| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹42.3 LAccepted-AOC | 1 | Accepted-AOC First lowest | |
| 2 | 2₹42.4 L+₹4,486.70 (0.11%)Rejected-AOC | 2 | Rejected-AOC Second lowest |
Tender Value
₹42.4 L
EMD Value
₹50,000
Closing Date
4 Jul 2023, 5:00 pmClosed
Project Engineer
Sabari gardens, Chandanakavu, Alappuzha- 688011
Construction of engine thara consruction of engine shed providing 3m pipe Deepening of thodu
2023_KLDC_578312_2
KLDC/ALP/PE/2023-24/01
Open Tender
Civil Works - Others
Item Rate
180 days
Vechoor Grama Panchayath, Kottayam District
Please refer Tender documents.
5 documents required · 5 mandatory
₹2,950
Yes
₹50,000
Yes
31 Jul 2023
19 Jun 2023
7 Jul 2023
19 Jun 2023
4 Jul 2023
19 Jun 2023
Amount
App: A - Construction of engine thara - 2nos ( valiyavelicham 2)
60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete.
60.2.2 : Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
60.64.1 : Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
60.64.4 : Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end
51.2.3 : Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.3 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.6 : Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.16.2 : Centering and shuttering including strutting, etc. and removal of form for:Edges of slabs and breaks in floors and wallsAbove 20 cm wide
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
2.36 : Deduct for disposed soil not levelled and neatly dressed.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
App: B -consruction of engine shed 1 nos ( ittiyakandankari)
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.3 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.6 : Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.2.25.1 : Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
50.10.1 : Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
12.50 : Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+0.05%), total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x55mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.
12.51.1 : Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm (+ 0.05%) total coated thickness, zinc coating 120 grams per sqm as per IS:mm(+0.05%) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/self tapping screws complete:Ridges plain (500-600 mm)
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
2.36 : Deduct for disposed soil not levelled and neatly dressed.
13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
50.6.4.1 : Hollow block masonry using pre cast blocks (Factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
10.6.1 : Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S. laths with 1.25 mm thick top cover
5.18.1 : Providing precast cement concrete jali 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 6 mm nominal size) reinforced with 1.6 mm dia mild steel wire including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement : 3 fine sand ) etc. complete excluding plastering of the jambs, sills and soffits.50 mm thick
13.37.1 : White washing with lime to give an even shade:New work (three or more coats)
13.44.1 : Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
60.4 : Locking Arrangements - Supplying and Fixing lock and locking arrangements with suitable chain hooks,and padlock of 65mm size.
App c - providing 3m pipe ( ittiyakandankari &amp;amp;amp; manadamkari )
19.35.4 : Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete.1000 mm dia RCC pipes. (Laying by mannual/mechanical means).
19.35.2 : Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete.600 mm dia RCC pipes.
App: D- Deepening of thodu
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
Sabu A Kuruvila
Bidder Name
SAJI A KURUVILLA
Sabu A Kuruvila
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.PDF
finance_860934.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .