing shall be fixed by teak wood beading having mitered joints as per drawings and shall be
fixed by means of approved neoprene based adhesive and nailing, the spacing between the
nails being no more than 300 mm.
All wooden surfaces shall be coated with 2 coats of approved make polyurethane with strainer mixed to
achieve desired shade.
The shutter shall be fixed to the door frame, by means of hinge @ minimum 3 hinges per leaf, maximum spacing of
hinges being 600 mm or as per drawing with suitable sized screws.
The shutter when fitted to the frame shall satisfy all operational aspects of the door like smooth movement,
proper closing against the door frame etc.
7.4 Aluminum Glazed Doors / Windows / Ventilators
Aluminum glazed doors / windows / ventilators shall be of specified sectional size, dimension and profile as per
7.4.2 Materials
All Aluminum sections shall be extruded sections of INDAL aluminum alloy as per IS:733 and IS:1285.
Aluminum sections shall be anodized as per IS: 7088 to min, 25 microns. Glass used for glazing shall be of
following type in accordance with item description.
i. 5.5 mm thick wired glass conforming to IS
ii. 6.3 mm thick laminated safety glass conforming to IS
iii. 5.5 mm thick transparent sheet glass conforming to IS: 2853 (Wt. 7.2 kg/sq.m).
7.4.3 Workmanship
Frames shall be square and flat, the corner of the frame being fabricated to true right angles. Details of
construction of frames, shutters etc., shall be as per drawings.
Side hung window shutters shall either be fixed to the frame with pivots, or aluminium alloy hinges. For
fixing the hinges, slots shall be cut in the fixed frames and the hinges inserted inside may be riveted to the
frame. The hinges shall normally be of the projecting type conforming to IS designation A-5-M of IS –617, IS
In which case peg stay of 300 mm long complete with locking bracket and conforming to IS codes same as for
hinges shall be provided. Friction hinges may also be provided in which case peg stays are not required.
The handles for side hung shutters shall be of cast aluminum conforming to IS designation A-5-M of IS 617 and
shall be mounted on a handle plate riveted to the opening frames. The handle shall have anodized finish with
minimum anodic film thickness of 25 micron of Electro color finish. The handle shall have a two point nose which
shall engage with an aluminum striking plate on the fixed frame. The striking plate shall be finished in the same
manner as for the handle.
In case of top hung shutters, aluminum alloy cast hinges and peg stays (same as per side hung shutters) shall be
Center hung shutters shall be hung on the two pairs of cup pivots of aluminum alloy of IS designation NS – 4 of IS
737 and IS designation A-5-M of IS 617 or chromium / cadmium plated brass / bronze cup pivots riveted to the
outer and inner frames to permit to swing through an angle of 850. Cast aluminum (conforming to IS designation
A-5-M of IS 617) or chromium / cadmium plated bronze spring catches shall be fitted in the center of the top bar of
the shutter. The spring catch shall be secured to the frame by screwing / riveting to the frame and shall close into
and aluminum catch plate riveted / welded to the outside of the outer shutter frame bar. Aluminum or cadmium
plated brass chord pulley wheel in an aluminum bracket shall be fitted at the sill of the shutter with Aluminum or
galvanized / cadmium plated steel screws.
The door shutters shall be fitted with pivots as specified. The handle for doors shall be of aluminum and as per
design. The door shutters shall be provided with locking device, floor spring, O/H door closer and any other
hardware’s, specified in item.
In case of composite Door / window / ventilator units shall be coupled as per drawing. Weather bar shall be
provided whenever a coupling member is fitted over an external opening shutter. Glazing shall be fixed to the
extruded sections by means of extruded aluminum beading. Glass panes shall be provided with rubber lining
The aluminum frames shall be fixed to the masonry by means of aluminum lugs fixed to the frame (by counter
sunk galvanized machine screws) and grouted with M-15 grade concrete in the hole in the masonry as per drawing.
In case of concrete wall, the frames shall be fixed by 96 mm long, 12 mm dia. metallic dash fasteners. Any steel
material coming in contact with aluminum shall be galvanized. The windows / ventilators / doors shall be
checked to ensure smooth operation, perfect level and plumb.
8. SPECIFICATION FOR FLOORING & PAVING
The Contractor shall furnish all labor, materials, tools, equipment, machinery operations and related items
necessary and required for the full performance of the contract under this section, as shown on the drawings or as
specified or reasonably implied or incidental to the construction.
The flooring shall be laid to the level except where slopes are called for on the drawings, in which case the slopes
shall be uniform and arranged to drain into the indicated outlets. Particular care shall be exercised to ensure that
all flooring, skirting etc., is perfectly matched for color and finish. The Contractor shall pave the areas indicated on
the plans and schedule of finishes with materials therein called for. All work shall be laid to the best practice
known to the trade.
The Contractor shall furnish for approval by the Consultant, samples of each type of floor, paving etc., the samples
shall be of sizes and thickness as specified.
8.3 POLISHED GRANITE STONE SLABS FOR FLOORING, STEPS, STAIRS, CLADDING ON PANTRY AND WASH
Providing & fixing granite of approved quality and color of required size mm double polished M/C cut of 20mm
thick over floor surface in proper line. Level in CM 1:4 including finishing the joint with matching color
cement, polishing the top surface etc., complete as per instruction of EIC/ Consultant.
Granite stone shall be of best quality machine polished, Machine Cut and of approved color, dense and
homogenous in texture free from cracks, decay, weathering and flaws. The stone shall be of required size and shall
be 20 mm thick. The material shall have to be approved by Consultant before and after procurement. Before laying
flooring, the surface shall be paved and thoroughly hacked, cleaned off all mortar scales, loose materials etc., unless
and until the surface is approved by Consultant / Engineer-in charge, the laying shall not be done. The bedding with
CM 1:4 proportion as directed by Consultant / Project-in-charge with minimum thickness of 30 mm layer shall be
laid evenly and to the required slope. The granite shall be truly and evenly set in thin paste of next cement apply to
the bottom and to the prepared base. The stone then shall be tempted down with wooden mallet until they are
exactly in true plane and in line with adjacent stone.
The stone shall be closed jointed and filled with matching cement. The entire surface of flooring shall be polished
with machine upto to mirror polish achieved including necessary use of antimony trioxide anxilix acid etc., as
directed by Consultant / Project-in-charge.
8.4.1 FINISHING
The finishing of the surface shall follow immediately after the cessation of beating. The surface shall be left for
sometime, till moisture gets dried from its joints or top, Excessive trowel ling shall be avoided. Use of dry cement or
cement and sand mixture sprinkled on the surface to stiffen the concrete or absorb excessive moisture, shall not be
The curing shall be done for a minimum period of ten days. Curing shall not be commenced until the top layer has
hardened. Covering with empty cement gunnies shall be avoided as the color is likely to be bleached with the
remnants of cement matter from the bags.
9 CERAMIC TILES GLAZED AND MATT FINISH
Ceramic tiles in toilets and other areas where called for shall be non-slip ceramic tiles of approved make and shade.
The tiles shall be laid to the pattern as approved by the Consultant. The tiles shall be of uniform color, true to size
and shape and free from cracks, twists, uneven edges, crazing and other defects. The size and thickness of the tiles
shall be as specified.
The tiles shall be laid as per the pattern shown in the drawings over a bed of specified thickness of cement mortar
leveled to a true surface. The surface of the bedding mortar shall be left rough to provide bond for the tiles. A
floating coat of thick cement slurry shall be laid over the screed to proper levels and the tiles set over the same
firmly to correct line and levels.
The joints shall be filled and finished neat with cement paste pigmented to the shade of the tile. The joints shall be
finished neat as directed and shall be straight, regular and uniform. On completion, the surface shall be washed
with water, rubbed with fine saw dust and left clean.
The finished floor surface shall be true to required levels.
9.1 VTRIFIED TILES IN FLOORING AND SKIRTING
9.1.1. VITRIFIED TILES
The tiles shall generally conform to latest IS standards shall be procured by the contractor. They shall be flat, true to
shape and free from cracks, crazing spots, chipped edges and corners. The glazing shall be of uniform shade and
color shall be as shown in the drawings.
The tiles shall be of specified size and thickness as per drawing. The tolerance on facial dimension value shall be +/-
1.0mm and +/- 0.5 mm in thickness.
The top surface of the tiles shall be glazed. The glazed shall be either glossy or matt as specified. The underside of
the tiles shall be completely free glazed in order that the tile may adhere properly to the base. Type edges of the
tiles shall be preferably free form glaze, however, and glazed if unavoidable, shall be permissible on any one edge of
The Vitrified tiles shall be laid over furrow cement slab & it shall be cleaned, wetted Mortar of specified mix shall be
spread to required thickness over a small area. The slab, washed clean, shall be laid on the mortar, pissed tapped,
with a wooden mallet, and brought to required level The tiles shall be laid as per the pattern shown on the
drawings or as approved by Consultant / Project-in-charge.
It shall then be removed and laid a side. The top of the mortar shall then by corrected by adding fresh mortar at
hollows. The mortar is then allowed to harden and cement slurry of paste like consistency shall be spread over the
same at the rate of 1 bag per sq mt. area. The edges of the tile already laid shall be buttered with slurry of cement
and pigment to match the shade of slabs. The tile to be laid shall then be placed back in position, pressed and
properly bedded in level with adjoining tiles with as fine a joint as possible. Other tiles are also laid in similar
manner to correct levels with fine joints. The surplus slurry on the surface shall be cleaned off. The tiles shall be
soaked in water, washed clean, and a coat of cement slurry applied liberally at the back of tiles and set in the
bedding mortar. The tiles shall be tamped and corrected to proper plans and lines.
The tiles shall be set in required pattern and butt jointed. The joints shall be as fine as possible. Where full size
tiles cannot be fixed these shall be cut to the required size and their edges rubbed smooth.
9.1.3 CURING AND FINISHING
The joints shall be cleaned off of the grey cement grout with soft wire brush or trowel to a depth of 2mm to 3mm
and all dust and loose mortar removed Joints shall then be flush pointed with white cement added with pigment if
required to match the color of tiles. The surface shall then be kept wet for 7 days. After curing, the surface shall be
washed and finished clean. The finished work shall not sound hollow when tapped with
10 WATER-PROOFING FOR ROOF
The waterproofing shall be integral cement based water proofing treatment including preparation of surface as
required for treatment of roofs, balconies, terraces etc. consisting of following operations:
a) Applying and grouting a slurry coat of neat cement using 2.75 kg/sqm. of cement admixed with proprietary
water proofing compound conforming to IS : 2645 over the RCC slab including cleaning the surface before
b) Laying cement concrete using broken bricks/brick bats 25mm to 100mm size with 50% of cement mortar 1:5 (1
cement: 5 coarse sand) admixed with proprietary water proofing compound conforming to IS: 2645 over
20mm thick layer of cement mortar of mix 1:5 (1 cement: 5 coarse sand) admixed with proprietary water
proofing compound conforming to IS: 2645 to required slope and treating similarly the adjoining walls upto
300mm height including rounding of junctions of walls and slabs.
c) After two days of proper curing applying a second coat of cement slurry admixed with proprietary water
proofing compound conforming to IS:
d) Finishing the surface with 20mm thick jointless cement mortar of mix 1:4 (1 cement: 4 coarse sand) admixed
with proprietary water proofing compound conforming to IS: 2645 and finally finishing the surface with trowel
with neat cement slurry and making of 300 x 300mm square.
e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and
for final test. All above operations to be done in order and as directed and specified by the Project-in-charge.
With average thickness of 120mm & minimum thickness at khurra as 65mm.
The treatment shall carry a guarantee for 10 years against leakage of water, dampness, seating and other defects.
The treated roof shall be tested by allowing water to stand on the areas to a depth of 150 mm for at least 72 hours.
All guarantee shall be furnished in the format approved by the Consultant/Project-in-charge duly signed by the
contractor and sub contractor.
10.2 SPECIFICATIONS FOR CURING
The finished surface shall be cured for at least 7 days
The Khurras shall be constructed before the brick masonry work in parapet wall is taken up, and it shall be 5 cm x
45 cm and shall be formed of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size) unless otherwise specified in the drawings.
A PVC sheet 1M X 1M X 400 micron shall be laid under the khurras and then cement concrete shall be laid over it to
a minimum thickness of 3 cm with its top surface lower than the level of adjoining roof surface as approved.
The khurras and sides of the outlet shall then be rendered with cement plaster of mix and thickness stipulated in
the drawings. This shall be done when the concrete is still green and shall be finished with a floating coat of neat
cement The sides of the khurras and sizes of finished outlet opening shall be as directed by the Consultant.
11 SPECIFICATION FOR PLASTERING WORK
The Contractor shall furnish all labour, materials scaffolding, equipment, tools, plants and incidentals
necessary and required for the completion of all plaster work.
Plaster as herein specified shall be applied to all internal surface where called for All plaster work shall be
executed by skilled workmen in a workman like manner and shall be of the best workmanship and in strict
accordance with the dimensions on drawings subject to the approval of the Consultant/Engineer- incharge.
The primary requirement of plaster work shall be to provide dense, smooth and hard enclosure and
devoid of any cracks of the interior and/or exterior.
11.3 SCAFFOLDING
Double scaffolding having two seats of vertical supports shall be provided The supports shall be sound and strong,
tied together with horizontal pieces over which scaffolding planks shall be fixed. The contractor shall get the
scaffolding approved from the Consultant well in advance.
11.4 CHASING AND BREAKAGE
Fixing of door and window frame, shall be completed before any plaster work is commenced on a surface. No
chasing or cutting of plaster shall be permitted normally. However, if the same is felt unavoidable at places, written
permission shall be obtained from the Consultant before cutting any such plaster. Broken corners shall be obtained
from the Consultant before cutting any such plaster, Broken corners shall be cut back out less than 150 mm on
sides and patched with cement mortar as directed. All corners shall be rounded to a radius of 80 mm or as directed
by the Consultant.
11.5 PREPARATION
Masonry and concrete surfaces which call for application of plaster shall be clean, free from dust and loose mortar.
Efflorescence if any shall be removed by brushing and scrapping. For masonry surfaces the joints shall be raked
out properly, while the concrete surfaces shall be roughed by wire brushing and hacking to provide the key,
thereby ensuring proper bond to the satisfaction of the Consultant. The surface shall then be thoroughly washed
with water, cleaned and kept wet before plastering is commenced.
11.6 CHICKEN WIRE MESH
Galvanized chicken mesh (22 gauge, 12 mm size) shall be provided at junctions of brick masonry and concrete
members, to be plastered and other locations as called for, properly stretched and nailed with galvanized wire
nails, ensuring equal thickness of plaster on both sides of the mesh. The width of the mesh shall be as approved by
the Consultant / Project-in-charge. The chicken mesh wherever. Specified, shall be fixed in place before plastering.
11.7 Samples of each type of plaster shall be prepared well in advance of undertaking the work for the approval of the
Consultant/Project-in-charge
The mortar of the specified mix shall be used Mortar shall be prepared as specified under” Brick Work”. It
shall be made in small quantities, as required, and applied within 15 minutes of adding water to the plaster mix
Cement shall be as per specifications under “Concrete Work”
Water shall be as per specifications under “Concrete Work”
For plaster work normally clean fine river sand shall be used. However, if specified in the drawing or schedule of
finishes, coarse sand conforming to the specifications under Concrete work” shall be mixed with fine river sand in
proportion specified or directed by the Consultant.
11.8.4 WATER PROOFING COMPOUND
FOSROC, ROFFE Chemicals or approved equivalent as approved by Consultant / Project-in-charge wherever
11.9. CEILING PLASTER
6mm thick Ceiling plaster shall be completed before commencement of wall plaster.
Plastering shall be started from the top and worked down towards the floor. To ensure even thickness and true
surface, plaster about 15 x 15 cm shall be first applied, horizontally and vertically, at not more than 2 meters
intervals over the entire surface to the plaster to serve as gauges. The surface of these gauged areas shall
be truly in place of the finished plaster surface. The mortar shall be laid between the gauges
with a trowel ensuring through filling of joints. The mortar shall be applied in a uniform surface slightly more
than the specified thickness and then brought to a true surface, by working a wooden straight edge reaching across
the gauge, with small upward and side movements at a time. Finally the surface shall
be finished off true with trowel or wooden float according as a smooth or a sandy granular texture is required.
Excessive trawling or over working the float shall be avoided.
All corners, arises angles and junctions shall be truly vertical or horizontal as the case may be and shall be carefully
finished. Rounding or chamfering corners, arises, junctions etc. Where required shall be done without any extra
payment. Such rounding shall be carried out with proper templates to the sizes required. No portion of the surface
shall be left out initially to be patched up late on. Grooves shall be provided at the junction of ceiling and wall
plaster without any extra cost.
In suspending work at the end of the day, plaster shall be left, cut clean to line both horizontally and vertically.
When recommencing the plastering, the edge of the old work shall be scraped, cleaned and wetted with cement
slurry before plaster is applied to the adjacent areas, to enable the two to be properly joined together. Plastering
work shall be closed at the end a of day on the body of the surface and not nearer than 15 cm to any corners or
arises. It shall not be closed on the body of the features such as pilasters, bands and cornices. Horizontal joints in
plaster work shall not also occur on parapet tops and copings, as these invariably lead to leakages.
Wherever directed all joints between concrete and brick masonry besides other locations as called for shall be
expressed by a groove cut in plaster at no extra cost
The plaster shall be finished to a true and plumb surface and to the proper degree of smoothness as required The
work shall be tested frequently as the work proceeds with a true straight edge not less than 2.5 m long and with
plumb bobs All horizontal lines and surfaces shall be tested with a level and all jambs and corners with a plumb bob
as the work proceeds.
Curing shall be started as soon as the plaster has hardened sufficiently not to be damaged when watered. The
plaster shall be kept wet for a period of at least 7 days. During this period, it shall be suitably protected from all
11.9.4 PRECAUTION
Any cracks which appear in the surface and all portions, which sound hollow when tapped or are found to be soft or
otherwise defective shall be cut out in rectangular shape and redone as directed by the Consultant
11.9.5 FLOATING COAT OF NEAT CEMENT
Where finishing with a floating coat of neat cement is specified in the drawings or directed by the Consultant,
specification, for this item of work shall be same described above except for the additional floating coat which
shall be carried out as below. When the plaster has been brought to a true surface with the wooden straight edge, it
shall be uniformly treated over its entire area with a paste of neat cement and rubbed smooth, so that the whole
surface is covered with neat cement coating. The quantity of cement applied for floating coat shall 1 kg. per sq. mt.
smooth finishing shall be completed with trowel immediately and in no case later than half an hour of adding water
to the plaster mix.
11.10 BEARING PLASTER
This shall be consist of cement plaster 1:3(1 cement : 3 coarse sand ) 20 mm thick finished with a coat neat cement
laid on top of walls as bearing for RCC lintels, beams and slabs. When dry, a thick coat of lime wash shall be given.
12. SPECIFICATION FOR PAINTING WORK
12.1 OIL BOUND DISTEMPER
12.1.1 MATERIALS
Oil emulsion (Oil Bound) washable distemper (IS : 428) of approved brand and manufacture shall be used.
The primer shall be of the same manufacture as distemper shall be diluted with water of any other prescribed
thinner in a manner recommended by the manufacturer. Only sufficient quantity of distemper required for
day’s work shall be prepared.
The distemper and primer shall be brought by the contractor in sealed tins in sufficient quantities at a time to
suffice for a fortnight’s work, and the same shall be kept in the joint custody of the contractor and the Project- in-
charge. The empty tins shall not be removed from the site of work, till this item of work has been completed and
passed by the Consultant / Project-in-charge.
12.1.2 PREPARATION OF SURFACE
The surface shall be thoroughly cleaned of dust. Any unevenness shall be made good by applying putty, made of
plaster of Paris mixed with water on the entire surface including filling up the undulations and then sand papering
the same after it is dry.
Pitting in plaster shall be made good with plaster of Paris mixed with the colour to be used. The surface shall then
be rubbed down again with a fine grade sand paper and made smooth. A coat of the distemper shall be applied over
the patches. The patched surface shall be allowed to dry thoroughly before the regular coat of distemper is applied
12.1.3 APPLICATION
15 cm double bristled distemper brushes shall be used. After each days work, brushes shall be thoroughly washed
in hot water with soap solution ands hung down to dry. Old brushes which are dirty and caked with distemper shall
not be used on the work.
12.1.4 SCAFFOLDING
The specifications in respect of scaffolding, protective measures shall be as described under white washing.
12.2 WATER PROOF CEMENT PAINT
12.2.1 MATERIAL
Cement paint of required color and of approved brand and manufacture conforming to IS : 5410 shall be used.
Before application of the cement paint the shade shall be got approved from the Consultant. Cement paint shall be
mixed with water in two stages. The first stage shall comprise of 2 parts of cement paint and one part of water
stirred thoroughly and allowed to stand for 5 minutes. Care shall comprise of adding further one part of
water to mix and stirring thoroughly to obtain a liquid of workable and uniform consistency. In all cases the
manufacturer’s instructions shall be followed meticulously.
Cement paint shall be mixed in such quantities as can be used up within a hour of its mixing as otherwise the
mixture will set and thicken, affecting flow and finish.
The lids of cement paint shall be kept tightly closed when not in use, as by exposure to atmosphere the cement
paint rapidly become air set due to its hygroscopic qualities.
12.2.2 PREPARATION OF SURFACE
For new work, the surface shall thoroughly be cleaned of all mortar dropping, dirt, dust, algae, grease and other
foreign matter by brushing and washing. The surface shall be thoroughly wetted with clean water before the
cement paint is applied.
12.2.3 APPLICATION
For new work, the treatment shall consist of a priming coat of cement paint following by the application of two or
more coats of cement paint till the surface shows on even colour. For each coat, the entire surface shall be coated
with the mixture, uniformly, with proper cement paint brushes in horizontal strokes followed immediately by
vertical ones which together shall constitute one coat.
The subsequent coats shall be applied only after the previous coat has dried The finished surface shall be even
and uniform and shall show no brush marks.
Enough cement paint shall be mixed to finish one room at a time The application of a coat in each room shall be
finished in one operation and no work shall be started in any room, which cannot be completed the same day After
each days work, the brushes shall be washed in hot water and hung down to dry Old brushes which are dirty or
caked with painting shall not be used.
12.2.4 SCAFFOLDING
The specifications in respect to 12.1.1 scaffolding protective measures shall be as described above under
13. SPECIFICATIONS FOR ACRYLIC EMULSION PAINTING:
13.1 Workmanship:
13.1.1 Scaffolding:
Wherever scaffolding is necessary, it shall be erected on double supports ties together by horizontal pieces, over
which scaffolding planks will be fixed No bellies, bamboos or planks shall rest on or touch the surface which is
being white washed Where ladders are used, pieces of old gunny bags shall be tied on their tops to avoid damage
or scratches to walls.
13.1.2 Preparation of surface:
Preparation of surface shall in general be in accordance with, except that any unevenness shall be made good by
applying putty (white cement based) mixed with water including up the undulation and then sand papering the
same after it is dry.
13.1.3 Preparation of paint
The paint mix, shall be continuously stirred while applying for maintaining uniform consistency. Number of coats
shall be as per item description. The painting shall be laid evenly and smoothly by means of crossing and laying
off. The crossing and laying off consists of covering the area with paint, brushing the surface ard at first, then
brushing alternatively in opposite direction 2/3 times and then finally brushing lightly in a direction at right angles
to the same. In this process, no brush marks, no hair marks no clogging of paint puddles shall be permitted. The full
process of crossing and laying off with constitute one coat.
The paint shall be applied by means of brush or roller.
Before starting painting with plastic emulsion paint, the prepared surface shall be reacted with two coats of primer
consisting of cement primer whiting and plastic emulsion paint shall start only after the preceding coat has become
sufficiently hard to resist brush marking. Subsequent coats of plastic emulsion paint shall also be started after the
preceding coat is dried by evaporation of water content.
The surface of finishing shall present a flat, velvets smooth finish, even and uniform shade without patches, marks,
paint drops etc.
13.1.4 Precautions:
i. Brushes shall be quickly washed in water immediately after use and kept immersed in water during
break periods to prevent the paint from hardening on the brush. Old brushes, if used shall be completely
dried of turpentine / oil paints by washing in warm soap water.
ii. No oil base puttied shall be used in filling cracks / holes.
iii. Washing of painted surface shall not be done within 3-4 weeks of application.
13.1.5 Protective measures
Surface of distempering over existing distempered surface, the existing distempering shall be scrapped by steel
scrapers leaving a clean surface.
All nails shall be removed. Pitting in plaster shall be made good with plaster of paris mixed with dry distemper of
color to be used. The surface then shall be rubbed down again with a fine grade sand paper and made smooth. A
coat of distemper shall be applied over the patches. The surface shall be allowed to dry thoroughly before the
regular coat of distemper is allowed.
The surface affected by moss, fungus, algae efflorescence shall be treated in accordance with IS
13.2 ACRYLIC COPOLYMER AGGREGATE FINISH
13.2.1 Material
It shall be an acrylic based textured wall coating consisting of quartz and silica aggregate, inorganic pigments and
other additives to form a crack free, flexible, tough, water proof coating.
13.2.2 Preparation of Surface
The surface to be coated shall be cleaned and all dirt, dust, grease and loose particles shall be removed. Any old
textures surface shall be removed with removing agent as per manufacturer’s instructions.
13.2.3 Application
Bonding agent and water shall be mixed first. Then the flakes / granules shall be added and mixed thoroughly and
kneaded till no lumps are found. The dough shall be left for 20-30 minutes before starting application. The
bonding agent, flakes / granules and water shall be mixed in different ratios for
different finishes as per manufacturer’s specifications.
The first application shall be by steel trowel. It shall be smoothened, if the specified finish required, by a plastic
13.3 VARNISHING
Varnishing of wood and wood based material shall be in accordance with IS 2338 (Part – II). Surface to be
Varnished shall be prepared to produce a smooth, dry and matt surface and all dust and dirt shall be removed from
The varnish shall be applied liberally with a bush and spread evenly over a portion of the surface with short light
strokes to avoid fronting. It shall be allowed to flow out while the next section is being laid in. Excess, varnish shall
be scraped out of the brush and then the first section be crossed, re crossed and laid off lightly. The varnish, once
it has begun to set, shall not be retouched. In case of any mistake, the Varnish shall be removed and the work shall
be started afresh.
Where two coats of varnish are applied, the first coat shall be hard drying under coating or flatting varnish which
shall be allowed to dry hard and then be flatted down before applying the finishing coat.
Sufficient time shall be allowed in between two coats.
When flat varnishing is used for finishing, a preparatory coat of hard drying under coating of flatting varnish shall
first be applied and shall be allowed to harden thoroughly. It shall then be lightly rubbed down before the flat
varnish is applied.
On larger areas, the flat varnish shall be applied rapidly, and the edges of each patch applied shall not be
allowed to set, but shall be followed up whilst in free working conditions.
13.3.1 French polish
French polish shall conform to IS: 348. Suitable pigments shall be added to get the required colour. The surface to
be French polished shall be rubbed down to smoothness with sand paper and shall be well dusted. Pores in the
surface shall be filled up with fillers. A pad of woolen cloth covered by a fine cloth shall be used to apply the finish.
The pad shall be moistened with polish and rubbed hard on the surface in a series of over lapping circles applying
the polish sparingly but uniformly over the entire area to give an even surface. A trace of linseed oil may be used
on the face of the pad for the purpose. The surface shall be allowed to dry and the remaining coats applied in the
same way. To finish off, the pad shall be covered with a fresh piece of clean fine cloth, slightly damped with
methylated spirit and rubbed lightly and quickly with circular motions. The finished surface shall have a uniform
texture and high gloss.
13.4 PAINTING OF STEEL AND OTHER METAL SURFACES
Reference shall be made to the following Indian Standards: IS 2524, IS
13.4.2 Preparation of surface
The surface, before painting, shall be cleaned of all rust, scale, dirt and other foreign matter with wire brushes,
steel wool, scrappers, sand paper etc. The surface shall then be wiped finally with mineral turpentine which shall
then be removed of grease etc. The surface then shall be allowed to dry. In case of GI surface so prepared shall be
treated with Mordant solution (5 liters for about 100 sq.m) by rubbing the solution generously with brush. After
about half an hour, the surface if required shall be retouched and washed down thoroughly with clean cold water &
allowed to dry.
13.4.3 Application of priming and paints
Approved quality primer and paint in specified no. of coats shall be applied as per manufacturer’s
recommendations either by brushing or spraying. Each subsequent coat shall be applied only after the preceding
13.5 SYNTHETIC ENAMEL PAINT TO WOOD WORK
13.5.1 Synthetic enamel paint of approved brand and manufacture and of the required colour shall be used for the top coat
and an under coat of shade to match the top coat as recommended by the manufacture shall be used.
13.5.2 One coat of specified paint of shade suited to the shade of the top coat shall be applied after rubbing with the finest
grade of wet abrasive paper to ensure a smooth and even surface, free from brush marks and all loose particles
13.5.3 Top coats of specified paint of required shade shall be applied after the first coat is thoroughly dry. Additional finishing
coats shall be applied if found necessary to ensure properly uniform glossy surface.
14. SPECIFICATION FOR FALSE CEILING
1. FALSE CEILING GRID SYSTEMS
1.1.1 ALUMINIUM GRID SYSTEM
Aluminium grid system for supporting false ceiling tiles shall be of approved make and shall be perfectly levelled
aligned at desired height and in accordance with the false ceiling pattern as per drawings.
1.1.2.1 MATERIAL
a. Main Runner shall be of extruded anodized (25 micron) aluminium Tee sections of 25mm x 35mm size (approved
make), 2.5 mm thick.
1.1.1.2 ERECTION
The grid system shall be assembled by interlocking the main and cross runners @ 600 mm c/c max. on
`bothways by means of aluminium angle cleats. The main runners shall be suspended from the ceiling by means of
mm thick MS flat clamp fixed to main runners @ 1200 mm max. and fixed to 6 mm dia MS hook which again is fixed
to the ceiling. 3 mm thick MS flat clamp shall be connected to main runner with 25 mm long MS clamp with leveling
nut and @ 1200 mm maximum. The MS hooks shall be suspended from the ceiling by means of slotting in 25mm x
3mm thick MS flat, `L’ shaped, fixed to the slab by 12 mm dia Dash fasteners @ 1200 mm C/C. The overall grid
system shall be rigid, in accordance with false ceiling pattern, perfectly leveled and aligned at desirable height.
1.1.2 GI GRID SYSTEM
GI grid system for supporting false ceiling tiles shall be perfectly leveled, aligned at desired height in accordance
with false ceiling pattern.
1.1.3.1 MATERIAL AND WORKMANSHIP
a. Wall Channels
Wall channels shall be made 0.5 mm thick GI of size 27 mm, one flange 20 mm and other 30 mm. Wall channels
shall be fixed to peripheral walls by raw plugs / dash fasteners @ 450 mm C/C.
b. Intermediate Channels (main runners) GI intermediate channels shall be 0.9 mm thick, of size 45 mm and with two
flanges of 15 mm each. The intermediate channels shall be suspended from the soft @ 1200 mm with 25 mm x 0.5 mm
GI hanger bolted to the channel and fixed to the ceiling (by means of bolting to GI cleat fixed to the ceiling with dash
c. Ceiling Sections (Cross runners)
GI channel shaped ceiling sections shall be 0.5 mm thick having a knurled Web of 51.1 mm and two flanges of
mm each with lips of 10.5 mm. The ceiling sections shall be fixed to the intermediate channels in perpendicular
direction at 450 mm C/C with the help of connecting clips.
1.2 GYPSUM BOARD TILES:
Gypsum board shall conform to IS:
The Gypsum boards used for false ceiling shall have following properties.
i Thermal Conductivity – 0 16 W / mk
ii Thermal Resistance
a. For 9.5 mm thick board – 0.06 m2 K/W
b. For 12.5 mm thick board – 0.08 m2 K/W
c. For 15 mm thick board – 0.09 m2 K/W
iii Fire Propagation
a. Fire Propagation
Index of performance not exceeding 12 and a sub index not exceeding 6 (when each side is tested separately to BS
b. Surface spread of flame Class 1 (both sides) as / test to BS 476 Part – 7).
Gypsum boards shall be of specified thickness, and of specified finish (painted / prelaminated). The Gypsum
`boards shall be screw fixed to the under side of false ceiling grid system with 12.5 mm dry wall screw @ 230 mm
C/C by drilling machine. Joint in the board shall be finished flush with fillers, finisher and primer as per
manufacturer’s recommendation to give a seamless finish.
Necessary cut-outs for Electrical / AC and other fixtures shall be provided with a framing of wall channels. In case
of fixing on modular grid system, the boards shall be cut to required size and fixed in the same manner as in
The finished false ceiling shall be perfectly leveled and aligned, at desired height as per drawings.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
E TENDER ABR SBM-G DHOLKA- 4 GP.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].