Executive Engineer, RWSS Division, Berhampur
Near Jarada Bunglow, Berhampur
Laying of pipelines, Construction of valve Chambers, Construction of 40KL ltrs capacity RCC OHR, ,providing 100percent FHTC etc. in connection with PWS to Kirtipur under Sheragada Block.
2020_RWSS_63866_7
EERWSSBAM- 13 ( C ) / 2020-21
National Competitive Bid
Civil Works - Water Works
Item Rate
140 days
PWS to Kirtipur under Sheragada Block.
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹34,470
Yes
11 Mar 2021
16 Nov 2020
27 Nov 2020
16 Nov 2020
26 Nov 2020
16 Nov 2020
16 Nov 2020 - 20 Nov 2020
Amount
Laying of pipe line ,Head works, Other Balance Works
Supplying all materials labour T&P for Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber, bore well platform,recharge pit,individual house hold connection,, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to B). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
Construction of 40,000 LTR OHR WITH 12M STAGING Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 40000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR at his own cost)
HIMANSHU SEKHAR PADHI
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .