Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance 16A 2151 SEC 16A VASUNDHARA GHAZIABAD UTTAR PRADESH 201012 | GHAZIABAD | UTTAR PRADESH | 201012 | Admitted-Finance |
| 2 | Rejected-Technical | Rejected-Technical Non Responsive |
| 3 | Rejected-Technical C 3 5 SECTOR 28 ROHINI DELHI 110042 | DELHI | NORTH DELHI | DELHI | 110042 | Rejected-Technical Non Responsive |
| 4 | Rejected-Technical PLOT NO 72 IMT MAIN ROAD SECTOR 68 FARIDABAD HARYANA 121004 | FARIDABAD | FARIDABAD | HARYANA | 121004 | Rejected-Technical Non Responsive |
Tender Value
₹72.8 Cr
EMD Value
₹1.5 Cr
Closing Date
13 Apr 2026, 4:00 pmClosed
General Manager C and M NWBP
JUSNL Building Kusai Colony Doranda Ranchi
Design Engineering Supply of Materials/ Equipments Erection Testing and Commissioning of 132/33 KV GSS including construction of Control Room Building and approach road as well as other civil works at Tundi on turnkey basis
2026_JSEB_111951_1
865/PR/JUSNL/2025-26
Open Tender
Electrical Works
547 days
Tundi Dhanbad
Please refer Tender documents.
2 documents required · 2 mandatory
₹23,600
₹1.5 Cr
9 Jun 2026
23 Mar 2026
15 Apr 2026
23 Mar 2026
13 Apr 2026
23 Mar 2026
Design, Engineering, Supply of Materials/ Equipments, Erection, Testing and Commissioning of 132/33 KV, 2 x 80 MVA Grid sub-station including construction of Control Room Building & approach road as well as other civil works at Tundi on turnkey basis on turnkey basis.
SUMMARY OF COST ESTIMATE FOR (SCHEDULE- A, B & C)
Design, Engineering, Supply, Erection, Testing and Commissioning of 132/33 kV, 2 x 80 MVA Grid sub-station including construction of Control Room Building & approach road as well as other civil works at ITI More Chas (Bokaro) and associated Transmission Line
Supply
Design, Engineering, Supply, Erection, Testing and Commissioning of 132/33 kV, 2 x 80 MVA Grid sub-station including construction of Control Room Building & approach road as well as other civil works at ITI More Chas (Bokaro)
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Chandankiyari - ITI More Chas Transmission line (28 KM)
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Dugda - Chas Transmission line (35 KM)
Grand Total
Manager
TC/Dhanbad
SCHEDULE - A (supply)
Schedule of Quantities and Prices for
Design, Engineering, Supply of Materials/ Equipments, Erection, Testing and Commissioning of 132/33 KV, 2 x 80 MVA Grid sub-station including construction of Control Room Building & approach road as well as other civil works at Tundi on turnkey basis on turnkey basis.
NIT No. 865/PR/ JUSNL/ 2025-26
Name of Bidder
Item No.
1600 A, 40KA, SF6 CB with Support Structure
FOTE Fiber Optic Terminal Equipment based communication system for all 220KV and 132KV Terminal lines including spare bay, approach cable, RTU Communication Modules, interfacing with SLDC (for speech + protection and for speech + data), PDH/SDH etc all complete along with for GSS end
1600A, VCB with Support Structure, 3 phase as per specification
Diesel Generator Set along with control panel (100 KVA)
High wall type split Air conditioners Units of 2 TR capacity
Lighting
Out Door Type Lighting panel.
Lighting fixture .
Street Lighting Poles including light fittings and junction box.
Galvanized Gantry structures, Equipment Support Structure, riser for earth mat and Nuts & bolts with fasteners for 132 kV & 33kV
Total Amount
SCHEDULE - A (Erection)
Schedule of Quantities and Prices for
Design, Engineering, Supply of Materials/ Equipments, Erection, Testing and Commissioning of 132/33 KV, 2 x 80 MVA Grid sub-station including construction of Control Room Building & approach road as well as other civil works at Tundi on turnkey basis on turnkey basis.
NIT No. 865/PR/ JUSNL/ 2025-26
Name of Bidder
Item No.
1600 A, 40KA, SF6 CB with Support Structure
FOTE Fiber Optic Terminal Equipment based communication system for all 220KV and 132KV Terminal lines including spare bay, approach cable, RTU Communication Modules, interfacing with SLDC (for speech + protection and for speech + data), PDH/SDH etc all complete along with for GSS end
1600A, VCB with Support Structure, 3 phase as per specification
Diesel Generator Set along with control panel (100 KVA)
High wall type split Air conditioners Units of 2 TR capacity
Lighting
Out Door Type Lighting panel.
Lighting fixture .
Street Lighting Poles including light fittings and junction box.
Galvanized Gantry structures, Equipment Support Structure, riser for earth mat and Nuts & bolts with fasteners for 132 kV & 33kV
TOTAL COST
SCHEDULE-C (Supply)
Schedule of Quantity & Prices for
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Chandankiyari - ITI More Chas Transmission line (28 KM)
Fabrication, Galvanizing and supply of various type of tower & Tower Parts, Tower extensions (Complete) excluding bolts & nuts, Step bolts and stubs but including hangers, D-Shackles pack washer etc.
Fabrication, galvanizing and supply of stubs & cleats for various type of towers, tower extensions (complete) with pack washers, excluding bolts & nuts
Supply of bolts & nuts including step bolts and spring washers
EARTHING OF TOWERS
Supply of Earthing of Towers
Tower Accessories
Supply of following tower accessories
Design, manufacture and Supply of following line materials
INSULATORS & HARDWARE FITTINGS (including Insulator)
SUPPLY OF ACSR PANTHER CONDUCTOR FOR 3 PHASE DOUBLE CIRCUIT TRANSMISSION LINE
OPGW with jointing and termination kit complete as per approved specification
ACCESSORIES FOR CONDUCTOR AND OPGW
TOTAL
3% Consultancy Charge
Grand Total
SCHEDULE-C (Erection)
Schedule of Quantity & Prices for
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Chandankiyari - ITI More Chas Transmission line (28 KM)
Survey
Soil Investigation
Detail Soil Investigation
Benching
Work Associated with Tower Foundations
Excavation in various types of soils
Concreting (Including all associated works related to foundation not covered in 4.1 & 4.3)
Supply and placement of reinforcement steel (Fe500)
Installation of stub including bolts and nuts
Erection of various type of towers, tower parts and tower extension (Complete) with bolts and nuts, including tack welding and supply and application of zinc rich primer and two coats of enamel paint
Installation of Earthing of tower
Installation of the following tower accessories
Protection of Tower Footing
Installation of insulator strings complete with arcing horns & necessary hardware, installing & stringing of conductor including fixing of conductor accessories, installing & stringing of OPGW including fixing of OPGW accessories
Normal Towers
Other items if required
Total
1% Labour Cess
3% Consultancy Charge
Grand Total
SCHEDULE-B (Supply)
Schedule of Quantity & Prices for
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Dugda - Chas Transmission line (35 KM)
Fabrication, Galvanizing and supply of various type of tower & Tower Parts, Tower extensions (Complete) excluding bolts & nuts, Step bolts and stubs but including hangers, D-Shackles pack washer etc.
Fabrication, galvanizing and supply of stubs & cleats for various type of towers, tower extensions (complete) with pack washers, excluding bolts & nuts
Supply of bolts & nuts including step bolts and spring washers
EARTHING OF TOWERS
Supply of Earthing of Towers
Tower Accessories
Supply of following tower accessories
Design, manufacture and Supply of following line materials
INSULATORS & HARDWARE FITTINGS (including Insulator)
SUPPLY OF ACSR PANTHER CONDUCTOR FOR 3 PHASE DOUBLE CIRCUIT TRANSMISSION LINE
OPGW with jointing and termination kit complete as per approved specification
ACCESSORIES FOR CONDUCTOR AND OPGW
TOTAL
3% Consultancy Charge
Grand Total
SCHEDULE-B (Erection)
Schedule of Quantity & Prices for
Engineering, Supply, Erection, Testing & Commissioning 132 KV D/C 3 Ph. Dugda - Chas Transmission line (35 KM)
Survey
Soil Investigation
Detail Soil Investigation
Benching
Work Associated with Tower Foundations
Excavation in various types of soils
Concreting (Including all associated works related to foundation not covered in 4.1 & 4.3)
Supply and placement of reinforcement steel (Fe500)
Installation of stub including bolts and nuts
Erection of various type of towers, tower parts and tower extension (Complete) with bolts and nuts, including tack welding and supply and application of zinc rich primer and two coats of enamel paint
Installation of Earthing of tower
Installation of the following tower accessories
Protection of Tower Footing
Installation of insulator strings complete with arcing horns & necessary hardware, installing & stringing of conductor including fixing of conductor accessories, installing & stringing of OPGW including fixing of OPGW accessories
Normal Towers
Other items if required
Total
1% Labour Cess
3% Consultancy Charge
Grand Total
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.20 MB
Tender-Document-Tundi-865.pdf
Tender Documents • 1.65 MB
Technical-Specification-865-Tundi.pdf
Tender Documents • 7.03 MB
BoQ-865-Tundi.XLS
Additional Documents • 0.19 MB
Download all tender documents and submit your bid