Executive Engineer (O&M), DGVCL Bharuch Rural Division
Annual Rate contract for Erection and Maintenance work of HT/LT Line and TC Structure and Laying, Testing & Commissioning of 11/22KV underground XLPE cable with cable end termination & straight though jointing kits under Wire Free City & Various Scheme under Amod & Other Sub Division under Bharuch Rural Division.
308144
BRH-2026-27-26
Open
Electrical and Maintenance Works
Bharuch
1 document required · 1 mandatory
₹2,360
Executive Engineer DGVCL, Bharuch
₹45,000
25 May 2026
25 May 2026
25 May 2026
4 Jun 2026
25 May 2026
1 Estimated cost Rs.
2 Tender fee [Non-refundable]
4 Last Date of downloading & Online submission of bid
5 Technical Bid Opening
6 Price Bid Opening
7 Time Limit of Work contact order 12 Months
1 The contractor has to sign on each tender documents and attach online. No physical documents
will be considered.
2 All works will have to be carried out as per specification and conditions of the contract.
3 Tender fee & EMD received by online mode (NEFT/RTGS/Net Banking) before last date of submission
of bid alone will be taken into consideration. Bidder has to attach slip of online transection receipt with
tender documents.
Below mentioned documents of tender must be uploaded in the form of scanned
documents (notarized/self-attested) in pdf form and shall remain legible and
should not be password protected.
A. Tender notice, Tender copy and Schedule-B.
B. Tender fee & EMD payment receipts.
C. PF registration.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
E. Partnership deed (In case of Partnership firm)
F. Electrical Contractor license.
G. Register copy of GST No.
H. Average Annual financial turnover during the last 3 years ending 31st March of the previous financial
year should be at least 30% of the tender value.
I . Experience of having successfully completed similar works during last 7 years ending last day of
month previous to the one in which Bids are invited should be either of the following.
a. Three similar completed works costing not less than the amount equal to
40% of the tender value.
b. Two similar completed works costing not less than the amount equal to
50% of the tender value.
c. One similar completed works costing not less than the amount equal to
80% of the tender value.
- Definition of similar; erection of HT, LT,TC and Laying, Testing & Commissioning of 11KV & above
class underground XLPE cable with cable end termination & straight though jointing kits.
J. Solvency Certificate of 20% amount of tender value
K. Undertaking in regard to Stop Deal / Black List Thereof As per ANNEXURE-A & Undertaking in regard
to Relationship with employee As Per ANNEXURE-B (On Letter head by properly filling all the data)
L. Insurance Copy
M. Appendix and Annexure
N. Technical Specifications & GTP’s
O. Labor License
All above documents (A to L) are mandatory. Bidder have to attach properly visible documents in pdf
format. Attach tender required documents only as per above list.
Seal & Signature of Contractor Executive Eng.
Bharuch Rural Division.
SECTION 1: INSTRUCTIONS TO BIDDERS
This part, Instruction to Bidders (ITB), Section-1 of the Bidding Documents provides the information
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
necessary for bidders to prepare responsive bids for laying of underground HT cable network with
terminations under Bharuch Industrial Division area. The Bharuch rural Division hereinafter called 'Owner'
will receive bids in respect of laying of underground HT cable network with terminations to be furnished in
the accompanying specifications. All bids shall be prepared and submitted by bidders in accordance with
2 GENERAL INSTRUCTION
2.1 The Executive Engineer, Bharuch rural Division having its Office at, Bharuch Circle / Division, hereafter
called the "Bharuch rural Division" intends to invite tender for laying of underground HT cable network
with terminations under Bharuch rural Division area.
2.2 The interested Bidder can download the Bid document from the website at www. DGVCL.com from 11-
05-2026. The complete Bidding Documents shall be available at Government e-procurement
portal http://tender.nprocure.com from 22-05-2026 up to 04-06-2026 .
2.3 Bids submitted after the time and date fixed for receipt of bids as set out in the INVITATION to Bid shall
2.4 The works referred herein shall cover the entire scope of the Bid which include as per describe in scope
of work, laying of cable testing and commissioning under selected Bharuch rural Division area, including
the successful completion of performance and tests which the Bharuch rural Division desires to get
2.5 The issuance of bid document would not mean that the bidder has qualified for the bidding. Hence
bidders should ensure themselves of their credentials before submitting their offer.
2.6 Documents towards payment of Tender fee and earnest money deposit (EMD) should be kept in the
Tender Fee and EMD cover only. First the Tender Fee & EMD cover will be opened and if the documents
towards payment of Tender fee and EMD are found in order then only online techno-commercial bid shall
be opened first. All those who are found technically and commercially competent to carry out the job will be
considered as qualified bidders and only their price bid will be opened.
2.7 At any time prior to the deadline for submission of bids, Bharuch rural Division may, for any reason,
whether at its own initiative or in response to a clarification requested by the Bidders, may modify the
terms and conditions by issuing amendment in the DGVCL website, bidder must be vigil as this addenda`s
will be uploaded only.
2.8 Bharuch rural Division reserves the right to spread / split the order, if required.
2.9 Bidder does not anticipate change in the ownership during the proposed period of work. (If such a
change is anticipated, the scope and effect thereof shall be defined.
2.10 Bharuch rural Division reserves the rights to instruct the contractor for carry out the works anywhere
in the jurisdiction of Bharuch rural Division and accordingly contractor shall carry out the work as per the
same rate and terms and condition of contract.
2.11 If at any stage it is found that bidder had hidden material information or had submitted information
which is false and fraudulent shall be debarred from bidding in Bharuch rural Division, tender for three
years and EMD shall be forfeited. The matter shall also be brought to notice to the registration authority of
2.12 The bidder shall be disqualified if;
a. The bidder had made misleading or false representation in the forms, statements and attachment
submitted in proof of qualification requirements and/or
b. A record of poor performance such as abandoning the work, not properly completing the contract,
inordinate delays in completion, litigation history or financial failures etc.
c. Every bidder should at the time of submission of bid, give a declaration that bidder and / or
proprietor / partner / director of the firm has not been placed on stop dealing / banned for business dealing /
blacklisting by GUVNL and its subsidiary companies.
The bidder should provide accurate information on litigation and/ or arbitration resulting from contract
completed or under execution by him over the last five years. A consistent history of arbitration awards/
judgments against the applicant or any partner of a joint venture may result in disqualification for proposed
work. If the details of litigation history are hidden by the applicant and later on it comes to knowledge of
the employer the bidder shall be disqualified for the proposed work and other appropriate actions shall be
taken against the bidder.
DGVCL would have the right to forfeit the EMD and black list to the bidder if any of the information given
by the bidder is found false / wrong or incorrect or misleading.
3 Bid Submission and Contents of Standard E-Bidding Document
3.1 The Bidders must ensure that all the schedules are completely filled in their Bids and the information
called for is given in totality. A set of complete Bid documents is required to be submitted duly
signed and stamped by authority competent to sign on behalf of bidder on each page of bid as
well as amendment thereof as a token of unconditional acceptance to the conditions of various
clauses of Bid documents through online mode on e-procurement module. The bidder's bid and
the documents attached there to shall be considered for forming part of the contract documents.
3.2 Tender fee & EMD received online (NEFT/RTGS/Net Banking) will only be taken into consideration.
Bidder have to attach slip of online transection receipt with tender documents.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
3.3 The Bidder has to send the Technical Bids and PRICE BID ON LINE only. No physical submission is
3.4 The Bharuch rural Division reserves the right to reject any bid, which is not submitted according to the
instructions, stipulated above.
3.5 The e-Bid document includes submission of following documents in stages:
Stage-1: Preliminary Qualifying Details (Online):
(b) Earnest Money Deposit
(c) Copy of GSTN Certificate
(d) Permanent Account Number (PAN Card)
(e) Techno-Commercial Details (Online Only):
4 QUALIFYING CRITERIA
Qualification of bidder will be based on meeting the criteria as specified in qualifying criteria Part-A and
qualifying criteria Part-B as demonstrated by the Bidder’s responses in the corresponding Bid Schedules.
Subcontractors’ technical experience and financial resources shall not be taken into account in determining
the Bidder’s compliance with the qualifying criteria. The bid can be submitted by an Indian individual firm
only. Joint Venture firms are not allowed.
Notwithstanding anything stated herein above, the Bharuch rural Division reserves the right to assess the
capacity and capability of the bidder, should the circumstances warrant such assessment in an overall
interest of the Bharuch rural Division. The Bharuch rural Division reserves the right to waive minor
deviations if they do not materially affect the capability of the Bidder to perform the contract.
ELIGIBILITY FOR QUALIFICATION:
4.1 Part-A: Technical:
4.1.1 The bidder should possess Electrical Contractor license issued by the Office of Govt. of Gujarat. The
contractors outside of Gujarat State must have to take approval from Government of Gujarat for Electrical
Contractor license.
4.1.2 Work experiences of the bidder shall be considered only if the works have been executed under Public
electrical utility of Central or State Govt. in India / Government Sector / Power Utility (Government or
Private) / Power sector PSUs & Power Sector CPSUs / private Developer under SITC Option II as per
applicable rates of Supervision Charges to DGVCL & state DISCOMs However SITC/ Option -2 Bidders
need to note that the labor portion of their work orders alone will be considered for evaluation against the
qualification criteria for determining eligibility. The labor potion of awarded work either need to be
separately shown in work order or certified in performance certificate from the client.
4.1.3 For qualifying the experience criteria; bidder shall submit Copy of Work Order (showing the statement
of quantity & amount in Rs.), work completion certificate (showing amount of actual work completed) for
the work completed before one year and said system / project is performing satisfactorily as on submission
of bid, from respective authority / client.
4.1.4 Bidder has to submit the copy of complete type test reports / certificates of offered make of major
supply items like HDPE Pipe, Indoor & Outdoor Termination Kits, Straight Joints (Any make approved by
GUVNL & Its Subsidiaries Company) as required in under-ground cable laying work. The Certificates /
reports should not be older than 7 (Seven) years.
4.1.5 Bidder has to provide the authorization letters from the manufacturer / authorized dealer of offered
make material. Guarantee also required from bidder as well as OEM / authorized dealer.
4.1.6 Experience as a sub-contractor shall not be considered for technical evaluation.
4.1.7 The above stated criteria are minimum and the Bharuch rural Division reserves the right to request
for any additional requirement and also reserves the right to reject the bid of any bidder, if in the opinion of
the Bharuch rural Division, the qualification criteria are not fulfilled.
4.1.8 Bidder must have Skilled Supervisor having Supervisor License & Skilled Technical staff & labour for
execution of work.
4.1.9 Bidder must own cable fault locator van / kit to identify cable fault location & HDD Machine for push
through work. If not, as an alternative, bidder should have out-sourced contract service facility with such
agency. For the same bidder must have to submit MOU (Memorandum of Understanding) with such agency
on Rs. 300/- non judicial stamp paper duly signed by respective authorized representative and notarized.
The registration and purchase details of equipment along with MOU shall be submitted with the bidding
Note: For tender estimated value below 5 Lakhs & ARC tender of estimated value more than Rs.
Lakhs, criteria stated at clause no. 4.1.2 & 4.1.3 shall not be applicable for New Bidders. Quantity
Allocation to new Agency up to 10% to 30 % of tender Amount/Quantity may be kept if tender
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
value more than Rs 5 lacs for ARC Tender .
4.2 Part-B: Commercial: For the purpose of this bid, the bidder shall meet the following minimum criteria
in past 7 years ending last day of month previous to the one in which bids are invited:
4.2.1 Similar Nature of Work: The bidder should have successfully completed or substantially
completed similar nature of work i.e. Under Ground Cable Laying Work for 11kV and above class
in last 7 years ending last day of month previous to the one in which bids are invited should be
either of the following:
The amount of work completed by bidder as per work completion certificate shall be considered.
i. (a) Experience in single completed work of projects execution not less than the amount equal
to 80% of the estimated amount of the project any under Public electrical utility of Central or
State Govt. in India / Government Sector / Power Utility (Government or Private) / Power sector
PSUs & Power Sector CPSUs / private Developer under Option II as per applicable rates of
Supervision Charges to DGVCL & state DISCOMs along with submit Copy of Work Order (showing
the statement of quantity & amount in Rs.), work completion certificate (showing amount of
actual work completed and Invoice with GST) for the work completed before one year and said
system / project is performing satisfactorily as on submission of bid, from respective authority /
client. Preferably in the state of Gujarat or other state utility/DGVCL in last 7 (Seven) years,
ending last day of month previous to the month in which tender is invited.
(b) The work experience of subcontract shall not be considered.
The Bidder shall submit the details of project/work executed invariably along with its
authentication i.e. work completion and performance certificate from the work order (AT) issuing
authority as per prescribed format for evaluation. The work completion certificate and
performance certificate issued by work order (AT) issuing authority shall be considered for
evaluation. The amount of work completion certificate with GST shall be considered for
ii. (a) Experience in two completed work of projects execution not less than the amount equal
to 50% of the estimated amount of the project any under Public electrical utility of Central or
State Govt. in India / Government Sector / Power Utility (Government or Private) / Power sector
PSUs & Power Sector CPSUs / private Developer under Option II as per applicable rates of
Supervision Charges to DGVCL & state DISCOMs along with submit Copy of Work Order (showing
the statement of quantity & amount in Rs.), work completion certificate (showing amount of
actual work completed and Invoice with GST) for the work completed before one year and said
system / project is performing satisfactorily as on submission of bid, from respective authority /
client. Preferably in the state of Gujarat or other state utility/DGVCL in last 7 (Seven) years,
ending last day of month previous to the month in which tender is invited.
(b) The work experience of subcontract shall not be considered.
The Bidder shall submit the details of project/work executed invariably along with its
authentication i.e. work completion and performance certificate from the work order (AT) issuing
authority as per prescribed format for evaluation. The work completion certificate and
performance certificate issued by work order (AT) issuing authority shall be considered for
evaluation. The amount of work completion certificate with GST shall be considered for
iii. (a) Experience in three completed work of projects not less than the amount equal to 40% of
the estimated amount of the project any under Public electrical utility of Central or State Govt.
in India / Government Sector / Power Utility (Government or Private) / Power sector PSUs &
Power Sector CPSUs / private Developer under Option II as per applicable rates of Supervision
Charges to DGVCL & state DISCOMs along with submit Copy of Work Order (showing the
statement of quantity & amount in Rs.), work completion certificate (showing amount of actual
work completed and Invoice with GST) for the work completed before one year and said system /
project is performing satisfactorily as on submission of bid, from respective authority / client.
Preferably in the state of Gujarat or other state utility/DGVCL in last 7 (Seven) years, ending last
day of month previous to the month in which tender is invited.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
(b) The work experience of subcontract shall not be considered.
The Bidder shall submit the details of project/work executed invariably along with its
authentication i.e. work completion and performance certificate from the work order (AT) issuing
authority as per prescribed format for evaluation. The work completion certificate and
performance certificate issued by work order (AT) issuing authority shall be considered for
evaluation. The amount of work completion certificate with GST shall be considered for
* However SITC/ Option -2 Bidders need to note that the labor of their work orders alone will be
consider for evolution evaluation against the qualified criteria for determining eligibility. The
labor potion of awarded work either need to be separately shown in work order or certified in
performance certificate from the client.
4.2.2 Minimum Average Annual Turnover (MAAT) for last three years, ending 31 st March of the previous
financial year, of the bidder should be at least 30% of the estimated cost of the tender. In this regard,
separate notarized certificate from CA must be submitted.
4.2.3 Net-worth of the last Financial Year shall be positive.
Note: Turnover & Net-worth shall be certified by CA on his letter head and duly attested. Turnover for
preceding year shall be considered subject to submission of provisional / audited certificate from CA by the
4.2.4 Separate EPF Code No. allotted by RPFC & last six months of current year EPF Challan paid copy is
4.2.5 Details of Partners/Directors of the Firm/Company.
· Partnership deed in case of Partnership Firm
· Memorandum of Association & Article of Association in case of Company
4.2.6 GSTN Certificate & Permanent Account Number (PAN Card).
4.2.7 Group Insurance: A copy of the valid insurance policy of the insured labourer’s under W.C. Act. The
contractor shall renew the same till completion of the contract.
4.2.8 Available Bid Capacity:
The bidder who fulfills the qualifying criteria mentioned above shall be qualified only if he fulfills the
requirement of bidding capacity i.e. sum of value of all contracts on hand plus value of this bid should be
less than twice the Average Annual Turnover of Last three financial years.
The bidder’s capacity shall be computed as shown below.
A = Sum of value of all contracts on hand in Rs.
B = Estimated cost of this bid in Rs
C = Average Annual Turnover of Last three financial years in Rs.
If; A + B < 2 X C then qualified, else disqualified.
For the same, bidder shall have to submit the details of works on hand as per attached Annexure–IV.
Note: For tender estimated value below 5 Lakhs & ARC tender of estimated value more than Rs.
Lakhs, criteria stated at clause no. 4.2.1, 4.2.3 & 4.2.8 shall not be applicable for New Bidders.
Quantity Allocation new be Agencies up to 10% to 30% of tender Amount/Qty may be kept if
tender more than Rs. 5laks for tender.
5 SCOPE OF WORK
5.1 Bidder has to maintain the records of allotted cable drum with actual cable length. Cable length
must be measured before laying. Cable joints are to be done as per requirement only and length of cable
must be utilized accordingly.
5 . 2 Cable is to be laid in trench as per instructions of Engineer-in-Charge. While the shortest
practicable route should be preferred, the cable route shall generally follow fixed developments such as
roads, foot paths etc. with proper offsets so that future maintenance, identification etc. are rendered easy.
Cross country run merely to shorten the route length shall not be adopted. Cable route shall be planned
away from drains and near the property, especially in the case of LV/MV cables, subject to any special local
requirements that may have to be necessarily complied with. As far as possible, the alignment of the cable
route shall be decided after taking into consideration the present and likely future requirements of other
services including cables enroute, possibility of widening of roads/lanes etc. Corrosive soils, ground
surrounding sewage effluent etc. shall be avoided for the routes.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
5.3 Laying of cable, testing and commissioning: Cable trench up to the depth of 1200 mm is to be
dug with width of 300/500 mm as mentioned in schedule (BOQ) / specification in any type of soil. Spreading
of sand at the bottom of the trench up to 100 mm before Lying of power cable in the Centre of the trench.
Spreading of another layer of to 100mm sand above laid cable. Utmost care should be taken while loading /
unloading and unwinding the cable drums. Covering the cable with RCC half round hume pipe 30mm thick,
150mm inner dia., Back feeling the trench so as to make ground level as per original. Erection of 11 KV
XLPE cable on DP structure with fixing of polymer clamps, aluminum tags and with permanent
identification of each cable at top and bottom with permanent identification.
5.4 Whenever cables are laid along well demarcated or established roads, the LV/MV cables shall be
laid farther from the kerb line than HV cables. Cables of different voltages, and also power and control
cables shall be kept in different trenches with adequate separation. Where available space is restricted
such that this requirement cannot be met, LV/MV cables shall be laid above HV cables. Where cables cross
one another, the cable of higher voltage shall be laid at a lower level than the cable of lower voltage.
5.5 Horizontal drilling without damage to surface road should not below 2 mtr from ground level and
putting HDPE/G.I pipe or any other pipe during the execution of U.G network (as per the direction of
Engineer-in-charge). The pipes shall be in conformity to the various relevant IS codes and laying of 11 KV
XLPE cable of different sizes as per site condition & instruction of Engineer in charge. The detail map and
excel sheet (hard copy & soft copy) indicating the respective depth and distance from adjacent land mark
for each segment for HDD is to be submitted as per instructions of Engineer in charge.
5.6 Power and communication cables shall as far as possible cross each other at right angles. The
horizontal and vertical clearances between them shall not be less than 60cm.
5.7 Spare Cable ring near transformer center / DP structure to be provided for future work having
meter and to be buried 1 meter in ground.
5.8 At transformer center; for providing termination cable along with pole structure erected with GI
/ HDPE Pipe. GI / HDPE Pipe confirms to the specifications as per IS and amendment thereof, should be
buried 300mm below ground level and 2700mm above ground supported on DP structure with polymer
cleats. If any case, GI / HDPE Pipe cannot have buried in ground level the same should be concreted at
5.9 Supply and fixing of indoor / outdoor termination kit & Straight Joint Kit (Any make approved by
GUVNL & Its Subsidiaries Company) suitable for XLPE as per size of cable Shown in schedule (BOQ).
5.10 Separate Earthing is to be provided using 25 x 3 mm GI Strip covered by uPVC pipe (Standard
Make) with earth enhancement powder for Outdoor Cable Box.
5.11 Supply and fixing of HDPE/DWC/G.I pipe or any other pipe during the execution of U.G network
(as per the direction of Engineer-in-charge). The pipes shall be in conformity to the various relevant IS
5.12 Cables under railway tracks shall be laid in spun reinforced concrete, or cast iron or steel pipes at
such depths as may be specified by the railway authorities, but not less than 1m, measured from the bottom
of the sleepers to the top of the pipe. Inside railway station limits, pipes shall be laid up to the point of the
railway station limits, pipes shall be laid up to a minimum distance of 3m from the centre of the nearest
track on either side.
5.13 Contractor shall liable to get the approval from Electrical Inspector. After receiving the approval
of Electrical Inspector, system shall be charged in the presence of Engineer-in-Charge.
5.14 Liaisoning for Preparation of site drawing and approval / NOC of Electrical inspector & other local
utilities like telecom networking, GAS, water, drainage, road authority, Maha Nagar Palika, Nagarpalika
etc. is in scope of contractor. The stipulated fees for getting the NOC / way-leave / approval shall be paid
b y Bharuch rural Division, after submission and verification of adequate invoice / demand note from
respective authority.
5 . 1 5 Liasoning with Western Railway Department and their respective competent authority. The
contractor shall acquire the necessary permission from the Railway Authority for carting the cable and
before handing over the cable for actual loading condition.
5.16 While working within railway boundary any damage to the railway infrastructure, asset and / or
system shall be liable to the contractor. The contractor shall have to make the payment of the damage as
assessed by the railway authority.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
5.17 The trench excavation and filling-in shall be so executed that all walls, roads, sewers, drains,
pipes, cables, structures, places and things shall be reasonably secured against risk of injury and shall be
carried out to the satisfaction of the authorities concerned. However, if any, damages to existing services
made, contractor shall arrange and pay for any necessary repair, to make good the damages.
5.18 A pre-warning PVC yellow tap 8-inch-wide and 300 microns thick (LDPE) shall also be laid. The
warning tap shall be printed in RED Letter (In English as well as Gujarati) as “CAUTION: 11000 VOLTS
DGVCL CABLE” and to be placed at about 300 mm to 450 mm depth from ground level along the route of
cable to protect cable from mechanical injuries.
5 . 1 9 Route Markers are to be installed at every 50 / 100 meters length as per requirement,
specification and drawing. It should be put at bends, curves, road crossing etc. of cable route. The marker
should incorporate the following relevant information:
Division Name: Bharuch rural Division
Voltage Class: 11kV Cable
5.20 Empty drums are to be credited at Bharuch rural Division’s respective stores at bidders cost and
risk after successful completion and execution of work. Otherwise recovery will be imposed on bidder.
5.21 Work may be required to be executed in any 66/132/220KV Sub-Stations also.
5.22 Necessary shutdown for connection/jumper of UG cable with existing network will be provided as
per availability or convenience of the Bharuch rural Division which shall be acceptable to the contractor &
contractor shall try to complete the work in minimum time.
5 . 2 3 Construction of Transformer Structure / Double Pole Structure with provision of busbar /
connections / jumper must be as per standard with all required accessories like LA, Box and Fuse etc.
5.24 The Work for the erection of Poles, Guys, Earthing, Transformer and Concreting, Stringing and
Guarding must be done as per standard.
5 . 2 5 Dismantling of existing overhead HT line is in scope of contractor. The material which is
dismantled from site during the execution of work must be credited to respective Divisional stores
immediately after completion of work with complete inventory and measurement details and length to
weigh conversion calculations.
5.26 It is mandatory for the bidder to test the Main and Spare cable for continuous 72 Hrs at load
5 . 2 7 A caution board indicating “CAUTION – CABLE JOINTING WORK IN PROGRESS” shall be
displayed to warn the public and traffic where necessary.
5.28 All the sundries material like Clamps, Screws, nuts, bolts, nails etc. is at Contractor’s cost.
5.29 Any kind of the restoration work to be done by the Contractor during execution of the work.
5.30 In case of any Disputes, Superintending Engineer of Concerned area is the final Authority to take
5.31 Bids not covering the above entire scope of works shall be treated as incomplete and shall be
5.32 Bids containing deviations form will be considered as non-responsive.
5 . 3 3 Any other item not specifically mentioned in the specifications but which are required for
Erection, Laying, Testing, Commissioning and satisfactory operation of the Distribution lines are deemed to
be included in the scope of the specification unless specifically excluded.
5.34 The contractor shall map the complete work on the ‘Geo-Urja’ portal after completion of the
5.35 The contractor shall enter the work details and route in the ‘CBUD’ application before
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
commencing any digging work.
6 STANDARD & REGULATION
The survey, engineering, design, manufacture, erection, cable laying and testing of the equipment’s and
material to be supplied shall comply with latest revisions of relevant Indian Standards or equivalent IEC
standards. In addition, the Indian Electricity Rules, Electricity Act 2003, CEA Regulations, Statutory
requirements of Central Govt., GERC and State Government of Gujarat (applicable codes), shall also be
complied with. Any complications arising out of it will be set right by the bidder without any implication to
DGVCL. The bidder shall submit his offer as per information given in submission of Bid.
The bidder shall quote in the appropriate schedule of bid form on item rate / % above or below basis.
However, the financial evaluation will be done as per commercial clause 4.2. Prices quoted should be FIRM
and Total Unit End Cost with GST and Cess as applicable stating the Unit Ex- works price, freight, packing
& forwarding charges, Insurance Charges, GST and Cess as applicable Separately in price bid, which is a
If the Supplier/Contractor has opted for the Composition scheme of GST, the same must be clearly specified
with valid declaration & self-certified Certificate from Department. In the event of withdrawal/cessation of
the Supplier from Composition scheme during the tenure of the contract, the rate (i.e. Price) mentioned in
the price bid shall be final and any additional GST will have to be borne by the Bidder himself. In no case
additional amount towards GST or otherwise will be paid / reimbursed to supplier/contractor. Further
Statutory Variation clause will not be applicable in case of Supplier / Contractor has opted for Composition
Scheme under GST.
Also, please mention separate applicable HSN / SAC Code and rate of GST and Cess as applicable for each
item of Goods/Service. If not specifically mentioned, then COMPANY will have the option to take the prices
as exclusive of taxes and duties at maximum higher slab rates for the evaluation of the Bids.
The offered prices to be indicated in online mode of Bid in the format given (i.e. Schedule). The price bid
submitted in physical mode shall not be considered.
The Bidder should invariably indicate the total unit end cost price considering all their costs / calculations in
the Price bid itself for each item and all sub-items if any. This is a must. Cost components hidden / furnished
elsewhere will not be considered and will be ignored out rightly.
Every bidder shall inform their GSTIN No.
8 AMENDMENT TO BID
At any time prior to the deadline for submission of bids, Bharuch rural Division may, for any reason,
whether at its own initiative or in response to a clarification requested by a respective bidder, modify the
bidding documents by amendments.
The amendment will be notified on Websites only. Bharuch rural Division will bear no responsibility or
liability arising out of noncompliance of the same in time or otherwise.
Such amendments, clarification etc. shall be binding on the bidders and will be given due consideration by
the bidders while they submit their bids and invariably enclose such documents as a part of the bid.
The tender fee once paid for tender document will not be refunded under any circumstances or
not transferred to other bidder. In case of online payment, no physical document submission is
Exemption in EMD is not admissible.
EMD of the successful bidder to whom a contract is awarded will be returned after the said bidder provides
the contract Security Deposit and signs the contract agreement.
If the successful bidder fails to submit a Security Deposit within 15 days after the date of LOA of the
contract or fails to sign the contract agreement, then the EMD amount will be forfeited by DGVCL without
any notice or proof of damages etc.
The EMD of all bidders except that of the successful bidder will be returned after the award of the contract.
No interest will be payable by the Bharuch rural Division on the above Deposit.
Validity of EMD (six) 6 months from the date of submission of bid for this Bid.
11 INFORMATION REQUIRED WITH THE PROPOSAL
The Bidders, along with his proposal, shall submit all the filled annexure given in Section of Annexure &
Appendix (Annexure of Qualification Information & Bank Guarantee).
The bids must clearly indicate the name of the manufacturer, the type and/or model of each principal item
of equipment proposed to be furnished and erected. The bid should also contain drawings and descriptive
materials indicating general dimensions, materials from which the parts are manufactured, principles of
operation, the extent of pre-assembly involved, major construction equipment proposed to be deployed,
method of erection and the proposed organizational structure.
The above information shall be provided by the Bidder in the form of separate sheets, drawings, enclosed
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
etc. - Any bid not containing sufficient descriptive material to describe accurately the equipment proposed
may be treated as incomplete and hence rejected. Such descriptive materials and drawings submitted by
the Bidder will be retained by the Owner. Any major departure from these drawings and descriptive
material submitted will not be permitted during the execution of the Contract without specific written
permission of the Owner.
Oral statements made by the Bidder at any time regarding quality, quantity or arrangement of the
equipment or any other matter will not be considered.
Standard catalogue pages and other documents of the Bidder may be used in the bid to provide additional
information and data as deemed necessary by the Bidder.
The Bidder, along with his Proposal, shall submit a list of recommended erection equipment and materials
which will be required for the purpose of erection of equipment and materials supplied under the Contract.
In case the ‘Proposal’ information contradicts specification requirements, the specification requirements
will govern, unless otherwise brought out clearly in the technical commercial deviation schedule.
The materials should be offered strictly confirming to ISS/BIS/Bid specifications given in the Bid. If the
Bidder’s desires to quote with any technical deviation they should specifically quote the deviation and the
ISS/BIS numbers in the body of the Bid itself under the Annexure VII of e-Bid only. If technical deviations
furnished by the Bidder are not agreeable to Bharuch rural Division, the offers may be ignored. However, it
will be solely at Bharuch rural Division discretion to consider the technical deviation OR not for considering
the Bidder. No correspondences of the Bidder after opening of the bid will be entertained in this matter.
12 DELAYED AND LATE BIDS
No Bid shall be accepted/opened in any case which are received after due date and time of the receipt of
Bid irrespective of delay due to postal services of any other reasons and company shall not assume any
responsibility for late receipt of Bid. Any correspondence in the matter will not be entertained.
13 REJECTION OF BID
The Bidders is expected to examine all instructions, terms, conditions, schedules and other details called for
in this specification and keep himself fully informed about all which may, in any way, affect the work, or
cost thereof. Failure to furnish the required information or submission of Bid not as per the specification
will be at the Bidders risk may result in rejection.
The offer is liable summarily rejected if it contains:
Ø Deviation / Addition / Alternations / Omissions in bidding schedules.
Ø Deviation and contradictions to the terms and conditions specified in this Bid.
14 DGVCL’S RIGHT
The DGVCL reserves the right to terminate this contract or part thereof at any time during its tendency
without giving notice of Termination or the reasons thereof.
The Bidders shall specifically note that any over writing or corrections or manuscript in the bid shall be
ignored and will not be considered authentic unless same are signed with Bidder's Stamp/Seal
DGVCL reserves the right to split the contract into two or more bidders. In such cases, the term for
completion period will be negotiated and reduced proportionate to the order quantity/value.
In case of any doubt or interpretation of the terms and condition, the decision of the SUPERINTENDING
ENGINEER, CIRCLE OFFICE, DGVCL will be final and binding upon the Bidders and no dispute in this
regard will be entertained.
DGVCL reserves the right to accept any bid or reject any or all Bids or cancel /withdraw RE INVITATION to
bid without assigning any reason. Such decision of the DGVCL shall not be subject to question by any
Bidders and the DGVCL shall bear no liability whatsoever for such decision.
15 LANGUAGE OF THE BID
All information in the bid shall be in English. Information in any other language shall be accompanied by its
translation in English. Failure to comply with this may disqualify a bid. In the event of any discrepancy in
meaning, the English language copy of all documents shall govern.
16 SIGNATURE OF BIDDER
The bid must contain the name, residence, address and place of business of the person or persons making
the bid and must be signed and sealed by the bidder with his usual signature. The name of all persons
signing should also be typed or printed below the signature.
Bids by corporation/ company must be signed with the legal name of the corporation/ company by the
President, Managing Director or by the Secretary or other person or persons authorized to bid on behalf of
such corporation/ company in the matter.
A bid by a person who affixes to his signature the word 'President', 'Managing Director' 'Secretary', 'or
other designation without disclosing his principal will be rejected.
Satisfactory evidence of authority of the person signing on behalf of the Bidder shall be furnished with the
The Bidder's name stated on the Bid shall be exact legal name of the firm.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Erasures or other changes in the bid documents shall be over the initials of the person signing the bid.
17 UNDERSTANDING AND CLEARIFICATIONS ON DOCUMENTS & SPECIFICATIONS
Bidder is required to carefully examine all the Bid Documents, Technical Specifications and Bid Drawing,
Commercial Terms & Condition or any other terms & conditions and fully inform himself as to all the
conditions and matters which may in any way affect the Work or the cost thereof. If any Bidder finds
discrepancies or omissions in the specifications and documents or is in doubt as to the true meaning of any
part, he shall at once request in writing for an interpretation/clarification by the Bharuch rural Division. The
Bharuch rural Division will issue interpretation and clarifications if required.
Verbal clarifications and information given by the Bharuch rural Division or his employee(s) or his
representative(s) shall not in any way be binding on the Bharuch rural Division.
18 PRICE BASIS CURRENCY AND PAYMENTS
Bidder shall indicate bid prices in Indian Rupees only.
19 EFFECTS AND VALIDITY OF BID
The bid should be kept valid for a period of 180 DAYS from the date set for opening of the technical bid.
Bid submitted by the bidder shall remain valid for acceptance for a period of 180 days from the date of
opening of the technical bid. The Bidders shall not be entitled during the validity of bid, to revoke or cancel
bid or vary any term thereof. In case of bidder revoking or canceling his bid or varying any term in regard
thereof, the bidder's earnest money deposit shall be forfeited by the Owner.
20 EVALUATIONS AND COMPARISION OF BIDS
Generally, the bids received and accepted will be evaluated by the Bharuch rural Division Team.
The Owner will examine the Bid to determine, whether they are complete, whether they meet all the
conditions of the Contract, whether required Tender fee, Bid EMD and other required documents have been
furnished, and whether the Bids are generally in order. Any Bid not fulfilling these requirements shall be
The technical eligibility will be decided upon evaluation as per clause 4.1. The Owner will evaluate and
and technical Bids are found responsive as per the conditions of the Bid.
No additional payments shall be made for completion of any contractual obligation beyond the quoted
prices. If the Bidder does not accept the correction of errors if any, its Bid shall be rejected and its Bid
security may be forfeited.
Documents submitted by the contractor shall be crosschecked /verified by the Bharuch rural Division team
at any stage of the contract period.
Bidder does not anticipate change in the ownership during the proposed period of work.
21 ARITHMETICAL ERRORS
Arithmetical errors will be rectified on the following basis: If there is a discrepancy between words and
figures, the amount in words will prevail. If there is discrepancy between the unit price and the total price
which is obtained by multiplying the unit price and quantity, or between sub-total and the total price, the
unit or sub-total price shall prevail, and the total price shall be corrected. In case of discrepancy between
sub-total price obtained by adding various prices in the schedule and the sub-total price indicated for that
particular schedule, the sub-total obtained by addition of various arithmetically corrected prices would be
considered for evaluation.
However, the Bharuch rural Division shall be entitled to award the contract at the lowest of the prices
arrived at from various schedules, identified for that purposes, in the bid proposal sheets. If the bidder does
not accept the correction of the errors as above, his bid will be rejected.
22 AWARD OF CONTRACT
Notification of award of contract will be made in writing to the successful bidder by the Bharuch rural
The contract will be awarded to the best qualified and responsive bidder offering the lowest evaluated bid in
conformity with requirements of these specifications and documents and Bharuch rural Division shall be the
sole judge in this regard and subject to the provisions of these instructions to bidders and other terms and
conditions detailed out in these documents and specifications. A responsive bid is one which accepts all
terms and conditions of these specifications and documents without any modifications.
The Owner shall not be bound to accept the lowest or any Bid and reserves to itself the right of accepting
the whole or a portion of any of the Bid as it may deem fit, without assigning any reason thereof. The Owner
reserves the right to accept or reject any bid, and to annul the bidding process and reject all bids at any
time prior to award of contract, without thereby incurring any liability to the affected Bidder or bidders or
any obligation to inform the affected Bidder or bidders of the grounds for the Owner's action.
Any approach/canvassing etc. official or otherwise by the bidder or his/their representative/agent to
influence the consideration of their Bid shall render the Bid liable to summary rejection. In the case of there
being a number of bidders quoting same rates thereby forming a cartel to jack up the prices, the SBD’s of
such bidders shall be summarily rejected.
The Owner reserves the right to vary the quantity of any of the spares and/or delete any items of spares
altogether at the time of Award of Contract.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
23 Notification of Award
Prior to the expiration of the period of bid validity, the Owner will notify the successful Bidder in writing,
that its bid has been accepted. The notification of award will constitute the formation of the contract.
The Owner shall promptly respond in writing to any unsuccessful Bidder who, after notification of award in
accordance with above, requests in writing the grounds on which its bid was not selected.
24 Signing the Contract Agreement
At the same time as the Owner notifies the successful Bidder that its bid has been accepted, the Bidder will
prepare the Contract Agreement provided in the Bidding Documents, incorporating all agreements between
the parties. The Contract Agreement shall be prepared within Fifteen (15) days of the Notification of Award
and the successful Bidder and the Owner shall sign and date the Contract Agreement immediately
25 PERFORMANCE GUARANTEE TOWARDS EXECUTION PERIOD
The successful bidder should be paid Performance Guarantee towards execution period within 15 days after
issuance of LOA for an amount equal to 5% (Five Percent) of the total Contract Value towards faithful
performance of the Contract in accordance with the terms and conditions specified therein.
The Performance Guarantee is payable as for the option of Bharuch rural Division by:
(a) If Performance Guarantee amount is less than Rs. 1 Lakh, it shall be paid either by RTGS/NEFT/Online
(b) Otherwise it shall be paid either by Bank Guarantees of specified Banks as notified by Finance
Department of Government of Gujarat time to time in this regard.
In the case of Bank Guarantee, you should undertake to renew the guarantee one-month before the expiry
of the validity date failing which Bharuch rural Division will encash the Bank Guarantee. The Performance
Guarantee will be returned to the Contractor without any interest after completion of guarantee period.
NOTE: The supplier may submit single or separate Bank Guarantee, to cover execution period
and Guarantee period, equivalent to higher of Two Bank Guarantees i.e Security Deposit and
Performance Guarantee as mentioned in Clause No: -25 and 26 of tender’s terms and condition
mentioned in Instructions to Bidders.
It should be valid till the completion of Guarantee / Warrantee period including additional one month; i.e.
total duration of Bank Guarantee will be from twelve months of Date of Work Order plus twelve months of
Warrantee period plus additional 1 months.
However, in case of the delay in execution, the contractor shall have to extend such Bank Guarantee
The Contractor shall guarantee in accordance with the Contract documents and free from defects in
material/equipment supplied by contractor like Indoor / Outdoor / Joint kits, HDPE Pipes etc. and
workmanship for a period of twelve (12) calendar months from date of completion of sub work order by
contractor. For the same, sticker must be provided incorporating Date of Installation and due date of
guarantee on materials used by Successful Bidder.
27 INDEMNITY BOND
The successful bidder will have to give indemnity bond to Bharuch rural Division against any possible claim
of compensation for damage to Contractor’s equipment or staff or any of third parties during the execution
of work as per attached format.
27 JURISDICTION OF CONTRACT
The laws applicable to the contract shall be the laws in force in India. The courts of Bharuch shall have
exclusive jurisdiction in all matters arising under this contract.
28 COMPLETION PERIOD
The execution of this contract shall be completed within 12 months after commencement period of 30 days
from the date of letter of acceptance (LOA).
The concern field office of Bharuch rural Division will issue sub work order as a part of Contract as per
requirement. The work completion period of each sub work order will be decided by concern Engineer-in-
Charge from the date of issue of sub work order.
The work completion period of all sub work orders cannot exceed the total period of original work order.
The completion date will be deemed to be the date on which all works of the sub work orders are
demonstrated to be completed in all respects as per the terms and conditions of this contract to the
satisfaction of the DGVCL / Engineer.
Successful bidder has to submit technical specification & drawing for HDPE Pipes, Indoor &
Outdoor termination kits, Joint Kits etc. for necessary approval during commencement period for
the material he wishes to utilize actually.
29 CONFLICT OF INTEREST AMONG BIDDERS / AGENTS
A bidder shall not have conflict of interest with other bidders. Such conflict of interest can lead to anti-
competitive practices to the detriment of Procuring Entity’s interests. The bidder found to have a conflict of
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
interest shall be disqualified. A bidder may be considered to have a conflict of interest with one or more
parties in this bidding process, if:
a) they have proprietor/ partner(s)/ Director(s) in common; or
b) they receive or have received any direct or indirect subsidy/ financial stake from any of them; or
c) they have the same legal representative/ agent for purposes of this bid; or
d) they have relationship with each other, directly or through common third parties, that puts them in a
position to have access to information about or influence on the bid of another bidder; or
e) bidder participates in more than one bid in this bidding process. Participation by a bidder in more than
one Bid will result in the disqualification of all bids in which the parties are involved. However, this does not
limit the inclusion of the components/ sub-assembly/ assemblies from one bidding manufacturer in more
f ) in cases of agents quoting in offshore procurements, on behalf of their principal manufacturers, one
agent cannot represent two manufacturers or quote on their behalf in a particular tender enquiry. One
manufacturer can also authorize only one agent/ dealer. There can be only one bid from the following:
1. The principal manufacturer directly or through one Indian agent on his behalf; and
2. Indian/ foreign agent on behalf of only one principal.
g ) a Bidder or any of its affiliates participated as a consultant in the preparation of the design or
technical specifications of the contract that is the subject of the Bid;
h) in case of a holding company having more than one independently manufacturing units, or more than
one unit having common business ownership/ management, only one unit should quote. Similar restrictions
would apply to closely related sister companies. Bidders must proactively declare such sister/ common
business/ management units in same/ similar line of business.
i) Bidder shall not act in contravention/ violation to the provisions of competition act, as amended from
Every bidder should, at the time of submission of bid; give a declaration, that bidder shall not have conflict
of interest with other bidders, as above.
If, the Company during the procurement process, observes or suspects any activity on the part of bidders or
obtains any knowledge which indicates the existence of cartel formation amongst the bidders or apprehends
the possibilities of cartel as defined under The Competition Act, 2002, the Board of the Company being a
government Company involved in public procurement work, reserve all rights to allot quantities to such
bidders, who are not part of the cartel, in any manner deemed fit in the interest of the Company without
assigning any reason thereof.
Besides the above the purchaser Company, may initiate actions under the Competition Act/ other laws and /
or the bidder(s)/ firm(s) will be black listed / stop deal, at its sole discretion.
GENERAL INFORMATION ABOUT THE BIDDER
(To be completely filled by the bidder)
1. Name of the Bidder
2 Postal Address
Telephone nos. Fax no.
4 e-mail address & URL
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Type of Company
5 Attach Proof of Company Registration along
Proprietorship/ Partnership/ Private Limited/
with a copy of the Partnership Deed/ Article of
Association and Memorandum of Understanding
Name and designation of the representative of
the Bidder to whom
all reference shall be made to expedite technical
7 Office Address
Stores Address where materials issued 1)
by Bharuch rural Division will be stored
9 Store Documents to be submitted
(Rental/ Bharuch rural Division)
10 Office Telephone/Fax no.
11 Office e-mail address
12 Permanent Account Number(PAN),
15 Electrical Contractor/Labour License No.
Policy No. Nos.
of Labours Insured in this policy
Insurance Policy No. and for nos. of Labours in
the name of bidder
17 Adhaar Card No.(Optional)
It is certified that the information provided above is true to the best of my knowledge and belief. If any
information found to be concealed, suppressed or incorrect at later date, our tender shall be liable to
rejected and our company debarred from executing any business with DGVCL.
SECTION 2: GENERAL CONDITION OF CONTRACT
The "OWNER" shall mean the Dakshin GUJARAT VIJ COMPANY LIMITED, having its Circle / Bharuch rural
Division office at BHARUCH, Gujarat, India.
The "Contractor" / Successful Bidders shall mean the Bidders; whose Bid has been accepted by the Bharuch
rural Division for award of the contract and shall include his authorized representatives.
The "Engineer-in-Charge" shall mean the authorized officer of the Bharuch rural Division to act as
Engineer-in- Charge to supervise the work – for the purpose of the contract.
The "Specification" shall mean the Bid forming a part of the contract along with Performa, schedules and
The "Order" shall mean the official letter issued by the Bharuch rural Division, informing the bidder that his
Bid has been accepted.
The "Contract" shall mean the agreement to be entered into by the Bharuch rural Division with the
contractor and shall include the commercial technical and general conditions, schedules, drawings and any
other conditions specifically agreed between the parties forming a part of the contract.
The "EMD" shall mean Earnest Money Deposit.
The "Contract Value" shall mean the total amount indicated in the contract agreement as per order placed
The "Contract Value" shall mean the total amount indicated in the contract agreement as per order placed
by the Bharuch rural Division and calculated from the quantities indicated in the Bid.
The "Completion Period" shall mean the period starting from the date of issue of "Order" and required to
complete the work in all respect.
The "Similar Work" shall mean activities to carry HT / LT underground cable laying network with
terminations for Distribution System.
“Inspector” shall mean the any person nominated by Bharuch rural Division from time to time to inspect the
works under the contract and/or duly authorized representative of the Bharuch rural Division.
“Letter of Award” shall mean the official notice issued by the Bharuch rural Division notifying the
contractor that his bid has been accepted.
“Date of Commencement” is the date when LOA placed by the Owner.
“Date of Contract” Shall mean the date on which Letter of award has been issued.
“Month” shall mean the calendar month day or days unless herein otherwise expressly defined shall mean
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
calendar day or days of 24 hours each.
“A Week” shall mean the continuous period of seven days.
'Commissioning' shall mean integrated activity covered under 'Pre-commissioning Operation', 'Initial
Operation', 'Trial Operation' and carrying out 'Performance Tests'.
HT means High Tension
U/G means Under Ground.
“New Bidder” shall mean the bidders who are participating without qualification criteria mentioned under
Section 1 Instructions to bidders Clause No. 4 Qualifying Criteria and remaining bidders in line with the
same clause will be considered as an “experienced / regular bidders”.
The price bid submitted by the contractor shall include all duties, taxes, insurance, freight etc., and any
other taxes that may be levied in accordance with the laws and regulations.
2.1 The successful bidder shall be deemed to have carefully examined all the papers, drawings, etc.
attached & if has any doubt as to the meaning of any portion of any condition / specification, etc. he shall
before signing the contract submit the particulars thereof to Bharuch rural Division in order that such
doubts are removed.
2 . 2 The successful bidder shall not, without the consent in writing of Bharuch rural Division,
transfer, assign or sublet the work under this contract or any substantial part thereof to any other party.
2 . 3 Notices, Statements and other communications sent by Bharuch rural Division through
registered post or telegram or telex or any other way of communication to the successful bidder at his
specified address shall be deemed to have been delivered to the successful Bidder. The work shall be
carried out by the successful bidder with prior approval of Bharuch rural Division. Work carried out without
Bharuch rural Division’s approval shall not be accepted and the DGVCL shall have right to reject it and to
recover the cost from the successful bidder. He will be liable against all losses, expenses or claims arising in
connection with the death of or injury to any person employed by the successful bidder or his
subcontractors for the purposes of the Works.
2.4 The successful bidder shall be responsible for any damage to the equipment during transit due
to improper or inadequate packing, handling, loading and unloading. The cases containing easily
damageable material shall be very carefully handled. Adequate protection must be provided for outdoor
storage at site in tropical humid climate, wherever necessary. The successful bidder without any extra cost
shall supply any material found short inside intact store area.
2 . 5 If the successful bidder neglects to execute the work with due diligence and expedition or
refuses or neglect to comply with any reasonable orders within two days’ notice given in writing to the
successful bidder and if he fails to comply with the notice, then in such a case Bharuch rural Division shall
be at liberty to get the work or any part of it, executed through any other agency/Bidder in the manner and
on the terms it thinks proper. If the cost of executing the work as aforesaid shall exceed the balance due to
the Bidder, and the Bidder fails to make good the deficiency, Bharuch rural Division may recover it from the
Bidder in any lawful manner.
2.6 Bharuch rural Division shall have at all reasonable time access to the works being carried out by
the Bidder under this contract and stores where material issued by Bharuch rural Division is stored. All the
works shall be carried out by the Bidder to the satisfaction of Bharuch rural Division.
2 . 7 The quantities mentioned in the accompanying schedule B are only approximate same may
decrease or increase. The Bharuch rural Division reserves the right for revising or omitting any of the
quantities. The actual work executed by the successful bidder will be calculated at the rate given in the
contract schedule of the rates binding to the successful bidder.
2.8 No higher rate or revised rate will be application for the work, if work is held-up/closed due to
whatever so reasons.
2.9 Price shall not be changed subject to any upward/downward revision on any account whatsoever
through the period of contract.
2 . 1 0 All other general terms and conditions as prevailing in the Bharuch rural Division shall be
applicable to this work contract.
2.11 The successful bidder has to co-ordinate and co-operate fully with Engineer In Charge and for
execution of the works.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
2 . 1 2 Either successful bidder or successful bidder’s authorized person should
contact our Engineer In Charge as well as Division Office, BHARUCH RURAL. daily for the availability of
materials required for this work, failing to which this work order shall be terminated without giving
2 . 1 3 The successful bidder has to maintain site register covering all aspects of material
received/utilized/dismantled for day to day work and has to obtain signature of Engineer in Charge.
2.14 In case of any dispute doubt, the decision of Executive Engineer Bharuch rural Division shall be
unchallengeable and final, which will be binding to the contractor.
2.15 The successful bidder will be solely responsible for any accident/damage either to equipment or
any human being during the time of execution of work.
2 . 1 6 The successful bidder will have to make his own arrangement for required all kinds of tools,
tackles, required for the execution of work.
2.17 The cost of damages, if any will be recovered from the successful bidder’s bill. The assessment of
which will be done by Engineer In Charge in consultation with division office, and his sole discretion and his
decision shall be binding to the successful bidder and shall be considered as final and unchallengeable.
2.18 The successful bidder will have to complete entire work, as mentioned in Schedule-B of contract
awarded to him, as per directive and instruction of Engineer In Charge. If he fails to do so entire work will
be carried out at the risk and cost of Contractor.
2 . 1 9 The contractor must engage sufficient knowledgeable person round the clock, exclusively for
execution of work.
2.20 Specification in any items mentioned in tender are subject to change without any prior notice and
binding to the contractor.
2.21 The DGVCL shall deduct the Income-Tax and other taxes as per prevailing rules of all relevant
Govt. Authorities from the bill.
2 . 2 2 If the work is required to be carried out during fix outage then the successful bidder has to
deploy adequate man power, material, tools etc. well in advance and has to complete the entire work during
this specific outage period only, failing to which Company shall be at liable to deduct the amount of revenue
loss due to prolong outage.
2.23 The tender includes all minor accessories and items of work which may not have been specifically
mentioned in the specification / Schedule etc. but are essential for completion of work. The contractor will
not be eligible for any extra payment in respect of such minor accessories and item of work.
2.24 The successful bidder shall not refuse to execute the work order at any time and it will be his sole
responsibility to execute and complete this work as per the instruction of Engineer in Charge.
2 . 2 5 The successful bidder has to carry out all the works in accordance with revised and latest
provision under I.E. Rule Act made there under and as per instruction of Engineer in Charge.
2.26 All the materials issued by Bharuch rural Division shall be transported to the work site on same
day and to be preserved in safe custody failing to which DGVCL shall initiate Police action. Similarly, as per
instruction of Engineer in Charge, you have to credit the material at Bharuch rural Division store without
any loss of time failing to which DGVCL shall initiate Police action.
2.27 Any delay causing extension of outages shall be successful bidder’s
responsibility and appropriate amount (in term of Rupees) as decided by Superintending/Executive
Engineer, Bharuch Circle/ Bharuch rural Division shall be recovered from successful bidder’s bill as a
penalty with applicable GST.
2.28 No tools, tackles, manpower, crane facilities etc. will be provided by the Bharuch rural Division.
2 . 2 9 The contractor has to follow all labour laws, safety rules and regulations. The Bharuch rural
Division does not take any responsibility in case of accident or injury to the workers. The safety, security of
men, materials and equipment shall be sole responsibility of the contractor.
2.30 The compliances of all Central / State Govt. Rules, safety and insurance rules etc. and that of
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
local body is a must condition for the successful bidder.
2.31 The contractor shall be responsible for breakages, losses and a theft of material during transit or
erection after the materials issued from the stores till the completion of work and is taken over by
the Bharuch rural Division.
2.32 As regard damages to the materials, equipment, successful bidder himself will be responsible. If
there is any compensation to be paid in respect of “WORKMAN” Compensation Act or any other statutory
provisions, the same will be paid by contractor directly. If he thinks fit, he may take necessary insurance
covering at his cost.
2.33 The competent authority can delete any item in schedule of the tender if he feels that the rate
quoted by the contractor for the item is abnormally high when compared to the estimated rates.
2.34 The erection work should be carried out according to the specification as per instructions and
programmed laid out by the Engineer in charge. Contractor has to ensure safe shifting and erection of all
accessories / equipment as per standard norms.
2.35 The Bidder shall not display the photograph of the work and shall not take advantage through
publicity of the work without written permission of Bharuch rural Division.
2 . 3 6 Under the Contract, the Contractor shall be responsible for loss or damage to the line and
Electrical Equipment until the successful completion as defined elsewhere in the Bid document.
2.37 All demurrage, wharf age and other expenses incurred due to delayed clearance of the material
or any other reason shall be to the account of the Contractor.
2.38 The law applicable to the contract shall be the laws in force in India. The courts of Bharuch shall
have exclusive jurisdiction in all matters arising under the contract.
2.39 The contractor shall submit the CAR (Contractor All Risks) policy for the awarded value of work
and valid for the entire duration of the work including extending period of work, if any. The contractor shall
provide to the Owner, copy of insurance policies and documents taken out by him, in pursuance of the
contract, immediately after such insurance coverage. If the contractor fails to effect and keep in force
insurance, as per the term of contract, the Owner may effect and keep in force such insurance and pay such
premium or premiums as may be necessary for that purpose and from time to time deduct the amount so
paid by the Owner as aforesaid, from any money due or which may be come due to the contractor, or
recover the same as debit due from the contractor.
2.40 The contractor shall be responsible for preparing all claims and make good for all damages or
Loss by way of repairs and or replacement of portion of any works damaged or lost. The transfer of title
shall not in any way relieve the contractor of his responsibility during the period of contract including the
defect liability period.
2.41 The contractor shall abide by the local laws and regulations governing labour and applicable from
time to time. During continuance of the contract the contractor shall abide at all times by all existing labour
enactments and rules made their under, regulations notification and byelaws of State and Central Govt. of
Local authority and any other labour law (including rules, regulations bylaws that may be passed or
notifications that may be issued under any labour in future either by the state or the central govt. or the
local authority)
2.42 Nothing shall be paid for any loss or damage done due to rains, floods, or any other act of God
during the execution period, trial run & defect liability period. The payment shall be made only for
material/works acceptable to the Department.
2.43 Material purchased in excess shall not be measured and paid for and if not removed from the site
within one month after completion of work, the material shall become the property of DGVCL and no claim
on this account shall be entertained.
2.44 The contractor shall provide suitable measuring equipment /arrangement at site for checking of
various material supplied by him.
2.45 In case of duplicity/variations/contradiction of terms and condition in the printed Bid documents
and special terms and conditions, the terms and conditions mentioned in the special terms and conditions
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
2.46 The Owner reserves the right of modification of layout plans, if found necessary, before actual
execution of work even after designing the same, nothing extra shall be payable to the firm for these
changes in the layout plan.
2 . 4 7 Contractual agency shall bear the cost of repairing the damages of other utility services like
water, telecom, road or sewerage during excavation of electrical cable trench. Suitable measures to be
adopted during road crossing and cutting of metaled portion of the road including taking prior permission
from the concerned department. Bharuch rural Division will not involve in the coordination with the other
utility services although for the sake of the progress of the project they may take initiatives. The
contractor shall enter the work details and route in the ‘CBUD’ application before commencing
any digging work.
3. ENGINEER-IN-CHARGE'S REPRESENTATIVE
(i) The Owner will appoint any of his officers or any agency as the case may be as engineer-in-charge to
deal with all the matters related to the execution and operation of contract.
(ii) However, the Owner/Owner's representatives reserves the right in checking/tests checking of the
operation of the contract in respect of quality, testing, and measurement of works either directly or through
a separate agency or both.
(iii) The Engineer-in-charges representative may appoint any number of persons to assist the Engineer-in-
Charges Representative in carrying out of his duties. He shall notify to the contractor the names, duties and
the scope of authority of such persons. Such assistants shall have no authority to issue any instructions to
the contractor save in so far as such instructions may be necessary to enable them to carry out their duties
and to `secure their acceptance of materials plants or workmanship as being in accordance with the
contractor, and any instructions given by any of them for those purpose shall be deemed to have been given
by the Engineer-in-charge's Representative.
4 GENERAL OBLIGATIONS
4.1 Contractor's general responsibilities
The contractor shall with due care and diligence (to the extent provided in the contract) execute and
complete the work and remedy any defects therein in accordance with the provisions of the contract. The
contractor' shall provide all supervisory, labour, materials, plant, construction equipment and all other
things, whether of temporary or permanent nature, required in and for such design, execution, completion
and remedying of any defects, so far as the necessity for providing the same is specified in or is reasonably
to be inferred from the contract. The contractor shall provide the same in specified form which is
reasonably to be inferred from the contract. The contractor shall promptly notify the Owner and the
Engineer-in-charge of any effort, omission, fault or any other defect in the design or specifications for the
work which he discovers when reviewing the contract documents or in the process of execution of the
works. The contractor shall take the full responsibility for the adequacy, stability and safety of all site
operations and methods of construction, provided that the contract shall not be responsible (except as
stated hereunder or as may be otherwise agreed) for the specification of works, not prepared by the
contractor. Whereas this contract expressly provides that all of the components of this work shall be
designed by the contractor, he shall be fully responsible for all the works, notwithstanding any approval by
the Engineer-in-charge.
4.2 Inspection of site
The contractor shall deem to have inspected the site and examined its surroundings and collected
information available in connection therewith and to have satisfied himself (so far as is practicable, having
regard to considerations of cost and time, at his own responsibility and expense) before submitting his bid,
(a) the form and nature thereof, including the sub surface conditions
(b) the hydrological and climatic conditions
(c) the extent and nature of work, labour and materials necessary for speedy execution of the works, their
availability and other related matters and remedying of any defects therein, and
(d) The means of access to the site and accommodation he may require. And in general, shall be deemed to
have obtained all necessary information as above mentioned, as to risks, contingencies and all other
circumstances which may influence or affect his bid.
4.3 Sufficiency of Bid
The contractor shall be deemed to have satisfied himself as to the correctness and sufficiency of the Bid and
of the rates and prices stated in the bill of quantities all of which shall except in so far as it is otherwise
provided in the contract, cover all his obligations under the contract (including those in respect of the
supply of good, materials, plant or services) and all matters and things necessary for the proper execution
and completion of the works and remedying of any defects therein. The rate quoted against each item or
work shall be for the complete finished item of work and shall be inclusive of all taxes duties and all cost
and expenses which may be required in and for execution and full protection of the work as described
together with all general risks/liabilities and obligations set forth or implied in the documents on which the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Bid is based. The rates quoted against each item in the bill of quantities shall be deemed to cater for all
minor constructional details which are not specifically mentioned, but are fairly and obviously intended and
are essential for the full and final completion of works and the contractor is not entitled to make any extra
claim on this account.
4.4 Work to be in accordance with contract
Unless it is legally or physically impossible, the contractor shall execute and complete the works and
remedy any defects therein in strict accordance with the contract to the satisfaction of the Engineer- in-
charge. The contractor shall comply with and adhere strictly to the Engineer-in-charge's instruction on any
matter, whether mentioned in the contract or not, touching or concerning the work. The contractor shall
take instructions only from the Engineer-in-Charge or from the Engineer-in-charges representative.
4.5 Engineer-in-charge at Liberty to Object
The Engineer-in-charge shall be at liberty to object to and require the contractor to remove forthwith from
the works any persons provided by the contractor who, in the opinion of the Owner/ Engineer-in- charge,
misconducts himself or is incompetent or negligent in the proper performance of his duties, or whose
presence on site is otherwise considered by the Engineer-in-charge to be undesirable, and such persons
shall not be again allowed upon the works without the consent of the Engineer-in-charge. Any person so
removed from the works shall be replaced as soon as possible.
4.6 Setting out
The contractor shall be responsible for:
(a) The accurate setting out of the works in relation to original points, lines and levels, of reference given by
the Engineer-in-charge in writing based on approved survey data.
(b) The correctness of the position, levels, dimensions and alignments of all part of the works.
(c) The provision of all necessary instruments, appliances and labour in connection with the forgoing
responsibilities, if, at any time during the execution of the works any error appears in the position, levels,
dimensions or alignment of any part of the works the contractor on being required to do so by the Engineer-
in-Charge, shall at his own cost rectify such error to the satisfaction of Engineer-in- Charge, unless such
error is based on incorrect data supplied in writing by the Engineer-in-Charge.
(d) The checking of any setting - out or of any Line or level by the Engineer-in-Charge shall not in any way
relieve the contractor of his responsibility for the accuracy thereof and the contractor shall carefully protect
and preserve all bench marks sight - rails, pegs and other things used in setting out of the works.
4.7 Safety, Security and Protection of the Environment
The contractor shall throughout the execution and completion of the works and the remedying of any
defects therein;
(a) Have full regard for the safety of all persons entitled to be upon the site and keep the site (so far as the
same is under his control) and the works (the same are not completed or occupied by the Owner) in an
orderly state appropriate to the avoidance of danger to such persons.
(b) Provide and maintain at his own cost all lights, guards, fencing, warning signs and watching, when and
where necessary or required by the Engineer-in-Charge or by any duly constituted authority, for the
protection of the works or for the safety and convenience of the public or others.
(c) Take all reasonable steps to protect the environment on and off the site and to avoid damage or nuisance
to persons or to property of the public or others resulting from pollution, noise or other causes arising as a
consequence of his methods or operation. In case of the failure on the part of the contractor on above
accounts, the consequences of the same shall be borne by the contractor. Alternatively, the Engineer-in-
Charge may take reasonable steps to comply with the above at the risk and cost of the contractor.
4.8 Care of works
The contractor shall take full responsibility for the care of the works and materials and plant for
incorporation therein from the commencement date until the date of issue of the taking over certificate for
the whole of the works, when the responsibility for the said care shall subject to pass to the Owner provided
(a) If the Engineer-in-Charge issues a taking over certificate for any section or part of the works, the
contractor shall cease to be liable for the care of that section or part from the date of issuing of the taking
over certificate, when the responsibility for the care of that section shall pass to the Owner, and
(b) The contractor shall take full responsibility for the care of any outstanding works and materials and
plant for incorporation therein he undertakes to or is otherwise required to finish during the defects
liabilities period along with the defects if any until such outstanding works have been completed.
4.9 Responsibility to Rectify or Damage
If any loss or damage happens to the works or any part thereof, or materials or plant for incorporation
therein, during the period for which the contractor is responsible for the care thereof, from any cause
whatsoever, other than the risks defined in sub clause 5.11 of Instructions to Bidder, the contractor shall at
his own cost, rectify such toss or damage so that the works confirm in every respect with the provision of
the contract to the satisfaction of the Engineer-in-Charge.
4.10 Owner’s Risks
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
(a) The Owner's risks are;
1) War, hostilities (whether war be declared or not) invasion act of foreign enemies.
2) Rebellion, revolution, insurrection or military or usurped power or civil war.
3) Pressure waves caused by aircraft or other Arial devices traveling at sonic or
supersonic speeds.
(b) Loss or damage due to the use or occupation by the Owner of any section of part of the works except as
may be provided for the contract.
(c) Any operation of the forces of nature (in so far as it occurs on the site) such as earthquakes, tornado,
lightening and unprecedented floods etc. against which an experienced contractor could not reasonably
have been expected to take precautions.
All fossils, coins, articles of value or antiquities and structures and other remains or things of geological or
archaeological interest discovered on the site of the works shall be deemed to be absolute property of the
Owner and the contractor shall take reasonable precautions to prevent his workmen or any other person
from removing or damaging any such article or thing and shall immediately upon discovery thereof and
before removal, acquaint the Engineer-in-Charge or Engineer-in-Charge's representative of such discovery
and carry out the Engineer-in-Charge instructions for dealing with the same.
4.12 Underground works
During excavation if existing underground network are noticed and the same is needed to be removed /
relocated, the cost of removal / relocation shall be determined by the Engineer-in-Charge, on the basis of
awarded rate of contract or SOR rate of DGVCL / State Government / Central Government Utilities and
reimbursed to the contractor after getting approval of AT as per DOP of DGVCL. Other than power utility,
Engineer – in – Charge shall inform concerned stakeholders for relocating the same.
4.13 Taking Over
Upon successful Trial – Operation of the Facilities or any part thereof, the Owner shall issue to the
Contractor a Taking Over Certificate as a proof of the acceptance of the Facilities or any part thereof. Such
certificate shall not relieve the Contractor of any of his obligations which otherwise survive, by the terms
and conditions of Contract after issue of such certificate. If within twenty-one (21) days after receipt of the
Contractor's notice, the Owner fails to issue the Taking Over Certificate or fails to inform the Contractor in
writing of the justifiable reasons why the Owner has not issued the Taking Over Certificate, the Facilities or
the relevant part thereof shall be deemed to have been Taken Over as at the date of the Contractor's said
notice. Upon Taking Over of the Facilities or any part thereof, the Owner shall be responsible for the care
and custody of the Facilities or the relevant part thereof, together with the risk of loss or damage thereto,
and shall thereafter take over the Facilities or the relevant part thereof.
4.14 Allotment of Material and Its Storage
Required material for the work as per Schedule shall be allotted from any store Centres of Bharuch rural
Division jurisdiction and successful bidder has to take delivery from these stores at his own only.
4.15 Account of material issued
The successful bidder shall have to maintain accurate day to day item wise account of use of issued
materials which shall be got checked from time to time by the Engineer in Charge of the Company. The
contractor will be responsible for custody and preserving the issued materials till the work is hand over by
the contractor after completion.
The successful bidder has to maintain site register, covering all the daily details of material receipt and
utilization, progress of work etc. The successful bidder shall bound provision made for issuance of material
to agency in E-urja system of DGVCL. This register shall be checked and signed by Engineer in
Charge/Deputy/Executive Engineer, Bharuch rural Division during the site visit as per requirement and
exigency of work if deem fit.
After completion of the work against each Sub Work Order, all the surplus materials issued by the DGVCL
shall be returned by you to the respective divisional /Regional stores only at contractor’s cost. Such
Material shall not be credited in S/Dn store.
5 MATERIALS HANDLING AND STORAGE
5.1 All the equipment furnished under the Contract and arriving at Site shall be promptly received,
unloaded, transported and stored in the storage spaces by the Contractor.
5.2 Contractor shall be responsible for examining all the shipment and notify the Engineer immediately of
any damages, storage, discrepancy etc., for the purpose of Engineer’s information only. The Contractor
shall submit to the Engineer every week a report detailing all the receipts during the week. However, the
Contractor shall be solely responsible for any shortages or damages in transit, handling and / or in storage
and erection of the equipment at Site. Any demurrage, wharf age and other such charges claimed by the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
transporters, railways etc., shall be to the account of the Contractor.
5.3 The Contractor shall maintain an accurate and exhaustive record detailing out the list of all equipment
materials received by him for the purpose of erection and keep such record open for the inspection of the
Engineer in-charge.
5.4 All equipment shall be handled very carefully to prevent any damage or loss. The equipment stored shall
be properly protected to prevent damage either to the equipment or to the floor where they are stored. The
equipment from the store shall be moved to the actual location at the appropriate time so as to avoid
damage of such equipment at Site.
5.5 The consumable and other supplies likely to deteriorate due to storage must be thoroughly protected
and stored in a suitable manner to prevent damage or deterioration in quality by storage.
5.6 All the materials stored in the open or dusty location must be covered with suitable weatherproof and
flame proof covering material wherever applicable.
6 PROTECTION OF PROPERTY AND CONTRACTOR’S LIABILITY
The Contractor shall be responsible for any damage resulting from his operations. He shall also be
responsible for protection of all persons including members of public and employees of the Owner and the
employees of other Contractors and Sub-Contractors and all public and private property.
7.1 COMPREHENSIVE GENERAL LIABILITY INSURANCE: The insurance shall protect the Contractor
against all claims arising from injuries, disabilities, disease or death of members of public or damage to
property of others, due to any act of omission on the part of the Contractor, his agents, his employees, his
representatives and Sub-Contractors or from riots, strikes and civil commotion. The hazards to be covered
will pertain to all the works and areas where the Contractor, his Sub-Contractors, his agents and his
employees have to perform work pursuant to the Contract. The above is only illustrative list of insurance
covers normally required and it will be the responsibility of the Contractors to maintain all necessary
insurance coverage to the extent both in time and amount to take care of all his liabilities either direct or
indirect, in pursuance of the Contract.
7.2 The Contractor at his cost shall arrange, secure and maintain all insurance as may be pertinent to the
Works and obligatory in terms of law to protect his interest and interests of the Owner against all perils
detailed herein. The form and the limit of such insurance as defined herein together with the under-writer
in each case shall be acceptable to the Owner. However, irrespective of such acceptance, the responsibility
to maintain adequate insurance coverage at all time during the period of Contract shall be of Contractor
alone. The Contractor’s failure in this regard shall not relieve him of any of his contractual responsibilities
and obligations. The insurance covers to be taken by the Contractor shall be in the name of the Contractor.
The Contractor shall, however, be authorized to deal directly with Insurance Company or Companies and
shall be responsible in regard to maintenance of all insurance covers. Further the insurance should be in
freely convertible currency.
7.3 Any loss or damage to the equipment during handling, transportation, storage, erection, putting into
satisfactory operation and all activities to be performed till the successful completion of commissioning of
the equipment shall be to the account of the Contractor. The Contractor shall be responsible for preference
of all claims and make good the damages or loss by way of repairs and/or replacement of the equipment,
damaged or lost. The transfer of title shall not in any way relieve the Contractor of the above
responsibilities during the period of Contract. The Contractor shall provide the Owner with copy of all
insurance policies and documents taken out by him in pursuance of the Contract. Such copies of documents
shall be submitted to the Owner immediately after such insurance coverage. The Contractor shall also
inform the Owner in writing at least sixty (60) days in advance regarding the expiry/cancellation and/or
change in any of such documents and ensure revalidation, renewal etc., as may be necessary well in time.
7.4 The perils required to be covered under the insurance shall include, but not be limited to fire and allied
risks, miscellaneous accidents (erection risks) workman compensation risks, loss or damage in transit, theft,
pilferage, earth quake, riot and strikes and malicious damages, civil commotion, weather conditions,
accidents of all kinds, etc. The scope of such insurance shall be adequate to cover the
replacement/reinstatement cost of the equipment for all risks up to and including delivery of goods and
other costs till the equipment is delivered at Site. The insurance policies to be taken should be on
replacement value basis and/or incorporating escalation clause. Notwithstanding the extent of insurance
cover and the amount of claim available from the underwriters, the Contractor shall be liable to make good
the full replacement/rectification value of all equipment/materials and to ensure their availability as per
project requirements.
7.5 All costs on account of insurance liabilities covered under the Contract will be on Contractor’s account
and will be included in Contract Price, However, the Owner may from time to time, during the pendency of
the Contract, ask the Contractor in writing to limit the insurance coverage, risks and in such a case, the
parties to the Contract will agree for a mutual settlement, for reduction in Contract price to the extent of
reduced premium amount. The Contractor, while arranging the insurance shall ensure to obtain all
discounts on premium which may be available for higher volume or for reason of financing arrangement of
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
7.6 The clause entitled ‘Insurance’ covers the additional insurance requirements for the portion of the
works to be performed at the Site.
7.9 Storage-cum-Insurance:
a. The contractor shall take suitable storage-cum-erection insurance cover at his cost to the extent of
100 % cost of materials, which are required to complete the work. Contractor shall have to take
comprehensive insurance policy against any loss, damage, theft, pilferage, fire etc. for the complete period
of storage, erection and commissioning up to the time of taking over by DGVCL. The Contractor shall deal
directly and pursue the claim with the Insurance Company and shall be responsible in regard to
maintenance of all insurance coverage as well as for settlement of claim. The proof of insurance policy
taken by the successful Contractor shall be furnished to Engineer-In-Charge. In absence of the above
insurance policy, R.A. Bill payment will be withheld.
b. In the event of any damage, theft, loss, pilferage, fire, etc., Contractor will be responsible to lodge,
pursue and settle all the claims with the Insurance Company for all items, materials and the DGVCL shall be
kept informed about it. Contractor shall replace the lost / damaged materials / items promptly irrespective
of the settlement of the claims by underwriter and ensure that the work progress is as per agreed schedule.
The loss, if any, such replacement will have to be borne by the Contractor and Bharuch rural Division will
not entertain any claim / representation in this regard. However, it will be contractor's responsibility to
insure the entire project is taken over by the Bharuch rural Division.
7.10 Workmen’s Compensation Insurance
This insurance shall protect the Contractor against all claims applicable under the Workmen’s
Compensation Act, 1948 (Government of India). This policy shall also cover the Contractor against claims
for injury, disability, disease or death of his or his Sub-Contractor’s employee, which for any reason are not
covered under the Workmen’s Compensation Act, 1948. The liabilities shall not be less than:
Workmen’s Compensation -As per statutory Provisions
Employee’s liability -As per statutory Provisions
7.11 Comprehensive General Liability Insurance
The insurance shall protect the Contractor against all claims arising from injuries, disabilities, disease or
death of members of public or damage to property of others, due to any act of omission on the part of the
Contractor, his agents, his employees, his representatives and Sub-Contractors or from riots, strikes and
civil commotion. The hazards to be covered will pertain to all the works and areas where the Contractor, his
Sub-Contractors, his agents and his employees have to perform work pursuant to the Contract. The above
are only illustrative list of insurance covers normally required and it will be the responsibility of the
Contractors to maintain all necessary insurance coverage to the extent both in time and amount to take
care of all his liabilities either direct or indirect, in pursuance of the Contract.
8 UNFAVOURABLE WORKING CONDITIONS
The Contractor shall confine all his field operations to those works, which can be performed without
subjecting the equipment and materials to adverse effects during inclement weather conditions, like
monsoon, storms etc. and during other unfavorable construction conditions. No field activities shall be
performed by the Contractor under conditions, which might adversely affect the quality and efficiency
thereof, unless special precautions or measures are taken by the Contractor in a proper and satisfactory
manner in the performance of such Works and with the concurrence of the Engineer. Such unfavorable
construction conditions will in no way relieve the Contractor of his responsibility to perform the Works as
per the schedule.
9 WORK & SAFETY REGULATIONS
The Contractor shall ensure proper safety of all the workmen, materials, plant and equipment belonging to
him or to DGVCL or to others, working at the Site. The Contractor shall also be responsible for provision of
all safety notices and safety equipment required both by the relevant legislations and the Engineer, as he
may deem necessary.
All equipment used in construction and erection by Contractor shall meet Indian/International Standards
and where such standards do not exist, the Contractor shall ensure these to be absolutely safe. All
equipment shall be strictly operated and maintained by the Contractor in accordance with manufacturer’s
Operation Manual and safety instructions and as per Guidelines/rules of DGVCL in this regard.
Periodical examinations and all tests for all lifting/hoisting equipment & tackles shall be carried- out in
accordance with the relevant provisions of Factories Act 1948, Indian Electricity Act 2003 and associated
Laws/Rules in force from time to time. A register of such examinations and tests shall be properly
maintained by the Contractor and will be promptly produced as and when desired by the Engineer or by the
person authorized by him.
The Contractor shall provide suitable safety equipment of prescribed standard to all employees and
workmen according to the need.
The Contractor shall provide safe working conditions to all workmen and employees at the Site including
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
safe means of access, railings, stairs, ladders, scaffoldings etc. The scaffoldings shall be erected under the
control and supervision of an experienced and competent person. For erection, good and standard quality of
material only shall be used by the Contractor.
The Contractor shall not interfere or disturb electric fuses, wiring and other electrical equipment belonging
to the Owner or other Contractors under any circumstances, whatsoever, unless expressly permitted in
writing by Bharuch rural Division to handle such fuses, wiring or electrical equipment Before the
Contractor connects any electrical appliances to any plug or socket belonging to the another Contractor or
Owner, he shall:
a. Satisfy the Engineer in charge that the appliance is in good working condition;
b. Inform the Engineer in charge of the maximum current rating, voltage and phases of the appliances;
Obtain permission of the Engineer detailing the sockets to which the appliances may be connected.
The Engineer will not grant permission to connect until he is satisfied that;
The appliance is in good condition and is fitted with suitable plug;
The appliance is fitted with a suitable cable having two earth conductors, one of which shall be an earthed
metal sheath surrounding the cores.
No electric cable in use by the Contractor/Owner will be disturbed without prior permission. No weight of
any description will be imposed on any cable and no ladder or similar equipment will rest against or
attached to it.
No repair work shall be carried out on any live equipment. The equipment must be declared safe by the
Engineer and a permit to work shall be issued by the Engineer before any repair work is carried out by the
Contractor. While working on electric lines/equipment, whether live or dead, suitable type and sufficient
quantity of tools will have to he provided by the Contractor to electricians/workmen/officers.
In case any accident occurs during the construction/ erection or other associated activities undertaken by
the Contractor thereby causing any minor or major or fatal injury to his employees due to any reason,
whatsoever, it shall be the responsibility of the Contractor to promptly inform the same to the Engineer in
prescribed form and also to all the authorities envisaged under the applicable laws.
The Engineer shall have the right at his sole discretion to stop the work, if in his opinion the work is being
carried out in such a way that it may cause accidents and endanger the safety of the persons and/or
property, and/or equipment. In such cases, the Contractor shall be informed in writing about the nature of
hazards and possible injury/accident and he shall comply to remove shortcomings promptly. The Contractor
after stopping the specific work can, if felt necessary, appeal against the order of stoppage of work to the
Engineer within 3 days of such stoppage of work and decision of the Engineer in this respect shall be
conclusive and binding on the Contractor.
The Contractor shall not be entitled for any damages/compensation for stoppage of work due to safety
reasons and the period of such stoppage of work will not be taken as an extension of time for completion of
work and will not be the ground for waiver of levy of liquidated damages.
It is mandatory for the Contractor to observe during the execution of the works, requirements of Safety
Rules which would generally include but not limited to following.
Each employee shall be provided with initial indoctrination regarding safety by the Contractor, so as to
enable him to conduct his work in a safe manner.
No employee shall be given a new assignment of work unfamiliar to him without proper introduction as to
the hazards incident thereto, both to himself and his fellow employees. Employees must not leave naked
fires unattended. Smoking shall not be permitted around fire prone areas and adequate firefighting
equipment shall be provided at crucial location.
There shall be a suitable arrangement at every work site for rendering prompt and sufficient first aid to the
Requirements of ventilation in underwater working to licensed and experienced divers, use of gum boots for
working in slushy or in inundated conditions are essential requirements to be fulfilled. The Contractor shall
follow and comply with all DGVCL Safety Rules, relevant provisions of applicable laws pertaining to the
safety of workmen, employees, plant and equipment as may be prescribed from time to time without any
demur, protest or contest or reservations. In case of any discrepancy between statutory requirement and
DGVCL Safety Rules referred above, the latter shall be binding on the Contractor.
In case the Owner is made to pay such compensation then the Contractor is liable to reimburse the Owner.
10 PRICE EVALUATION
No price preference shall be given on any account. All tenders must be submitted firm price basis (Inclusive
of all Taxes) and lowest evaluated bid in the interest of the Bharuch rural Division, for the complete works
covered under these specifications and documents.
If more than one party is to be considered for placement of order, they will have to match their end cost
with end cost of L-1 technically acceptable bidder. Bharuch rural Division (tender Inviting Authority) may
go to the L-2, L-3 and so on depending upon the requirement at DGVCL’s sole discretion. If Bharuch rural
Division (tender Inviting Authority) feels that there is lack of serious competition or any other reasons,
Bharuch rural Division (tender Inviting Authority) may negotiate with the L-1 party. Bharuch rural
Division’s (tender Inviting Authority) decision shall be final and binding on all the parties.
In case of bid found quoted with abnormally low rates, DGVCLs may reject the offer at its sole discretion
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
after examining quality and resources of bidders with due approval of next higher authority.
11 QUANTITY DISTRIBUTION
11.1 Bharuch rural Division may allot quantity to L-1, L-2 and so on bidders depending on the requirement
subject to matching final rate of L1 bidder.
11.2 The competent authority of the DGVCL as per delegation of power shall decide to consider nos. of
bidders for placement of order under ARC, at its own discretion and considering field requirement.
However, Bharuch rural Division would not place order on more than 50% of the total bidders who are
bidding for the order.
11.3. If L1 bidder is experienced / regular bidder, heavy weightage in order placement will be given to L1
11.3.1 Total amount / quantity allotted to new bidders shall be restricted up to 25% of tender quantity /
11.3.1 Total amount / quantity allotted to new bidders shall be restricted up to 25% of tender quantity /
11.3.2 If L1 is new bidder, they will get heavy weightage in amount / quantity allotment from the total
amount / quantity allotted to new bidders.
(Note: The said clause is applicable to the ARC tender. If tender is invited with value more than
Rs. 5 Lakhs for specific single work, experience criteria may be kept in line with Clause No:
Accordingly, this clause may be adopted / deleted while inviting tenders).
12 ADDITIONAL ORDER
The Company may place additional order after obtaining written consent of successful contractor, provided
there is no conspicuous downtrend in the price of such item after obtaining approval from next authority of
order approving authority.
The Company reserve the right to place repeat orders / additional orders on the successful Tenderers up to
25% of the original quantity of the A/T at the same Prices, Terms and Conditions stipulated in the original
contract within completion of contractual period. If, repeat order is placed in the last month of Contractual
delivery schedule of main order, commencement period of one month should be given for repeat order. The
delivery schedule for repeat order should be given considering proportionate delivery schedule of main
order and it will be started on completion of contractual delivery schedule of main order. However, in
special circumstances the Company may place repeat order for 25% of the original quantity of the A/T with
early delivery schedule of material, as mutually agreed upon.
The company reserves the right to reduce the quantity, if required.
13 CHANGE OF QUANTITY
During the execution of the Contract, the Bharuch rural Division reserves the right to increase or decrease
the quantities of items under the Contract but without any change in unit price or other terms & conditions.
Such variations unless otherwise specified in the accompanying GCC and/or Technical Specifications, shall
not be subjected to any limitation for the individual items but the total variations in all such items under the
Contract shall be limited to the extent of 30% (Thirty Percent) of the contract price by way of suitable
amendment to the contract.
The Contract price shall accordingly be adjusted based on the unit rates available in the Contract for the
change in quantities as above. The base unit rates, as identified in the Contract shall however remain
constant during the currency of the Contract, In case the unit rates are not available for the change in
quantity, the same shall be derived and subjected to mutual agreement.
As this is an EPC contract, engineering work will be done by the Contractor. Responsibility of material will
be that of the contractor.
14 CODE REQUIREMENTS
The erection requirements and procedures to be followed during the installation of the equipment shall be
in accordance with the relevant Codes and accepted good engineering practice, the Engineer’s drawings
and other applicable Indian recognized codes and laws and regulation of the Government of India.
15 COMPLIANCE WITH LAWS
a. The Contract shall in all respects be interpreted in accordance with the laws in force in India, including
any such laws passed or made or coming into force during the period of the Contract.
b. The Contractor shall be fully responsible for deducting the P.F. of the employees / labour Working under
him as per statutory regulations and depositing the same with the concerned authorities.
c. The Contractor shall comply with the relevant laws of India.
The Contractor shall be liable for and shall indemnify the Employer against all losses, expenses or claims
arising in connection with the death of or injury to any person employed of the Contractor or his sub-
Contractors for the purposes of the Works.
17 FORCE MAJEURE
Force Majeure means any circumstances beyond the control of the parties including:
17.1 War and other hostilities, (whether war be declared or not), invasion, act of foreign enemies,
mobilization, requisition or embargo;
17.2 Ionizing radiation or contamination by radioactivity from any nuclear fuel or from any nuclear
waste from the combustion of nuclear fuel, radioactive toxic explosive, or other hazardous properties of any
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
explosive nuclear assembly or nuclear components thereof;
17.3 Rebellion, revolution, insurrection, military or usurped power and civil war;
17.4 Riot, commotion or disorder, except where solely restricted to employees of the Contractor.
1 7 . 5 Neither party shall be considered to be in default or in breach of his obligations under the
Contract to the extent is that performance of such obligations prevented by any circumstances of Force
Majeure that arise after the date of the Notification of Award.
17.6 If either party considers that any circumstances of Force Majeure have occurred which may affect
performance of his obligations he shall promptly notify the other party.
17.7 Upon the occurrence of any circumstances of Force Majeure, the Contractor shall endeavor to
continue to perform his obligations under the Contract so far as reasonably practicable. The Contractor
shall notify the Engineer-in-Charge of the steps he proposes to take including any reasonable alternative
means for performance, which are not prevented by Force Majeure. The Contractor shall not take any such
steps unless directed so to do by the Engineer-in-Charge.
17.8 If circumstances of Force Majeure have occurred and shall continue for a period of 180 days,
notwithstanding, the Contractor may by reason thereof, having been granted an extension of Time for
Completion of the Works, either party shall be entitled to serve upon the other, 30 days’ notice to terminate
the Contract. If at the expiry of the period of 30 days Force Majeure shall continue, the Contract shall
18 TAXES AND DUTIES
18.1 Bought out items from vendors/sub-suppliers:
All levies, duties, GST and Cess etc. payable on equipment/material components, sub- assemblies, raw
materials and any other items used for the bidder's consumption or dispatched directly to the owner from
its sub-supplier and any such taxes, duties levies additionally payable shall be to bidders account and no
separate claim on this behalf shall be entertained by the Bharuch rural Division.
18.2 DGVCL’s GSTIN Registration Nos. is 24BRDT01136C1D2
1 8 . 3 The bidder shall be liable and responsible for payment of all taxes as attracted under the
Provisions of the law.
18.4 “In case any tax or duty is newly introduced by the Government applicable for this contract with
effect from the next day of the date submission of the bid and if the contractor is required to pay new tax or
duty, then the owner shall reimburse the contractor the new tax or duty so paid by the contractor against
submission by the contractor of documentary evidence to the satisfaction of the owner.”
18.5 At the time of payment, statutory deduction will be made as per applicable rules and rates for
TDS, WCT, welfare cess etc. All other statutory liabilities towards contract will be on the part of contractor.
18.6 Before quoting, the bidder may ascertain from the concerned tax authorities of Government the
applicability of GST and Cess, etc. in respect of this work. No separate claim in this regard will be
entertained by the DGVCL, as it is the responsibility of the Bidder to pay all these taxes.
18.7 Tax collected at source will be payable as per provision of income tax act 1961 on submission of
documentary evidence by eligible contractor to the satisfaction of DGVCL.
18.8 Goods and Service Tax (GST):
The F.O.R. destination prices are excluding GST and Cess as applicable which will be paid extra on a given
taxable goods and/or services within the original contractual delivery period. The amount of GST/ and Cess
as applicable should clearly be indicated separately. (GST/Cess means all applicable Tax/Cess under GST
Laws. GST Laws means IGST Act, GST (Compensation to the State for Loss of Revenue) Act, CGST Act,
UTGST Act and SGSCT Act, 2017and all related ancillary legislations).
1 8 . 9 You shall have to submit a C.A Certificate & duly authorized Signatory of successful bidder,
certifying that you have not claimed Refund of any applicable GST/ and Cess, charged to COMPANY or shall
not claim any such Refund, on a future date, from the concerned Authorities and if, any Refund, in respect
of such GST/ and Cess, is claimed by you, it will be immediately passed on to the COMPANY, without
/COMPANY making any specific Claim, for the same, either from the Department or from you.
18.10 The offers having price INCLUSIVE OF GST and Cess is likely to be rejected if the rate of GST and
Cess is not mentioned clearly unless the bidder has opted for Composition Scheme under GST Act, which
should be clearly indicated in the price bid. /COMPANY may at its discretion consider such offer with
presumption of highest applicable rate of GST/Cess prevailing when the price quoted is inclusive of GST
18.11 If the Supplier/Contractor has opted for the Composition scheme of GST, the same must be clearly
specified with valid Declaration & Certificate from Department. In the event of withdrawal/cessation of the
Supplier from Composition scheme during the tenure of the contract, the rate mentioned in the price bid
shall be final and any additional GST will have to be borne by the Bidder. In no case additional amount
towards tax or otherwise will be paid / reimbursed to supplier/contractor. Further Statutory Variation
clause will not be applicable in case of Supplier / Contractor has opted for Composition Scheme under GST.
18.12 Supplier/Contractor should charge GST in Invoice at the rate as agreed to mention in acceptance of
Bid only and any deviation in the same shall not be accepted. Further, any additional liability of GST (later
on due to wrong mentioning of GST rate, mis-interpretation of HSN/SAC Code, etc.) over and above as
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
charged in the invoice shall be borne by the Supplier/Contractor. However, any refund received by the
supplier / contractor on account of GST charged from the company; such refund shall have to be passed on
to the company, along with interest if any. Such refund along with interest needs to be passed on suo-moto
by the supplier / contractor.
18.13 Further, the Company has a right to recover the amount of GST along with penal interest at the
rate of 15% per annum if GST charged is not paid / short paid to the government or fail to upload the details
or uploads inaccurate particulars on GSTIN portal by the Supplier / Contractor within the stipulated time
18.14 In case, Govt. revises the rate of GST rate / Code during the tenure of the contract, the provision of
Bharuch rural Division’s statutory variation clause shall apply.
18.15 Input Tax Credit Benefit
In the event of any statutory increase in the rate of Input Tax Credit and / or due to inclusion of any other
additional item of their inputs/input services under the ambit of the Input Tax Credit provisions under the
GST Act, subsequent to the date of submission of the offer, the same should be passed on to COMPANY and
you should inform such changes to COMPANY from time to time
19 Statutory Variation / Changes in Taxes
Any statutory increase or decrease in the taxes and duties including GST and Cess as applicable or in the
event of introduction of new tax/cess or cessation of existing tax/cess in the taxes subsequent to your offer
if it takes place within the contract period will be DGVCL account subject to the claim being supported by
documentary evidence. However, if any decrease takes place during contract period the advantage will have
to be passed on DGVCL.
Statutory Variation clause shall not be applicable in case of Supplier / Contractor has opted for Composition
Scheme under GST.
20 Taxes, Permits & Licenses
20.1 The Contractor shall be liable and pay all foreign taxes, duties, levies lawfully assessed against
the Owner or the Contractor in pursuance of the Contract. In addition, the Contractor shall be responsible
for payment of all Indian duties, levies and taxes lawfully assessed against the Contractor for his personal
income & property only.
INCOME TAX –TDS & GST-TDS
20.2 “Income-tax at source & GST-TDS at the prevailing rates will be deducted from bills in accordance
with the provision of Income-Tax Laws and Goods Service Tax Act and to that effect a certificate will be
issued to the contractor as per provision of relevant act, however added as contractor has to submit
separate invoice for supply parts item as well as works part item separately, otherwise TDS will be
deducted on entire invoice value.”
20.3 Applicable welfare cess will be deducted from contractors each bill by DGVCL to pay the same to
the respective Govt. Department. Tax will be deducted as per applicable statutory rules. Contractor should
quote accordingly i.e. inclusive of welfare cess.
21 COMPLIANCE OF LAWS
The successful bidder will certify that he has complied with the provisions of Industrial & Labor Laws
including PF Act, ESI Act etc. as may be applicable. Copy of challans of PF related to be submitted along
22 LIABILITIES FOR ACCIDENTS AND DAMAGES
Under the Contract, the Contractor shall be responsible for loss or damage to the plant until the successful
completion of commissioning as defined elsewhere in the Bid document.
23 TERMINATION OF CONTRACT ON OWNER`S INITIATIVE
The Owner reserves the right to terminate the Contract either in part or in full due to reasons other than
those mentioned under clause entitled ‘Contractor’s Default’. The Owner shall in such an event give fifteen
(15) days’ notice in writing to the Contractor of his decision to do so.
The Contractor upon receipt of such notice shall discontinue the work on the date and to the extent
specified in the notice, make all reasonable efforts to obtain cancellation of all orders and Contracts to the
extent they are related to the work terminated and terms satisfactory to the Owner, stop all further sub-
contracting or purchasing activity related to the work terminated, and assist Owner in maintenance,
protection, and disposition of the works acquired under the Contract by the Owner. In the event of such a
termination the Contractor shall be paid compensation, equitable and reasonable, dictated by the
circumstances prevalent at the time of termination.
If the Contractor is an individual or a proprietary concern and the individual or the proprietor dies and if the
Contractor is a partnership concern and one of the partners dies then unless the Owner is satisfied that the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
legal representatives of the individual Contractor or of the proprietor of the propriety concern and in the
case of partnership, the surviving partners, are capable of carrying out and completing the Contract the
Owner shall be entitled to cancel the Contract as to its in completed part without being in any way liable to
payment of any compensation to the estate of deceased Contractor and/or to the surviving partners of the
Contractor’s firm on account of the cancellation of the Contract. The decision of the Owner that the legal
representatives of the deceased Contractor or surviving partners of the Contractor’s firm cannot carry out
and complete the Contract shall be final and binding on the parties. In the event of such cancellation the
Owner shall not hold the estate of the deceased Contractor and/or the surviving partners of the estate of
the deceased Contractor and/or the surviving partners of the Contractor’s firm liable to damages for not
completing the Contract.
a. All disputes or differences in respect of which the decision, if any, of the Engineer has not become final
or binding as aforesaid shall be settled by arbitration in the manner here in after provided.
b. The arbitration shall be conducted in accordance with provisions of Indian Arbitration Act 1996 or latest
amendment thereof.
c. The arbitrator shall have full powers to review and/or revise any decision, opinion, direction, certification
or valuation of the Engineer in accordance with the Contract, and neither party shall be limited in the
proceedings before such arbitrator to the evidence or arguments put before the Engineer for the purpose of
obtaining the said decision.
d. No decision given by the Engineer in accordance with the foregoing provisions shall disqualify him as
being called as a witness or giving evidence before the arbitrator on any matter whatsoever relevant to the
dispute or difference referred to the arbitrator as aforesaid.
e. During settlement of disputes and arbitration proceedings, both parties shall be obliged to carry out
their respective obligations under the Contract.
If after the Engineer has given written notice of his decision to the parties, no claim to arbitration has been
communicated to him by either party within thirty (30) days from the receipt of such notice, the said
decision shall become final and binding on the parties.
THE REFERENCE TO ARBITRATION PROCEEDINGS UNDER THIS CLAUSE SHALL NOT
i. Affect the right of the Engineer -in charge to take possession of all or any tools, plants, materials and
stores, in or upon the work or site thereof or belonging to the contractor or procured by him and intended
to be used for the execution of the work or any part thereof.
ii. Preclude the Engineer-in charge from utilizing the materials purchased by the Contractor in any work or
from removing such materials to other place, during the period the work is stopped or suspended in
pursuance of notice given to the contractor under General Conditions.
iii. Entitle the contractor to stop the progress of the work or carrying out the additional or altered work in
accordance with the prevision of General Conditions for the work where there is no specification.
iv. Preclude the DGVCL from getting the work done by another agency. Neither party is entitled to bring a
claim to arbitration latest by thirty days after the expiration of the defects liability period.
All questions, disputes or differences whatsoever, which may, at any time, arise between the parties i.e.
Bharuch rural Division and the contractor upon or in relation to or in connection with the Contract shall be
referred to sole Arbitrator appointed by the Managing Director DGVCL for that purpose, who shall be
retired High Court Judge or a retired District Judge and the decision of the said Arbitrator shall be final and
binding upon the parties. Reference to the Arbitrator shall be final and binding upon the parties governed
by the provisions of The Arbitration & Conciliation Act, 1996 as amended from time to time and the Rules
made there under. The Arbitration proceedings shall be conducted at Bharuch rural Division of DGVCL or
at any such place as the sole Arbitrator may determine. The award of the sole Arbitrator shall be final and
binding upon the parties. Performance under this contract shall, if reasonably possible, continue during the
Arbitration proceedings and no payments due or payable by Bharuch rural Division shall be withheld unless
they are the subject matter of the Arbitration proceeding.
RESOLUTION OF DISPUTES, SETTLEMENT OF DISPUTES
a. Any dispute(s) or difference(s) arising out of or in connection with the Contract shall, to the extent
possible, be settled amicably between the parties.
b . If any dispute or difference of any kind, whatsoever, shall arise between the Owner and the
Contractor, arising out of the Contract for the performance of the Works whether during the progress of the
Works or after its completion or whether before or after the termination, abandonment or breach of the
Contract, it shall, in the first place, be referred to and settled by the Engineer, who, within a period of thirty
(30) days after being requested by either party to do so, shall give written notice of his decision to the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Owner and the Contractor.
c. Save as hereinafter provided, such decision in respect of every matters so referred shall be final and
binding upon the parties until the completion of the Works and shall forthwith be given effect to by the
Contractor who shall proceed with the Works with all due diligence, whether he or the Owner requires
arbitration as hereinafter provided or not.
d. If after the Engineer has given written notice of his decision to the parties, no claim to arbitration
has been communicated to him by either party within thirty (30) days from the receipt of such notice, the
said decision shall become final and binding on the parties.
25 EMPLOYMENT OF LABOUR
Persons below the age of 18 years shall not be employed for the work. No female worker shall be employed
in the night shift between 07.00 p.m. and 06.00 a.m. next day.
Contractor shall maintain a valid labour license under the Contract Labour (Regulation and Abolition) Act
for employing necessary manpower required by him. In the absence of such a license, the contract shall be
liable to be terminated without assigning any reason thereof. Contractor should also employ qualified and
experiences persons as per requirement of Electricity Act and rules for carrying out supply and erection
work under this contract.
In case Bharuch rural Division becomes liable to pay any wages or dues to labour or any Government
agency under any of the provisions of the Minimum Wages Act, Payment of Wages Act, Employee
Compensation Act, Contract Labour Regulation Abolition Act, Employee Provident Fund or any other law
due to act of omission of the Contractor, Bharuch rural Division may make such payment and shall recover
the same from the Contractor’s bills.
26 PROVIDENT FUND AND FAMILY PENSION SCHEME
The Contractor shall submit along with his bills (month wise) a Statement regarding deduction against
employees Provident Fund and Family Pension Scheme in respect of each concerned employee. The
contractor's contribution and the workers’ contribution towards Provident Fund and Family Pension
Scheme shall be done at the rate made applicable by the Government from time to time and deposited by
the contractor with Regional Provident Fund Commissioner.
General Contractor shall adhere to the safe construction practice and guard against hazardous and unsafe
working conditions and shall comply with Owner's safety rules as set forth herein.
Safety Regulation: In respect of all labour, directly or indirectly employed in the work for the performance
of contractor's part of this agreement, the contractor shall at his own expenses arrange for all the safety
provisions as per safety code of Indian Standards Institution, the Electricity Act and such other acts as
The contractor shall observe and abide by all fire and safety regulations.
First Aid: Contractor shall maintain adequate first aid facilities for its employees and labour, an MBBS
doctor with assisting nurses and helpers should be available throughout the pendency of the contract.
Contractor shall make outside arrangements for Ambulance service and for the treatment of injuries.
Names of those providing these services shall be furnished to the Owner and their telephone numbers shall
be prominently posted in contractor's field office.
All critical industrial injuries shall be reported promptly to the Owner, and a copy of the contractor's report
covering each personal injury requiring the attention of a physician shall be furnished to the Owner.
Contractor's Barricades and lighting Arrangement: Contractor shall erect and maintain barricades required
in connection with his operations to guard the excavations and Hoisting Areas. These should be properly
lighted during the night.
Excavation and Trenches: All trenches 1.2meters or more in depth shall at all times be supplied with at
least one ladder for each 50 meters Length or fraction thereof. Ladder shall be extended from bottom of the
trench to at least one meter above the surface of the ground. The sides of the trenches, which are
meters in depth, shall be stepped back to give suitable slope or securely held by timber bracing, so as to
avoid the danger of sides to collapse. The excavated materials shall not be placed within 1.5 meters of the
edge of the trench or half of the trench width whichever is more. Cutting shall be done from top to bottom.
Under no circumstances undermining or under cutting shall be done.
Cares in Handling Inflammable Gas: The contractor has to ensure all precautionary measures and
exercise utmost care in handling the inflammable gas cylinders/ inflammable Liquids/paints etc. as required
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
under the law and/ or as advised by the Fire Authorities.
Preservation of Peace: The contractor shall take requisite precautions and use his best endeavors to
prevent any riotous or unlawful behavior by or amongst his workmen and others employed on the works
and for the preservation of peace and protection of the inhabitants and security of property in the
neighborhood of the work in the event of the Owner requiring the maintenance of a special police force at
or in the vicinity of the site during the tenure of works, the expenses thereof shall be borne by the
contractor and if paid by the Owner, shall be recoverable from the contractor.
Outbreak of Infectious Disease: The contractor shall remove from his camp such labour and their
families who refuse to protective inoculation and vaccination when called upon to do so by the Engineer-in-
Charges representative. Should Cholera, Plague or other infectious diseases break out, the contractor shall
burn the huts, beddings, clothes and other belonging used by the infected parties and promptly erect new
huts on healthy sites as required by the Engineer-in-Charge failing which, within the time specified in the
Engineer-in-Charge's requisition, the work may be done by the Owner and the cost thereof recovered from
the contractor.
Use of intoxicants: The unauthorized sale of spirits or other intoxicating beverages upon the work in any
of the buildings, encampments or tenements owned, occupied, by or within the control of the contractor, is
prohibited and the contractor shall exercise his influence and authority to the utmost extent to secure strict
compliance with this condition.
Change in Laws and Regulations: If, after the date seven (07) days prior to the date of Bid Opening, any
law, regulation, ordinance, order or by-law having the force of law is enacted, promulgated, abrogated or
changed in India (which shall be deemed to include any change in interpretation or application by the
competent authorities) that subsequently affects the costs and expenses of the Contractor and/or the Time
for Completion, the Contract Price shall be correspondingly increased or decreased, and/or the Time for
Completion shall be reasonably adjusted to the extent that the Contractor has thereby been affected in the
performance of any of its obligations under the Contract. However, these adjustments would be restricted
to direct transactions between the Owner and the Contractor and not on procurement of raw materials,
intermediary components etc. by the Contractor for which the Owner shall be the sole judge.
Notwithstanding the foregoing, such additional or reduced costs shall not be separately paid or credited if
the same has already been accounted for in the price adjustment provisions where applicable.
28 FUNCTIONAL AND COMPOSITE TESTING
Following test shall be conducted on equipment after completion of erection in the presence of Engineer-
in-charge from point of view of completeness in the presence of Bharuch rural Division’s Authorized
Representative.
Ø Visual inspection of total system.
Ø Checking of continuity of power and HT cables.
Ø Checking of cable terminations and laying, dressing etc. in the equipment kiosk.
Ø Checking of safe accessibility of components.
Ø The insulation resistance test shall be carried out by 2500V Megger for HV Installation.
29 REGULATIONS OF LOCAL AUTHORITIES AND STATUTES
The Contractor shall comply with all the rules and regulations of local authorities during the performance of
his field activities. He shall also comply with the Minimum Wages Act, 1948 and the Payment of Wages Act
(both of the Government of India) and the rules made there under in respect of any employee or workman
employed or engaged by him or his Sub- Contractor. He shall abide by labour laws.
All initial registration and statutory inspection fees, if any, in respect of his work pursuant to this Contract
shall be borne by the contractor.
30 OWNER’S LIEN ON EQUIPMENT
The Owner shall have lien on all equipment brought to the Site for the purpose of cable laying, erection,
testing and commissioning of the equipment to be supplied & erected under the Contract. The Owner shall
continue to hold the lien on all such equipment throughout the period of Contract. No material brought to
the Site shall be removed from the Site by the Contractor and/or his Sub-Contractors without the prior
written approval of the Engineer. All expense for this shall be borne by the contractor.
31 LINES AND GRADES
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
All the works shall be performed to the lines, grades and elevations indicated on the drawings. The
Contractor shall be responsible to locate and lay-out the works. Basic horizontal and vertical control points
will be established and marked by the Engineer at site at suitable points. These points shall be used as
datum for the works under the Contract. The Contractor shall inform the Engineer well in advance of the
times and places at which he wishes to do work in the area allotted to him so that suitable datum points
may be established and checked by the Engineer to enable the Contractor to proceed with his works. Any
work done without being properly located may be removed and/or dismantled by the Engineer at
Contractor’s expense.
32 PENALTY FOR DELAY
32.1 The time limit allowed for carrying out the work as entered in Bid shall strictly observed by the
contractor. The work shall throughout the stipulated period of contract proceeds with due diligence (time
being essence of the contract).
32.2 The execution of this contract shall be completed within 12/24/36 months after commencement
period of 30 days from the date of letter of acceptance (LOA).
3 2 . 3 If the work is not completed within the scheduled period as prescribed in Sub Work
Order, penalty shall be @ 0.5% per Week or part thereof plus applicable tax (if any) subject to
ceiling of 10% plus applicable tax (if any) of the Sub Order Value with GST and Cess as applicable
rates. This will be deducted from the bills payable either against this contract or any bank
guarantee or any other amount payable under any contract with the DGVCL.
32.4 For calculating delayed portion, start date of sub work order for penalty calculation will
be the Day / Date on which the first material is issued against the Sub work order and final date
of actual completion of work shall be consider. The penalty will be invariably deducted from the bill of
the contractor and no refund will be given unless the competent authority approved the waiver/ reduction in
penalty. In case of material supplied late by Bharuch rural Division to the contractor, clause no. 32.13 shall
32.5 The concern field office of Bharuch rural Division /Bharuch Circle will issue sub work order as a
part of contract as per requirement. The work completion period of each sub work order will be decided by
concern Engineer-in-Charge from the date of issue of sub work order. The delay of commissioning is liable
3 2 . 6 Penalty for non-submission of bills timely: Sub work order wise bill along with excess
material credited to store to be submitted by contractor within 30 days from the date of work completion. If
the bill for the work, after reconciling inventory given to contractor and depositing back the surplus
material to respective RSO / Divisional Stores, is not submitted within three months from the work
completion date as per work completion date, then penalty @ Rs. 500 per week or part thereof plus
applicable GST subject to maximum of 10% of order value plus applicable GST will be deducted.
32.7 Penalty for violating safety rules: During the execution of Work, if Contractor/Labour are found
violating the Safety rules and Regulations, then Engineer-in-Charge will serve the warning Notice on first
Instance. On second Instance the amount of Fine will be Rs. 500.00 or 0.1 % of amount of SWO (Whichever
is higher) with GST and cess. Even If after above two instances, still Contractor found violating Safety Rules
and Regulations then Procedures for Stop dealing shall be initiated against him as per rules and
3 2 . 8 Further, it is to state that in rainy season and / or for any other reasons beyond the
control of contractor and / or if Municipal Corporation or Nagarpalika or Local Government
Bodies or any other utilities do not allow to execute work or any ROW issues; stoppage period will
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
be allowed for such period subject to submission of representation with documentary evidences.
Stoppage Period will be approved by next higher authority of order approving authority.
32.9 FORCE MAJEURE CLAUSE”
“If, at any time during the continuance of this contract, the performance in whole or in part by either party
of any obligation under this contract shall be prevented or delayed by reason of any war, hostility, act of the
public enemy, civil commotion, sabotage fires, floods, explosion, epidemics, quarantine restrictions, strikes
lockouts or acts of God (hereinafter referred to as event)”, then provided notice of the happening of any
such event is given by either party to the other within twenty one days from the date of occurrence there of
neither party shall by reason of such event be entitled to terminate this contract nor shall either party shall
have any claim for damages against the other in respect of such nonperformance of delay in performance,
and deliveries under the contract shall be resumed as soon as practicable after such event has come to end
or ceased to exist, and the decision of the Managing Director as to whether the deliveries have been so
resumed or not shall be final and conclusive.
Extension in Contractual Period:
32.10 It will be Contractor’s responsibility to ensure that work is completed in stipulated time limit.
However, if on account of reasons beyond one’s control as laid down in the Force Major Conditions,
Bharuch rural Division may consider extension of contractual period with or without statutory variations
and with or without price variation.
32.11 In case of any non-supply of materials from stores, the contractor will have to intimate the Sub-
Division Office or Division office quoting the MR No and date for non-receipt of materials. The intimation
will be considered for extension in time limit. The time limit will be considered on the basis of number of
“Working Days” or “Months”.
32.12 It will be the responsibility of the contractor to intimate the closing down and recommencement of
work at all stages to the engineer in charge or vice versa in writing with reason for the closing down of the
work with specific of days for which work will remain closed.
32.13 In case of failure on the part of the contractor, his claim for extension of time limit will be
entertained with penalty.
32.14 In case, intimation is not given in these regard, the reason for delay will not be accepted.
32.15 However, time limit extensions will be considered only after execution of the sub work order fully
and upon submission of documentary evidence for the reasons of delay. Extension of Contractual period
will be approved by next higher authority of order approving authority.
If some material/Item is not installed/fixed for allotted work and as per SOR by contractor due to non-
availability of particular item/material for long period of time and TLE cannot be approved for that work
beyond certain time limit or such item if not required to be installed at particular location, then Recovery is
to be made as mentioned below for not carrying out that work from SWO issued for that work.
Ø Empty Wooden Drum (Assorted Sizes) : Rs. 325.00 per Drum
Ø Empty Iron Drum (Assorted Sizes 1000Mtr) : Rs. 10000.00 per Drum
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
All work other than above must be completed by contractor and No any other Recovery should be made
other than above Work.
34 PAYMENT TERMS
The payment to the Contractor for the performance of the works under the Contract will be made by the
Owner as per the guidelines and conditions specified herein. All payments made during the Contract shall
be on account payments only. The final payment will be made on completion of all Works / Order and on
fulfillment by the Contractor of all his liabilities under the Contract.
Ø Currency of Payment
All payments under the Contract shall be in Indian Rupees only.
Ø Mode of Payment
All payments under the Contract shall be made after the issue of work certificates by the Engineer in
charge, for the quantum of work completed.
Ø Deductions from Contract Price
All costs, damages or expenses which the Owner may have paid, for which under the Contract the
Contractor is liable, or any other retention award will be claimed by the Owner. All such claims shall be
billed by the Owner to the Contractor regularly as and when they fall due. Such bills shall be supported by
appropriate and certified vouchers or explanations, to enable the Contractor to properly identify such
claims. Such claims shall be paid by the Contractor within thirty (30) days of the receipt of the
corresponding bills and if not paid by the Contractor within the said period, the Owner may then deduct the
amount, from any monies due or becoming due by him to the Contractor under the Contract or may be
recovered by sections of Law or otherwise.
Ø Terms of Payment
The owner shall pay to the Contractor as per the terms of payment mentioned hereunder:
1. The bidder shall raise sub work order wise bills only after completion of all the specified activities
complete for each sub work order.
2. Bills will be processed and paid within 30 days after submission bills.
3. Contractor will be issued only 3 (Three) Sub work orders at a time. He will be issued Fourth Sub Work
Order only after the submission of Inventory sheet with sketch and material account statement and bills
thereof for any of the three previously issued Sub Work Orders.
4. The order value is based on the quantity, unit rates and values quoted and shall be subject adjustment
based on actual quantities executed and certified by the Engineer – in – Charge.
5. Payment of the actual material used and work done will be paid on above basis.
Ø Presentation of Bills
The bills along with required documents for work executed including cost of material consumed is to
be prepared in Quadruplicate and submitted 03 copies to the concern Deputy Engineer of Sub Division
Office. These bills shall be serially numbered.
Contractor has to submit Bills along with required documents for work executed including cost of
material consumed material account along with quantities of work executed for each item. Location
wise inventory of all the material used is to be submitted in detail. All required documents including
EPF should be produced by the contractor along with bills.
For non-submission or part submission of above information, no bills shall be processed.
The technical information, drawings, specifications and other related documents forming part of the
enquiry or Contract are property of DGVCL and shall not be used for any other purpose, except for the
execution of the contract. All rights related to the technical specifications, drawings and records are
reserved by DGVCL only and no part or partial should be reproduced, copied or alter without prior
permission to DGVCL in writing. In the event of the breach of this provision, DGVCL can claim the damages
caused by such events.
36. DISCONTINUATION FOR INSOLVENCY
DGVCL may at any time terminate the Contract by giving Notice to the Contractor, if the Contractor
becomes bankrupt or otherwise insolvent. In such event, discontinuation will be without compensation to
the Contractor, provided that such discontinuation will not prejudice or affect any right of action or remedy
that has accrued or will accrue thereafter to DGVCL.
37. MINOR CIVIL WORKS:
During the installation / erection of the outdoor equipments /materials or any other erection activity as per
the scope of tender, any civil structure / slab, wall, road, Indoor or Outdoor cable trench etc. which may
need to be altered / modified or damaged shall be rectified / made it good by the successful bidder at no
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
extra cost to the DGVCL within stipulated time period. No deviation in the time limit of work would be
considered on account of the above repairing/modification of civil work.
38. FRUSTRATION OF CONTRACT
a) In the event of frustration of the Contract because of supervening impossibility in terms of Section 56 of
the Indian Contract Act, parties shall be absolved of their responsibility to perform the balance portion of
the Contract, subject to provisions contained in sub-clause 10.3 below.
b) In the event of non-availability or suspension of funds for any reasons, whatsoever (except for reason of
willful or flagrant breach by the Owner) and/or Contractor then the works under the Contract shall be
Furthermore, if the Owner is unable to make satisfactory alternative arrangements for financing to the
Contractor in accordance with the terms of the Contract within three months of the event, the parties
hereto shall be relieved from carrying out further obligations under the Contract treating it as frustration of
In the event referred to in sub-clauses 10.1 & 10.2 above the parties shall mutually discuss to arrive at
reasonable settlement on all issues including amounts due to either party for the work already done on
quantum merit_ basis which shall be determined by mutual agreement between the parties.
39. CONTRACTOR’S FIELD OPERATION
a. The Contractor shall keep the Engineer informed in advance regarding his field activity plans and
schedules for carrying-out each part of the works. Any review of such plan or schedule or method of work
by the Engineer shall not relieve the Contractor of any of his responsibilities towards the field activities.
Such reviews shall also not be considered as an assumption of any risk or liability by the Engineer or the
Owner or any of his representatives and no claim of the Contractor will be entertained because of the
failure or inefficiency of any such plan or schedule or method of work reviewed. The Contractor shall be
solely responsible for the safety, adequacy and efficiency of plant and equipment and his erection methods.
b. The Contractor shall have the complete responsibility for the conditions of the Work-site including the
safety of all persons employed by him or his Sub– Contractor and all the properties under his custody
during the performance of the work. This requirement shall apply continuously till the completion of the
Contract and shall not be limited to normal working hours.
40.0 CO-OPERATION WITH OTHER CONTRACTORS
The Contractor shall co-operate with all other Contractors or tradesmen of the Owner, who may be
performing other works on behalf of the Owner and the workmen who may be employed by the Owner and
doing work in the vicinity of the Works under the Contract. The Contractor shall also so arrange to perform
his work as to minimize, to the maximum extent possible, interference with the work of other Contractors
and their workmen. Any injury or damage that may be sustained by the employees of the other Contractors
and the Owner, due to the Contractor’s work shall promptly be made good at the Contractor’s own expense.
41. PROGRESS REPORT
The Contractor shall furnish three (3) copies each to the Engineer of progress including if any, photographs
of the work done at Site.
The weekly progress report detailing-out the progress achieved on all erection activities shall highlight
comparison to the schedules. The report shall also indicate the reasons for the variance between the
scheduled and actual progress and the action proposed for corrective measures, wherever necessary.
42. MAN-POWER REPORT
The Contractor shall submit to the Engineer, on the first day of every month, a man hours schedule for the
month, detailing the man hours scheduled for the month, skill-wise and area-wise.
43. PROTECTION OF WORK
The Contractor shall have total responsibility for protecting his works till it is finally taken over by the
Engineer. No claim will be entertained by the Owner or by the Engineer for any damage or loss to the
Contractor’s works and the Contractor shall be responsible for complete restoration of the damaged works
to original conditions to comply with the specification and drawings.
44. FIRE PROTECTION
The work procedures that are to be used during the erection shall be those, which minimize fire hazards to
the extent practicable. Combustible materials, combustible waste and rubbish shall be collected and
removed from the Site at least once each day. Fuels, oils and volatile or inflammable materials shall be
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
stored away from the construction and equipment and materials storage areas.
All the Contractor’s supervisory personnel and select number of workers shall be trained for firefighting.
Enough of such trained personnel must be available at the Site during the entire period of the Contract.
The Contractor shall have total responsibility for all equipment and materials in his custody/stores, loose,
semi-assembled and/or erected by him at Site. The Contractor shall make suitable security arrangements
ensure the protection of all materials, equipment and works from theft, fire, pilferage and any other
damages and loss.
46. THIRD PARTY INSPECTION OF WORK
Bharuch rural Division may assign the work of supervision and inspection to third party for work of
contractor’s workmanship and quality on 24 x 7 hours basis. The periodical inspection reports shall be
accessed and any defects or poor quality of workmanship has to be got rectified by the contractor invariably
within stipulated time limit. Bharuch rural Division reserves the right of stop payment on non- response of
contractor on this issue.
In case, Unit rates for items are not available for suggested changes/revisions/alterations, Bharuch rural
Division will decide Unit rate for such items with suggested changes/revisions/alterations and it shall be
binding to bidder and bidder has to accept the rate decided by Bharuch rural Division.
Bidder/Contractor shall be put under Stop Deal due to following reasons.
47.1 Has submitted fake, false or forged documents/certificates.
47.2 Has revised/withdrawn price bid after opening of Techno: commercial bid, until and unless it is
47.3 Has tampered with the stipulated tendering process.
47.4 Has refused to accept Letter of Acceptance/Purchase Order/Work Order after the same is issued
by the Company within the validity period and as per agreed terms and conditions.
4 7 . 5 Has committed breach of contract or has failed to perform a contract or has abandoned the
47.6 Has failed to provide suitable expertise for the work as per prescheduled program
4 7 . 7 Has failed to submit all the necessary Test reports/documents within time schedule / as per
Company's time limit, as mentioned in the LOA, if the Letter of Acceptance (LOA) is placed subject to
submission of type reports / documents to the firm.
47.8 Has indulged in construction and erection of defective works.
4 7 . 9 Has supplied inferior quality / defective materials and refused to replace with stipulated time
frame, as specified by the company.
47.10 Has substituted materials In lieu of materials supplied by the Company or has not returned or has
short returned or has unauthorized disposed of materials/ documents/ drawings/ tools or plants or
equipment supplied by the Company
47.11 Has involved in malpractices such as bribery, corruption, fraud, canvassing and pilferage
47.12 Has unauthorized obtained official company information or copies of documents, in relation to the
Tender/Contract
47.13 Has failed to follow the stipulated mode of communication, if specified by the tendering authority/
47.14 Any other ground for which in the opinion of the Company makes it undesirable to deal with the
47.15 In case the State Government directs the Company to place a firm in stop dealing/ banned for
business dealing/ blacklisting
47.16 The firm, stop deal and/or banned for business dealing and/ or blacklist by GUVNL or any
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
subsidiary Companies of GUVNL shall be considered as a stop deal and/ or banned for business dealing
and/ or blacklisting for all Companies.
48 Effect of putting a proprietor/firm for Stop dealing/Banned for business dealing are as below:
48.1 The proprietor/all the partners/directors of the stop deal/ banned for business dealing/ blacklisting
firm shall also be considered for stop deal/ banned for business dealing.
48.2 Once the name of the firm and/ or proprietor/ partner/ director of the firm appears in the list of
Stop dealing / Banned for business dealing in any Company of GUVNL and its Subsidiary Companies,
I. No enquiry shall be issued to a firm.
I I . No bids / tender shall be considered for evaluation and the bid submitted by the Firm shall be
48.3 Action to be taken, when a Firm and/or proprietor/ partner/ director of the firm is put on Stop
dealing/ Banned for business dealing by GUVNL or any of its subsidiary Companies, during tender process:
I. Before opening Technical bids, the bid submitted by the Firm will be treated as “Disqualified Bid” and
automatically stand as “Rejected Bid” at the time of scrutiny of Preliminary / Technical Bid.
II. After opening Technical bid but before opening the price bid, the price bid of the Firm should not be
opened and the bid submitted by the Firm will be treated as “Disqualified Bid” and automatically stand as
“Rejected Bid” at the time of scrutiny of Technical Bid.
III. After opening of price bid, the offer of the Firm should be ignored and will not be further evaluated.
The Firm will not be considered for issue of order even if its price is the lowest. In this situation, the next
lowest bidder shall be considered as L1.
IV. The BG/EMD submitted by the Firm with tender should be returned after obtaining confirmation from
GUVNL and its other subsidiary Companies that there are no outstanding dues recoverable from the firm.
48.4 If a Firm is put on Stop dealing / Banned for business dealing in one Company and is already
executing work and/ or Letter of Acceptance/ purchase order awarded to them by another Company, then
the firm should be allowed to complete such awarded work / supply.
48.5 The amount of EMD/SD/ any payment against supply withheld at the instance of GUVNL or any of
its subsidiary Companies shall be appropriated against the dues recoverable from the firm by GUVNL or
any of its subsidiary Companies. EMD/ SD/ PG in the form of bank Guarantee shall be encashed and
48.6 The Stop dealing/ Banned for business dealing shall be Firm- specific and when a Firm is put on
Stop dealing/ Banned for business dealing, all the manufacturing works of the Firm shall be on Stop
dealing/ Banned for business dealing for GUVNL and its Subsidiary Companies & for all Services of the
48.7 If the Firm placed on Stop Dealing/ Banned for business dealing is a Proprietary Concern, then all
the Concerns of the same Proprietor shall also be considered to be on Stop Dealing/ Banned for business
48.8 The Board of Directors of the concerned Company may however, if he considers it to be in the
interest of the Company, remove the ban in respect of any specific Service from any Contractor for that
48.9 Every bidder should, at the time of submission of bid, give a declaration as per Annexure VIII
attached with this Tender, that bidder and/or proprietor/ partner/ director of the firm has not been placed
on Stop dealing / Banned for business dealing / blacklisting by GUVNL and it’s any Subsidiary Companies.
49 Defense of Suits:
If any action in court is brought against the Owner or Engineer or an officer or agent of the Owner, for the
failure, omission or neglect on the part of the Contractor to perform any acts, matters, covenants or things
under the Contract, or for damage or injury caused by the alleged omission or negligence on the part of the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Contractor, his agents, representatives or his Sub-Contractors, or in connection with any claim based on
lawful demands of Sub-Contractors, workmen, suppliers or employees, the Contractor shall in all such cases
indemnify and keep the Owner, and the Engineer and/or his representative, harmless from all losses,
damages, expenses or decrees arising of such action.
………………………………… (Name of work)
We commit ourselves to trust, transparency and setting ethical standards in implementation of various
works for ultimate long-term benefits for society. We also reiterate our commitment to development to
mutual respect and best practices for setting very high-quality standards in works and attitude.
We abide to accomplish our work with
· Integrity and trust
· Ethics and courtesy
· Transparency and quality.
DGVCL Commitment Contractor’s Commitment
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
· To maintain high ethical standards · Not to bring pressure/recommendation
from outside to influence decision.
· To ensure transparency in transactions
· To abide by general discipline to be
· To ensure to abide by the terms of agreement of maintained in our dealings.
contract and to consider the views of parties objectively.
· To be prompt and reasonable in fulfilling
· To try to ensure timely payments for work done. the terms of agreement of contract and
legal obligations.
· To ensure that no improper demand is made by
employees or by anyone on their behalf. · To ensure high standards are set for
quality of work or supplies at lowest
· To provide maximum possible help to all contractors/ possible cost.
vendors/suppliers and any other party working with us so
that the contracted assignment is completed in time. · Not to use any pressure, threat,
intimidation or inducement of any kind of any of
· To be true and honest in furnishing
specification and information and make all
efforts for completing the contracted
The Executive Engineer, assignment well in time.
Bharuch rural Division
Signature of Contractor
Building ethical Partnership and working Together
SECTION 3: APPENDIX
Sr. No. Appendix Details Particulars Remarks
Bank Guarantee (For Period of To be submitted after
1 Appendix – II
Execution of Works) LOA
To be submitted after
2 Appendix – III Contract Agreement
Bank Guarantee (For Guarantee / To be submitted after
3 Appendix – IV
Warrantee Period) completion of works
Combined Bank Guarantee (For
To be submitted after
4 Appendix – V Period of Execution of works and
completion of works
Guarantee Period)
ON STAMP PAPER OF RS.300/-
FORM OF BANKER’S UNDERTAKING
[For Performance Guarantee (PBG) towards execution/ supply Period as per Commercial Terms
and Conditions of Tender]
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
We, (Name of the Bank and Address of the Branch giving the Bank Guarantee) having our registered
office at (Address of Bank’s registered office) hereby give this Bank Guarantee No.
and hereby agree Unequivocally and Unconditionally to pay immediately on demand in writing
from the beneficiary Company (Name of Gujarat Urja Vikas Nigam Ltd./ subsidiary Company) or
any officer authorized by it in this behalf any amount up to and not exceeding Rs. (Amount of
Performance Guarantee towards execution/ supply period), (Rupees (in words)) to the said
(GUVNL/ subsidiary Company) on behalf of M/s. who have entered into a contract for the
supply/works specified below:
LOA No. dated .
This agreement shall be valid and binding on this Bank up to and inclusive of
(Date of validity of the Bank Guarantee) and shall not be terminable by notice or by change in the
constitution of the Bank or the firm of Contractors / Suppliers or by any other reasons whatsoever and our
liability hereunder shall not be impaired or discharged by any extension of time or variations or alterations
made, given conceded or agreed, with or without our knowledge or consent, by or between parties to the
said within written contract.
Notwithstanding anything contrary contained in any law for the time being in force or banking practice, this
Guarantee shall not be assignable, transferable by the Beneficiary (i.e. GUVNL or Subsidiaries). Notice or
invocation by any person such as assignee, transferee or agent of beneficiary shall not be entertained by the
Bank. Any invocation of the Guarantee can be made only by the beneficiary directly.
NOTWITHSTANDING anything contained herein before, our liability under this guarantee is restricted to
Rs. (Rupees only). Our guarantee shall remain in force until
(Date of validity of the Bank Guarantee). Unless demands or claims under this Bank Guarantee are
made to us in writing on or before (Date of validity of the Bank Guarantee), all rights of
Beneficiary under this Bank Guarantee shall be forfeited and we shall be released and discharged from all
liabilities there under:
Please Mention here Complete Postal Address of Signature of the Bank’s Authorised Signatory
the Bank with Branch Code, Telephone and Fax with Official Round Seal.
NAME OF DESIGNATED BANKS:
1. All Nationalized Banks including Public Sector Bank IDBI Bank Ltd.
2. Private Sector Banks authorized by RBI to undertake the state Government business, which are (i) Axis
Bank (ii) ICICI Bank (iii) HDFC Bank
Note: The banks shall be the Banks recognized / notified by the Finance Department, Government of
Gujarat (GoG) from time to time.
THIS AGREEMENT made on this ____ day of ______ Two Thousand Eighteen.
M/s.___________________________________________________, having Registered Office at
_____________________ Authorized Person of the ONE PART.
DAKSHIN Gujarat Vij Company Ltd, having Registered Office at Bharuch rural Division, Maktampur
Bharuch and represented by __________________________________________________ of the OTHER PART.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
WHEREAS, the Supplier willingly submitted bids for the Tender No ____________________________ of the
Purchaser company for supply of
___________________________________ as specified and as per delivery instructions provided in the Acceptance
of Tender (AT) / Letter of Acceptance (LOA) issued vide No
Company at the accepted respective prices or rates mentioned against the said items / materials.
AND WHEREAS THE PURCHASER Company has accepted the tender of the Supplier for the supply for
upon the terms and subject to the conditions herein mentioned in the agreement.
AND WHEREAS, a list is made out in the “SCHEDULE” hereunder written and all of which said
documents of the Schedule are deemed to form part of this agreement and included in the expression “the
Supply” wherever herein used, upon the terms and subject to the conditions hereinafter mentioned.
NOW THIS AGREEMENT WITNESSES AS UNDER AND IT IS HEREBY AGREED AND DECLARED
I ) The Supplier has accepted the Terms and Conditions set out in the Tender Notice
No. ______________________________________________ as well as in the form of Acceptance of Tender (AT) /
Letter of Acceptance (LOA) No. ________________________________________ Dtd. ____________________ which will
hold good & valid during the period of this Agreement.
I I ) The supplier shall do and perform for all supplies and things in this agreement mentioned and
described or which are implied therein or there from respectively or are reasonably necessary for the in-
time and in manner supplies as mentioned and subject to the general / commercial terms & conditions and
stipulations contained in this agreement.
I I I ) In consideration of the due provision, executions, completion of the Supply, as agreed to by the
Supplier as aforesaid, the Purchaser company hereby agrees to pay all the sums of money as and when they
become due and payable to the supplier under the provisions of the agreement and such payment to be
made at such times and in such manner as provided in the agreement.
I V ) In respect of the said Tender as per the terms & conditions of this Agreement, the Supplier has
deposited amount in Cash or DD or has provided valid Bank Guarantee of Rs
Purchaser Company towards performance guarantee of execution period i.e. for security deposit of the
supply material / items.
V) Upon breach by the Supplier of any of the conditions of this Agreement, the Purchaser Company may
give a notice in writing to rescind, determine and put to an end to the A/T without prejudice to the right of
the Purchaser company to claim damages for antecedent breaches thereof on the part of the Supplier and
also to claim reasonable compensation / risk & cost purchase for the loss occasioned by the Purchaser
Company due to failure of the Supplier to fulfill the Order as certified in writing by the Purchaser for which
Certificate shall be conclusive evidence of the amount of such compensation payable by the Supplier to the
V I ) The Purchaser Company shall not be bound to take the whole or any part of the ordered quantity
herein or therein mentioned in the LOA / AT and may cancel the contract at any time after giving TWO
MONTH’S NOTICE IN WRITING without compensating the Supplier.
VII) This Agreement shall remain in force till the expiry of satisfactory performance of the Supply during
Guarantee / Warranty period including for the quantity mentioned in the repeat order, if any as per the
terms & conditions of the LOA / AT.
VIII) Any Notice in connection with the Supply including the Notice for termination may be given by
the Purchaser or any Authorized Officer for the said purpose as per the Commercial Terms & Conditions of
I X ) If subject to the circumstances beyond control i.e. Force Majeure conditions, the Supplier fails to
deliver the materials, the same shall be governed as per the Tender Documents.
X) The agreed value, extent of supply, delivery dates, specifications, and other relevant matters may be
altered by mutual agreement as per the policy of the purchaser Company and if so altered shall not be
deemed or construed to mean or apply to affect or alter other general / commercial terms & conditions of
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
the agreement and the agreement so altered or revised shall be and shall always be deemed to have been
adhered subject to and without prejudice to said stipulation.
XI) The following is the Schedule forming part of this agreement as provided herein above:
List of documents:
2. Tender technical specification and GTP.
3. Tender’s terms and conditions.
In witness whereof the parties here to have set their hands and seals this day, month and year first
1. Signed, Sealed and delivered by:
Authorized Person
In the presence of Name, Full Address & Signature:
2. Signed, Sealed and Delivered by:
For and on behalf of M/s. Dakshin Gujarat Vij Company Ltd. (Purchaser)
DGVCL, Corporate office,
In the presence of Name, Full Address & Signature:
ON STAMP PAPER OF RS.300/-
FORM OF BANKER’S UNDERTAKING
[For Performance Guarantee (PBG) towards Guarantee/ Warranty Period as per commercial terms and
conditions of tender]
We, (Name of the Bank and Address of the Branch giving the Bank Guarantee) having our registered
office at (Address of Bank’s registered office) hereby give this Bank Guarantee No. dated
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
and hereby agree Unequivocally and Unconditionally to pay immediately on demand in writing from the
Beneficiary Company (Name of Gujarat Urja Vikas Nigam Ltd./ subsidiary Company) or
any officer authorized by it in this behalf any amount up to not exceeding Rs. (Amount of Performance
Guarantee towards Guarantee/ Warranty period), (Rupees (in words)) to the said
(GUVNL/ subsidiary Company) on behalf of M/s.
who have entered into a contract for the supply/works specified below:
P. O. (A/T). No. dated .
This agreement shall be valid and binding on this Bank up to and inclusive of
(Date of validity of the Bank Guarantee) and shall not be terminable by notice or by change in the constitution
of the Bank or the firm of Contractors / Suppliers or by any other reasons whatsoever and our liability hereunder
shall not be impaired or discharged by any extension of time or variations or alterations made, given conceded or
agreed, with or without our knowledge or consent, by or between parties to the said within written contract.
Notwithstanding anything contrary contained in any law for the time being in force or banking practice, this
Guarantee shall not be assignable, transferable by the Beneficiary (i.e. GUVNL or Subsidiaries). Notice or
invocation by any person such as assignee, transferee or agent of beneficiary shall not be entertained by the Bank.
Any invocation of the Guarantee can be made only by the beneficiary directly.
NOTWITHSTANDING anything contained herein before, our liability under this guarantee is restricted to Rs.
(Rupees only). Our guarantee shall remain in force until (Date of
validity of the Bank Guarantee). Unless demands or claims under this Bank Guarantee are made to us in writing
on or before (Date of validity of the Bank Guarantee) , all rights of the Beneficiary under this Bank Guarantee
shall be forfeited and we shall be released and discharged from all liabilities there under:
Please mention here Complete Postal Address of the Bank Signature of the Bank’s Authorized Signatory
with Branch Code, Telephone and Fax Nos.
With Official Round Seal.
NAME OF DESIGNATED BANKS:
1. All Nationalized Banks including Public Sector Banks IDBI Bank Ltd.
2 . Private Sector Banks authorized by RBI to undertake the state Government business, which are (i) Axis
Bank (ii) ICICI Bank (iii) HDFC Bank
Note: The Banks shall be the Banks recognized / notified by the Finance Department, Government of Gujarat (GoG)
from time to time.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
ON STAMP PAPER OF RS.300/-
FORM OF BANKER’S UNDERTAKING
[Combined Performance Guarantee (PBG) towards Execution /supply Period and Guarantee/ Warranty
Period as per commercial terms and conditions of Tender]
We, (Name of the Bank and Address of the Branch giving the Bank Guarantee) having our registered
office at (Address of Bank’s registered office) hereby give this Bank Guarantee No. dated
and hereby agree Unequivocally and Unconditionally to pay immediately on demand in writing from the
Beneficiary Company (DGVCL) or any officer authorized by it in this behalf any amount up to not
exceeding Rs. (Amount of combined Performance Guarantees towards Execution /supply Period and
Guarantee/ Warranty Period),
(Rupees (in words)) to the said (DGVCL) on behalf of M/s. who have entered into a contract for the
supply/works specified below:
L.O.A. No. dated .
This agreement shall be valid and binding on this Bank up to and inclusive of
(Date of validity of the Bank Guarantee) and shall not be terminable by notice or by change in the constitution
of the Bank or the firm of Contractors / Suppliers or by any other reasons whatsoever and our liability hereunder
shall not be impaired or discharged by any extension of time or variations or alterations made, given conceded or
agreed, with or without our knowledge or consent, by or between parties to the said within written contract.
Notwithstanding anything contrary contained in any law for the time being in force or banking practice, this
Guarantee shall not be assignable, transferable by the Beneficiary (i.e. GUVNL or Subsidiaries). Notice or
invocation by any person such as assignee, transferee or agent of beneficiary shall not be entertained by the Bank.
Any invocation of the Guarantee can be made only by the beneficiary directly.
NOTWITHSTANDING anything contained herein before, our liability under this guarantee is restricted to Rs.
(Rupees only). Our guarantee shall remain in force until (Date of
validity of the Bank Guarantee). Unless demands or claims under this Bank Guarantee are made to us in writing
on or before (Date of validity of the Bank Guarantee), all rights of the Beneficiary under this Bank Guarantee
shall be forfeited and we shall be released and discharged from all liabilities there under:
Please Mention here Complete Postal Signature of the Bank’s Authorized Signatory
with Official Round Seal.
Address of the Bank with Branch Code,
Telephone and Fax Nos.
NAME OF DESIGNATED BANKS:
1. All Nationalized Banks including Public Sector Banks IDBI Bank Ltd.
2. Private Sector Banks authorized by RBI to undertake the state Government business, which are (i) Axis Bank
(ii) ICICI Bank (iii) HDFC Bank
Note: The Banks shall be the Banks recognized / notified by the Finance Department, Government of Gujarat (GoG)
from time to time.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
SECTION 4: ANNEXURE
Sr. No. Annexure Details Particulars
1 Annexure – I Self-Certificate
2 Annexure – II Details of the Experience
3 Annexure – III List of Performance Certificate
4 Annexure – IV Details of Pending Orders as on Bidding Date
5 Annexure – V Self-Declaration
6 Annexure – VI Declaration regarding Conflict among bidders
7 Annexure – VII Technical & Commercial Deviation, if any
8 Annexure – VIII Undertaking in regard to Stop Deal / Black List
9 Annexure – IX Certificate A
10 Annexure – X Important Instructions
11 Annexure – XI List of Type Test Reports / Certificate
Details of Fatal / Non-Fatal Accidents Occurred To the
12 Annexure – XII
Contractor Labours
UNDERTAKING IN REGARD TO ANY PENDING CRIMINAL
13 Annexure – XIII
CASE FOR FRAUD OR MISHANDALING OF MATERIAL
14 Annexure – XIV List of Safety Gadget owned by the bidder
15 Annexure – XV Indemnity Bond
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
Reference: Tender enquiry No.: COMPANY/ /
Due on date: / / 201 .
In connection with the above subject and reference I/ We confirm the following:
1. I / We, the under signed have read and examined the Tender Specifications in tender mentioned under
reference along with the Commercial terms and conditions.
2 . I / We, declare that our Technical Bid is strictly in line with the Tender specifications (except the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
deviations shown in Annexure - VII of Technical Deviations as per clause no. 11 of this tender document).
3. Further, I / We also agree that additional conditions / deviations, if any, found in the Commercial terms
& conditions (except reference under clause no. 11 of this tender document), our offer shall be out rightly
rejected without assigning any reason thereof.
Seal of the Firm Signature of the Authorized Representatives of
Name of the Tendering Firm / Agency:
DETAILS OF THE EXPERIENCE FOR SUPPLY OF TENDER ITEM /SIMILAR TYPE OF TENDER ITEM IN
LAST FIVE YEARS FROM THE DUE DATE OF TENDER:
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
Description of Work Amount
No No./Date placing
Completion date as Date of commencement Date of actual
per order of work completion of work
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
LIST OF SATISFACTORY PERFORMANCE CERTIFICATES
(PHOTO COPY/IES OF PERFORMANCE REPORT/S TO BE UPLOADED IN TECHNICAL STAGE OF
ONLINE MODE / e-TENDER FORMAT ONLY)
Name of the Authority by whom
Reference No. & Date Details of items supplied
No. certificate is issued
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Details of Pending Orders, tendered for & on hand, as on the date of the submission of this
(To be completely filled by the Bidder)
NAME OF WORK ON HAND WORK TENDERED FOR
SR ITS COST OF ANTICIPATED DATE WHEN
TENDER ESTIMATED DATE OR REMARKS
NO LOCATION REMAINING DATE OF DECISION IS
COST COST PERIOD OF
AND WORK COMPLETION EXPECTED
• If necessary, separate sheet may be used to submit the information.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
(Strike off whichever is not applicable)
This is to declare that Mr. /Ms. , employee of DGVCL at _____________ (place), is
related to our _______________designation & name).
This is to declare that none of the Proprietors/ Partners/ Directors are having any relatives
employed or working with DAKSHIN Gujarat VijCo.Ltd.at any of its offices or its parent
Department i.e. Energy & Petrochemicals Dept., Govt. of Gujarat.
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
(Duly Notarized) on Rs.300/- Non-Judicial Stamp Paper
(as per tender condition)
I_____________________________________ authorized signatory of M/s.
that Mr./Mrs./Ms. ________________________________ is our Company’s
authorized representative and he/she is employee of our Company/Firm. It is
further declared that he/she is not representative/employee of any other
He/She is authorized for coordination/follow up relating to this tender.
Details of Authorized Representative
Designation : ______________________
Contact Number : __________________
Office Address : ___________________
Accepted and confirmed the above facts
Specimen Signature : __________________
It is certified that signed made by above authorized representative in my
Signature of Authorized signatory : ________________
Designation : ______________________
Contact Number : __________________
Office Address : ___________________
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
TECHNICAL& COMMERCIAL DEVIATIONS, IF ANY, TO BE FURNISHED IN THIS ANNEXURE ONLY
Deviation offered to Chapter
No, Clause No. of the tender
document Deviation offered
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
ANNEXURE – VIII
(UNDERTAKING IN REGARD TO STOP DEAL / BANNED FOR BUSINESS DEALING / BLACK LIST
Sub: Undertaking in regard to Stop Deal / Banned for Business dealing / Black List Thereof.
Ref: Tender No.:
their proprietor / any partner / any directors of the firm is not stop deal and/or banned for business dealing
and/or black listed by GUVNL and/or their any subsidiary company viz. GSECL / GETCO / DGVCL / MGVCL
/ UGVCL / PGVCL.
Signature of the Tenderer
Seal of the Firm
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Tender No. COMPANY/
On Firm’s Letter Head
CERTIFICATE – “A”
hereby certify that M/s.______________________________________ is not related with other firms who have
submitted tenders for the same items under this inquiry / Tender.
Seal of the Firm Signature of the Tenderer
With Designation
(TO BE SUBMITTED / FILLED IN ONLINE / e-TENDER FORMAT ONLY)
Tender No. COMPANY/
IMPORTANT INSTRUCTIONS
1. The Tenderer should clearly give certificate along with the Technical Bid:
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
“This is to confirm and certify that the offer submitted by me is strictly in accordance with COMPANY Tender
specifications, Guaranteed Technical Particulars and drawing as mentioned in the Tender Specifications. There is
no commercial or Technical deviation (except the deviations shown in Annexure of Technical Deviations as per this
tender document) in the offer from COMPANY Tender Specification. I undertake to abide by COMPANY Technical
specification / Guaranteed Technical Particulars / Drawing, I undertake to supply materials strictly as per
COMPANY Technical specification / Guaranteed Technical Particulars / Drawing, even if any technical deviations
are mentioned by me. I also undertake to abide by all commercial conditions of COMPANY, including delivery
2 . Any offer without above certificate will not be considered and the tender will be out rightly ignored in the
absence of above certificate.
3. After opening of the Tender, if it is found that the offer given by the Tenderer is not according to COMPANY
specifications, Guaranteed Technical Specifications, Drawing and commercial terms and conditions and false
certificate is given by the Tenderer, then COMPANY will not deal with the firm for the present Tender. It is,
therefore requested that the Tenderer should take care in giving their offer and submission of documents,
including Type Test certificate.
4. The conditional tenders will not be accepted.
5. In connection with the above subject and reference I/We confirm the following:
I. I/We the under signed have read and examined the Bid specifications in Bid mentioned
under reference along with the Condition of Contract (Commercial and Legal)
II. I/We declare that our Technical Bid is strictly in line with the Bid specifications (expect the
deviation shown in Annexure of technical deviation as per Clause no. 7.7 of section 2 of the Bid document).
III. Further I/We also agree that additional conditions/deviations, if any found in the Condition of
Contract (Commercial and Legal) (except reference under clause no. 7.7 of section 2 of this Bid document) our
offer shall be out rightly rejected without assigning any reason thereof.
(Signature of the Tenderer)
LIST OF TYPE TESTS REPORTS SUBMITTED WITH THE TECHNICAL BID
(For the work of Laying of HT/LT Underground Cable) (Not Older than 7 Years)
Sr. No Type Test Tests Carried out Rating & Type / Name of the test Results Of
Report No. & at (Name of Designation of Item / Conducted the Tests.
Date Laboratory) Equipment
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
Details of Fatal/Non-Fatal Accidents Occurred To the Contractor Labours during Last Five Years
Nos. of Affected
Sr. Type Of Accident Fatal/Nonfatal Labour/s Brief Reason for the
No. (Electrical/Mechanical) Accident
UNDERTAKING IN REGARD TO ANY PENDING CRIMINAL CASE FOR FRAUD OR
MISHANDALING OF MATERIAL
All bidders will have to furnish the following undertaking duly filled in signed and stamped for each quoted
item of the tender along with the Technical Bid.
M/s_____________________________________________ hereby declare that none of the Proprietors/ Partners/
Directorsis not under any criminal investigation for any kind of fraud for theft of material or/and with
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
handlings the material and any civil and/or criminal case pending for such matter listed by GUVNL and or
any subsidiary companies viz. PGVCL / UGVCL / DGVCL / MGVCL / GSECL / GETCO for the tendered items
Seal of the Firm
Signature of the Tenderer with Designation
List of Safety Gadgets Owned by Bidder
Sr. Nos. gadgets owned by
No. List of Safety Gadget Unit bidder
2 Earthing Rod No
4 Safety Belt No
5 Hand Gloves for LT Pair
6 Hand Gloves for HT Pair
7 Other safety items
In consideration of the DAKSHIN GUJARAT VIJ COMPANY LTD. , herein after known as the COMPANY
having given contract for the work of
as per A/T No. , dated and all future contract that may be awarded to me in
the next one year and in terms of the condition in instruction to bidder clause 27 of the COMPANY’s tender
and contract for work.
I residing at by this Bond bind myself responsible for and shall pay compensation to my
workmen payable under the workmen’s compensation ACT – 1923 (viii of 1923) hereinafter called the said
Act for death or injuries caused to the workmen engaged by this presents, if such compensation is paid by
the COMPANY as principal under such sub-section (1) of section 12 of the said Act on behalf of me, to pay
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Letter No: DGVCLDBHR/0455/05/2026 Approved Date: 22-05-2026
such amount of compensation on demand within 48 hours to the COMPANY that it might have to spend as
legal and other incidental charges in defending any suit or action arising out of the death of injuries in
regard to compensation paid to the workmen or heirs of the deceased workmen.
Now the condition of the above written Bond is such that any suit of action arising out of the death or
injuries to the workmen engaged by me. During the execution of work of said contract and all future
contracts that may be awarded to me in the next one year is filed by the worker against the COMPANY, I
shall imbrues to the COMPANY such sum that the COMPANY is required to spend as legal and other
incidental charges in defending such suit or action and also the amount that may be ordered to be paid to
the worker / or his heirs as compensation and that the above written bind shall remain in full force and
virtue till the COMPANY is required to defend such suit or action filed by the workers and or heirs against
the COMPANY. Further it is applicable on death of contractor himself also. No any compensation will be
claimed by legal heirs of contractor.
Witnesses: Signature of the
File No: DGVCLDBHR/TEN/e-file/4444/2026/1489/Technical
Approved By: Executive Engineer,Technical,DGVCLDBHR
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Schedule B Amod.pdf
Tender Condition BRH-2026-27-26.pdf
Tender Notice BRH-2026-27-26.pdf
Download all tender documents and submit your bid