| 1 | L1₹1.5 CrAccepted-AOC B 184 SECOND FLOOR GUPTA JI PLAZA NHPC CHOWK FARIDABAD HARYANA 121010 FARIDABAD HARYANA 121010 | FARIDABAD | HARYANA | 121010 | ₹1.5 Cr | L1 | Accepted-AOC Awarded cost includes SITC cost and Operation and Maintenance cost. |
| 2 | L1₹4.1 CrRejected-Finance | ₹4.1 Cr | L1 | Rejected-Finance Being b L12 |
| 3 | L2₹1.6 CrRejected-Finance | ₹1.6 Cr | L2 | Rejected-Finance Being L2 |
| 4 | L3₹1.7 CrRejected-Finance | ₹1.7 Cr | L3 | Rejected-Finance Being L3 |
| 5 | L4₹1.9 CrRejected-Finance | ₹1.9 Cr | L4 | Rejected-Finance Being L4 |
Tender Value
₹1.7 Cr
Closing Date
29 Sept 2021, 6:00 pmClosed
AGM Engg (E)
Operational Office, NSCBI Airport, Kolkata - 700052
Construction of 3 Hangars for C category aircrafts connecting apron and taxi link (Naryanpur side) at NSCBI Airport, Kolkata. SH SITC of 75 KLD Sewage Treatment Plant (STP) based on MBR Treatment, Water Treatment Plant (WTP) and submersible pump
2021_AAI_84760_1
AAC/CIRCLE - III/ WTP and STP/ 2021-22
Open Tender
Electrical Works
Item Rate
150 days
NSCBI Airport, Kolkata
Please refer Tender Document
17 documents required · 17 mandatory
₹1,120
Exempted
7 Jan 2022
31 Aug 2021
1 Oct 2021
1 Sept 2021
29 Sept 2021
1 Sept 2021
1 Sept 2021 - 20 Sept 2021
Amount
SH-I PUMP ROOM
Design, Supplying, installing, testing & commissioning of on Membrane Bio Reactor (MBR) Sewage Treatment Plant of 75 KLD in one module of 75 kld capacity (excluding Civil construction work) for the following duty Sewage treatment plant shall include the following items Screen chambers with SS Screen as per the technical specification. Equalization Tank in RCC Aerobic tank in MSFRP (Inside coating) Anoxic tank in MSFRP (Inside coating) MBR TANK in MSFRP (Inside Coating) Sludge Holding tank in MSFRP ( Inside Coating) Air Blowers (Seperate sets for MBR & Aeration, EQT & SHT)) Submerged MBR Membranes Recirculation pumps, backpulse pump, permeate pump etc. Chemical Cleaning System Air Compressors if necessary CIP System Electrical Panel, Cabling (Power & Control), Earthing Clear Water tank and Soft Water tank in MSFRP (Inside Coating)
(i) Supply, installation, testing & commissioning MSFRP Tanks as mentioned above of 5 mm thick MS plate & 2 mm thick FRP Coating (Inside)
Supply, installation, testing & commissioning of Stainless Steel Perforated, Corrugated Bar Screen with suitable lifting arrangement of following mesh sizes:
(i) Coarse Screen - 10 mm mesh size
(ii) Screen - 5 mm punched hole
(iii) Automatic Fine Screen (Rotary Drum Type) with Self Cleaning Backpulse arrangement - MOC: SS 304, Flow Rate: As per Vendor , Provision for Overflow & Drain. With Greated Motor - 15 to 20 RPM & required torque for continuous operation.
Supply,Installation,Testing and Commissioning of automatic belt type oil skimmer SS for grease trap of suitable size of minimum1200mm liquid depth in brick work of class 75 with cement mortar (1:6), inside plastering 16 mm thick with cement mortar 1:3 with floating coat of neat cement and rough plaster on outside. Including SS bucket to collect the grease. (suitable of 75 KLD flow)
Supply,Installation,Testing and Commissioning of MS hot dip galvanized puddle flanges in accordance to BS:10 table D as required to be provided (in the structural slab and wall) of various diameters. Puddle flanges shall be provided for all the structural component of the STP. For the installation of the puddle flanges vendor to depute the engineer to the same at the required levels & position.
Supply,Installation,Testing and Commissioning of plastic manhole step / foot rest (@ 300 mm c/c) with polypropelene compound injection molded around 16 mm dia (Fe-415) steel reinforcing bar. Provision of the foot rest is envisaged in all the tanks/ components of the STP for the purpose of accessability. The installation of the foot rest shall be done by the civil contractor as per civil GA drawing
Supply, installation, testing & commissioning of double seal CI medium duty rectangular manhole cover with frame for the feasibility of access in the tank with locking arrangement. Size : 600 x 900x 10 mm thick (Approximate 45 Kg weight)
Supply, installation, testing & commissioning of non clogging type pumps having CI casing & SS impeller complete with all accessories, motor of required capacity including pressure gauge on delivery line with isolation cock, isolation valve, check valve, flow meter, level switch, level controller (with wiring) to control the level of sump automatically. Pumps shall have following duty Submersible Sewage Pumps for transfer of Effluent from EQT to Anoxic Tank (1 working + 1 Standby) Flow rate (each) - 3.75 cubic meter /Hr Head (Mtr) - 15 m (Solid handling size for this pump shall be 30 to 50 mm). Provision of guide ropes to guide submersible pump from upper level to operational level in sump basin with channels / angle section of MSEP shall be made by the STP contractor
Submersible Agitator / Mixer for Anoxic Tank with suitable RPM in SS / PP MOC each suitable of one module of 75 KLD.
(i) For MBR (1 Working + 1 Standby) Capacity : As per Membrane Manufacturer
(ii) Root blower for Equalisation tank, Aeration tank & Sludge holding tank ( 1 working +1 stand by) Capacity : 90 cubic meter/hr @ 5000 mm WC ( Minimum)
(i) Diffuser complete with hold down assemblies for equity tank
(ii) Diffuser complete with hold down assemblies for sludge holding tank
(iii) Diffuser complete with hold down assemblies for aeration tank
Air piping shall comprise of pipes droppers/ laterals with MS epoxy (non submerged) / SS 304 (submerged) Header complete with all fittings such as tees, crosses, plugs, sockets, elbows, reducers, supports & clamps, puddle flanges etc cutting chases & making good. Contactor to submit detailed P & I indicating their proposal.
Providing and fixing all piping (as described below) and isolation control valves for making the system complete.All pump should have strainer,suction valve ,discharge valve and NRV. SS 304 : Submerged air piping MS Epoxy : Air piping & pumped effluent riser (non submerged) PVC piping : Pumped effluent (submerged) & tank overflow pipe line GI (Heavy) : Interconnecting pipe line after delivery header of pump/ filter
Supplying, installing, testing & commissioning of semiautomatic hydraulic filter press along with screw pump (1 working +1 stand by), pressure gauge with isolation cock, Isolation valve. Capacity : 1 m3 / hr. Discharge Head : 60 m RPM : 1500
Supply, installation, testing & commissioning of sludge re circulation pump. Each shall be of non-submersible type centrifugal pump with suction grid and automatic discharge connection. Pump casing and impeller shall be of cast iron material. Shaft shall be of CS material.( 1 working +1 standby) Capacity : 20 cubic meter/hr @ 10 mtr (1 working + 1 standby)
Supply, installation, testing & commissioning of Chemical Cleaning system comprising Chemical Cleaning tank filled with Sodium Hypochlorite solution in required proportion and centrifugal pump. The system shall be comprising of following in addition to isolation valves, check valves, level switches and and other associated piping, valves and items as per approved P&I. Tank Capacity : As per Membrane Manufacturer Pump capacity : As per Membrane Manufacturer Head : As per Membrane Manufacturer
Supply, installation, testing and comissioning of membrane modules consisting of hollow fibre membranes housed in SS 304 housing with SS 304 permeate water manifold and aeration diffuser system capable of delivering the required flow of 75 KLD of effluent through the module. The cost shall be inclusive of cyclic air valve, level transmitter of membrane tank, isolation valves, pressure transmitter and other associated piping, valves and items as per approved P&I. The flux shall be max 25 LMH Membranes shall be physically strong enough to withstand the operating conditions associated with continuous operation in an aerated tank of mixed liquor at concentrations of up to 10,000 mg/L. If required, membranes shall be capable of regular backwashing with and without cleaning chemicals to minimize pore fouling. Max 25 LMH flux shall be considered to arrive at total membrane area required to treat specified waste water quantity. The minimum membrane warranty for life of membranes should be for minimum 5 years The membrane rack / cassette shall include connection points for agitation air and permeate water. All metallic components of each membrane rack/cassette shall be manufactured from stainless steel with a minimum grade of at least Type SS 316. It shall be possible to isolate and remove each membrane rack / cassette from the manifold header pipework while the system is in operation. Permeate System: All the racks/cassettes in each membrane tank shall be connected to a common header which discharges the permeate by pumping. Back pulse pumps, if required, shall also be provided. Clean-In-Place System: The membranes shall be cleaned “in-place” without removal from the membrane tank. The system shall consist of a chemical feed pump (if required) and storage tank (if required) and include all interior piping, valving, and in-tank piping and supports. Maintenance Cleaning: The “maintenance clean” system must be fully automated. This type of cleaning shall not be performed more than once a week and shall not require each MBR tank to be taken out of service for more than 30 minutes. Recovery Cleaning (if required): The “recovery clean” system shall be either fully automated or partially automated with only limited operator’s attention needed. This type of cleaning shall not be performed more than two times a year. Neutralization system, if required, must be included to handle the soak solution after the cleaning process. The cleaning period shall not require each MBR tank to be taken out of service for more than 12 hours.
Supply, installation, testing & commissioning of Chemical Cleaning system comprising Chemical Cleaning tank filled with Citric Acid solution in required proportion and centrifugal pump. The system shall be comprising of following in addition to isolation valves, check valves, level switches and and other associated piping, valves and items as per approved P&I. Tank Capacity : As per Membrane Manufacturer Pump capacity : As per Membrane Manufacturer Head : As per Membrane Manufacturer
Supply, installation, testing & commissioning of the PLC based compartmentalized control panel of 14 gauge CRCA sheet steel, powder coated with interlocking arrangement with supply pumps, suction pumps, chemical cleaning tank, modulating or shut-off valves including necessary wiring, RS 485 communication port, magnetic switches & sensors complete to make the system functional with following interlocking Suction pump stop Suction pump`s head loss greater then set suction head Supply pump stop Suction pump stop & Chemical cleaning pump start Suction pump`s head loss greater then set suction head Suction pump`s suction header valve stop Suction pump`s head loss greater then set suction head Chemical pumps delivery valve open in suction pump`s suction header
Supplying, installing, testing & commissioning of (Permeate / Backpulse Pumps) Horizontal centrifugal non clog water pumps with CI Head & Base, bronze Impeller with VFD drive along with motor, pressure gauge with isolation cock, Isolation valve, NRV on delivery line. Isolation valve, stainer (with by-pass) at suction. Mechanical seal, suitable vibration elimination pads of approved design, drain pipe with valve (25 dia) for the pump. The pump shall be suitable for 415±10% volts 3 phase AC supply. (1 working + 1 standby) Capacity : As per Membrane Manufacturer Discharge Head : As per Membrane Manufacturer RPM : As per Membrane Manufacturer
Supplying, installing, testing & commissioning of Process Instruments, MBR Accessories, Solneoid Valves for Automation & Membrane Ejector as per details below common for entire system Note: The cost shall be inclusive of following instrumentation: Permeate isolation valves Drain valves Backpulse isolation valves Permeate discharge isolation valves Permeate Flow meter Turbidity meter (controller + sensor) (Offline) Permeate pump ejector Solenoid valve on line pH meter digital type Permeate suction pressure guage Permeate suction Isolation valve Other associated piping, valves and items as per approved P&I.
Providing & fixing level controllers for water pumps to start / stop the pump at set level. Including wiring, cabling from pump to panel & all other accessories as required to operate the system automatically. (Quantity as per vendor design).
Providing & fixing on line Electro magnetic type flow meter cum Totaliser for Monitoring the total flow, Flow rate. etc. Including electrical wiring from panel to flow meter. Complete with all type of Plumbing & Electrical connections, accessories, wiring, conduits & supports complete with all respect. The signal from read out shall be 4-20 m.amps to be received on BAS.To be installed at input sewage and Outlet product water of MBR (1 for each module)
(i) 40 mm dia
ELECTRICAL INSTALLATION FOR SEWAGE TREATMENT PLANT Design, fabrication, assembling, wiring, supply, installation, testing and commissioning of compartmentized motor control centre shall be fabricated out of 14 gauge CRCA sheet steel in form in 3b formation with reinforcement of suitable size angle iron, channel ‘T’ sections irons and/or flats wherever necessary. Cable gland plates shall be provided on top as well as at the bottom of the panels. Panels shall be treated with all anticorrosive process before painting as per specifications with 2 coats of red oxide primer and final approved shade of powder coated paint. 2 Nos. earthing terminals shall be provided for 3 phase, 4 wire, 50 Hz supply system. Lifting hooks shall also be provided in case of large panels. Approval shall be taken for each panel before fabrication. Cadmium Plated hardware shall be used in fabrication of panels. Quoted rates shall inclusive of cables, cable trays, control cabling, earthing (in accordance to specification) with earthing from panel to each motor / equipment. Incomer 1 Nos. 200 Amp four pole Moulded Case Circuit Breaker (Ics = Icu = 25 KA) with built in thermal based release unit with adjustable setting. BUSBARS 300 Amp TPN busbars (25 KA) of high conductivity electrolytic quality aluminium alloy with heat shrinkable insulation sleeves. INSTRUMENTS 1 Set of digital multifunction meter for 3 phase, 4 wire operation to measure V, A, Hz, W, PF, Wh, THD with RS 485 facility. Acc. class: 1 as per specification. 1 Set of ON, OFF, Trip indicating lamps, LED type, shall be protected by 2 amp SP MCB. 1 Set of LED Phase indicating lamps RYB, shall be protected by 2 amp SP MCB 1 Set of 200/5A, Class 1, 10VA, Cast Resin CT for metering.
SH-II WATER TREATMENT PLANT
Supply, installation, testing & commissioning of water filteration plant (20 m3/h) comprising of the following including all necessary inter connecting piping, control valves, electrical cables, control cables, other accessories etc. as directed and required at site to complete the work.
FILTER FEED PUMPS
Supply, installation, testing and commissioning of single stage, horizontal, centrifugal, 2 pole, 50 HZ, AC, monoblock pumps (as per IS : 9079) incorporating C.I. casing and frame, stainless steel shaft, SS impeller, TEFC induction motor directly coupled to the pump, IP44 protection, class B insulated, C.I. body, hydraulically and dynamically balanced to give vibration free operation, with mechanical seal arrangement, fixed on a base plate with suitable vibration eleminator pads complete with PCC foundation, bolts grouted in CC blocks of 1:2:4, suitably rated DOL / star-delta starter fixed inside main electrical panel complete with level controller, necessary wiring, pressure gauge on the delivery side and strainer on suction side, including non-return valve and isolating valves on suction and delivery sides as required, including suction and delivery headers complete in all respects.
Filter Feed Pumps - 2 nos (1W+1S), having discharge : 20.0 m3/hr (each) at 30 meter head
OXIDATION CHAMBER
Supply, installation , testing and commissioning of vertical floor mounted MSEP Oxidation Chamber of suitable size, provided with an inlet distributor, complete with frontal piping & butterfly valves, back wash system & filter media etc. complete with standard fittings like manhole cover, pressure gauge at inlet & outlet, sampling cock, rinse drain valve, air vent valve with piping, bolts, nuts & rubber gaskets.
Flow rate = 20.0 M3/hr Vessel Dia = 800 mm HOS = Min. 600 mm Filteration rate = 50 M3/M2/Hr Shell/ Dish thickness = 5 / 6 mm MOC: MSEP
MULTI GRADE FILTER
Supply, installation , testing and commissioning of vertical floor mounted MSEP Multi Grade filter of suitable size, provided with an inlet distributor, complete with frontal piping & butterfly valves, back wash system & filter media etc. complete with standard fittings like manhole cover, pressure gauge at inlet & outlet, sampling cock, rinse drain valve, air vent valve with piping, bolts, nuts & rubber gaskets.
Flow rate = 20.0 M3/hr Vessel Dia = 1200 mm HOS = Min. 1800 mm Filteration rate = 20 M3/M2/Hr Shell/ Dish thickness = 5 / 6 mm MOC: MSEP
Activated Carbon Filter Supply, installation & testing and commissioning of vertical floor mounted MSEP Activated Carbon filter of suitable size, provided with an inlet distributor, complete with frontal piping & butterfly valves, back wash system & filter media etc. complete with standard fittings like manhole cover, pressure gauge at inlet & outlet, sampling cock, rinse drain valve, air vent valve with piping, bolts, nuts & rubber gaskets.
Flow rate = 20.0 M3/hr Vessel Dia = 1300 mm HOS = Min. 1800 mm Filteration rate = 15 M3/M2/Hr Shell/ Dish thickness = 5 / 6 mm MOC: MSEP
SOFTENER Supply, installation & testing and commissioning of vertical floor mounted MSEP Softener of suitable size, provided with an inlet distributor, complete with frontal piping & butterfly valves, regeneration system with ejector & resin etc. complete with standard fittings like manhole cover, pressure gauge at inlet & outlet, sampling cock, rinse drain valve, air vent valve with piping, bolts, nuts & rubber gaskets.
Flow rate = 20.0 M3/hr Vessel Dia = 1300 mm HOS = Min. 2500 mm Resin Volume = 1400 L Shell/ Dish thickness = 5 / 6 mm OBR=200 m3 MOC: MSEP
Providing & fixing on line Electro magnetic type flow meter cum Totaliser for Monitoring the total flow, Flow rate. etc. Including electrical wiring from panel to flow meter. Complete with all type of Plumbing & Electrical connections, accessories, wiring, conduits & supports complete with all respect, capable of trasmitting 4-20mA output. To be installed at outlet of softening unit.
CLORINE DOSING SYSTEM:
Supply, installation, testing & commissioning of Chlorine dosing system consisting of one HDPE tank of 200 litres capacity with a positive displacement diaphragm dosing pump having variable flow rate of (0‐6 LPH). The motor shall be suitable for operation at 240 V / single phase 50 Hertz AC supply. The pump shall be supplied complete with necessary polypropylene piping, valves, strainers & injection fittings for complete automatic dosing.
MAIN DISTRIBUTION BOARD (WATER TREATMENT PLANT) Design, fabrication, assembling, wiring, supply, installation, testing and commissioning of compartmentized motor control centre shall be fabricated out of 14 gauge CRCA sheet steel in form in 3b formation with reinforcement of suitable size angle iron, channel ‘T’ sections irons and/or flats wherever necessary. Cable gland plates shall be provided on top as well as at the bottom of the panels. Panels shall be treated with all anticorrosive process before painting as per specifications with 2 coats of red oxide primer and final approved shade of powder coated paint. 2 Nos. earthing terminals shall be provided for 3 phase, 4 wire, 50 Hz supply system. Lifting hooks shall also be provided in case of large panels. Approval shall be taken for each panel before fabrication. Cadmium Plated hardware shall be used in fabrication of panels. Quoted rates shall inclusive of cables (except submersible pump feeder cable), cable trays, control cabling, earthing (in accordance to specification) with earthing from panel to each motor / equipment.
BOREWELL SUBMERSIBLE PUMP "Supply, installation, testing and commissioning of Multistage vertical submersible pump motor set of CI Body, Stainless steel shaft and impeller , suitable for operation on 3 phase 415 volts + 10% - 15 %, 50 HZ A.C supply, speed 2900 RPM, including supply & laying of copper flat cable of 2 nos 3 core x 6 Sq. m. size upto 45 Mtr length including lowering with U clamp , C class GI pipe of 100 mm NB with necessary sockets & bends etc upto 40 Mtr, 10 mm double steel wire rope upto 80 mtr., well cover (12"" x 8""), NRV and gate valve, supporting clamps, flanges, pressure gauge etc.as per following specifications: Discharge: 600 LPM minimum Head : 45 M minimum. HP : 20 HP"
Design, Fabrication, supply, installation, Testing and commissioning of Floor Mounted outdoor type, suitable size control panel cum feeder pillar made of CRCA sheet steel of 2 mm thick for frame work and covers i/c cleaning and finishing complete with powder coating in approved shade, having 150 amps capacity TPN aluminium busbars, bottom base of MS channel and Legs, have a common GI earth bar with 2 nos earth stud, internal connection by suitable aluminium strip/bar or aluminium cable as per specification and control wiring with 2.5 Sq.mm PVC insulated copper conductor cable i/c providing the following switch gears and same should be fixed 2 ft. height (from ground level) on brick foundation i/c outgoing and incoming electrical connection etc as required.
Supply of following size 1.1 KV grade XLPE insulated, PVC sheathed, armoured Aluminium conductor power cable conforming to IS 7098 (Part 1) amended upto date.
3.5 core X 50 Sq.mm
Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 kV grade of following size direct in ground including excavation, sand cushioning, protective covering and refilling the trench etc. as required.
3.5 core X 50 Sq.mm
Laying and fixing of one number PVC insulated PVC sheathed / XLPE power cable of 1.1 KV grade of following sizes on wall/ surface/ cable tray as required.
3.5 core X 50 Sq.mm
Supplying and making cable end termination with brass compression gland and aluminium lugs for following size of PVC insulated PVC sheathed/ XLPE aluminium conductor cable of 1.1 kV grade as required.
3.5 core X 50 Sq.mm
Earthing with GI earth pipe 4.5 mtr Long, 40mm dia i/c all accessories and providing masonary enclosure with cover plate, having locking arrangement and watering pipe etc. with charcoal/coke and salt as required.
Supply & laying 25 mm x 5mm size GI strip at 0.5 m below ground level as strip earth electrode, including connection/ termination with GI nut, bolt, spring, washer etc as required. (Jointing shall be done by overlapping and with 2 sets of brass nut bolt & spring washer spaced at 50 mm)
Supply & laying 25 mm X 5 mm size GI strip on surface or in recess for connection etc as required.
SH-III Operation and Maintenance
"Operation, upkeeing and carrying out day to day maintenance of all equipments, machinaries and accessories related to 75 KLD Sewage Treatment Plant, Water Treatment Plant & submersible pumps involving operation minor condition of the systems, ensuring serviceability / satisfactory working condition of the systems, maintenacne of records / documentation of the above works etc., as per the detailed specification, terms & conditions covered under this contract on all days including sundays & holidays of the month complete as required. The required minimum man power (One Technician cum Operator and One helper in each shift for round the clock operation ) to be deployed for each shift of 8 hrs for the equipments to be operated and upkeeped shall be as per special condition of contract. " (i) First Year ( During DLP ) (18.8813 % per year of total amount of SITC work of STP & WTP) - 1 Job (ii) Second Year ( Yearly 5% cumulative enhancement on First year Rate) - 1 Job (iii) Third Year ( Yearly 5% cumulative enhancement on Second year Rate) - 1 Job (iv) Fourth Year ( Yearly 5% cumulative enhancement on Third year Rate) - 1 Job (v) Fifth Year ( Yearly 5% cumulative enhancement on Fourth year Rate) - 1 Job (vi) Sixth Year ( Yearly 5% cumulative enhancement on Fifth year Rate) - 1 Job
"Comprehensive Maintenance of 75 KLD Sewage Treatment Plant inclusive of all spares, chemicals & material & carrying out breakdown & the preventive maintenance as per OEM recommendations after Defect Liability Period." (i) First Year (5.9318 % per year of amount of SITC work of STP) - 1 Job (ii) Second Year ( Yearly 1.4931 % cumulative enhancement on First year Rate) - 1 Job (iii) Third Year ( Yearly 1.5403 % cumulative enhancement on Second year Rate) - 1 Job (iv) Fourth Year ( Yearly 1.5851% cumulative enhancement on Third year Rate) - 1 Job (v) Fifth Year ( Yearly 1.6778% cumulative enhancement on Fourth year Rate) - 1 Job
LANDMARK AQUATEC PRIVATE LIMITED
HITECH SWEET WATER TECH PVT LTD
Rysa Infratech Private Limited
QUALICOM SOLUTIONS PRIVATE LIMITED
B S ENVIRO N INFRACON PVT LTD
HITECH ENVIRO ENGINEERS AND CONSULTANTS PVT LTD
UY TRIENVIRO PVT. LTD.
SAWEN CONSULTANCY SERVICES PVT. LTD.
POLLUCON TECHNOLOGIES LIMITED
Sainath Envirotech
Trans Organics (India) Pvt. Ltd
MECO TECHNOLOGIES PVT LTD
ENSYS TECHNOLOGIES (I) PVT LTD
WTE INFRA PROJECTS PVT LTD
stage.html
html • 0.10 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .