Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.8 CrAdmitted-Finance | ₹2.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.9 Cr+₹7.5 L (2.68%)Admitted-Finance | ₹2.9 Cr+₹7.5 L (2.68%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical non furnish of document |
| 4 | Rejected-Technical | - | - | Rejected-Technical non furnish of document |
| Sl No | Description | Qty | Unit | Akash Dalai L2 | KAPIL CONSTRUCTION CO. L1 |
|---|---|---|---|---|---|
| 1.00Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, stand post,Compound wall, 100KL RCC ESR with 12Mtr. Staging,. providing 100% functional house tape connections etc. With 5 years operation & maintenancefor PWS to Pandiajholi village of Rohigam G.P. under Kukudakhandi Block. | |||||
| 1.01 | Supplying all materials labour T&P for construction of Compound wall .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,stand post,recharge pit,individual house hold connection, Drinking Water supply provision to School / AWC / G.P. Office, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge. | 1 | Nos | 50,48,384 ₹50,48,384 | 49,34,000 ₹49,34,000 Lowest |
| 1.02 | Construction of 100,000 LTR OHR WITH 12M STAGING
Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 100,000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR/PMEC,Berhampur at his own cost) | 1 | Nos | 23,10,463 ₹23,10,463 | 22,58,000 ₹22,58,000 Lowest |
| 1.03 | The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned. | 1 | Nos | 3,67,942.3 ₹3,67,942.3 Lowest | 3,75,000 ₹3,75,000 |
| 2.00Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, Compound wall, pump house, 100KL RCC OHR, 12Mtr. staging providing 100% functional house tape connections etc. With 5 years operation & maintenance for PWS to P.K.CH PUR village of Masiakhali G.P. under Kukudakhandi Block. | |||||
| 2.01 | Supplying all materials labour T&P for construction of Compound wall .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,stand post,recharge pit,individual house hold connection, Drinking Water supply provision to School / AWC / G.P. Office, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge. | 1 | Nos | 56,63,274 ₹56,63,274 | 55,35,000 ₹55,35,000 Lowest |
| 2.02 | Construction of 100,000 LTR OHR WITH 12M STAGING
Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 100,000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR/PMEC,Berhampur at his own cost) | 1 | Nos | 23,10,463 ₹23,10,463 | 22,44,000 ₹22,44,000 Lowest |
| 2.03 | The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned (As per Annexure-G& H) | 1 | Nos | 3,98,686.9 ₹3,98,686.9 Lowest | 4,00,000 ₹4,00,000 |
| 3.00Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, Compound wall, 6.00 dia intake wall with laying of infiltration gallery , pumping unit installation,providing 100% functional house tape connections etc With 5 years operation & maintenance in connection with to PWS to Balajipalli under Kukudakhandi Block. | |||||
| 3.01 | Supplying all materials labour T&P .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,individual house hold connection, Construction of 6.00 mtr dia intake well with laying of infiltration gallery, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge. | 1 | Nos | 22,88,023 ₹22,88,023 | 21,00,000 ₹21,00,000 Lowest |
Tender Value
₹3.0 Cr
Closing Date
3 Jan 2022, 5:00 pmClosed
Superintending Engineer, RWSS Division, Berhampur
Nera Jarada Bunglow- Berhampur-760004
PWS to (1)Pandiajholi, (2)P.K.ChPur,(3) Balajipalli (4)Medinipur under Kukudakhandi Block
2021_RWSS_74063_8
EERWSSBAM- 25 / 2021-22
National Competitive Bid
Civil Works - Water Works
Item Rate
330 days
PWS to (1)Pandiajholi, (2)P.K.ChPur, (3) Balajipal
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
Exempted
21 Feb 2022
13 Dec 2021
4 Jan 2022
13 Dec 2021
3 Jan 2022
13 Dec 2021
13 Dec 2021 - 29 Dec 2021
Amount
Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, stand post,Compound wall, 100KL RCC ESR with 12Mtr. Staging,. providing 100% functional house tape connections etc. With 5 years operation & maintenancefor PWS to Pandiajholi village of Rohigam G.P. under Kukudakhandi Block.
Supplying all materials labour T&P for construction of Compound wall .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,stand post,recharge pit,individual house hold connection, Drinking Water supply provision to School / AWC / G.P. Office, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
Construction of 100,000 LTR OHR WITH 12M STAGING Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 100,000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR/PMEC,Berhampur at his own cost)
The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned.
Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, Compound wall, pump house, 100KL RCC OHR, 12Mtr. staging providing 100% functional house tape connections etc. With 5 years operation & maintenance for PWS to P.K.CH PUR village of Masiakhali G.P. under Kukudakhandi Block.
Supplying all materials labour T&P for construction of Compound wall .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,stand post,recharge pit,individual house hold connection, Drinking Water supply provision to School / AWC / G.P. Office, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
Construction of 100,000 LTR OHR WITH 12M STAGING Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 100,000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR/PMEC,Berhampur at his own cost)
The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned (As per Annexure-G& H)
Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, Compound wall, 6.00 dia intake wall with laying of infiltration gallery , pumping unit installation,providing 100% functional house tape connections etc With 5 years operation & maintenance in connection with to PWS to Balajipalli under Kukudakhandi Block.
Supplying all materials labour T&P .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,individual house hold connection, Construction of 6.00 mtr dia intake well with laying of infiltration gallery, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned .
Supplying Labour, Materials and T&P for Laying of pipelines, Construction of valve Chambers, Compound wall, pump house, 100KL RCC ESR with 12Mtr. staging, providing 100% functional house tape connections etc. With 5 years operation & maintenance.in connection with to PWS to Medinipur under Kukudakhandi Block.
Supplying all materials labour T&P design, drawing ,soil testing etc. complete in all respect for construction of RCC Roof building Pump House and construction of Compound wall for Pump House .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber,stand post, bore well platform,recharge pit,individual house hold connection, Drinking Water supply provision to School / AWC / G.P. Office, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to D). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
Construction of 100,000 LTR OHR WITH 12M STAGING Supplying of all labour,T&P,material including taxes for soil testing ,supply of design, drawing, construction,errection,testing & commissioning etc. of RCC elevated storage reservoir of 100,000 ltrs capacity with necessary staging height of 12 mtr consisting of cylindrical container with minimum 6 nos RCC columns and circular dome with full raft using CC M-25 with RCC stair case as per approved drawing,supplying, fitting & fixing of 100 mm medium grade GI pipe Tata/Jindal/Sail make confirming to IS specification of required length from production well to ESR & ESR to rising main including in-let,out-let,over flow & washing line of ESR,use of 32 mm GI pipe for Gallary and vertical post. and Aluminium ladder inside and outside the ESR,CI puddle collar,0.6 m dia CI manhole cover at dome , RCC vent with brass jally, lightening arrestor and water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR /VSSUT,Burla /NIT,Rourkela/IIT,BBSR/PMEC,Berhampur at his own cost)
The contractor shall maintain the PWS Project for five ( 5 ) calender years from the completion date concurrent with defect liability period of one year in such a manner that all the house hold of the PWS Scheme covered area will get ( adepuate ) required quantity of supply water taking supply hour as 8 hour / day without facing any problems. The contractor shall repair and replace any types of defect arise within 24 Hrs of receipt of complain either from public or from Department. The contractor shall maintain all structure of the PWS Schemes as per terms and conditions of DTCN & Technical spacification mentioned.
Akash Dalai
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.86 MB
A08DTCNPandiajholi.pdf
Tender Documents • 2.23 MB
BOQ_382938.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .