| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.0 LAccepted-AOC C O GK POWER TECH ENTERPRISES VILL DOKRU PO ROHAL TEHSIL JHANDUTTA DISTT BILASPUR H P | ₹5.0 L Quoted ₹5.1 L | L1 | Accepted-AOC Award letter |
| 2 | L2₹5.2 L+₹5,783.56 (1.13%)Rejected-Finance VILL BHANTREHED PO BAROTI SUB TEH DEHAR MANDI HP 175030 | MANDI | HIMACHAL PRADESH | 175030 | ₹5.2 L+₹5,783.56 (1.13%) | L2 | Rejected-Finance Higher side |
| 3 | L3₹5.3 L+₹14,458.89 (2.83%)Rejected-Finance VILL BAROTA JATTAN P O BERI RAJDIYA TEHSIL SADAR DISTT BILASPUR HP | ₹5.3 L+₹14,458.89 (2.83%) | L3 | Rejected-Finance Higher Side |
Tender Value
₹4.8 L
EMD Value
₹4,820
Closing Date
15 Jun 2026, 10:00 amClosed
Sr. Executive Engineer
Electrical Engineer HPSEBL, Ghumarwin.
Tender for SOP to subject matter specialist (Horticulture) Ghumarwin, Distt- Bilaspur, for HP Shiva Cluster Lehad by Augmentation of 63 KVA to 100 KVA, 11/0.4 KV S/Stn. Dohra Sunhani along with 3 phase LT line in (E) section Berthin1st under ESD BRT
2026_HPSEB_136053_1
NIT-21/2026-27
Open Tender
Electrical Works
Percentage
15 days
Ghumarwin
Please refer Tender documents.
4 documents required · 4 mandatory
₹590
₹4,820
24 Jun 2026
8 Jun 2026
15 Jun 2026
8 Jun 2026
15 Jun 2026
8 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Erection of 63 KVA ,11/.4 KV Sub-Station | |||||
| 0.000 | Erection of 100 KVA 11/0.4 KV S/Stn. , LT Cable 3.5 core 120 mm2, LT distribution pannel box with MCCB & Energy meter etc. complete in all respect. | 1 | Job | - | - |
| 0.000 | Mannual carriage of 100 KVA 11/0.4 KV transformer a/w LT boxes with MCCB ,LT cable3.5 Core 120 mm2 etc. from nearest road head side to site of work, considering average lead 0.150 KM. | - | Km | - | - |
| 0.000 | Dismantelling of existing 63 KVA 11/0.4 KV Distribution Transformer a/w accessories etc. & carriage of dismentalled material from site to HPSEBL Divisional Store. | 1 | Job | - | - |
| 0.000 | Erection of LT Line | - | - | - | - |
| 0.999 | Erection of Steel tubular pole 9 mtr. Long (LT) :-Digging of pit for poles, drilling of holes in poles,,erection of poles, erection of RCC muff, erection of D-iron, shackle insulator,earth hook filling of pit and ramming,Painting of poles etc, complete in all respect. | 3 | Nos. | - | - |
| 0.000 | Stay set (LT):- Digging of pit(0.8x1.2x1.35m),fixing of stay rod, filling and ramming of pit, nozzelling and tightening, . complete in all respect. | 5 | Set | - | - |
| 0.999 | Earthing set(LT):- Digging of pit(0.8x1.2x1.5m),fixing of G.I wire to earth system, filling and ramming of pit, etc. complete in all respect. | 3 | Set | - | - |
| 0.000 | Laying, stringing and sagging of AAAC/ACSR 50 mm, (4 wire) 3-Ø LT line:-Laying of conductor, stringing and sagging, binding with insulator, making jumpers on dead poles etc. complete in all respect.(Rate to be quoted per KM per wire) | - | KM | - | - |
| 0.999 | Laying, stringing and sagging of G.I. earth Wire, (1 wire) of 3- Ø LT line:-Laying of G.I. Wire, stringing and sagging, binding with insulator, making jumpers on dead poles etc. complete in all respect.(Rate to be quoted per KM per wire) | - | KM | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.57 MB
BOQ_201412.xls
BOQ • 0.31 MB
Biddocument21to25.pdf
Tender Documents • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .