Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹39.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | Rejected-Technical | - | Rejected-Technical Not qualified |
Tender Value
Refer Docs
EMD Value
₹81,173
Closing Date
10 Mar 2026, 4:00 pmClosed
G.M,BKTPP
Bakreswar Thermal Power Project,P.O. - BkTPP, District-Birbhum Pin - 731104
BIENNIAL CONTRACT FOR BREAKING AND SHIFTING OF REJECTED STONE BOULDERS FROM CHP TO DUMPING YARD AT BKTPS.
2026_WBPDC_1001190_1
WBPDCL/BKTPP/NIT/E4085/25-26
Open Tender
Miscellaneous Services
Percentage
730 days
BKTPP
As per NIT.
4 documents required · 4 mandatory
₹0
₹81,173
Yes
BKTPP
28 Jul 2026
18 Feb 2026
13 Mar 2026
18 Feb 2026
10 Mar 2026
25 Feb 2026
24 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Breaking of stone boulders at platform of Track Hopper #1, 2 & wagon Tippler area and stacking of same coal boulders at some earmarked area within a distance of 500m to facilitate the loading and unloading as per direction of the Engineer-in-Charge. | - | tonne | - | - |
| 1.02 | Carriage & disposal of stone boulders (more than 250 mm size)from CHP site (mainly from Track Hopper, Wagon tippler area,TP#2 area, Conv. 3A/B area, Conv. 2A/B area, FOB area etc.)to various areas within BkTPP plant, township area & U#6 area by means of manpower & machineries full loading at lifting point including weighment (tare weight and gross weight for each trip) at weigh bridge and complete unloading at dumping zone as per direction of the EIC | - | tonne | - | - |
| 1.03 | Carriage & disposal of stone boulders (less than 250 mm size)from CHP site (mainly from area below different conveyor belt area) to various areas within BkTPP plant area by means of manpower and machineries full loading at lifting point including weighment (tare weight and gross weight for each trip) at weigh bridge and complete unloading at dumping zone as per direction of the EIC within BkTPP area. | - | tonne | - | - |
| 1.04 | Carriage & disposal of stone boulders of any size from CHP site(mainly from track hopper, wagon tippler area) to different areas like Bk. DAM, Ash pond etc. beyond Main Gate (Zilla Parishad) by means of manpower and machineries full loading at lifting point including weighment (tare weight and gross weight for each trip) at weigh bridge and complete unloading at afore mentioned area as per direction of the EIC. | - | tonne | 1 | - |
| 1.05 | Cost of PPE for workers. Helmet 01no./ 2 year; Safety shoe Bata or similar make - 01 no./ 2 year; Hand Gloves - 01no./6 month; Rain Coat 01no./ 2 year, Nose Guard - 01 no. / 6 months, Ear Plug 01 no./ 6 months as per requirement and as per direction of EIC. (Payment will made on submission of gate entry challan & original bill as per market rate after issuance to the workers) | - | AU | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.12 MB
BOQ_2453292.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .