| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹40.3 LAccepted-AOC | ₹40.3 L | L1 | Accepted-AOC L1 EXECUTED AGREEMENT |
| 2 | L2₹41.9 LRejected-AOC | ₹41.9 L | L2 | Rejected-AOC L1 EXECUTED AGREEMENT |
| 3 | L3₹46.1 LRejected-AOC | ₹46.1 L | L3 | Rejected-AOC L1 EXECUTED AGREEMENT |
| 4 | Not Admitted-Fee/PreQual/Technical/Finance | - | - | Not Admitted-Fee/PreQual/Technical/Finance Others-bidders valid registration certificate EXPIRED ON 31-03-2023 |
| Sl No | Description | Qty | Unit | PURUSHOTHAMAN P. L2 | Mukundan P. L3 | M P MUSHTHAK L1 |
|---|---|---|---|---|---|---|
| 1.00ROAD | ||||||
| 1.00 | 11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 IV. R.C.C grade M 20 | 54.75 | cum | 8,300 ₹4.5 L | 8,787 ₹4.8 L | 8,627.36 ₹4.7 L |
| 1.00 | 11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 | 1.37 | tonne | 80,000 ₹1.1 L | 88,000 ₹1.2 L | 87,640.85 ₹1.2 L |
| 1.00 | 2.3.A.1:Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201. A. Lead upto 100 m (i) Girth above 300 mm to 600 mm | 115 | each | 300 ₹34,500 | 1,000 ₹1.1 L | 632.38 ₹72,723.70 |
| 1.00 | 4.11.2:Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii) Using Gravel mix soil. | 273.75 | cum | 2,540 ₹7.0 L | 3,077 ₹8.4 L | 2,169.13 ₹5.9 L |
| 1.00 | 4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead | 273.75 | cum | 3,480 ₹9.5 L | 3,480 ₹9.5 L | 3,277.42 ₹9.0 L |
| 1.01 | 5.1.1a:Prime Coat :- Low porosity Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 | 1,825 | sqm | 73.17 ₹1.3 L | 73.17 ₹1.3 L | 72.09 ₹1.3 L |
| 1.01 | 5.2.3a:Tack Coat <br>Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. | 1,825 | sqm | 15.2 ₹27,740 | 15.2 ₹27,740 | 15.57 ₹28,415.25 |
| 1.01 | 5.11.2.B.2a:Mix Seal Surfacing - Mechanical Means - Type B - Bitumen S-65 Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 By Mechanical Means :- Type B (II) Bitumen (S-65) | 1,825 | sqm | 254.1 ₹4.6 L | 254.1 ₹4.6 L | 197.6 ₹3.6 L |
| 2.00SIDE PROTECTION | ||||||
Updated dates
Tender Value
₹42.3 L
EMD Value
₹50,000
Closing Date
20 Jan 2026, 6:00 pmClosed
Executive engineer,HED malappuram
OFFICE OF THE EXECUTIVE ENGINEER MALAPPURAM DIVISION PONNANI
contractors own earth , GSB and WMM BT Road,DR Masonry and Geotextile
2025_HED_822765_1
HED/CEHED/TR/774/2024_5_1_1/1
Open Tender
Civil Works - Roads
300 days
VETTOM
Please refer Tender documents.
11 documents required · 11 mandatory
₹2,760
Yes
₹50,000
Yes
25 May 2026
19 Dec 2025
22 Jan 2026
21 Dec 2025
20 Jan 2026
21 Dec 2025
19 Dec 2025 - 6 Jan 2026
11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 IV. R.C.C grade M 20
11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202
2.3.A.1:Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201. A. Lead upto 100 m (i) Girth above 300 mm to 600 mm
4.11.2:Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. (ii) Using Gravel mix soil.
4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead
5.1.1a:Prime Coat :- Low porosity Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
5.2.3a:Tack Coat <br>Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503.
5.11.2.B.2a:Mix Seal Surfacing - Mechanical Means - Type B - Bitumen S-65 Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 By Mechanical Means :- Type B (II) Bitumen (S-65)
SIDE PROTECTION
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
GEOTEXTILE
OD5016/2024-2025:Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free movement of water without creating any uplift head on the pitching.
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
viewsbd.pdf
Tender Documents • 2.44 MB
BOQ_1378933.xls
BOQ • 0.31 MB
viewnit.pdf
Tender Documents • 0.03 MB
regi.pdf
Additional Documents • 0.03 MB
pre.pdf
Additional Documents • 0.21 MB