Loading…
Tender ID
Tender Value
₹81.9 L
EMD Value
₹1.6 L
Closing Date
20 Mar 2026, 3:00 pmClosed
CHIEF ENGINEER
NAGAR NIGAM BAREILLY
Construction work of rcc drain and bricks drain from nasheman colony to akash ganga colony and nisha enclave in ward 17.
2026_DOLBU_1124533_1
417/CE/CD/25-26 (1 To 20) Sr No 6 Tender List 24 Date-11.03.2026
Open Tender
Civil Works
Percentage
180 days
BAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹9,676
Bareillye-tender.com
₹1.6 L
13 Mar 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
Dismantling of cement concrete or brick or granolithic floors.including base concrete and stacking of dismantlled materials as directed by E/I.within a distance of 60.00M.(S.I.No.697)
Dismantling of old damage brick work and stone work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M. (S.I.No.692)
Excavation in foundation in ordinary Soil (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. excluding royalty.( S.I. No.251)
Excavation in foundation in ordinary Soil (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. excluding royalty.( S.I. No.251)
Cartage of Surplus malwa upto 5km.
Providing and laying cement concrete in 1:4:8 (1 cement : 4 C sand : 8 stone ballast 40 mm gauge) and curing complete, including cost of form work in foundation and floors-completion of the work as per direction of E/ I.
R.C.C. work with cement,approved coarse sand and 4cm gauge stone ballast in proportions of 1:2:4 in raft and foundation excluding supply of reinforcement and its bending but including its fixing & binding the same with 24 B.W.G G.I wire and including necessary centring and shuttering etc.and also including supply of all materials labour ,tools & plants etc required for proper completion of work. Binding wire cost being included in the item,(S.I.No.287)
R.C.C. work with cement,approved coarse sand and 4cm gauge stone ballast in proportions of 1:1.5:3 in wall and coloumn excluding supply of reinforcement and its bending but including its fixing & binding the same with 24 B.W.G G.I wire and including necessary centring and shuttering etc.and also including supply of all materials labour ,tools & plants etc required for proper completion of work. Binding wire cost being included in the item,(S.I.No.289)
RCC 1:2:4 with cement c'sand stone grit of 20 mm gauge in slab of culvert excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. SI No. 284
Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as per E/I SI No. 504
S/L of empty cement bags filled with local earth sand and carriage upto site of work including stiching loading and unloading stackimg and also including supply of all material, labour T&P required for proper complition of the work etc. as per direction of E/I as per NEW ITEM No. 1
Providing cost of Dewatering I/C cost of boaring, laying of 4" dia PVC pipe, hire charges of pump set with diesel PVC pipeall omplete As per Non Schedule Item No. A
Close Timbering in trenches including struting, shoring and packing cavities (Wherever required) complete (Measurments to be taken of the face of area timbered)
Providing Barricading for three days with sall ballies having certical posts (dia 10-15cm) at distance 2.1 mtr c/c and horizontal ballies (dia 7.50-10cm) in three row including digging holes for fixing certicla post and binding with nariyal role complete. Height of vertical post should not be less than 1.8m above ground level and it should be minimum 0.45m below ground level. The job work includes erection & dismantling of barricades and also includes reffilling of dugged holes after dismantling of barricades. As per Non Schedule Item No. 10
Providing and laying cement concrete in 1:6:12 (1 cement : 6 Fine sand : 12 Brick ballast 40 mm gauge) and curing complete, including cost of form work in foundation and floors-completion of the work as per direction of E/ I. (S.I No. 273)
First class B/w in 1:4 Cement C'sand mortor in F/P including supply of all meterial labour T&P etc required for proper completion of work SI N0.305
12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimume thickness not less then 10 mm including all supply of meterial , Labour T&P etc S.I.No. 584(i)
Providing and laying cement concrete in 4:2:1 of not less than strength of M-150 stone ballast (20 mm nominal size), approved coarse sand and cement, curing complete including of cost of form work in foundation and floors-completion of the work as per direction of the E / I.
Deduction cost of brick bats
Deduction cost of bricks
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 17.78 MB
BOQ_2095600.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .