SE ETC-II,MORADABAD
220 KV S/S CAMPUS MAJHOLA MORADABAD
WORK OF REPLACEMENT OF GASKET OF 40 MVA T/F-I IMP MAKE AT 220 KV S/S AMROHA UNDER ETD AMROHA
2020_UPTCL_434194_1
SHORT TERM E-T-41/ETC-II/M/2020
Open Tender
Electrical Works
45 days
AMROHA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
EE ETD AMROHA ,SBI CURRENT ACCOUNT NO. 30723557626
₹6,000
26 Feb 2020
13 Feb 2020
26 Feb 2020
13 Feb 2020
26 Feb 2020
13 Feb 2020
Amount
The following works are to be carried out at 220 KV S/S Amroha under ETD, Amroha
Shifting of oil tank 25 KL including loading, unloading & carriage from any near place to 220 KV S/S Amroha.
Drain out of T/F oil from main tank of filling in empty oil drums.
Dismantling of HV/LV/Neutral bushing, turrent from T/F Tank, Radiators, conservator Tank, explosion vent pipe, bucholz relay, oil pipe line, colling fans, opening of electricals connections & proper blanking for open space of replacement of gasket.
Centrifuging of oil in oil tank by connecting the centrifuging pipes, circulating the T/F oil through centrifuging machine to increases BDV.
Repalcement of old & Damage gasket of 40 MVA T/F by providing new gasket as per required size of good quality rubberized cork sheet of NU COCK/TALBROS make at required places of complete T/F including top covers & accessories.
Complete erection of 40 MVA T/F by erection of radiator, conservator tank, bushing with its turret (if available) turret, HV/LV/TV/N bushing, all pipe lines, radiator, oil, etc.
Cleaning of Core and winding by fresh T/F oil and removed the slug from bottom.
Create the vacuum inside the tank for period for 24 Hrs.
Centrifuging of oil in the transformer. taking the IR/BDV value of period of 4 hrs. as per norms of T/F manufacturer of till the desired values are attained filling of centrifuging T/F oil up to required oil levels of T/F. Centrifuging machine shall be arranged by the contractor at his own cost.
Overhauling of diverter switch after removing of oil and dirty T/F oil from its chamber filling the fresh centrifuged T/F oil its centrifuged T/F oil its centrifuged circulation as per norms of T/F.
Painting of 40 MVA T/F with suitable gray paint.
Gupta Elect and Engg Works
SUN ENGINEERING WORKS
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid