| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹35.9 LAccepted-AOC | L1 | Accepted-AOC Agreement Executed | |
| 2 | L2₹37.3 L+₹1.4 L (3.88%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹33.9 L
EMD Value
₹50,000
Closing Date
18 Jan 2024, 6:00 pmClosed
Executive Engineer pazhassi Irriga
Office of the Executive Engineer pazhassi Project Division No 2 Kannur 670002
GENERAL Pathiriyad Distributary PyIP Desiltation and repair of aqueducts of Pathiriyad Distributary of Mahe Branch Canal for the year 2023 24 General Civil Work
2024_Irrig_642490_1
IRR/PI/TR/3667/2023_5_1_1/1
Open Tender
Civil Works - Canal
Item Rate
365 days
PATHIRIYAD
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹50,000
Yes
18 Mar 2024
10 Jan 2024
22 Jan 2024
10 Jan 2024
18 Jan 2024
10 Jan 2024
Amount
Appendix 1- Desilting and Felling trees
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
OD8242/2023-2024:Removing and cleaning the deposited silt from the UT/Flume by mechanical<br> means (Hydraulic Excavator)/manual means including providing safety measures like oxygen mask, lighting<br> arrangement and getting out the excavated silt and other debris within a distance of 50metre and including<br>all labour charges , watering charges etc complete as per the direction of officers at site All kinds of soil<br>Details of cost for 10 cum.<br>MACHINERY:
2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth
2.33.2:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 60 cm girth up to and including 120 cm girth
2.33.3:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyond 120 cm girth up to and including 240 cm girth
50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete.
Appendix 2 - Rectification of pillar of aqueducts
26.28.1:Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge75mm average thickness
26.29.1:Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge.Bars upto 12 mm diameter
OD7243/2023-2024: Applying corrosion inhibitor one coat of nitozinc / approved equivalent make primer (two component system based on metallic zinc and epoxy resin and shall be mixed until a homogenous mixture is obtained) on the cleaned and dried reinforcing bar using a small paint brush such that the zinc rich primer coated should make an unbroken continuous film on the bars. ( If in doubt of having achieved an unbroken coating, a second application should be made as soon as the first coat is fully dry). After drying the treated surface, apply one coat of bonding agent Nitobond A R/SBR. Measurement is made for whole exposed area including cost of materials, labour charges, conveyance of materials to site, hire charges of tools etc complete
26.31.2:Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect.Epoxy bonding adhesive having coverage 2.20 sqm/kg of approved make
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
26.33.2:Providing, mixing and applying SBR polymer (of approved make @ minimum 2% by wt. of cement used) modified plain/reinforced cement concrete for structural members having minimum characteristic compressive strength [with ordinary portland cement, coarse sand and graded stone aggregate of 10mm maximum size in proportion as per design criteria] with specified average thickness. Note: Rates shall be for finished surface area of concrete and shall include the cost of labour, concrete and appropriate approved Super-Plasticiser for rendering concrete as flowable and SBR polymer but shall exclude cost of reinforcement, bond coat, Shear Keys, centering and shuttering, strutting, propping etc (Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding/tapping with a blunt metal instrument)75mm thick in Grade M 25 with cement content not less than 330 kg per cum
26.32.1:Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. Note: Measurement and payment: The pre-measurement of thickness shall be done just after the surface preparation is completed and Payment under this item shall be made only after proper wet curing has been done and surface has been satisfactorily evaluated by sounding / tapping with a blunt metal instrument and/or the 75mm size cube crushing strength at the end of 28 days to be not less than 30 N/Sqmm2).12 mm average thickness.
Appendix 3 - Canal Lining -Pathiriyad Dist. near Ch : 1/475km
2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
OD7247/2023-2024:Laterite roughly dressed stones of size 30 x 20 x 20 cm laid dry masonry including cost and conveyance of all materials and all labour harges etc complete.
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
Appendix 4 - Flume construction -Sankaranellur FB near Ch 0/500km
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for: Edges of slabs and breaks in floors and wallsUnder 20 cm wide
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
SHUHAIB N P
Bidder Name
shabeer
SHUHAIB N P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_981116.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .