Tender Value
₹97.2 L
EMD Value
₹1.9 L
Closing Date
25 Feb 2026, 4:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
ENGGCONNJP
30 conditions · 2 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:
Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, Or
Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, Or
One similar work each costing not less than the amount equal to 60% of advertised value of the tender.
In case of composite works tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited
Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, Or
Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, Or
One similar work costing not less than the amount equal to 60% of advertised value of each component of tender.
Note for A (ii): Separate completed works of minimum required values 1.4.4 shall also be considered for fulfillment of technical eligibility criteria for different components.
Note: (a) The 'work' includes subletted works also, if awarded to subleting contractor with the approval of main client. The work experience certificate of subletted work should be issued by the main client only, to be eligible for consideration. To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the 1.4.5 subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfillment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Engineer in writing.
Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover o f R s 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate 1.4.6 has been issued by a person authorized by the Public listed company to issue such certificates. In c a s e tenderer submits w o r k experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details o f payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender.
In case a work is started prior to 07 (seven) years, ending last day of month previous to the one in which tender is invited, but completed in last 07 (seven) years, ending last day of month previous t o the one in which tender i s invited, t h e completed w o r k shall be considered for fulfillment of credentials.
If a work is physically completed and completion certificate to this extent is issued by the concerned organization b u t final bill i s pending, such work shall be considered for fulfillment of credentials
In case of completed work, the value of final bill (gross amount) including the PVC amount (if paid) shall be considered as the completion cost of work. In case final bill is pending, only the total gross amount already paid including the PVC amount (if paid) shall be considered as the completion cost of work. In case of substantially completed work, the total gross amount already paid including the PVC amount (if paid), as mentioned in the certificate, shall be considered as the cost of substantially completed work.
If a bidder has successfully completed a work as subcontractor and the work experience certificate has been issued for such work to the subcontractor by a Govt. Organization or public listed company as defined in Note for Item 2(A) Para 2 of the Tender above, the same shall be considered for the purpose of fulfillment of credentials
In case a work is considered similar in nature for fulfillment of technical credentials, the overall cost including the PVC amount (if paid) of that completed work or substantially completed work, shall be considered and no separate evaluation for each component of that work shall be made to decide eligibility
Similar nature of work : Any work of Geotechnical investigation and soil exploration.
4 conditions · 2 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
I/ We have visited the works site and I / We am / are aware of the site conditions.
Conducting geotechnical investigations along with preparation & submission of final report foundation of bridges (Major, Minor, RUB & LHS), station building and embankment in connection with Alubari Road-Thakurganj BG doubling project of N. F. Railway.
DyCE-CON-GEOTECH-NJP-01~NFRCON
DyCE-CON-GEOTECH-NJP-01
Open
Works - General
3 Months
Jalpaiguri, West Bengal
₹0
₹1.9 L
25 Feb 2026
3 Feb 2026
11 Feb 2026
33 items across 2 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 97,22,208.34 | ||
| — | 580.00 | — | — | ||
| Exploratory drilling of Boreholes down to required depth, drilling of 150mm diameter boreholes in all type of soils except hard rock and large boulders (boulder core more than 30cm), including refilling, reinstating surface and disposing off surplus material including use of mechanical rigs with power operated winches as well as percussion / chiselling tool for advancing through occasional seams of hard strata to be employed where necessary in River bed area including standing/flowing water with all necessary arrangements except making of platform under water which shall be paid under relevant item of SOR. 0m to 10m | — | — | — | 10,25,601.68 | |
| — | 400.00 | — | — | ||
| Exploratory drilling of Boreholes down to required depth, drilling of 150mm diameter boreholes in all type of soils except hard rock and large boulders (boulder core more than 30cm), including refilling, reinstating surface and disposing off surplus material including use of mechanical rigs with power operated winches as well as percussion / chiselling tool for advancing through occasional seams of hard strata to be employed where necessary in River bed area including standing/flowing water with all necessary arrangements except making of platform under water which shall be paid under relevant item of SOR. 10m to 20m | — | — | — | 7,25,193.91 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
1.TGeotechNIT.pdf
ATTACHMENT
2.TGeotechChapter-1.pdf
ATTACHMENT
3.TGeotechChapter2.pdf
ATTACHMENT
4.TGeotechChapter3-4-5.pdf
ATTACHMENT
5.TGeotechChapter6to9.pdf
ATTACHMENT
6.TGeotechChapter10.pdf
ATTACHMENT
7.TGeotechChapter11.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .