Tender Value
₹10 L
EMD Value
₹30,000
Closing Date
8 Jun 2026, 3:00 pm3d left
EE Division Office No 1 Junagadh PGVCL
Work for E/O HT,LT Line and Transformer center Erection/Replacement work, underground cabling work and line and maintenance work for ND scheme under Visavadar-1 Sub Division (2 Years)
303331
SEJND/T-2/TN-326/1061 DT:01-05-2026 SR No 02 under Junagadh Division-1
Open
Electrical and Maintenance Works
Junagadh
11 documents required · 11 mandatory
₹1,475
PASCHIM GUJARAT VIJ COMPANY LIMITED
₹30,000
27 May 2026
27 May 2026
27 May 2026
8 Jun 2026
27 May 2026
aiY) n)c[ jNiv[l lien kimmi> rs Frivti t[mj an&Bv) q[kd[ iri[ pis[Y) e-T[ºDr dviri Bivi[ mi>gvimi> aiv[ C[.
an&.n>br kimn) (vgt a>diJt j¸Yi[ a>diJt rkm binin) rkm Smy myi<di
p.g&.(v.k>.l).ni j&nigQ (vBig)y kc[r)-1 h[Ql siY[ j[iD[l 10,00,000=00 10,000=00 2 {vP<}
p[Ti (vBig)y kc[r): - (vsivdr-1
kimg)r):- a[n.D). yi[jni h[qL a[c.T)./
a[l.T). tYi T).s) uBi krvin&> kim tYi
a[c.T)./ a[l.T). tYi T).s) ni lienn[ lgt&
kim an[ lien m[ºT[nºs vk< miT[.
siY[ ji[D[l S[Dy&l an[ Srt[i m&jb.
1. Bivp#ik p\t) a[kn) (k>mt $i.750=00+135.00 J.a[s.T)=885=00 C[. {j[ prt YE SkS[ n(h.}
2. Bivp#ik Brvin) C[Ãl) tir)K :- As per tender notice smy bpi[rni> a>diJt bir vi³yi s&F)ni[ rh[S[.
3. Bivp#ik Av)kirvin) C[Ãl) tir)K :- As per tender notice smy bpi[rni> a>diJt #iN vi³yi s&F)ni[ rh[S[.
4. Bivp#ik Ki[lvin) C[Ãl) tir)K :- If Possible smy bpi[rni> a>diJt cir vi³yi s&F)ni[ rh[S[.
5. upri[kt kim miT[ Bivp#iki[ siY[ j[-t[ kimn) dSi<v[l binin) rkm ai[n lien p)Jv)s)a[l ni a[kiuºTmi> jmi> krivvin)
rh[S[.{a[kiuºT n>br 66024933257 aie.a[f.s). n>.SBIN0060046}.
6. ki[epN u>ci k[ n)ci Bivp#ik k[ b)ji p#iki[ Av)kirvi k[ n(h t[ni aiKr) (nN<yni[ hÊ n)c[ sh) krnirn[ C[. j[ miT[ t[ai[~) ki[epN
jitn&> kirN dSi<vvi b>Fiy[l nY).
7. upri[kt T[ºDrni> tmim Di[ky&m[ºT T[ºDr Brt) vKt[ ai[n lien apli[D krvini> rh[S[. j[mni miT[ ki[e pN jitn&> kvr p)Jv)s)a[l
kc[r)-1 j&nigQ n[ mi[klvin&> rh[S[ nh).
Deputy Engineer(T-1)
(vBig)y kc[r) n>-1, j&nigQ
{1} Superintendent of Account, Rrual-1 Division, PGVCL,Junagadh
Sign & Stamp of the Bidder P a g e 1 |
PASCHIM GUJARAT VIJ CO. LTD
Junagadh Rural Division-1,
B.S.N.L. Office compound, Gandhigram, Junagadh-362001
Tender for Labour Work for ND Scheme under E/O of HT, LT Line and
Transformer Erection/Replacement work, Underground Cabling work
and Line Maintenance
Work under Visavadar-1 Sub-Division
Sign & Stamp of the Bidder P a g e 2 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Regd.Office: “Paschim Gujarat Vij Seva Sadan”, Off.Nana Mava Main Road, Laxminagar, Rajkot-360004
Junagadh Rural Division-1, B.S.N.L. Office compound,Gandhigram, Junagadh-362001
CIN: U40102GJ2003SGC042908
Sub: Tender for Work for Erection of ND Scheme under Visavadar-1 S/Dn E/O HT, LT
Line and Transformer centre Erection / Replacement work, Underground Cabling work
and Line Maintenance Work
Executive Engineer Junagadh Division-1 invites “On line Tenders” for erection of All Scheme
under Visavadar-1 S/Dn E/O HT, LT Line and Transformer centers, Replacement work,
Underground Cabling work and Line Maintenance Work.
Tender Details: Table No.1
Sr. Description
1 Tender No.: No.
2 Estimated cost in Rs. 10,00,000=00
3 Tender Fee in Rs. (non-refundable) 885=00
4 During the time limit mention here, after payment of Tender fees.
(Payment RTGS/NEFT to
the details of bank account
Earnest Money Deposit amount in Rs. is the details of bank
(1 % of Tender Amount) account is SBI IFSC Code:
(During the time limit mention here, after payment of Earnest Money Deposit SBIN0060046and name
fees.) of account holder Paschim
Gujarat Vij Company
6 On line ( e-tendering ) tender / offer ON LINE AS PER
submission last Date __________ up to 00:00 hours only TENDER TIME
7 Date & Time for pre bid meeting ( If Required) No.
8 Physical submission of all the relevant ON LINE AS PER
Documents, last Date:__________ up to 00:00 hours. TENDER TIME
9 Date of opening of Tender fee , EMD cover of bid at IF POSSIBLE NEX DAY
Date___________@_______ hours (if possible)
10 Date of opening of Technical Bid at Date___________ @_______ hours (if IF POSSIBLE NEX DAY
11 Date of on line opening of Price bid, Date___________ @_______ hours (if IF POSSIBLE
12 Validity of Bid
Executive Engineer
Rural Division-1 Junagadh
Sign & Stamp of the Bidder P a g e 3 |
Sr. Prticulars Page
1 Tender Details Table No 1
2 SECTION I: INSTRUCTIONS TO THE BIDDER
3 SECTION II: Schedule A
4 SECTION III: General Instructions to the
successful bidder
5 SECTION IV : TERMS & CONDITIONS REGARDING
INDUSTRIAL LAWS AND OTHER RELATED MATTERS
6 SECTION V : TAXES
7 SECTION VI : General Terms & Conditions
8 SECTION VII : Annexures I to XI, BG Formats
for EMD and, SD, Agreement and Indemnity
9 SECTION VIII Schedule B
10 SECTION IX Technical Specifications
11 SECTION X Drawings
Sign & Stamp of the Bidder P a g e 4 |
GENERAL INFORMATIONS FOR BIDDERS
1.1 The "PGVCL"shall mean the Executive Engineer _Junagadh Division-1, PASCHIGUJARAT VIJ
COMPANY LTD., having its corporate office at Nanamava Main Road, Laxminagar, Rajkot. With
expression shall unless repugnant to the context include its permitted assigns or successor /
authorized representatives.
1.2 The "Contractor" / Successful Bidders shall mean the Bidders, whose tender has been accepted
by the PGVCL for award of the contract and shall include his authorized representatives.
1.3 The "Engineer-in-Charge" shall mean the authorized officer of the PGVCL to act as Engineer-in-
Charge to supervise the work – for the purpose of the contract.
1.4 The "Specification" shall mean the tender forming a part of the contract along with Performa,
schedules and drawings.
1.5 The "Order" shall mean the official letter issued by the PGVCL, informing the bidder that his tender
has been accepted.
1.6 The "Contract" shall mean the agreement to be entered into by the PGVCL with the contractor
and shall include the commercial technical and general conditions, schedules, drawings and any
other conditions specifically agreed between the parties forming a part of the contract.
1.7 The "EMD" shall mean Earnest Money Deposit.
1.8 The "Contract Value" shall mean the total amount indicated in the contract agreement as per
1.8 The "Contract Value" shall mean the total amount indicated in the contract agreement as per
order placed by the PGVCL and calculated from the quantities indicated in the tender.
1.9 The "Completion Period" shall mean the period starting from the date of issue of "Order" and
required to complete the work in all respect.
1.10 The "Work" shall mean activities to carry out for the entire scope of this Tender.
1.11 “Inspector” shall mean the any person nominated by PGVCL from time to time to inspect the
works under the contract and/or duly authorized representative of the PGVCL “Letter of Award”
shall mean the official notice issued by the PGVCL notifying the contractor that his bid has been
1.12 “Date of Contract” Shall mean the date on which Letter of award has been issued.
1.13 “Month” shall mean the calendar month day or days unless herein otherwise expressly defined
shall mean calendar day or days of 24 hours each.
1.14 “A Week” shall men the continuous period of seven days.
1.15 HT means High Tension
1.16 LT means Low Tension,
1.17 U/G means Under Ground
1.18 Electricity Rules: - All the works shall be carried out in accordance with latest rules under Electricity
1.19 Testing: - After completion of work execution required Tests are to be taken in presence of
Engineer in Charge whenever required.
1.20 Definition of “Similar work” for overhead network: Erection of overhead electric Network up to
voltage level 22 KV
1.21 Definition of “Similar work” for underground network: Laying of HT / LT
Underground Power cable network for Distribution system.
2. PRE QUALIFICATION CRITERIA / ELIGIBLE CRITERIA FOR BIDDERS
Sign & Stamp of the Bidder P a g e 5 |
2.11 Bidders fulfilling eligibility criteria as mentioned in section 1 Sr. no. 2.2. and having
experience of erection & maintenance of overhead HT/LT lines, Transformers,
underground cable work, along with satisfactory work completion certificate regarding
execution of work, including work order outward number along with its value, from order
issuing authority, for last 3 (three Years) _ ending last day of month previous to the one in
which tenders are invited., of any DISCOM of GUVNL or any Govt. / Private DISCOM of
any state of India. The work executed through open / advertised tender shall only be
considered for experience of work. The work done through limited tender shall not
be considered for experience.
These bidders will be considered as an experience bidder.
2.12 Bidders fulfilling eligibility criteria as mentioned in section 1 Sr. no. 2.2.
and not possessing any experience of erection & maintenance of overhead HT/LT lines,
Transformers, underground cable work can also participate in tender for erection &
maintenance of overhead HT/LT lines, Transformers, underground cable work.
These bidders will be considered as an NEW bidder.
2.2 Following documents are mandatory for the Bidders.
Work Completion certificate (by Order Issuing Authority only) with copies of Work Orders
for the similar works executed.
Memorandum of Association or partnership deed.
Document showing P.F. Number obtained by the bidder.
Power of attorney if any for signing the bid documents.
Latest solvency certificate issued by Nationalized or scheduled bank for a sum of Minimum
20% of Tender cost
Registration Number under Shop and Estt. Act (If as case may be applicable)
PF Code Number allotted by concerned PF Authority
Labour License (If as case may be applicable)
Registration under ESIC (If as case may be applicable)
Type test certificates for Cable Box, straight through Joints (In Case of UG Work Involved).
E. P. F. Registration in the name of bidder.
GST Registration Certificate in the name of bidder
PAN card in the name of bidder
Valid Labour Insurance Policy in the name of bidder
Latest bank solvency certificate from any Nationalized/Scheduled bank
Adhar Card (Optional) (In case of Bidding is done on Individual name)
Vendor registration Certificate
Solvency Certificate of current year
Online Payment Receipt and Receipt collect from PGVCL Division Office-1 Junagadh very
Work Experience certificate by agency
3.0 INSTRUCTIONS FOR e TENDERING (ON LINE TENDERING) TO BIDDERS.
Sign & Stamp of the Bidder P a g e 6 |
3.1 Bidders willing to participate in tender will have to get themselves registered on website
www.nprocure.com
3.2 Bidders willing to participate in tender should have valid digital certificate / Digital Signature
as per Information Technology Act 2000 using which they can sign their electronic bids.
Bidders can also procure the same from (n) code solutions, a division of GNFC Ltd., who
are licensed certifying authority by Govt. of India.Download tender Documents from
PGVCL web site up to date shown in the tender document.
3.3 For details regarding digital certificate and related training the below mentioned address
may be contacted (n) Code Solution A division of GNFC, 403, GNFC Info Tower,
Bodakdev, Ahmedabad 380054.Tel: +91 26857316/17/18; Fax: +91
mail: [email protected]
3.4 Bidders who already possess valid Digital certificate need not procure a new digital
3.5 Bidders can prepare and edit their offers number of times before tender submission date
and time as mentioned in this tender details table no1. After tender submission date and
time, bidder cannot edit their offer submitted in any case. No written or online request in
this regard shall be granted.
3.6 Bidder shall submit their offer, i.e. Technical Bid as well as price bid in Electronic format
on website www.nprocure.com before the validity period mentioned in tender details Table
3.7 Offers submitted without digitally signed will not be accepted.
3.8 Offers only in physical form will not be accepted in any case
4. UNDERS TANDING AND CLEARIFICATIONS ON DOCUMENTS AND
SPECIFICATIONS.
4.1 All interested parties are requested to understand this Tender Document in detail in order
to comply with PGVCL’s requirements including but not limited to the Tender fees, EMD
and deadlines, selection criteria, selection methodology, scope of work, and minimum
technical standards.
4.2 The Bidder is required to carefully examine the specifications and documents and fully
inform himself as to all the conditions and matters which may in any way affect the Work
or the cost thereof. If any Bidder finds discrepancies or omissions in the specifications and
documents or is in doubt as to the true meaning of any part, he shall at once request in
writing in advance before filling in the tender, within the time limit as per Table no 1, for an
interpretation / clarification by the PGVCL Junagadh Division-1 office. Then The
PGVCLJunagadh Division-1 office will issue interpretation and clarifications as he may
think fit of such interpretations and clarifications, the Bidder may submit his bid but within
the time and date as specified in the Table no1. All such interpretations and clarifications
shall form a part of the specifications and documents, and accompany the bidder's
proposal. In case of difference of opinion about interpretation of specification etc. the decisi
of Superintending/Executive Engineer, Junagadh Division-1 will be final and shall be
binding to the contractor.
4.3 Verbal clarifications and information given by the PGVCL or his employee(s) or his
representative(s) shall not in any way be binding on the PGVCL.
17. All interested parties requested to strictly abide by all terms prescribed in this RFP
Document and provide accurate information to the best of their knowledge without
misleading PGVCL to be considered for participation in this Project.
18. Bidders should be in touch with websites https://pgvcl.nprocure.com
Sign & Stamp of the Bidder P a g e 7 |
&www.pgvcl.com for information regarding revision / corrigendum / Amendment in
the Tender Document till due date of online / off line submission and thereafter. No
separate information shall be sent in this regards and also not publish in
5. TENDER FEES (Non Refundable & Non-transferable)
Existing rate of GST will be levied on following tender fees as per GST Rules in force
during this Tender Period.
5.1 The Tender fees is payable, as per following Table, between the dates mentioned in Table
no 1 , by cash & DD if total amount of Tender fees plus applicable GST is less than Rs
no 1 , by cash & DD if total amount of Tender fees plus applicable GST is less than Rs
10,000/- or only by Demand Draft (DD), if the said amount is more than Rs 10,000/-, in
favour of the Paschim Gujarat Vij Company Limited payable at Junagadh on any
Nationalized /Scheduled banks
Tender Fees in Present rate of
Sr.No Tender Amount
Above Rs 5,00,000/- up
Above Rs 10,00,000/- up
Above Rs 25,00,000/- up
5.2 The tender fees once paid for tender document will not be refunded under any
circumstances or not transferred to other bidder.
6. EARNEST MONEY DEPOSIT (EMD)
6.1 The EMD payable, between the dates mentioned in Table no 1 ,by cash if total amount of
6.1 The EMD payable, between the dates mentioned in Table no 1 ,by cash if total amount of
EMD is less than Rs 10,000/- or by Payment RTGS/NEFT, if the said amount is more
than Rs 10,000/-, in favour of the Paschim Gujarat Vij Company Limited payable at
Junagadh on any Nationalized /Scheduled banks or by Bank guarantee from any
Nationalized/Scheduled nationalized bank decided by Government of Gujarat time to time
only. The EMD Amount is 1% of the Tender Estimated Cost.
6.2 The money receipts of payment of Tender fees and EMD On line pay.
6.3 The EMD of all unsuccessful bidders except that of the successful bidder will
be returned after the award of the contract.
6.4 EMD of the successful bidder to whom a contract is awarded will be returned
after the said bidder pays the security deposit and signs the contract agreement.
6.5 If the successful bidder fails to submit a Security Deposit within 15 days from the date of
LOA of the contract or fails to sign the contract agreement then the EMD amount will be
forfeited in favour of PGVCL without any notice or and action for “Stop deal” will be initiated
as decided by tender inviting authority.
6.6 No interest will be payable by the PGVCL on the above Deposit.
6.7 EMD can be exempted as per Industries & Mines Department, GoG New
Purchase Policy Resolution No. SPO/1095/2636(97)/CH dated 23.09.1997 for
Small and Micro Scale Industries.
Sign & Stamp of the Bidder P a g e 8 |
6.8 In cases, where EMD need not to be paid, valid exemption Certificates duly notarized has
to be produced/attached in place of EMD documents as per the Tender Terms and
6.9 The Micro and Small Scale Industrial (manufacturing) Units registered under Small Scale
Industries of Gujarat State and holding subsequent registration with NSIC/DGS&D,
Registration Certificates for the item under Tender will be eligible for exemption from
payment of EMD on submission of attested copies of their SSI (SSI/ MSME Part-II) &
NSIC/DGS&D Registration Certificates and Udhyog Adhar Certificate/Memorandum in
EMD Cover. The Certificates should indicate the manufacture/service/works of items/work
offered. This benefit of exemption will not be admissible if they take part in the tender
indirectly either through their dealers, agents, distributors or other intermediates.
6.10 Tenders submitted without Earnest Money Deposit by the firms, who are not
eligible for any exemption, will be rejected without entering in to further
correspondence in this regard and no reference will also be made.
7. In case of On line Tenders
7.1 Technical & Commercial Bid cover:
7.11 Following documents are mandatory and to be in submitted through On line.
1. Attested Copy of successful work Completion certificate, as mentioned
on page no 5 point no 2.11 of this document.
2. Attested copy of Memorandum of Association or partnership deed.
3. Attested copy of document showing P.F. Number obtained by the
4. Attested copy of power of attorney if any for signing the bid
5. Attested copy of latest solvency certificate issued by Nationalized or
scheduled bank.
6. Attested Copy of registration Number under Shop and Estt. Act (If as
case may be applicable)
7. Copy of PF Code Number allotted by concerned PF Authority
8. Copy of Labour License (If as case may be applicable)
9. Copy of Registration under ESIC (If as case may be applicable)
10. All Annexures of this tender documents , duly signed bythe bidder,in
chronological order only
11. Certificate – A
12. Copy of Tender Document duly signed and stamped on each page.
13. Type test certificates for Cable Box, Straight through Joints (In Case
of UG Work Involved).
14. The contractor shall have a separate provident fund code of RPFC
and the Contractor who do not possess separate P.F. Code shall not
be considered for acceptance of tender.
15. Contractor has to submit such certificate showing separate P.F. Code
along with tender.
16. List of available safety gadgets, as per annexure XI, with the bidder.
17. Copy of documents mentioned in sr. no 2.2 of this tender.
Sign & Stamp of the Bidder P a g e 9 |
7.2 Commercial / Price Bid:
7.21The bidder must clearly quote their rates in Schedule – B of this tender, in percentage
above than, below than or equal to, the tender rate in figure as well as in words. The bidder
should specify whether the quoted rates are with or without prevailing taxes, if applicable,
in force at that time, The bidder must work out the total price of their tender offered
accordingly and the total amount should be clearly written in words & figure, in case of any
accordingly and the total amount should be clearly written in words & figure, in case of any
discrepancy whatever written in words shall prevail. Company shall at liberty to decide the
matter as it deem fit.
7.22 In case of non SOR rate, Item wise rate should be mentioned and item wise
rate will be consider for the lowest party.
7.23 Further bidders, for “On line tenders”, are requested to submit price – bid on-line
only and not to submit the price bid in physical form. This is mandatory. If price bid is
submitted in physical form, same will not be opened and only on-line submitted price bid
will be considered for evaluation. In On Line price Bid, GST is to be mentioned in
separate raw/Column.
PGVCL reserves the right to reject any OR all tenders without assigning any reasons
8. In case of Off line Tenders
8.1 Technical Bid cover
8.11 All the documents as specified in Section I sr no. 7.1 are mandatory and to be in
submitted through On line.
8.2 Commercial / Price Bid cover:
8.21 All the documents as per Section 1 sr no 8.22 & 8.23 are mandatory and should be
submitted in On line.
8.22 The bidder must clearly quote their rates in Schedule – B, attached with this tender, in
percentage above than, below than or equal to, the tender rate in figure as well as in
words. The bidder should specify whether the quoted rates are with or without prevailing
taxes, if applicable, in force at that time, The bidder must work out the total price of their
tender offered accordingly and the total amount should be clearly written in words & figure,
tender offered accordingly and the total amount should be clearly written in words & figure,
in case of any discrepancy whatever written in words shall prevail. Company shall at liberty
to decide the matter as it deem fit.
8.23 In case of non SOR rate, Item wise rate should be mentioned and item wise
rate will be consider for the lowest party.
8.24 No deviation in terms & condition in Schedule-B and Technical Specification will be
entertained. All the documents related to this Tender shall be final and binding to all the
bidders. Any ignorance for this shall not relieve the contractor from their contractual liability
arising as per Tender documents.
9. The works referred herein shall cover the entire scope of the Tender.
10. The issuance of bid document would not mean that the bidder has qualified for the bidding.
Hence bidders should ensure themselves of their credentials before submitting their offer.
11. Executive Engineer, PGVCL, Junagadh Division-1 reserves the right to spread the order
12. Does not anticipate change in the PGVCL ownership during the proposed period of work.
Sign & Stamp of the Bidder P a g e 10 |
13. AMENDMENT TENDER
13.1 At any time prior to the deadline for submission of bids, as mentioned in Table1,PGVCL
may, for any reason, whether at its own initiative or in response to a clarification requested
by a respective bidder, modify the bidding documents by amendments.
13.2 The amendment will be notified, only on PGVCL Website & nprocure website in case of
on line tender, PGVCL will bear no responsibility or liability arising out of noncompliance
of the same in time or otherwise.
13.3 Such amendments, clarification etc. shall be binding on the bidders and will be given due
consideration by the bidders while they submit their bids and invariably enclose such
documents as a part of the bid.
14. SUBMISSION OF TENDERS
14.1 Follow all the instructions narrated this tender document for submission and no any
further communication in the matter will be entertained.The Bidders must ensure that all
the Annexures are completely filled in their tenders and the information called for is given
in totality. A set of complete tender documents is required to be submitted duly signed and
stamped by authority competent to sign on behalf of bidder on each page as a token of
unconditional acceptance to the conditions of various clauses of tender documents. The
bidder's bid and the documents attached there to shall be considered for forming part of
the contract documents.
14.2 For “On Line Tenders”
14.21 Tender Papers & Specifications may be down-loaded from Web site
https://pgvcl.nprocure.com (For view, download and on line submission) and PGVCL web
site www.pgvcl.com (For view & down load only).
14.22 The bidder has to follow instruction given in this section point no 4 to 7. Both these
covers, as mentioned in this section point no 6.2, 7.11, should be submitted in one main
cover, this cover shall be clearly marked “EMD Cover, Technical _Commercial bid
covers for Tender no. __________” along with the name of the Bidder and his
Price bids to be submitted ON LINE only before time limit specified in “Tender
Details” Table no1 of this document.
14.3 For “Off Line Tenders”
14.31 Tender Papers & Specifications may be down-loaded from PGVCL web site
www.pgvcl.com (For view & down load only).
14.32 The bidder has to follow instruction given in this section point no 4 to 8. All these
three covers, as mentioned in this section point no 6.2, 7.11, 8.2 ,should be submitted in
one main cover,
15. REJECTION OF TENDER:
15.1 The Bidders is expected to examine all instructions, terms, conditions, schedules and
other details called for in this specification and keep himself fully informed about all which
may, in any way, affect the work, or cost thereof. The bidder should sign on each page of
tender documents , as mentioned in Section 1 point no. 2.15, filure to furnish the required
information or submission of tender not as per the specification will be at the Bidders risk
may result in rejection.
15.2 The offer is liable summarily rejected if it contains.
a) Deviation/Addition/Alternations/Omissions in bidding schedules.
b) Deviation and contradictions to the terms and conditions specified in this tender.
Sign & Stamp of the Bidder P a g e 11 |
15.3 If any bidders firm or/and partner or proprietary firm anywhere in companies (PGVCL,
UGVCL, MGVCL, GETCO, DGVCL, GSEC) under GUVNL are under criminal
investigation for any kind of fraud for public and theft of material or/and with handlings the
material and any civil and/or criminal case pending at any stage than offer of such bidder
/firm will be out rightly rejected.
15.4Bids submitted after the time and date fixed for the receipt of bids as set out in the Table
no1, shall be rejected.
15.5 Any deviation found in Data/Details/Documents between online offer (e-tendering) and
physically submitted documents of bidder, offer of the same shall be liable for rejection at
the discretion of PGVCL.
15.6 The Bidders shall specifically note that any over writing or corrections or manuscript in
the bid shall be ignored and will not be considered authentic unless same are signed with
Bidder's Stamp/Seal as mentioned in Section 1-point no.
15.7 Conditional bids shall not be accepted.
15.8 DELAYED AND LATE TENDERS:
No tender shall be accepted/opened, as mentioned in the Table no 1, in any case which
are received after due date and time of the receipt of tender irrespective of delay
due to postal services of any other reasons and company shall not assume any
responsibility for late receipt of tender. Any correspondence in the matter will not
be entertained.
16. LANGUAGE OF THE TENDER
All information in the bid shall be in English. Information in any other language shall be
accompanied by its translation in English. Failure to comply with this may disqualify a bid.
In the event of any discrepancy in meaning, the English language copy of all documents
17. SIGNATURE OF BIDDER
17.1 The bid must contain the name, residence, address and place of business of the person
or persons making the bid and must be signed and sealed by the bidder with his usual
signature. The name of all persons signing should also be typed or printed below the
17.2 Bids by corporation/ company must be signed with the legal name of the corporation/
company by the President, Managing Director or by the Secretary or other person or
persons authorized to bid on behalf of such corporation/ company in the matter.
17.3 A bid by a person who affixes to his signature the word 'President', 'Managing Director'
'Secretary', 'or other designation without disclosing his principal will be rejected.
17.4 Satisfactory evidence of authority of the person signing on behalf of the
Bidder shall be furnished with the bid.
17.5 The Bidder's name stated on the tender shall be exact legal name of the
17.6 Erasures or other changes in the bid documents shall be over the initials of the person
signing the bid.
17.7 The bidder should sign, as described above, on each page of tender documents & then
they have to submit this tender documents.
Sign & Stamp of the Bidder P a g e 12 |
18. PRICE BASIS CURRENCY AND PAYMENTS
Bidder shall indicate bid prices in Indian Rupees only.
19. EFFECT AND VALIDITY OF TENDER
The bid should be kept valid for a period of 120 DAYS from the date set for opening of
the technical bid.
20. EVALUATION AND COMPARISION OF TENDERS
Generally the qualifying price bids, Bid price shall mean the bid price quoted by each
bidder in his bid for the complete scope of works including all duties and Taxes ,.will be
evaluated by the PGVCL to ascertain the best and lowest evaluated bid in the interest of
the PGVCL, for the complete works covered under these specifications and documents.
21. ARITHMETICAL ERRORS
Arithmetical errors will be rectified on the following basis:
If there is a discrepancy between words and figures, the amount in words will prevail. If
there is discrepancy between the unit price and the total price which is obtained by
multiplying the unit price and quantity, or between sub-total and the total price, the unit or
sub-total price shall prevail, and the total price shall be corrected. In case of discrepancy
between sub-total price obtained by adding various prices in the schedule and the sub-
total price indicated for that particular schedule, the sub-total obtained by addition of
various arithmetically corrected prices would be considered for evaluation.
However, the PGVCL shall be entitled to award the contract at the lowest of the prices
arrived at from various schedules, identified for that purposes, in the bid proposal sheets.
If the bidder does not accept the correction of the errors as above, his bid will be rejected.
22. AWARD OF CONTRACT
22.1 Notification of award of contract will be made in writing to the successful bidder by the
22.2 The contract will be awarded to the best qualified and responsive bidder offering the
lowest evaluated bid in conformity with requirements of these specifications and
documents and PGVCL shall be the sole judge in this regard and subject to the provisions
of these instructions to bidders and other terms and conditions detailed out in these
documents and specifications. A responsive bid is one which accepts all terms and
conditions of these specifications and documents without any modifications.
22.3 PGVCL Reserves the right to award separate contract to two or more parties in line with
the terms and conditions specified in the specification.
23. ADDITIONAL DOCUMENTS:
At the time of evaluation of tender PGVCL Junagadh Division-1 office may ask bidder to
submit required documents other than mentioned in section I Point no 2.2, if required.
24. COMPLETION PERIOD
The contractual period for execution of the work stated in Schedule – B of this Tender
consist ________ Days. The commencement date of Order shall be Date of issue of the
Sign & Stamp of the Bidder P a g e 13 |
GENERAL INFORMATION ABOUT THE BIDDER
(To be completely filled by the bidder)
1. Name of the Bidder
2 Postal Address
4 e-mail address & URL
Type of Company
Attach Proof of Company Registration
Proprietorship/Partnership/Private
5 along with a copy of the Partnership
Limited/ Public Limited
Deed/ Article of Association and
Memorandum of Understanding
Name and designation of the
representative of the Bidder to whom all
reference shall be made to expedite
technical co-ordination.
7 Office Address
Stores Address where materials issued
by PGVCL will be stored
Store Documents to be submitted
10 Office Telephone/Fax no.
11 Office e-mail address
12 Permanent Account Number(PAN),
15 Labour License No.
Insurance Policy No. and for nos of
16 Nos of Labours Insured in this policy_______
labours in the name of bidder
17 Solvency Certificate No.
18 Adhar Card No.(Optional)
It is certified that the information provided above is true to the best of my knowledge and
belief. If any information found to be concealed, suppressed or incorrect at later date, our
tender shall be liable to rejected and our company debarred from executing any business
Sign & Stamp of the Bidder P a g e 14 |
SECTION II Schedule A:
1.0 For Underground Cable
1. Bidder has to maintain the records of allotted Cable Drum with actual Cable/Conductor
length. Cable length must be measured before laying. Cable joints are to be done as per
requirement only and length of cable must be utilized accordingly.
2. Cable is to be laid in Trench as per instructions of Engineer-in-Charge.
3. The trench excavation and filling–in shall be so executed that all walls, roads, sewers,
drains, pipes, cables, structures, places and things shall be reasonably secured against
risk of injury and shall be carried out to the satisfaction of the authorities concerned.
However, if any, damages to existing services made, Contractor shall arrange and pay for
any necessary repair, to make good the damages.
4. When the excavation of the trenches has been accurately executed, the contractor shall
inform engineer in-charge for approval. Lying of cables shall not be started until engineer
in-charge approves the trench.
5. All the related material for laying the cable in trench i.e. Half round RCC Pipes having
_both sides smooth surfaces, 25.4 mm thick , 152.4 mm inner diameter, 1000 mm long
and well cured and good quality; Sand from river bed, HDPE Pipes, GI Pipes and sundries
material if any (As per Schedule B) are to be supplied by Bidder at his own Cost. All such
material must be approved from concerned Engineer-in-charge before utilization and it
must be ISI marked where ever applicable.
6. Cable laying work must be executed as per prescribed in Schedule B. sand filling in Trench
must be done as mentioned in Schedule B. Megger test of Cable must be taken in
presence of Engineer-in-charge before laying and Bidder has to maintain separate
Records duly signed by Engineer-in-Charge for each results. After laying the Cable in
trench it is to be covered with half round pipe of RCC as prescribed in Schedule B and
approved sample. Each Half round Pipe must be marked with “PGVCL” with solid Red
7. Proper methodology of laying is to be adopted by the Bidder. Bidder has to lay Cable in
the stretch on small pulleys kept in the Trench so that it can be prevented from any
scratches on Cable. Drum must be fixed on Drum Machine while stretching and to be kept
on one end of Trench for smooth laying.
8. After completion of laying as above, remaining trench must be filled with sand. Leveling
with Road is to be done after complete sand filling. No any stones or any other debris are
to be utilized in filling of Trench. The contractor shall dispose of surplus material at his own
9. A pre-warning PVC yellow tape 8-Inch wide and 300 microns thick (LDPE) shall also be
laid. The warning tape shall be printed in RED letter (IN ENGLISH AS WELL AS
GUJARATI) as “CAUTION: 11000 VOLTS PGVCL CABLE” and to be placed at about
300 mm To 450 mm depth from ground level along the route of cable.
10. Trench route is to be made as per instructions of concerned Engineer-in-Charge and then
laying of cable in this trench accordingly.
11. Cable Laying with Mechanical Boring across the Road without disturbing the asphalt is to
be done instructions of concerned Engineer-in-Charge with prior approval and work is to
be executed as per Specifications in Schedule B only.
12. For Cable kit Make (Brand) Bidder has to submit any NABL accredited Lab Type test
certificate not older than Seven years and as per relevant IS 13573:2011 with latest
Sign & Stamp of the Bidder P a g e 15 |
amendment if any along with sample before installation of cable kit at concern Division
office. GTP is to be submitted with Technical Bid.
13. If any Hard Rock area is encountered during the digging of Trench, Bidder must have all
the modernized equipment i.e. Erath Cracker JCB etc. to execute the required Trench.
Such area must be certified by a formation of Committee at Division Level headed by
Executive Engineer and to be executed in presence of Engineer-in Charge.
IS 1255-1983 is to be followed for the depth of trench in such area.
14. Route Markers are to be installed at every 100 Meters length as per specifications in
Schedule B The marker should incorporate the following relevant information:
1) The name of the Company – PGVCL.
2) Voltage – 11 KV Cable
3) Distance of cable from the marker
The interval should be maximum 50/100 meters (As per EIC instructions and requirements)
between two markers. It shall also be put at bends, curves, road crossing, Cable Joints
etc. of cable route as per requirement over and above specified distance.
15. Empty Drums are to be credited at PGVCL respective stores at Bidders cost and Risk after
successful completion and Execution of work. Otherwise Recovery will be proposed as
per Section V Clause No.
16. After Laying of Cable in Trench and filling of all type Cable Box and Joints, testing must
be carried out with help of Voltage Surge Testing Kit as per IE Act by applying 22 KV for
continuous Five Minutes and Cable must hold the satisfactory Results. Bidder must have
such testing facility. Following Pre commissioned Tests are also to be carried out.
a) Insulation Resistance of each cable drum length after laying and before jointing.
b) Before laying of cable, tests for detection of damage to outer sheath, if any.
c) After laying each cable with end termination shall withstand a voltage of 10 KV DC for one
minute between each phase to phase & phase to cable earth.
d) Test for 5 min. with system voltage applied between the conductor and the screen.
e) Continuity & Phase confirmation
17. During the Execution if any deficit found in allotted material OR in case of any theft of
PGVCL allotted material, then PGVCL will recover the cost of such material from Bidder
as per the prevailing Market Rates.
18. No any Advance Payment will be made after issuing of Order.
19. PGVCL will be not responsible and liable for the material supplied by the Bidder.
20. During Execution of work for Trench and Cable Laying authorized representative of Bidder
who is in knowledge of Engineer-in-Charge must remain present.
21. Bidder must have to submit the List of all related Equipment and Testing facility necessary
for the Tendered work while quoting the Bid.
22. PGVCL reserves the right to change/modify/alter/addition in condition in case of any
dispute and holds the power to decide the final verdict.
23. GST as per prevailing rates are applicable to Bidder for this work.
24. In case of any Disputes, Superintending Engineer of Concerned area is the final Authority
to take any Decision.
25. Work may be required to be executed in any 66/132/220KV Sub-Stations also.
26. Necessary shutdown for connection/jumper of UG cable with existing network will be
provided as per availability or convenience of the PGVCL which shall be acceptable to the
contractor & contractor shall try to complete the work in minimum time.
27. All the sundries material like Clamps, Screws, nuts, bolts, nails etc. is at Contractor’s cost.
Sign & Stamp of the Bidder P a g e 16 |
28. Work is to be performed as per Drawing No. PGVCL/Tech/UG cable/01/14-15 and
PGVCL/Tech/UG cable/02/14-15 are attached in Section XI.
2.0 For Overhead Line
1. Bidder has to maintain the records of allotted Conductor Drum with actual Conductor
length. Conductor length must be measured before Stringing.
2. E/o Poles must be according to RE Standards. Pole Pit, stringing installation of Fabrication
must be done as per standards and esthetically.
3. Earthing of Poles and Transformers must be as per Drawings and RE Standards. The
Coal and Salt composition must be followed as per rules. The Earth Pit must be kept at a
distance mentioned in Standard form the Pole. Earth Pit must be as per Drawing.
4. Concreting of Poles/Guys are to be carried out as per site situation and as per instructions
of Engineer –In-Charge.
5. Construction of Transformer Structure must be as per standard with all required
accessories like LA, Box and Fuse etc.
6. Delta Type Three Earthing are compulsory for each Transformer Centre.
7. All the jumpers at Shackle Points/DP Structures must be of “D” Type only.
8. Wherever required, Guarding as per standard must be done.
9. Pole Concreting: Whenever concreting of poles (PSC/RSJ) required, subdivision officers
has to submit the proposal to the division office with all justification before commencement
of work. Committee of Executive Engineer, DE Tech of Division office has to verify the
submitted proposal and decide whether concreting is required or not. After the approval of
committee work of concreting should be process as per specification attached herewith.
10. Bidder must have records of each work carried out with every material inventory and
account thereof issued to him.
11. Bidder must have the well-drawn sketch of each work and to be submitted with Inventory
sheet within 15 Days of work completion.
12. All the fabricated material and Girder Poles must be painted with Coats of Silver Oxide
and without this work, work completion will not be accepted.
13. Pole Numbering must be completed within week time as per Engineer-in- Charge
14. Bidder must have proper pole accounting for the work carried out by him. He must have
the location details from where the poles are lifted and where these poles are utilized for
each work. A separate Register is to be maintained by him and details are required to be
submitted with Inventory and Sketch submission.
15. Necessary shutdown for connection/jumper of newly erected line with existing network
will be provided as per availability or convenience of the PGVCL which shall be
acceptable to the contractor & contractor shall try to complete the work in minimum time.
16. Successful Bidder must have ensured for that the safety Gadgets are issued to his Labour
, by him, and required regulations of Safety will be followed while carrying out the line
17. The Work for the erection of of Poles, Guys, Earthing, Transformer and Concreting,
Stringing and Guarding must be done as per attached Specifications and Drawings.
18. The material which is dismantled from site during the execution of work must be credited
to respective Divisional stores immediately after completion of work with complete
inventory and measurement details and length to weigh conversion calculations.
19. Any violation of Electricity Act 2003 Section No. 136 & 137, necessary action will be
initiated against the Contractor
20. In case of any Disputes, Superintending Engineer of Concerned area is the final Authority
to take any Decision.
Sign & Stamp of the Bidder P a g e 17 |
General Instructions to the successful bidders
1. Letter of Intent (LOI) / Letter of Acceptance (LOA) shall be issued to the successful Bidders
indicating the quantity allocated to them and the security deposit amount to be deposited
by them with PGVCL. Short listed Bidders will be required to deposit the requisite security
deposit within 15 days from issuance of LOI / LOA.
2. Security Deposit:
2.21 Security deposit will be accepted in Cash if the amount is less than Rs. 10000.00 and, if
the amount is more than Rs. 10000.00 then will be payable by Demand Draft (DD) or Bank
Guarantee (BG) from Nationalized / Scheduled Banks as per Govt. GR No. EMD / 10 /
2014 / 570 / DMO dated 01.04.15 will be acceptable. DD should be drawn on any
Nationalized /Scheduled banks in favour of Paschim Gujarat Vij Company Ltd. payable at
Junagadh or by Bank guarantee from any Nationalized/Scheduled nationalized bank
decided by Government of Gujarat time to time only. Cheque will not be acceptable
2.22 The successful Bidders will be required to deposit the requisite security deposit within
days from the date of issuance of LOI / LOA of an amount equivalent to 5 % of the
value of the work to be allotted to him and as mentioned in LOI / LOA.
2.23 In case, if the Bank Guarantee is furnished / submitted, it should have a clear one time
validity till the completion of awarded work of this work order. Bank Guarantee for interim
period will not be allowed. Security Deposit shall be suitably extended time to time as per
2.24 If by any reasons the completion period of this work order is extended, then supplier
should undertake to renew the Bank Guarantee at least one month before the expiry of
the validity failing which PGVCL will be at liberty to encase the same. CORPORATE
GUARANTEES NOT ALLOWED.
2.25 No interest will be paid on the Security Deposit.
2.26 In the event of awarding the order of additional quantity, the successful Bidders will be
required to deposit additional Security Deposit on prorate basis within two weeks of the
issuance of LOA /LOI for the additional order quantity.
2.27 In the event of failure to carry out work offered by successful Bidders and as accepted by
them while receiving the order within given time period, will lead to forfeiture of the Security
Deposit up to 100% and will lead to disqualification of the bidder to transaction business
with PGVCL for at least TWO years or the time duration as may be decided by the
Managing Director, PGVCL.
2.28 Security deposit will be returned on after completion of awarded work.
2.29 If the successful Bidders fails to pay security deposit within given time limit then the letter
of intent will stand cancelled. EMD amount will be forfeited in favour of PGVCL without
any notice or and action for “Stop deal” will be initiated as decided by tender inviting
Sign & Stamp of the Bidder P a g e 18 |
3.0 SIGNING AGREEMENT
The successful Bidders will have to sign an agreement, within 15 days from the receipt of
LOI/LOA, on Stamp Paper of Rs 100/-as per Company’s rules in the prescribed form of the
P.G.V.C.L. attached with this Tender. The cost Rs.100.00 of the Stamp Paper will have to
be borne by the successful Bidders.
4. For the Tendered work, other than turnkey work, entire material will be issued by PGVCL.
Any other related material required to carry out work mentioned in Schedule A is to be
brought by Bidder. No any extra cost will be paid towards such material.
5. Successful Bidder has to follow all the rules and Regulations of Work Safety. Required
tools and Tackles for Safety are to be arranged by Bidder only.
6. Bidder is responsible to any type theft/damages of Company’s material and also
responsible to any type damages to any property and any kind fatal/non-fatal accidents to
anybody during the execution of work. Insurance of all workers is compulsory, who are
involved in Execution of Tendered work. There will be no any financial liabilities of PGVCL
for damage charges paid such way. Copy of valid Labour Insurance Policy in the name of
bidder is to be submitted with Tender Documents.
7. Rules and Regulations of PGVCL Works and Contracts Book are abided to Bidder.
8. Work must be completed in in specified Schedule narrated in the Tender. If concerned
Engineer not satisfied with quality of work, no any Time limit extension will be granted and
Penalty with applicable GST and other taxes in force at that time will be levied on delayed
portion of work.
9. Agreement must be executed within 15 (Fifteen) Days from the date of issue of LOA.
Security Deposit (In form of DD/BG) and Insurance Policy is also to be submitted with
Agreement within this time limit i.e. 15 (Fifteen) Days.
10. Remaining material is to be credited at Respective Stores of PGVCL within a month after
completion of work.
11. Agreement and Indemnity Bond is to be executed on Rs. 300/- Stamp Paper and cost of
stamp paper is to be borne by Bidder. Solvency Certificate is to be submitted as per
PGVCL rules and Tender Condition.
12. Bidder is solely responsible for the material supplied by PGVCL.
13. Coal and Salt are to be brought by Bidder at his own expenses, for earthig work, and work
to be done as per PGVCL rules and RE specification for this work.
14. Work is to be carried out in presence of PGVCL authorized representative and to be duly
certified also.
15. No idle labour charges will be paid by the PGVCL in case such occasion of idle labour
arises, due to want of any materials or any other situations.
16. PGVCL have full rights to accept or reject the offer received against the Tender.
17. Bidder has to submit the Performance Certificates under whom the similar kind of
Tender work has been executed. Such Certificates must not older than 3 Years from
Date of submission of the Bid. Such Certificate must be duly signed by Cadre
Executive Engineers and above only.
Sign & Stamp of the Bidder P a g e 19 |
TERMS & CONDITIONS REGARDING INDUSTRIAL LAWS AND OTHER RELATED MATTERS:
1. COMPLIANCES WITH LAW:
The Contract shall in all respects be interpreted in accordance with the laws in force in
India, including any such laws passed or made or coming into force during the period of
2. Wages to be paid at the time of payment etc.by the contractor
2.1 The successful bidder shall pay minimum prevailing rates per day, as may be specified here
after, or rates fixed under the Minimum Wages Act, whichever is higher. The wages of every
contract labour employed by him under this contract shall be paid by him before the expiry
of 7th day of the month irrespective of which the wages are payable i.e. wages of a last
month have to be paid by him in the first week of the next month). The contractor shall have
to make wages to his workers through bank only. The agency shall have to submit the copy
of a letter given to the Bank advising for crediting wages in individual account of the
workmen along with photocopy of the cheque showing total payment to be made to all such
workmen whose accounts are operated in that branch. (If there is more than one Branch,
the agency will have to submit separately for each branch.)
2.2 The successful bidder shall give his telephone number and address to the company so
that in case of labour trouble etc. the contractor can be contacted. The contractor shall
arrange to have his office outside the factory premises and the contractor shall keep
himself present through the work hours.
3. Persons below the age of 18 years shall not be deployed for the said work.
4. No female worker shall be employed in the night shift between 07.00 p.m. to 6.00 am.
5. Identity cards as prescribed under the factories Act/Shops and establishment Act (As the
case may be applicable) with Photo affixed thereto, for identification.
6. The successful bidder shall maintain a valid Labour license under the contract labour
(regulation and abolition) Act for employing necessary manpower required by them. In
absence of such license, the contract shall be liable to be terminated without assigning
any reason thereof.
7. The successful bidder shall at his own expenses comply with all labour laws and keep the
PGVCL indemnified in respect thereof. Some of the major liabilities under various labour
and industrial laws which the Contractor shall comply with below conditions.
7.1 Payment of contribution by way of employer's contribution towards provident fund,
administrative charges etc. at the rates made applicable from time to time by the
Government of India / Government of Gujarat or other statutory authority.
7.2 Payment of deposit in respect of each contract labour at the prevailing rate with the office
of the commissioner of labour as per the Contract Labour (Regulation and abolition) Act.
7.3 License fee as prescribed under the contract labour (Regulation and abolition) Act rules
framed there under depending upon the number of workmen.
7.4 Paid leave facility and wages as per the provision of the Factories Act at the rate of one
day for every 20 days of working.
7.5 Payment of retrenchment compensation, Notice pay and other liabilities as per industrial
Dispute Act. Any payment to the Contractor's employee arising out of any claim of disputes
under the Industrial Dispute Act 1947 or any other labour Laws.
7.6 Payment of compensation in case of accidental death or injury as per Employee's
compensation Act.
7.7 Maternity leave as per the provisions of the Maternity Benefit Act.
7.8 In case, PGVCL becomes liable to pay any wages or dues to any manpower deployed or
any government Contractor under any of the provisions of the Minimum wages act,
Payments of wages Act, Employee's compensation Act, Contract Labour regulation
abolition Act, Employee provident fund or any other law due to act of omission of the
Sign & Stamp of the Bidder P a g e 20 |
Contractor, the PGVCL may make such payment and shall recover the same from the
successful bidder 's Bill.
7.9 If the PGVCL is caused to pay under any law as a principal employer such amount as may
be necessary to cause of observe, or for non-observance of the provisions stipulated in
the notifications/byelaws/Acts/Rules/Regulations/ including amendments. If any, on the
part of the Contractor, the PGVCL shall have the right to deduct any money due to the
successful bidder under this contract or any other contract with the PGVCL including his
amount of security deposit for adjusting the payment. The PGVCL shall also have right to
recover from the Contractor any sum required or estimated to be required for making good
the loss or damage suffered by the PGVCL.
8. Employee's compensation fund and employer's liability insurance: -
The successful bidder shall cover all his employees under employee's compensation fund and
under the liabilities insurance. The Contractor will arrange insurance policies for arranging
payment to his staff injured / met with accident (Fatal / nonfatal) on duty of sufficient
amount as per Labour laws. In case of any such happening Contractor will be liable for
any other payment to workers / staff engaged as per existing rules. Contractor will not
make any such payment to the Contractor's staff or any compensation etc. during the
pendency of the contract.
9. Following Salient features of some major laws are applicable to establishments engaged.
9.1 Employee PF and Misc. Provision Act
9.2 Payment of Gratuity Act
9.3 Maternity Benefit Act
9.4 Equal Remuneration Act
9.5 Payment of Bonus Act
9.6 Industrial Dispute Act
9.7 Industrial Employment (Standing orders) Act
9.8 Trade Union Act
9.9 Employees compensation Act
9.10 Contract Labour (Regulation and abolition) Act
9.11 Child Labour (Prohibition and regulation) Act
9.12 Inter-state migrant workmen's (Regulation of Employment and
conditions of service ) Act
9.13 Minimum wages Act
9.14 Payment of Wages Act
9.15 Factories Act
9.16 Shops and Est. Act
9.17 The Employees’ State Insurance Act and the scheme ,
The above are some of the major liabilities of the Contractor in addition to other liabilities
prescribed under the various labour laws, in force from time to time, from statutory
authorities like GOI-GOG, which the Contractor shall have to comply with.
10. It should be ensured that before commencing the said work, the successful bidder should
submit the details of their labourer such as a full name, address and age with proof and
subsequently changes of workers details are submitted accordingly.
11. The successful bidder shall employ adequate number of an experienced staff at site for daily
supervision and for maintenance of various register and records required under the law
and contract. No payment for supervision shall be admissible.
12. PGVCL does not accept any responsibility as Factory Act, Minimum Wages Act, Workmen’s
Compensation Act, Insurance Rules etc. or any other act, rules or regulations that have to
be observed by the contractor for carrying out the work.
13. The contract will be governed by the company as per works terms & conditions of the
Sign & Stamp of the Bidder P a g e 21 |
14. EMPLOYMENT OF LABOUR:
14.1 Persons below the age of 18 years shall not be employed for the work. No female worker
shall be employed in the night shift between 07.00 p.m. and 06.00 a.m. next day.
14.2 Contractor shall maintain a valid labour license under the Contract Labour (Regulation and
abolition) Act for employing necessary manpower required by him. In the absence of such
a license, the contract shall be liable to be terminated without assigning any reason
thereof. Contractor should also employ qualified and experiences persons as per
requirement of Electricity Act and rules for carrying out supply and erection work under
14.3 In case PGVCL becomes liable to pay any wages or dues to labour or any Government
agency under any of the provisions of the Minimum Wages Act, Payment of Wages Act,
Employee Compensation Act, Contract Labour Regulation Abolition Act, Employee
Provident Fund or any other law due to act of omission of the Contractor, PGVCL may
make such payment and shall recover the same from the Contractor’s bills.
15. PROVIDENT FUND AND FAMILY PENSION SCHEME
The Contractor shall submit along with his bills (month wise) a Statement regarding
deduction against employees Provident Fund and Family Pension Scheme in respect of
each concerned employee The contractor's contribution and the workers’ contribution
towards Provident Fund and Family Pension Scheme shall be done at the rate made
applicable by the Government from time to time and deposited by the contractor with
Regional Provident Fund Commissioner, Rajkot.
16. DEPOSIT LINKED INSURANCE SCHEME
The contractor shall have to deposit 1.2% of the wages in respect of employees who are
members of the Provident Fund as the contribution to the Deposit Linked Insurance
Scheme with Regional Provident Fund Commissioner, Rajkot.
17. ADMINISTRATIVE CHARGES
Administrative charges for maintaining Provident Fund Account shall be deposited by the
Contractor with Regional Provident Fund Commissioner, Rajkot at the rates applicable.
18. PAID LEAVE FACILITY
Paid Leave Facility at the rate of one day for every twenty days worked by the Contract
Labour shall be provided by the Contractor to his, workers. He shall maintain Leave
Records, Leave Cards for individual labourer which shall be duly verified, approved and
certified by the Authorized Officer of PGVCL. Remuneration for such leave period shall be
fully borne by the Contractor.
19. Workmen’s Compensation and Employer’s Liability Insurance
Insurance shall be affected for all the Contractor's employees engaged in the performance
of this contract.
20. Wages to be Paid & Time of Payment etc. by the Contractor
20.1 The Contractor shall pay minimum wages per day to his Labours/ Workers as per rates
fixed under the Minimum Wages Act. The wages of every Contract Labour employed by
him under this contract shall also be paid by him before the expiry of 7th day from the last
day of the month in respect of which the wages are payable (i.e. wages of a month have
to be paid by him in the first week of the next month).
20.2 Any default will result in cancellation of contact forthwith or else the Contractor shall be
punishable to the extent of Rs. 100/- for each day of default.
20.3 The Contractor shall give his Addresses, Telephone Number and etc. to PGVCL, so that,
in case of labour trouble etc. the Contractor can be contacted. The Contractor shall
arrange to have his office within working area and the contractor keep himself present
throughout the working hours.
20.4 The separate P.F. code issued from RPFC is required to be taken by the contractor and if
it is not taken, offer of the firm will not be considered. The attested documentary evidence
to be submitted along with the offer.
Sign & Stamp of the Bidder P a g e 22 |
20.5 The contractors who are having separate P.F. Code No. from RPFC, it should be
ensured that all the contract labourers are covered under the provident fund scheme and
employees’ pension scheme and their contributions are remitted regularly to the
concerned RPFC. The photo copies of the Chelan in this regard should be collected from
the concerned contractor and kept in the file of the concern contractor.
21. CONTRACTOR TO INDEMNIFY THE COMPANY
The successful bidder shall indemnify the Company and every member officer and
employees of the Company, also engineer in charge and his staff against all actions,
proceedings, claims of demands, coasts and expenses, which may be made against the
Company or Government for or in respective of or performance of his obligation under the
contract documents the Company shall not liable for or in respective of or in consequence
of any accident or inquiry to any workman or other person in the employment of the
contractor or his sub-contractor and the contractor shall Indemnify and keep indemnified
the Company against all such damage and compensation and against all claims,
demands, proceedings costs, charges and expenses whatsoever in respective thereof in
relation thereto.
The Bidder’s insurance liabilities pertaining to the scope of Works are detailed out in
Clauses titled Insurance Bidder’s attention is specifically invited to these clauses. Bid price
shall include all the costs in fulfilling all the insurance liabilities under the Contract.
28.1 The Contractor at his cost shall arrange, secure and maintain all insurance as may be
pertinent to the Works and obligatory in terms of law to protect his interest and interests
of the PGVCL against all perils detailed herein. The form and the limit of such insurance
as defined herein together with the under-writer in each case shall be acceptable to the
PGVCL. However, irrespective of such acceptance, the responsibility to maintain
adequate insurance coverage at all time during the period of Contract shall be of
Contractor alone. The Contractor’s failure in this regard shall not relieve him of any of his
contractual responsibilities and obligations. The insurance covers to be taken by the
Contractor shall be in the name of the Contractor. The Contractor shall, however, be
authorized to deal directly with Insurance Company or Companies and shall be
responsible in regard to maintenance of all insurance covers. Further the insurance should
be in freely convertible currency.
23. Any loss or damage to the equipment during handling, transportation, storage,
erection, putting in to satisfactory operation and all activities to be performed till
the successful completion of commissioning of the equipment shall be to the
account of the Contractor. The Contractor shall be responsible for preference of all
claims and make good the damages or loss by way of repairs and/or replacement
of the equipment, damaged or lost. The transfer of title shall not in any way relieve
the Contractor of the above responsibilities during the period of Contract. The
Contractor shall provide the PGVCL with copy of all insurance policies and
documents taken out by him in pursuance of the Contract. Such copies of
documents shall be submitted to the PGVCL immediately after such insurance
coverage. The Contractor shall also inform the PGVCL in writing at least sixty (60) days
in advance regarding the expiry/cancellation and/or change in any of such documents and
ensure revalidation, renewal etc., as may be necessary well in time.
24. The perils required to be covered under the insurance shall include, but not be limited to
fire and allied risks, miscellaneous accidents (erection risks) workman compensation risks,
loss or damage in transit, theft, pilferage, earth quake, riot and strikes and malicious
damages, civil commotion, weather conditions, accidents of all kinds, etc. The scope of
such insurance shall be adequate to cover the replacement/reinstatement cost of the
equipment for all risks up to and including delivery of goods and other costs till the
equipment is delivered at Site. The insurance policies to be taken should be on
replacement value basis and/or incorporating escalation clause. Notwithstanding the
extent of insurance cover and the amount of claim available from the underwriters, the
Sign & Stamp of the Bidder P a g e 23 |
Contractor shall be liable to make good the full replacement/rectification value of all
equipment/materials and to ensure their availability as per project requirements.
25. All costs on account of insurance liabilities covered under the Contract will be on
Contractor’s account and will be included in Contract Price, However, the PGVCL may
from time to time, during the pendency of the Contract, ask the Contractor in writing to limit
the insurance coverage, risks and in such a case, the parties to the Contract will agree for
a mutual settlement, for reduction in Contract price to the extent of reduced premium
amount. The Contractor, while arranging the insurance shall ensure to obtain all discounts
on premium which may be available for higher volume or for reason of financing
arrangement of the project.
26. The clause entitled ‘Insurance’ covers the additional insurance requirements for the
portion of the works to be performed at the Site.
27. The successful bidder will not be allowed to work after working hours except in special
28. The successful bidder has to engage required strength of skilled persons for execution of
work and proper supervisor to avoid complication and unnecessary delay to complete work
timely. The successful bidder will be solely responsible for labour claims arising out of the
labour employed for this job.
29. The successful bidder should furnish details of past experience of such job of similar nature
completed by him satisfactorily within the time limit in PGVCL will be preferable.
30. The successful bidder will be abide by and fulfil all the terms and provisions of the “Tender
and contract” for works as applicable and in case of any default there to the PGVCL
Company shall forfeit the S.D. or any other action as may be decided by Executive
Engineer Junagadh Division-1.
31. The successful bidder will certify that he has complied with the provisions of
Industrial & Labour Laws including PF Act, ESI Act etc. as may be applicable. Copy
of challans of PF related to be submitted along with bill.
32. The successful bidder will have governed by the PGVCL general conditions of works
contract. The Booklet will be available in the concerned office in any working days. In the
event of placing order, the successful bidder will be bound to the terms & conditions of the
booklet. All the usual terms and conditions of the Company though the same might have
not been mentioned in this specification or contractor booklet will applicable to this contract,
and the decision of the Executive Engineer, Junagadh Division-1 shall be binding on the
Sign & Stamp of the Bidder P a g e 24 |
SECTION V TAXES and Duties: GST
1. The prices are excluding GST and Cess as applicable which will be paid extra on a given
taxable goods and/or services. The amount and % of GST and Cess as applicable should
clearly be indicated separately. (GST/Cess means all applicable Tax/Cess under GST
2. GST Laws means IGST Act, GST (Compensation to the State for Loss of Revenue) Act, CGST
Act, UTGST Act and SGSCT Act, 2017 and all related ancillary legislations).
3. Contractor shall have to submit a C.A Certificate & duly authorized Signatory, certifying that
you have not claimed Refund of any applicable GST and Cess, charged to COMPANY or shall
not claim any such Refund, on a future date, from the concerned Authorities and if, any Refund,
in respect of such GST and Cess, is claimed by you, it will be immediately passed on to the
COMPANY, without COMPANY making any specific Claim, for the same, either from the
Department or from you.
4. The offers having price INCLUSIVE OF GST and Cess is likely to be rejected if the rate of GST
and Cess is not mentioned clearly unless the bidder has opted for Composition Scheme under
GST Act, which should be clearly indicated in the price bid. COMPANY may at its discretion
consider such offer with presumption of highest applicable rate of VAT/GST/Cess prevailing
when the price quoted is inclusive of GST and Cess.
5. If the Contractor has opted for the Composition scheme of GST, the same must be clearly
specified with valid Declaration & Certificate from Department. In the event of
withdrawal/cessation of the Supplier from Composition scheme during the tenure of the
contract, the rate mentioned in the price bid shall be final and any additional GST will have to
be borne by the tenderer. In no case additional amount towards tax or otherwise will be paid /
reimbursed to supplier/contractor. Further Statutory Variation clause will not be applicable in
case of Supplier / Contractor has opted for Composition Scheme under GST.
6. Contractor should charge GST in Invoice at the rate as agreed to/mentioned in acceptance of
tender only and any deviation in the same shall not be accepted. Further, any additional liability
of GST (later on due to wrong mentioning of GST rate, mis-interpretation of HSN/SAC Code,
etc.) over and above as charged in the invoice shall be borne by the Supplier/Contractor.
However, any refund received by the supplier / contractor on account of GST charged from
the company; such refund shall have to be passed on to the company, along with interest if
any. Such refund along with interest needs to be passed on suo-moto by the contractor.
7. Further, the Company has a right to recover the amount of GST along with penal interest at
the rate of 15% per annum if GST charged is not paid/short paid to the government or fail to
upload the details or uploads inaccurate particulars on GSTIN portal by the Supplier /
Contractor within the stipulated time limit.In case, Govt. revises the rate of GST rate / Code
during the tenure of the contract, the provision of GUVNL’s statutory variation clause shall
8. INPUT TAX CREDIT BENEFIT
In the event of any statutory increase in the rate of Input Tax Credit and / or due to inclusion
of any other additional item of their inputs / input services under the ambit of the Input Tax
Credit provisions under the GST Act, subsequent to the date of submission of the offer, the
same should be passed on to COMPANY and you should inform such changes to COMPANY
from time to time. PGVCL’s GST Registration No.is 24AADCP1453C1ZZ
Sign & Stamp of the Bidder P a g e 25 |
9. TAXES, PERMITS & LICENCES:
The Contractor shall be liable and pay all foreign taxes, duties, levies lawfully assessed against
the PGVCL or the Contractor in pursuance of the Contract. In addition, the Contractor shall be
responsible for payment of all Indian duties, levies and taxes lawfully assessed against the
Contractor for his personal income & property only.
10. Income Tax –TDS“Income-tax at source at the prevailing rate will be deducted from bills
in accordance with the provision of Income-Tax Laws and to that effect a certificate will be
issued to the contractor, however added as contractor has to submit separate invoice for
supply parts item as well as works part item separately, otherwise TDS will be deducted on
entire invoice value.”
11. Applicable welfare cess will be deducted from contractors each bill by PGVCL to pay the same
to the respective Govt. Department. Tax will be deducted as per applicable statutory rules.
12. Statutory Deduction
Statutory deduction will be made as per applicable rules & rates for TDS, GST TDS,
welfare cess or any other taxes applicable time to time etc. All other statutory liabilities
towards this contract will be on your part.
11. STATUTORY VARIATION
Any statutory increase in the taxes subsequent to your offer if it takes place within the
contract period will not be considered except GST. No statutory variation will be given for
this work except GST.
12. The Contractor shall be fully responsible for deducting the P.F. of the employees/labour
Working under him as per statutory regulations and depositing the same with the
concerned authorities.
13. The Contractor shall comply with the relevant laws of India.
The Contractor shall be liable for and shall indemnify the Employer against all losses, expenses
or claims arising in connection with the death of or injury to any person employed of the
Contractor or his subcontractors for the purposes of the Works.
Sign & Stamp of the Bidder P a g e 26 |
SECTION VI: TERMS AND CONDITIONS for successful bidders
1.1 The successful bidder shall be deemed to have carefully examined all the papers, drawings,
etc. attached & if has any doubt as to the meaning of any portion of any condition /
specification, etc. he shall before signing the contract submit the particulars thereof to
PGVCL in order that such doubts are removed.
1.2 The successful bidder shall not, without the consent in writing of PGVCL, transfer, assign
or sublet the work under this contract or any substantial part thereof to any other party.
1.3 The execution of work should be commenced as per the instruction of the Engineer In
Charge as per actual requirement and should be completed within the time limit thereafter.
1.4 PGVCL may at any time by notice in writing to the successful bidder either stop the work
altogether or reduce or cut it down. If the work is stopped altogether, the Bidder shall only
be paid for work done. If the work is cut down the Bidder shall not be paid for the work as
so cut down, but in neither case shall be paid any compensation what so ever for the loss
or profit which he might have made if he had been allowed to complete all the work
included in the contract.
1.5 Notices, Statements and other communications sent by PGVCL through registered post
or telegram or telex or any other way of communication to the successful bidder at his
specified address shall be deemed to have been delivered to the successful Bidder.
11.The work shall be carried out by the successful bidder with prior approval of PGVCL.
Work carried out without PGVCL’s approval shall not be accepted and the PGVCL shall
have right to reject it and to recover the cost from the successful bidder. He will be liable
against all losses, expenses or claims arising in connection with the death of or injury to
any person employed by the successful bidder or his subcontractors for the purposes of
1.6 The successful bidder shall be responsible for any damage to the equipment during transit
due to improper or inadequate packing, handling, loading and unloading. The cases
containing easily damageable material shall be very carefully handled. Adequate
protection must be provided for outdoor storage at site in tropical humid climate, wherever
necessary. The successful bidder without any extra cost shall supply any material found
short inside intact store area.
1.7 If the successful bidder neglects to execute the work with due diligence and expedition or
refuses or neglect to comply with any reasonable orders within two days’ notice given in
writing to the successful bidder and if he fails to comply with the notice, then in such a
case PGVCL shall be at liberty to get the work or any part of it, executed through any
other agency/Bidder in the manner and on the terms it thinks proper. If the cost of
executing the work as aforesaid shall exceed the balance due to the Bidder, and the
Bidder fails to make good the deficiency, PGVCL may recover it from the Bidder in any
1.8 PGVCL shall have at all reasonable time access to the works being carried out by the
Bidder under this contract and stores where material issued by PGVCL is stored. All the
works shall be carried out by the Bidder to the satisfaction of PGVCL.
1.9 The quantities mentioned in the accompanying schedule B are only approximate same
may decrease or increase. The PGVCL reserves the right for revising or omitting any of
the quantities. The actual work executed by the successful bidder will be calculated at the
rate given in the contract schedule of the rates binding to the successful bidder.
1.10 No higher rate or revised rate will be application for the work, if work is held-up/closed due
to whatever so reasons.
Sign & Stamp of the Bidder P a g e 27 |
1.11 Price shall not be changed subject to any upward/downward revision on any account
whatsoever through the period of contract.
1.12 All other general terms and conditions as prevailing in the PGVCL shall be applicable to
this work contract.
1.13 The successful bidder has to co-ordinate and co-operate fully with Engineer In Charge and
for execution of the works.
1.14 Either successful bidder or successful bidder’s authorized person should contact our
Engineer In Charge as well as Division Office, Junagadh-1 daily for the availability of
materials required for this work, failing to which this work order shall be terminated without
giving any notice.
1.15 The successful bidder has to maintain site register covering all aspects of material
received/utilized/dismantled for day to day work and has to obtain signature of Engineer In
1.16 Incase of any dispute doubt, the decision of Executive Engineer Junagadh Division-1 shall
be unchallengeable and final, which will be binding to the contractor.
1.17 Security Deposit (without any Interest) will be refunded after completion of guaranteed
1.18 All legal complication of disputes is subject to ________ jurisdiction only.
1.19 A fresh and valid solvency certificate to the extent of 20% of the ordered value will have to
be produced by the contractor and party has to submit attested copy of solvency certificate
to the company before commencing of work.
1.20 The successful bidder will be solely responsible for any accident/damage either to
equipment or any human being during the time of execution of work.
1.21 Prior institution in writing for starting the job will be given by PGVCL for the work.
1.22 The successful bidder will have to make his own arrangement for required all kinds of tools,
tackles, required for the execution of work.
1.23 The cost of damages, if any will be recovered from the successful bidder’s bill. The
assessment of which will be done by Engineer In Charge in consultation with division office,
and his sole discretion and his decision shall be binding to the successful bidder and shall
be considered as final and unchallengeable.
1.24 The successful bidder will have to give indemnity bond to PGVCL against any possible
claim of compensation for damage to Contractor’s equipment or staff or any of third parties
during the execution of work as per attached format.
1.25 The successful bidder will have to complete entire work, as mentioned in Schedule-B of
contract awarded to him, as per directive and instruction of Engineer In Charge. If he fails
to do so entire work will be carried out at the risk and cost of Contractor.
1.26 The contractor must engage sufficient knowledgeable person round the clock, exclusively
for execution of work.
1.27 Specification in any items mentioned in tender are subject to change without any prior notice
and binding to the contractor.
1.28 The PGVCL shall deduct the Income-Tax and other taxes as per prevailing rules of all
relevant Govt. Authorities from the bill.
1.29 If the work is required to be carried out during fix outage then the successful bidder has to
deploy adequate man power, material, tools etc. well in advance and has to complete the
entire work during this specific outage period only, failing to which Company shall be at
liable to deduct the amount of revenue loss due to prolong outage.
1.30 The tender include all minor accessories and items of work which may not have been
specifically mentioned in the specification / Schedule etc. but are essential for completion
of work. The contractor will not be eligible for any extra payment in respect of such minor
accessories and item of work.
Sign & Stamp of the Bidder P a g e 28 |
1.31 The successful bidder shall not refuse to execute the work order at any time and it will be
his sole responsibility to execute and complete this work as per the instruction of Engineer
1.32 For shortage of any materials issued by the PGVCL for the work, recovery shall be made
from you, on the basis of prices of the materials (prevailing on the date of settlement of
materials account) plus 15% supervision charges.
1.33 The successful bidder has to carry out all the works in accordance with revised and latest
provision under I.E. Rule Act made there under and as per instruction of Engineer In
1.34 All the materials issued by PGVCL shall be transported to the work site on same day and
to be preserved in safe custody failing to which PGVCL shall initiate Police action. Similarly
as per instruction of Engineer In Charge, you have to credit the material at PGVCL store
without any loss of time failing to which PGVCL shall initiate Police action.
1.35 Any delay causing extension of outages shall be successful bidder’s responsibility and
appropriate amount (in term of Rupees) as decided by Executive Engineer, Junagadh
Division-1 shall be recovered from successful bidder’s bill as a penalty with applicable
1.36 No tools, tackles, manpower, crane facilities etc. will be provided by the PGVCL.
1.37 The contractor has to follow all labour laws, safety rules and regulations. The PGVCL does
not take any responsibility in case of accident or injury to the workers. The safety, security
of men, materials and equipment shall be sole responsibility of the contractor.
1.38 The compliances of all Central / State Govt. Rules, safety and insurance rules etc. and that
of local body is a must condition for the successful bidder.
1.39 The successful bidder shall specifically note that PGVCL will not pay any extra amount
towards any type of claim except for the description indicated in Schedule –A. The party
has to carry out all other additional required activities / work as directed by Engineer In
Charge which is not mentioned in Schedule but required to be completed as per the site
condition and for this work no extra payment shall be made by PGVCL.
1.40 The contractor should employ as a Supervisor with sufficient qualification and experience
who could supervise the execution of work throughout. He should always be present on
1.41 The contractor shall be responsible for breakages, losses and a theft of material during
transit or erection after the materials issued from the stores till the completion of work and
is taken over by the PGVCL.
1.42 As regard damages to the materials, equipment, successful bidder himself will be
responsible. If there is any compensation to be paid in respect of “WORKMAN”
Compensation Act or any other statutory provisions, the same will be paid by contractor
directly. If he thinks fit, he may take necessary insurance covering at his cost.
1.43 The successful bidder shall co-operate with the PGVCL for taking measurement etc. as
early as possible and he shall fulfil the entire requirement which is necessary to finalize
1.44 The competent authority can delete any item in schedule of the tender if he feels that the
rate quoted by the contractor for the item is abnormally high when compared to the
estimated rates.
1.45 The successful bidder shall not refuse to execute this work order at any time and it will be
his sole responsibility to execute and complete this work as per the instruction of Engineer
1.46 The erection work should be carried out according to the specification as per instructions
and programmed laid out by the Engineer in charge. Contractor has to ensure safe
shifting and erection of all accessories / equipment as per standard norms.
Sign & Stamp of the Bidder P a g e 29 |
1.47 The Bidder shall not display the photograph of the work and shall not take advantage
through publicity of the work without written permission of PGVCL.
1.48 The inspection as mentioned in above clause No. 6 of this section by PGVCL’s
representative shall not relieve the successful bidder from full responsibility of completing
the work confirming to the requirement of this contract.
1.49 Under the Contract, the Contractor shall be responsible for loss or damage to the line and
Electrical Equipment until the successful completion as defined elsewhere in the Bid
1.50 All demurrage, wharf age and other expenses incurred due to delayed clearance of the
material or any other reason shall be to the account of the Contractor.
1.51 The law applicable to the contract shall be the laws in force in India. The courts of Rajkot
shall have exclusive jurisdiction in all matters arising under the contract.
1.52 If the work is not started within the limit of one year in the work order given to you, the
amount of SD filled by you will be confiscated and credited to the account of PGVCL, which
will not be refunded.
2 PRICE EVALUATION:
No price preference shall be given on any account. All tenders must be submitted firm
price basis (Inclusive of all Taxes) and lowest evaluated bid in the interest of the PGVCL,
for the complete works covered under these specifications and documents.If more than
one party is to be considered for placement of order, they will have to match their end cost
with end cost of L-1 technically acceptable bidder. PGVCL (tender Inviting Authority) may
go to the L-2, L-3 and so on depending upon the requirement. If PGVCL (tender Inviting
Authority) feels that there is lack of serious competition or any other reasons, PGVCL
(tender Inviting Authority) may negotiate with the L-1 party. PGVCL’s (tender Inviting
Authority) decision shall be final and binding on all the parties.
3. QUANTITY DISTRIBUTION
3.1 For Erection & Maintenance work of HT/LT/TC:
The Contractors whether non-experienced / New or experienced / Regular who have
confirmed /fulfilled pre eligibility criteria , as mentioned in Section 1 sr No 2 , will only be
considered for price evaluation. PGVCL will not consider the, price bid of any contractor
who does not confirm / fulfil the eligibility criteria as mentioned in Section 1 sr No
3.11 While placing the order, the quantity distribution to each new contractors / new firms shall
be restricted up to 30 % of the tender amount/Qty. for all such new bidders provided the
price of New contractor is lower than the regular/experienced contractor. New contractor
/ new firm will be considered as a regular contractor only after full filing experience criteria
as mentioned in Bidders qualifying criteria as per point no. 2 in Section I.
3.12 The new contractor will be asked to match the L-1 prices of the new contractor only and
the Regular contractor has to match the L-1 price of the Regular/experienced contractor
only.But if there are no Regular contractor OR if the rate of Regular contractor is very high,
the above condition no. 2.11 shall be suitably relaxed by PGVCL. L-1 regular contractor
however will get heavy weight age in order placement.
3.2 For laying of Under Ground Cable work:
3.21 While placing the order, the quantity distribution to each new contractors / new firms
Section 1 sr No 2, shall be restricted up to 10 % of the tender amount/Qty. for all such new
bidders provided the price of New contractor is lower than the regular/experienced
contractor. New contractor / new firm will be considered as a regular contractor only after
full filing experience criteria as mentioned in Bidders qualifying criteria as per point no.
3.22 The new contractor will be asked to match the L-1 prices of the new contractor only and
the Regular contractor has to match the L-1 price of the Regular/experienced contractor
only.But if there are no Regular contractor OR if the rate of Regular contractor is very high,
the above condition no. 2.21 shall be suitably relaxed by PGVCL. L-1 regular contractor
Sign & Stamp of the Bidder P a g e 30 |
however will get heavy weight age in order placement. The Contractors who have
confirmed /fulfilled pre eligibility criteria will only be considered for price evaluation. PGVCL
will not consider the price bid of any contractor who does not confirm / fulfil the eligibility
criteria. L-1 regular contractor however will get heavy weight age in order placement.
4 IDENTIFICATION OF SITE:
Details of each location shall be made available through Executive Engineer of each
concerned Divisions under above locations. The planning for each location has to be
prepared in consultation of the Deputy Engineer of the concerned Sub Division under whose
control the work is allocated. The work must be carried out under Supervision of concerned
S/dn Head or Authorized Staff appointed by SDO.
5.ALLOTMENT OF MATERIAL AND ITS STORAGE
Required material for the work as per Schedule shall be alloted from any store Centres of
PGVCL jurisdiction and successful bidder has to take delivery from these stores at his own
6. Contractor will be issued only 3 (Three) Sub work orders at a time. He will be issued
Fourth Sub Work Order only after the submission of Inventory sheet with sketch and
material account statement for any of the three previously issued Sub Work Orders.
7. . TAKING DELIVERY AND INSURANCE:
a. The contractor has to keep all materials in safe custody and transport to the respective sites
and will be fully responsible for any damage to or loss of all materials at any stage during
transportation or erection till taking over by PGVCL
7.2 The Contractor has to open site store/s (Maximum Two Nos.) and ensure for safe custody of
all the stored materials at his own cost. Material which is to be allotted by PGVCL is to be
carted, loaded and unloaded at Bidder’s cost and risk from PGVCL’s respective Stores.
PGVCL must have access to such Store/s at any time of Day thought the contractual period
and Contractor will cooperate for verification of such store/s and Inventory accounting. Failing
to which actions may be initiated after issuance of required Notice to the Contractor. Store
address/s is to be mentioned in the “General information about the Bidder” under Section I of
7.3 The Contractor shall have total responsibility for the entire materials stored, loose, semi
assembled and/or erected by him at site in his custody. The Contractor shall make suitable
security arrangements at his own cost to ensure the protection of all materials, equipment
and works from theft, fire pilferage and any other damages and loss. It shall be the
responsibility of the contractor to arrange for security till the works are finally taken over by the
7.4 STORAGE-CUM-INSURANCE: -
The contractor shall take suitable storage-cum-erection insurance cover at his cost to the
extent of 100 % cost of materials, which are required to complete the work. Contractor shall
have to take comprehensive insurance policy equivalent to the Order Value against any loss,
damage, theft, pilferage, fire etc. for the complete period of storage, erection and
commissioning up to the time of taking over by PGVCL. The Contractor shall deal directly and
pursue the claim with the Insurance Company and shall be responsible in regard to
maintenance of all insurance coverage as well as for settlement of claim. The proof of
insurance policy taken by the successful Contractor shall be furnished to Engineer-In-Charge.
In absence of the above insurance policy, R.A. Bill payment will be withheld.In the event of
any damage, theft, loss, pilferage, fire etc., Contractor will be responsible to lodge, pursue and
settle all the claims with the Insurance Company for all items, materials and the PGVCL shall
be kept informed about it. Contractor shall replace the lost / damaged materials / items
promptly irrespective of the settlement of the claims by underwriter and ensure that the work
progress is as per agreed schedule. The loss, if any, such replacement will have to be borne
by the Contractor and PGVCL will not entertain any claim / representation in this regard.
However, it will be contractor's responsibility to insure the entire project is taken over by the
Sign & Stamp of the Bidder P a g e 31 |
8.Account of material issued
8.1 The successful bidder shall have to maintain accurate day to day item wise account of use
of issued materials which shall be got checked from time to time by the Engineer In Charge
of the Company. The contractor will be responsible for custody and preserving the issued
materials till the work is hand over by the contractor after completion.
8.2 The successful bidder has to maintain site register, covering all the daily details of material
receipt and utilization, progress of work etc. This register shall be checked and signed by
Engineer In Charge/Deputy /Executive Engineer, ___________ Sdn/Division during the
site visit as per requirement and exigency of work if deem fit.
8.3 After completion of the work against each Sub Work Order, all the surplus materials issued
by the PGVCL shall be returned by you to the respective divisional /Regional stores only
at contractor’s cost. Do not credit this material in S/Dn store.
9. Work Completion Period:
9.1 In the event of placement of order, successful bidder shall have to complete the
ordered work within ____ Days from the Date of issue of Work Order.
9.2Time limit of Each sub work order should not be maximum up to 60 Days.
10.3 WORKING DAYS: -
In case, it is not possible for the successful bidder to continue the work either due to heavy
rains or other reasonable causes, such facts should be immediately brought to notice of
the Engineer In Charge. If the reasons for stopping the work are genuine the Engineer In
Charge may ask the successful bidder to start the work again as per condition. The period
of such stoppage will not be considered as a part of working days moreover the successful
bidder cannot claim
9.4 PROGRESS OF WORK
You will have to submit fortnightly progress report regularly in duplicate to Engineer In
Charge and Executive Engineer Junagadh. If found that the work is unsatisfactory or not
progressing as per schedule, then any action would be taken by the PGVCL as may
deemed fit to see that work is completed at the risk and cost of contractor. The completion
time allowed for each Sub work Order shall be strictly observed.
11. Time limit extension will be given, as per Clause No. 12 of this section, if material
is not supplied in time and in any case of objection not cleared in time. But if
materials given in time and there is no any objection, then no time limit extension
will be granted and penalty with applicable GST will be imposed as per rules.
12. CHANGE OF QUANTITY
b. During the execution of the Contract, the PGVCL reserves the right to increase or
decrease the quantities of items under the Contract but without any change in unit price
or other terms & conditions. Such variations unless otherwise specified in the
accompanying GCC and/or Technical Specifications, shall not be subjected to any
limitation for the individual items but the total variations in all such items under the Contract
shall be limited to the extent of 30% (Thirty Percent) of the contract price by way of suitable
amendment to the contract.
11.2 The Contract price shall accordingly be adjusted based on the unit rates available in the
Contract for the change in quantities as above. The base unit rates, as identified in the
Contract shall however remain constant during the currency of the Contract, In case the
unit rates are not available for the change in quantity, the same shall be subjected to
mutual agreement.
11.3As this is an EPC contract, engineering work will be done by the Contractor. Responsibility
of material will be that of the contractor.
13. Penalty with GST:
12.1 Penalty with GST is levied on the time limit of Sub Work Orders. If the work is not
completed within the scheduled period as prescribed in Sub Work Order, penalty + GST
at the rate of 0.5 % per week or part thereof on delayed portion subject to maximum up to
Sign & Stamp of the Bidder P a g e 32 |
10 % of the sub work order Value with GST as per applicable rate. This will be deducted
from the bills payable either against this contract or any bank guarantee or any other
amount payable under any other contract with the PGVCL. For Penalty calculations or
Time limit Extension, following points are to be observed.
12.2 Start Date of Sub Work Order for Penalty Calculation will be the Day/Date on which the
first material is issued against the Sub Work Order.
12.3 If material is not available in respective stores, then “NO STOCK” stamping by Store In-
charge/Store Keeper must be taken against the particular item by the contractor.
12.4 In Case of non-availability of Material, contractor must visit the respective store every
fortnight and no stock material details are to be submitted to respective Executive
Engineer and concerned SDO.
12.5 TLE of Sub work order can be granted on the basis of above such documents produced
12.6 Time limit Extension must be given as per F & A Letter No. PGVCL/F&A/5083/14-06-2017
and PGVCL/F&A/745/11-06-2018.
12.7 At the time of submission of Bill against SWO, all such Documents are to be submitted by
contractor for waiver of Penalty if applicable.
12.8 Time limit of Annual Work Order should be maximum up to 365 Days.
14. During the execution of Work, if Contractor/Labour are found violating OR Braking the
Safety rules and Regulations, then Engineer-in-Charge will serve the warning Notice on
first Instance. On second Instance the amount of Fine will be Rs. 500.00 or 0.1 % of
amount of SWO (Whichever is high). Even If after above two instances, still Contractor
found breaking of Safety Rules and Regulations then Procedures for Stop dealing must
be initiated against him as per rules and regulations.
15. Payment terms shall be as follows:
14.1 Payment will be made against Invoice value and shall be paid against actual execution. The
bills should be submitted in Duplicate to respective Superintending/Executive Engineer,
Circle/Division Office along with following documents:
• Measurement Report of each site by PGVCL authorized inspection Officer (not below the rank
of Deputy Engineer)
• Material Accounting for work duly certified by Engineer-in-charge
• Work Completion Certificate duly signed by Contractor for which the Bill is submitted.
• Copy of Insurance Policy against the Material equivalent to the Order Value as per
Tender Condition No. No.7 under this Section.
• Contractor must submit the above documents within Fifteen (15) Days from the actual
date of completion of work to respective S/dn Office.
• DOP is to be followed for Payments against the Work Orders.
14.2 R.A. Bill shall be paid by the PGVCL, if it satisfies with the output of works otherwise only
final bill shall be paid.
14.3 The time limit for the work may be reduced and contractor should make all his efforts to
complete the work within stipulated time limit as may be given by the Engineer In Charge
depending upon emergency of work.
15. FORCE MAJEURE:
Force Majeure means any circumstances beyond the control of the parties including:
15.1War and other hostilities, (whether war be declared or not), invasion, act of foreign enemies,
mobilization, requisition or embargo;
15.2Rebellion, revolution, insurrection, military or usurped power and civil war;
Sign & Stamp of the Bidder P a g e 33 |
15.3Ionizing radiation or contamination by radioactivity from any nuclear fuel or from any nuclear
waste from the combustion of nuclear fuel, radioactive toxic explosive, or other hazardous
properties of any explosive nuclear assembly or nuclear components thereof;
15.4Riot, commotion or disorder, except where solely restricted to employees of the Contractor.
15.5Neither party shall be considered to be in default or in breach of his obligations under the
Contract to the extent is that performance of such obligations prevented by any
circumstances of Force Majeure that arise after the date of the Notification of Award.
15.6If either party considers that any circumstances of Force Majeure have occurred which may
affect performance of his obligations he shall promptly notify the other party.
15.7Upon the occurrence of any circumstances of Force Majeure, the Contractor shall
endeavour to continue to perform his obligations under the Contract so far as reasonably
practicable. The Contractor shall notify the Engineer-in-Charge of the steps he proposes
to take including any reasonable alternative means for performance, which are not
prevented by Force Majeure. The Contractor shall not take any such steps unless directed
so to do by the Engineer-in-Charge.
15.8If circumstances of Force Majeure have occurred and shall continue for a period of
days, notwithstanding, the Contractor may by reason thereof, having been granted an
extension of Time for Completion of the Works, either party shall be entitled to serve upon
the other, 30 days’ notice to terminate the Contract. If at the expiry of the period of 30 days
Force Majeure shall continue, the Contract shall terminate.
16 TESTING & COMMISSIONING:
The successful bidder will ensure that completion of execution of work i.e. all works connected
with line having been completed correctly as per Indian Electricity Rules & procedure. Any
extra cost involved due to incompleteness of work or bad workmanship found out
subsequently shall be set right with and by you at your own cost.
17 HANDING OVER OF ASSET
17.1After successful completion of the lines and Transformers or any other electrical equipment
the entire newly created network is to be handed over to the concern Deputy Engineer of
PGVCL. The handing over note covering the details of all the materials used and total
work executed must be signed jointly by the bidder and PGVCL Engineer. Copy of handing
over note must be attached along with bill.
17.2The contractor shall arrange to hand over the complete work immediately on completion of
If some material/Item is not installed/fixed for allotted work and as per SOR by contractor
due to non-availability of particular item/material for long period of time and TLE cannot be
approved for that work beyond certain time limit Or such item if not required to be installed
at particular location, then Recovery is to be made as mentioned below for not carrying out
that work from SWO issued
All work other than above must be completed by contractor and No any other Recovery
should be made other than above Work.
19. CONTRACT QUALITY ASSURANCE:
19.1 The Bidder shall include in his proposal the Quality Assurance Program containing the
overall quality management and procedures which he proposes to follow in the
performance of the Works during various phases as detailed in relevant clause of the
General Technical Conditions.
19.2 At the time of Award of Contract, the detailed Quality Assurance Program to be followed
for the execution of the Contract. PGVCL reserve the right to inspect the work at any stage
of contract i.e. during the execution and after the execution of work.
19.3 The Bidder shall clearly specify the list of sub-vendors from whom the bought out items (if
any) are being supplied. Such details shall be accompanied by their list of previous
supplies made performance reports etc. However, in case of orders are placed, specific
approval shall be obtained from the PGVCL for the vendor supplied materials. The quality
assurance program shall be furnished for each material separately for approval.
Sign & Stamp of the Bidder P a g e 34 |
20. TERMINATION OF CONTRACT ON PGVCL’S INITIATIVE
20.1 In case of any type of misappropriations, cheating or intention of cheating, frauds,
irregularities, malpractice, etc. the Managing Director PGVCL reserves the right to cancel
the order without giving reasons thereof and forfeit the security deposit.
20.2 The PGVCL reserves the right to terminate the Contract either in part or in full due to reasons
other than those mentioned under clause entitled ‘Contractor’s Default’. The PGVCL shall in
such an event give fifteen (15) days’ notice in writing to the Contractor of his decision to do so.
20.3 The Contractor upon receipt of such notice, as per point no.19.2 above, shall discontinue
the work on the date and to the extent specified in the notice, make all reasonable efforts
to obtain cancellation of all orders and Contracts to the extent they are related to the work
terminated and terms satisfactory to the PGVCL, stop all further sub-contracting or
purchasing activity related to the work terminated, and assist PGVCL in maintenance,
protection, and disposition of the works acquired under the Contract by the PGVCL. In the
event of such a termination the Contractor shall be paid compensation, equitable and
reasonable, dictated by the circumstances prevalent at the time of termination.
20.4 If the Contractor is an individual or a proprietary concern and the individual or the proprietor
dies and if the Contractor is a partnership concern and one of the partners dies then unless
the PGVCL is satisfied that the legal representatives of the individual Contractor or of the
proprietor of the propriety concern and in the case of partnership, the surviving partners,
are capable of carrying out and completing the Contract the PGVCL shall be entitled to
cancel the Contract as to its in completed part without being in any way liable to payment
of any compensation to the estate of deceased Contractor and/or to the surviving partners
of the Contractor’s firm on account of the cancellation of the Contract. The decision of
the PGVCL that the legal representatives of the deceased Contractor or surviving partners
of the Contractor’s firm cannot carry out and complete the Contract shall be final and
binding on the parties. In the event of such cancellation the PGVCL shall not hold the
estate of the deceased Contractor and/or the surviving partners of the estate of the
deceased Contractor and/or the surviving partners of the Contractor’s firm liable to
damages for not completing the Contract.
21. ARBITRATION:
Any question, dispute or difference whatsoever arises between PGVCL and Bidder, in
connection with this agreement except as to matters, the decision for which has been
specifically provided, either party may forthwith give to the other notice in writing of
existence of such questions, dispute, difference and the same shall be referred to the sole
arbitration of a person nominated by Managing Director, PGVCL. This reference shall be
governed by Indian Arbitration Act prevailing at the time of dispute and the rules made
there under. The award in such arbitration shall be final and binding on all the parties.
Work under the agreement shall continue during the arbitration proceedings unless the
PGVCL or the Arbitrator directs otherwise.
The technical information, drawings, specifications and other related documents forming part of
the enquiry or Contract are property of PGVCL and shall not be used for any other
purpose, except for the execution of the contract. All rights related to the technical
specifications, drawings and records are reserved by PGVCL only and no part or partial
should be reproduced, copied or alter without prior permission to PGVCL in writing. In the
event of the breach of this provision, PGVCL can claim the damages caused by such
Sign & Stamp of the Bidder P a g e 35 |
23.Stop Dealing:
Bidder/Contractor shall be put under Stop Deal due to following reasons.
23.1 Has submitted fake, false or forged documents/certificates
23.2Has revised/withdrawn price bid after opening of Techno: commercial bid, until and unless
it is sought for
23.3Has refused to accept Letter of Acceptance/Purchase Order/Work Order after the same is
issued by the Company within the validity period and as per agreed terms and conditions
23.4Has committed breach of contract or has failed to perform a contract or has abandoned the
23.5Has failed to provide suitable expertise for the work as per prescheduled program
23.6Has failed to submit all the necessary Test reports/documents within time schedule / as per
Company's time limit, as mentioned in the LOA, if the Letter of Acceptance (LOA) is placed
subject to submission of type reports / documents to the firm.
23.7Has indulged in construction and erection of defective works.
23.8Has substituted materials In lieu of materials supplied by the Company or has not returned
or has short returned or has unauthorised disposed of materials/ documents/ drawings/
tools or plants or equipment supplied by the Company
23.9Has involved in malpractices such as bribery, corruption, fraud, canvassing and pilferage
23.10Has unauthorised obtained official company information or copies of documents, in relation
to the Tender/Contract
23.11Has failed to follow the stipulated mode of communication, if specified by the tendering
authority/ purchaser.
23.12Any other ground for which in the opinion of the Company makes it undesirable to deal
with the Firm, and
23.13In case the State Government directs the Company to place a firm in stop dealing/ banned
for business dealing/ blacklisting
23.14The firm, stop deal and/or banned for business dealing and/ or blacklist by GUVNL or any
subsidiary Companies of GUVNL shall be considered as a stop deal and/ or banned for
business dealing and/ or blacklisting for all Companies.
24. Effect of putting a proprietor/firm for Stop dealing/Banned for business dealing are as
24.1The proprietor/all the partners/directors of the stop deal/ banned for business dealing/
blacklisting firm shall also be considered for stop deal/ banned for business dealing.
24.2Once the name of the firm and/ or proprietor/ partner/ director of the firm appears in the list
of Stop dealing / Banned for business dealing in any Company of GUVNL and its
Subsidiary Companies,
(i) No enquiry shall be issued to a firm.
(ii) No bids / tender shall be considered for evaluation and the bid submitted by the Firm shall
24.3Action to be taken, when a Firm and/or proprietor/ partner/ director of the firm is put on Stop
dealing/ Banned for business dealing by GUVNL or any of its subsidiary Companies,
during tender process: -
(i) Before opening Technical bids, the bid submitted by the Firm will be treated as
“Disqualified Bid” and automatically stand as “Rejected Bid” at the time of scrutiny of
Preliminary / Technical Bid.
(ii) After opening Technical bid but before opening the price bid, the price bid of the Firm
should not be opened and the bid submitted by the Firm will be treated as “Disqualified
Bid” and automatically stand as “Rejected Bid” at the time of scrutiny of Technical Bid.
(iii) After opening of price bid, the offer of the Firm should be ignored and will not be further
evaluated. The Firm will not be considered for issue of order even if its price is the lowest.
In this situation, the next lowest bidder shall be considered as L1.
(iv) The BG/EMD submitted by the Firm with tender should be returned after obtaining
confirmation from GUVNL and its other subsidiary Companies that there are no
outstanding dues recoverable from the firm.
Sign & Stamp of the Bidder P a g e 36 |
24.4If a Firm is put on Stop dealing / Banned for business dealing in one Company and is already
executing work and/ or Letter of Acceptance/ purchase order awarded to them by another
Company, then the firm should be allowed to complete such awarded work / supply.
24.5The amount of EMD/SD/ any payment against supply withheld at the instance of GUVNL or
any of its subsidiary Companies shall be appropriated against the dues recoverable from
the firm by GUVNL or any of its subsidiary Companies. EMD/ SD/ PG in the form of bank
Guarantee shall be encashed and appropriated.
24.6The Stop dealing/ Banned for business dealing shall be Firm- specific and when a Firm is
put on Stop dealing/ Banned for business dealing, all the manufacturing works of the Firm
shall be on Stop dealing/ Banned for business dealing for GUVNL and its Subsidiary
Companies & for all Services of the Firm.
24.7If the Firm placed on Stop Dealing/ Banned for business dealing is a Proprietary Concern,
then all the Concerns of the same Proprietor shall also be considered to be on Stop
Dealing/ Banned for business dealing.
24.8The Board of Directors of the concerned Company may however, if he considers it to be in
the interest of the Company, remove the ban in respect of any specific Service from any
Contractor for that Company only.
25.Every bidder should, at the time of submission of bid, give a declaration as per Annexure VI
attached with this Tender, that bidder and/or proprietor/ partner/ director of the firm has
not been placed on Stop dealing / Banned for business dealing / blacklisting by GUVNL
and it’s any Subsidiary Companies.
26. Sealing of LT Stud of Transformers use of 2 inch Diameter & 6 inch length PVC Pipe around the
bushing with wiring connection to the bushing with M-seal. (3 Stud Per Transformer
Sign & Stamp of the Bidder P a g e 37 |
Annexures/BG/Agreement/Indemnity Bond
TIME SCHEDULE FOR COMPLETING THE WORK
(To be completely filled by the Bidder)
Name of the Bidder
Sr. No. Item Time required for work Mentioned in Tender
1 Labour work for Laying of
Underground cable and E/o HT LT
Line and Transformers and
Sign & Stamp of the Bidder P a g e 38 |
Details of work experience in last three years
(To be completely filled by the Bidder)
Company with full Ref. & date Work
Sr. Details of order
address, phone, fax Work Description of the Order
and name of contact order Value
• Copies of MAJOR Work orders along with Work completion certificates should be attached with this
• If necessary, separate sheet may be used to submit the information
Sign & Stamp of the Bidder P a g e 39 |
Details of Pending Orders as on Bidding Date
(To be completely filled by the Bidder)
Reason for non-
Company with full Ref. & date Work
Sr. completion with
address, phone, fax Work Description of the Order
No. Certification of Order
and name of order Value
issuing Authority
• Copies of Resumes and appropriate certifications should be attached with this information.
• If necessary, separate sheet may be used to submit the information.
Sign & Stamp of the Bidder P a g e 40 |
(Strike off whichever is not applicable)
This is to declare that Mr. /Ms. __________________________________, employee of PGVCL at
_______________________ (designation & name).
This is to declare that none of the Proprietors/ Partners/ Directors are having any relatives employed or
working with Paschim Gujarat VijCo.Ltd.at any of its offices or its parent Department i.e. Energy &
Petrochemicals Dept., Govt. of Gujarat.
Date: Sign. & Stamp of the Bidder
Sign & Stamp of the Bidder P a g e 41 |
DEVIATION SHEET
Any deviations offered from the terms and conditions of the Offer should be clearly specified below in this
sheet. If there are no deviations offered, it should be clearly mentioned on this page.
Deviation offered to Chapter
No, Clause No. of the tender Deviation offered
Sign & Stamp of the Bidder P a g e 42 |
List of Onsite Testing Facility (For the work of Laying of HT/LT Underground Cable)
(To be completely filled by the Bidder)
Sr. Name of equipment Date of purchase Date of calibration Utility
Sign & Stamp of the Bidder P a g e 43 |
Sub: -UNDERTAKING IN REGARD TO STOP DEAL/BLACK LIST THEREOF
All bidders will have to furnish the following undertaking duly filled in signed and stamped for each quoted
item of the tender along with the Technical Bid.
M/s_________________________________________________ is not stop deal/black listed by GUVNL
and or any subsidiary companies viz. PGVCL/UGVCL/DGVCL/PGVCL/GSECL/GETCO for the tendered item.
Seal & Signature of the Tenderer/Firm
Sign & Stamp of the Bidder P a g e 44 |
LIST OF TYPE TESTS REPORTS SUBMITTED WITH THE TECHNICAL BID
(For the work of Laying of HT/LT Underground Cable)
(Not Older than 7 Years)
Type Test Tests Carried out Rating & Type / Results
Sr. No Report No. & at (Name of Designation of Item Of the
Date Laboratory) / Equipment Tests.
Sign & Stamp of the Bidder P a g e 45 |
List of Performance Certificate:
Name of the Authority by whom
Sr. No. Reference No. & Date Details of items
certificate is issued
Sign & Stamp of the Bidder P a g e 46 |
Details of Fatal/Non-Fatal Accidents Occurred To the Contractor Labours during Last Five Years
Sr. Type Of Accident Nos. of Affected Brief Reason for the
No. (Electrical/Mechanical) Labour/s Accident
Sign & Stamp of the Bidder P a g e 47 |
Sub: -UNDERTAKING IN REGARD TO ANY PENDING CRIMINAL CASE FOR FRAUD OR MISHANDALING OF
M/s_____________________________________________ hereby declare we will provide ______ nos
of labours to carry out this tenders scope of work. We are having Labour Insurance Policy
No.____________________ for ________ nos of our labours. We declare that, as mention below table,
we are having following safety gadgets of our own and they all are in good condition.
List of Safety Gadget Unit owned by
2 Earthing Rod No
4 Safety Belt No
5 Hand Gloves for LT Pair
6 Hand Gloves for HT Pair
7 Other safety items
Sign & Stamp of the Bidder P a g e 48 |
On Firm’s Letter Head
CERTIFICATE – “A”
I/We__________________________________________ authorized signatory of
M/s._________________________________________ is not related with other firms who have
submitted tenders for the same items under this inquiry / Tender.
• Seal of the Firm Signature of the Tenderer
• Place: With Designation
E.M.D. BANK GUARANTEE FORMAT
Sign & Stamp of the Bidder P a g e 49 |
FOR TENDER NO.: ……………………………..…….
(Bank Guarantee on Non-Judicial Stamp Paper of Rs.100/-)
WHEREAS M/s. ____________________________________ (Name & Address of the Firm) having their
registered office at _____________________________________ (Address of the firms Registered office)
(hereinafter called the ‘Tenderer’) wish to participate in the tender No.
Erection/Supply & Erection Work) (Name of the material/equipment/Work) for
_________________________ Paschim Gujarat Vij Company Ltd. and WHEREAS a Bank Guarantee for
(hereinafter called the “Beneficiary”) Rs._____________ (Amount of EMD) valid till _________ (Mention here
date of validity of this Guarantee which will be 5 (FIVE) months beyond initial validity of Tender’s offer) which
is required to be submitted by the tenderer along with the tender.
We, __________________ (Name of the Bank and address of the Branch giving the Bank Guarantee) having
our registered office at ______________________ (Address of Bank’s registered office) hereby give this Bank
Guarantee No.________________ dated _________ and hereby agree unequivocally and Unconditionally to
pay immediately on demand in writing from the Paschim Gujarat Vij Company Ltd. or any officer authorized
by it in this behalf any amount not exceeding Rs. ______________ (Amount of E.M.D.), (Rupees
_________________________________ (In words) to the said Paschim Gujarat Vij Company Ltd. on behalf of
We ___________________________ (Name of the Bank) also agree that withdrawal of the tender or part
thereof by the Tenderer within its validity or Non submission of Security Deposit by the Tenderer within one
month from the date tender or a part thereof has been accepted by the Paschim Gujarat Vij Company Ltd.
would constitute a default on the part of the Tenderer and that this Bank Guarantee is liable to be invoked
and encashed within its validity by the Beneficiary in case of any occurrence of a default on the part of the
Tenderer and that the encashed amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive of ____________________
(Mention here the date of validity of Bank) and shall not be terminable by notice or by Guarantor change in
the constitution of the Bank or the firm of Tenderer Or by any reason whatsoever and our liability hereunder
shall not be impaired or discharged by any extension of time or variations or alternations made, given,
conceded with or without our knowledge or consent by or between the Tenderer and the PGVCL.
“Notwithstanding anything contrary contained in any law for the time being in force or banking practice, this
Guarantee shall not be assignable, transferable by the beneficiary (i.e. GUVNL or Subsidiaries). Notice or
invocation by any person such as assignee, transferee or agent of beneficiary shall not be entertained by the
Bank. Any invocation of the Guarantee can be made only by the beneficiary directly.”
NOTWITHSTANDING anything contained hereinbefore, our liability under this guarantee is restricted to Rs.
Guarantee shall remain in force till _________ (Date of validity of the Guarantee). Unless demands or claims
under this Bank Guarantee are made to us in writing on or before_______ (Date of Validity of the Guarantee),
all rights of Beneficiary under this Bank Guarantee shall be forfeited and we shall be released and discharged
from all liabilities there under:
Please Mention here Complete Postal Address
Signature of the Bank’s Authorized Signatory with
of the Bank with Branch Code, Telephone and
Official Round Seal.
NAME OF DESIGNATED BANKS:
• All Nationalized Banks including Public Sector Banks IDBI Bank Ltd.
• Private Sector Banks authorized by RBI to undertake the state Government business, which are (i) Axis
Bank (ii) ICICI Bank (iii) HDFC Bank Co-operative Banks and Commercial Banks and recognized/notified by
Government of Gujarat (GoG) Note: The Banks shall be the Banks recognized / notified by the Finance
Department, Government of Gujarat (GoG) from time to time.
FORM OF BANKER’S UNDERTAKING (For SD)
Sign & Stamp of the Bidder P a g e 50 |
(Bank Guarantee on Non-Judicial Stamp Paper of .100/-)
We, Bank of ___________________________________ hereby agree unequivocally and unconditionally to
pay immediately on demand in writing from the Paschim Gujarat Vij Company Ltd. or any Officer authorized
by it in this behalf any amount up to and not exceeding _______ (in words) Rupees ___________________ to
the said Paschim Gujarat Vij Company Ltd. on behalf of M/s.
_________________________________________________who have entered into a contract for the
supply/works specified below
This agreement shall be valid and binding on this Bank up to and inclusive of ______________ and shall not
be terminable by notice or by change in the constitution of the Bank or the firm of Contractors / Suppliers or
by any other reasons whatsoever and our liability hereunder shall not be impaired or discharged by any
extension of time or variations or alterations made, given conceded or agreed, with or without our knowledge
or consent, by or between parties to the said within written contract.
“Notwithstanding anything contrary contained in any law for the time being in force or banking practice, this
Guarantee shall not be assignable, transferable by the beneficiary (i.e. GUVNL or Subsidiaries). Notice or
invocation by any person such as assignee, transferee or agent of beneficiary shall not be entertained by the
Bank. Any invocation of the Guarantee can be made only by the beneficiary directly.”
“NOTWITHSTANDING” anything contained herein before, our liability under this guarantee is restricted to
Rs.___________ (Rupees ___________________________ only). Our guarantee shall remain in force until
____________________ (Date of validity of the Guarantee). Unless demands or claims under this Bank
Guarantee are made to us in writing on or before_______ (Date of validity of the Guarantee), all rights of
Beneficiary under this Bank Guarantee shall be forfeited and we shall be released and discharged from all
liabilities there under:
Please Mention here Complete Postal Address Signature of the
of the Bank with Branch Code, Telephone and Bank’s Authorized Signatory with Official
Fax Nos. Round Seal.
NAME OF DESIGNATED BANKS:
• All Nationalized Banks including Public Sector Banks IDBI Bank Ltd.
• Private Sector Banks authorized by RBI to undertake the state Government business, which are (i) Axis
Bank (ii) ICICI Bank (iii) HDFC Bank
• Co-operative Banks and Commercial Banks and recognized/notified by Government of Gujarat (GoG)
Note: The Banks shall be the Banks recognized / notified by the Finance Department, Government of
Gujarat (GoG) from time to time.
Sign & Stamp of the Bidder P a g e 51 |
This agreement is made at Junagadh the ___ day of ______month _______Year between the Paschim Gujarat
Vij Company Ltd. & __________________________ (hereinafter referred to as “the Contractor “which
expression shall unless excluded by or repugnant to the context included its successors or permit assigns) of
the one part and the Paschim Gujarat Vij Company Ltd. Having its Regd. and Corporate Office at Laxminagar,
Off Nanamava Road, Rajkot, 360004 (hereinafter called “The Company” which expression shall unless
excluded by or repugnant of the context include its successors of assigns) of the other part.
Whereas the aforesaid Company has accepted the tender of the aforesaid contractor for the work of
____________________, Dated ___________, hereinafter called “The works and more particularly desorbed
enumerated or referred to in the specifications, terms and
other letters and schedule of price which for the purpose of identification have been signed by The Executive
Engineer Junagadh Division-1, PGVCL on behalf of the Company, a list where of is made out in the schedule
here under written and all of which said documents are deemed to form part of this contract and include in
the expression “The works “wherever herein used, upon the terms and subject to the conditions hereinafter
And whereas the Company has accepted the tender of the contractors for the Maintenance & Erection of HT
/ LT Line & T/C and Underground cable up on the terms and subject to the conditions herein mentioned.
1.) The contractors shall do and perform all works and things in this contract mentioned and described
or which are implied therein of therefore respectively or are reasonable necessary for the completion
of the works as mentioned and at the time in the manner and subject to the terms conditions and
stipulation contained in this contract and in consideration of the due provision, executions,
construction and completion of the works agreed to by the contractors as aforesaid the company
both hereby covenant with the contractor to pay all the claims of money as and when they become
due and payable to the contractor under the provisions of the contract such payment to be made at
such times in such manner as is provided by the contract.
2.) The conditions and covenant stipulation here in before in this contract are subject to and without
prejudice to the right of the company to enforce for delay and or any other rights whatever including
the right to reject and cancel on default or breach by the contract of the conditions and the covenant
as stipulated in the general conditions specifications form Or tender schedule drawing etc. attached
with the Company LOA No. ____________________________, Dated ____________.
3.) The Contractor will strictly follow the safety Rules and Regulations during the execution of aforesaid
work. The Contractor will also provide all required Safety Gadgets to his Supervisors and labours to
execute the work mentioned in Tender. On violating or breaking the Safety Rules and Regulations,
and if Supervisors/Labours are found without Safety Gadgets, “The Company” reserves the right to
take actions as per the terms and conditions mentioned in Tender without any prejudice.
4.) The Company reserves the right to terminate the Contract either in part or in full due to reasons other
than those mentioned under clause entitled ‘Contractor’s Default’. The PGVCL shall in such an event
give fifteen (15) days’ notice in writing to the Contractor of his decision to do so.
5.) The Contractor upon receipt of such notice shall discontinue the work on the date and to the extent
specified in the notice, make all reasonable efforts to obtain cancellation of all orders and Contracts
to the extent they are related to the work terminated and terms satisfactory to the Company, stop all
further sub-contracting or purchasing activity related to the work terminated, and assist “The
Company” in maintenance, protection, and disposition of the works acquired under the Contract by
the Company. In the event of such a termination the Contractor shall be paid compensation, equitable
and reasonable, dictated by the circumstances prevalent at the time of termination.
6.) If the Contractor is an individual or a proprietary concern and the individual or the proprietor dies and
if the Contractor is a partnership concern and one of the partners dies then unless “the Company” is
satisfied that the legal representatives of the individual Contractor or of the proprietor of the
propriety concern and in the case of partnership, the surviving partners, are capable of carrying out
and completing the Contract “the Company” shall be entitled to cancel the Contract as to its in
completed part without being in any way liable to payment of any compensation to the estate of
deceased Contractor and/or to the surviving partners of the Contractor’s firm on account of the
cancellation of the Contract. The decision of the Company that the legal representatives of the
deceased Contractor or surviving partners of the Contractor’s firm cannot carry out and complete the
Contract shall be final and binding on the parties. In the event of such cancellation the Company shall
Sign & Stamp of the Bidder P a g e 52 |
not hold the estate of the deceased Contractor and/or the surviving partners of the estate of the
deceased Contractor and/or the surviving partners of the Contractor’s firm liable to damages for not
completing the Contract.
The contract value extent of supply delivery dates, specifications as other relevant matters may be altered by
mutual agreement and if so altered shall not be deemed or constructed to mean and to effect or alter other
terms and conditions of the contract and the contract so altered or revised shall be and shall always be
deemed to have been subject without prejudice to and stipulation.
In witness where of the parties here to have set their hands and seal this day and month year first above
1. Signed sealed and delivered by for and on
Behalf of the presence of name and address.
2. Signed sealed and delivered by for and on behalf
Of The Paschim Gujarat Vij Company Ltd
Sign & Stamp of the Bidder P a g e 53 |
In consideration of the PASCHIM GUJARAT VIJ COMPANY LTD., herein after known as the COMPANY having
given contract for the work of _________________________________
__________________________, dated _______________ and all future contract that may be awarded to me
in the next one year and in terms of the condition in clause 33 of the COMPANY’s tender and contract for
I residing at by this Bond bind myself responsible for and shall pay
compensation to my workmen payable under the workmen’s compensation ACT – 1923 (viii of 1923)
hereinafter called the said Act for death or injuries caused to the workmen engaged by this presents, if such
compensation is paid by the COMPANY as principal under such sub-section (1) of section 12 of the said Act on
behalf of me, to pay such amount of compensation on demand within 48 hours to the COMPANY that it might
have to spend as legal and other incidental charges in defending any suit or action arising out of the death of
injuries in regard to compensation paid to the workmen or heirs of the deceased workmen.
Now the condition of the above written Bond is such that any suit of action arising out of the death or injuries
to the workmen engaged by me. During the execution of work of said contract and all future contracts that
may be awarded to me in the next one year is filed by the worker against the COMPANY, I
shall imbrues to the COMPANY such sum that the COMPANY is required to spend as legal and other incidental
charges in defending such suit or action and also the amount that may be ordered to be paid to the worker /
or his heirs as compensation and that the above written bind shall remain in full force and virtue till the
COMPANY is required to defend such suit or action filed by the workers and or heirs against the COMPANY.
Further it is applicable on death of contractor himself also. No any compensation will be claimed by legal heirs
Signature of the Executant
Sign & Stamp of the Bidder P a g e 54 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
LABOUR RATE FOR CAPITAL WORKS FOR THE YEAR 2025-26
(The Labour rates are excluding of GST) (NO.:- PGVCL/Project/Scheme/SOR/1299 Date:-08.05.2025)
Quantity Labour Total
DETAILS OF WORKS UNIT Rate for
HT TAPPING FROM THE EXISTING POLE INCLUDING FIXING OFCROSS ARMS,
CLAMPS ANTI-CLIMBING DEVICES, DANGER BOARD, INSULATORS ETC.
1 COMPLETE AND PAINTING OF FABRICATED MATERIALS AND NUMBERING NO.
COMPLETE WITHCOST OF PAINTS AS PER STANDARD SPECIFICATION BUT
EXCLUDING ERECTION OF GUY SET AND EARTHING.
ERECTION OF PSC POLES OF 8 Mt ./200 KG INCLUDING EXCAVATION OF PIT
AND REFILLING OF EARTH, FIXING OFCROSS ARMS, TOP FITTING CLAMPS
ANTI-CLIMBING DEVICES, INSULATORS ETC. COMPLETE AND PAINTING OF
FABRICATED MATERIALS USED ON THE POLES AND NUMBERING WITH COST
OF PAINT AS PER STANDARD SPECIFICATION BUT EXCLUDING ERECTION OF
GUY SET AND EARTHING.
ERECTION OF STEEL POLES OF 9 TO 11 METERS INCLUDING EXCAVATION OF
PIT AND REFILLING OF EARTH, FIXING OF CROSS ARMS, TOP FITTING CLAMPS
ANTI-CLIMBING DEVICES, DANGER BOARD, INSULATORS ETC. COMPLETE AND
PAINTING OF STEEL POLE, FABRICATED MATERIALS USED ON THE POLE AND
NUMBERING WITH COST OF PAINT AS PER STANDARD SPECIFICATION BUT
EXCLUDING ERECTION OF GUY SET ANDEARTHING.
ERECTION OF STEEL POLE OF 13 METERS FOR RAILWAY CROSSING ON
BG/MG/NG LINE FOR 0.400/11/22KV OVERHEAD LINES I.E INCLUDING
EXCAVATION OF PIT & REFILLING OFEARTH, FIXING CROSS ARMS, TOP FITTING
4 CLAMPS, ANTI-CLIMBING DEVICES DANGER BOARD, INSULATORS ETC. NO.
COMPLETE AND PAINTING OF STEEL POLES, FABRICATED MATERIALS USED ON
THE POLES AND NUMBERING WITH COSTOF PAINT AS PER STANDARD
SPECIFICATION BUT EXCLUDING ERECTION OF GUY SETS AND EARTHING.
ERECTION OF DOUBLE POLE STRUCTURE OF 8 METERS 200 KG PSC POLES
INCLUDING EXCAVATION OF PITS & REFILLING OF EARTHING, FIXING OF
CHANNELS, SUPPORTING ANGLES,CLAMPS, ANTI-CLIMBING DEVICES DANGER
5 BOARDS,INSULATORS ETC.COMPLETE AND PAINTING OF FABRICATED NO.
MATERIALS USED ON THE POLES AND NUMBERING WITH COST OF PAINT AS
PER STANDARD SPECIFICATION BUT EXCLUDING ERECTION OF GUY SETS AND
EARTHING.(WITHOUT AB SWITCH)
ERECTION OF DOUBLE POLE STRUCTURE OF 9 TO 11 METERS.STEEL POLE
INCLUDING EXCAVATION OF PITS & REFILLING OF EARTH, FIXING OF
CHANNELS, SUPPORTING ANGLES, CLAMPS,ANTI-CLIMBING DEVICES DANGER
6 BOARDS, INSULATORS ETC.COMPLETE & PAINTING OF POLES,FABRICATED NO.
MATERIAL SUSED ON THE POLES AND NUMBERING WITH COST OF PAINTS AS
PER STANDARD SPECIFICATION BUT EXCLUDING ERECTION OF GUY SET AND
EARTHING.(WITHOUT AB SWITCH)
ERECTION OF DOUBLE POLE STRUCTURE WITH MOUNTING OFAB SWITCH, DO
FUSES OF 8 MTRS 200 KG PSC POLES INCLUDING EXCAVATION OF PITS AND
REFILLING OF EARTH, FIXING OF CHANNELS SUPPORTING ANGLES, CLAMPS,
7 ANTI-CLIMBING DEVICES, DANGER BOARDS, INSULATORS, DO FUSES ETC. NO.
COMPLETE AND PAINTING OF FABRICATED MATERIALS USED ON THE POLES
AND NUMBERING WITH COSTOF PAINT AS PER STANDARD SPECIFICATION
BUT EXCLUDING OF ERECTION OF GUY SET AND EARTHING.
ERECTION OF DOUBLE POLE STRUCTURE WITH MOUNTING OFAB SWITCH, DO
FUSES, 9 TO 11 METERS STEEL POLES INCLUDING EXCAVATION OF PITS AND
REFILLING OF EARTH, FIXING OF CHANNEL, SUPPORTING ANGLES, CLAMPS,
ANTI-CLIMBING DEVICES, DANGER BOARDS, INSULATORS, ETC. COMPLETE
AND PAINTING OF POLES FABRICATED MATERIALS USED ONTHE POLES AND
NUMBERING WITH COST OF PAINT AS PER STANDARD
Sign & Stamp of the Bidder P a g e 55 |
SPECIFICATION BUT EXCLUDING ERECTION OF GUY SET AND EARTHING.
ERECTION OF DOUBLE POLE STRUCTURES WITH MOUNTING OF AB
SWITCH, DO FUSES, TRANSFORMERS, LIGHTENING ARRESTORS,
DISTRIBUTION BOX. OF 8 METERS 200 KG AND PSC POLES
INCLUDING EXCAVATION OF PITS AND REFILLING OF EARTH, CARTING
OF TRANSFORMERS FROMSTORES TO SITE, FIXING OF CHANNELS,
9 SUPPORTING ANGLES, BRACINGS CROSS ARMS CLAMPS, NO.
ANTICLIMBING DEVICES, DANGER BOARDS, CONDUCTOR AND CABLE
WIRING ETC.COMPLETE AND PAINTING OF FABRICATED MATERIALS
USEDON THE POLES AND NUMBERING WITH COST OF PAINT AS PER
STANDARD SPECIFICATION BUT EXCLUDING ERECTION OF GUY SETS
ERECTION OF DOUBLE POLE STRUCTURE WITH MOUNTING OFAB
SWITCH,HG FUSES TRANSFORMERS, LIGHTENINGARRESTORS,
DISTRIBUTION BOX 9 TO 11 METERS STEEL POLESINCLUDING
EXCAVATION OF PITS & REFILLING OF EARTHCARTING OF
TRANSFORMERS FROM STORE TO SITE, FIXINGOF CHANNELS
10 SUPPORTING ANGLES, BRACING, CROSS ARMS,CLAMPS, NO.
ANTICLIMBING DEVICES, DANGER BOARDS,CONDUCTOR AND CABLE
WIRING ETC. COMPLETE ANDPAINTING OF POLES FABRICATED
MATERIALS USED ON THEPOLES AND NUMBERING AS PER STANDARD
SPECIFICATIONBUT EXCLUDING ERECTIONS OF GUY SETS AND
ERECTION OF GUY SET INCLUDING EXCAVATION OF PITS &REFILLING
OF EARTH AS PER STANDARD SPECIFICATION WITH STAY CLAMPS,
STAY WIRE, ANCHOR ROD, TURN BUCKLE, EYEBOLT, GUY INSULATOR,
CEMENT CONCRETE BLOCK ETC. BUT EXCLUDING CONCRETING.
CONCRETING OF POLES, GUYS, ETC. INCLUDING COST OF CEMENT
12 SAND METAL (1:2:4) AND WATER ETC. AS PER STANDARD CMT
ERECTION OF COIL TYPE EARTHING INCLUDING COST OF COALSALT
13 ETC. BUT WITHOUT COST OF GI WIRE AS PER STANDARD NO.
SPECIFICATION (20 Kg Salt + 20 Kg Coal)
ERECTION OF PLATE TYPE EARTHING INCLUDING COST OF COALSALT
14 ETC. BUT WITHOUT COST OF GI WIRE AS PER STANDARD NO.
SPECIFICATION (20 Kg Salt + 20 Kg Coal)
ERECTION OF STREET LIGHT FIXTURE COMPLETE WITHCLAMPS, BRASS
NIPPLE, BRASS HOLDER TECK WOOD BUSH, REFLECTORS FUSE,
WIRING ETC. AS PER STANDARD SPECIFICATION BUT EXCLUDING COST
STRINGING OF 30MM2 ACSR/34MM2,55MM2 AAACCONDUCTOR FOR
16 11/22KV & LT LINES INCLUDING FIXING OF INSULATORS, BINDING
17 STRINGING OF GI WIRE 8 SWG INCLUDING BINDING JUMPERINGETC. DO
PROVIDING SINGLE PHASE SERVICE CONNECTION WITH PVC2.5/4.0
MM2 TWIN CORE CABLE FROM TERMINAL POLE TOMETERING POINT
INCLUDING FIXING OF METER & COMPLETE WORK AS PER STANDARD
SPECIFICATION BUT EXCLUDING COST OF MATERIALS.
Sign & Stamp of the Bidder P a g e 56 |
PROVIDING THREE PHASE 4 WIRE SERVICE CONNECTION WITH PVC
4MM2/10MM2 FOUR CORE CABLE FROM TERMINAL POLETO
19 METERING POINT INCLUDING FIXING OF METER & COMPLETE WORK NO.
AS PER STANDARD SPECIFICATION BUT EXCLUDING COST OF
ADDITIONAL COST FOR EXCAVATION OF PIT IN HARD ROCKAREA FOR
ERECTION OF POLE/ GUY ETC. AS PER STANDARD SPECIFICATION
20 OVER & ABOVE NORMAL COST COVERED AGAINST EXCAVATION OF NO.
PIT UNDER NORMAL SOIL FOR ERECTION OF POLE, GUY, DOUBLE POLE
STRUCTURE EARTHING WITH THE APPROVAL OF SUPDT.ENGINEER.
21 PROVIDING GUARDING TO HT LINE ON ROAD/ RAIL CROSSING. MTR
22 PROVIDING GUARDING OF LT LINES ON ROAD/RAIL CROSSING. MTR
23 LT LINE TAPPING- SINGLE PHASE NO.
24 LT LINE TAPPING- THREE PHASE NO.
LAYING OF OVERHEAD LT CABLE FOR ROAD CROSSING,HT LINE Per
CROSSING AND TELEPHONE LINE CROSSING ETC.(PER SPAN) Span
ERECTION OF SINGLE POLE STRUCTURES WITH, DO FUSES,
TRANSFORMERS, LIGHTENING ARRESTOR, DISTRIBUTION BOX. ON
METERS 200 KG PSC POLE INCLUDING EXCAVATION OF PITS AND
REFILLING OF EARTH, CARTING OF TRANSFORMERS FROM STORES TO
SITE, FIXING OF CHANNELS, SUPPORTING ANGLES, BRACINGS CROSS
ARMS CLAMPS, ANTICLIMBING DEVICES DANGER BOARDS,
CONDUCTOR AND CABLE WIRING ETC.COMPLETE AND PAINTING OF
FABRICATED MATERIALS USED ON THE POLE AND NUMBERING WITH
COST OF PAINT AS PER STANDARD SPECIFICATION BUT EXCLUDING
ERECTION OF GUY SETS AND EARTHING.
ERECTION OF SINGLE POLE STRUCTURES WITH MOUNTING OF AB
SWITCH DO FUSES, TRANSFORMERS, LIGHTENING ARRESTOR, AND
DISTRIBUTION BOX. ON 9 to 11 METERS RSJ POLE INCLUDING
EXCAVATION OF PITS AND REFILLING OF EARTH, CARTING OF
TRANSFORMERS FROM STORES TO SITE, FIXING OF CHANNELS,
27 SUPPORTING ANGLES, BRACINGS CROSS ARMS CLAMPS, NO.
ANTICLIMBING DEVICES DANGER BOARDS, CONDUCTOR AND CABLE
WIRING ETC.COMPLETE AND PAINTING OF FABRICATED MATERIALS
USED ON THE POLE AND NUMBERING AS PER STANDARD
SPECIFICATION BUT EXCLUDING ERECTION OF GUY SETS AND
ERECTION OF SINGLE POLE STRUCTURES WITH, HG FUSES, TRANSFORMERS,
LIGHTENING ARRESTOR, DISTRIBUTION BOX ON EXISTING 8 METERS 200 KG
PSC POLE INCLUDING EXCAVATION OF PITS AND REFILLING OF EARTH,
CARTING OF TRANSFORMERS FROM STORES TO SITE, FIXING OF CHANNELS,
28 SUPPORTING ANGLES,BRACINGS CROSS ARMS CLAMPS, ANTICLIMBING NO.
DEVICES DANGER BOARDS, CONDUCTOR AND CABLE WIRING ETC.COMPLETE
AND PAINTING OF FABRICATED MATERIALS USED ON THE POLE AND
NUMBERING WITH COST OF PAINT AS PER STANDARD SPECIFICATION BUT
EXCLUDING ERECTION OF GUY SETS AND EARTHING.
ERECTION OF SINGLE POLE STRUCTURES WITH , HG FUSES, TRANSFORMERS,
LIGHTENING ARRESTOR, DISTRIBUTION BOX ON EXISTING 9 to 11 METERS RSJ
POLE INCLUDING EXCAVATION OF PITS AND REFILLING OF EARTH, CARTING
OF TRANSFORMERS FROM STORES TO SITE, FIXING OF CHANNELS,
29 SUPPORTING ANGLES,BRACINGS CROSS ARMS CLAMPS, ANTICLIMBING NO.
DEVICES DANGER BOARDS, CONDUCTOR AND CABLE WIRING ETC.COMPLETE
AND PAINTING OF FABRICATED MATERIALS USED ON THE POLE AND
NUMBERING WITH COST OF PAINT AS PER STANDARD SPECIFICATION BUT
EXCLUDING ERECTION OF GUY SETS AND EARTHING.
Sign & Stamp of the Bidder P a g e 57 |
ERECTION OF PSC POLES OF 10 Mt./ 270 KG INCLUDING EXCAVATION
OF PIT AND REFILLING OF EARTH, FIXING OFCROSS ARMS, TOP
FITTING CLAMPS ANTI-CLIMBING DEVICES, INSULATORS ETC.
30 COMPLETE AND PAINTING OF FABRICATED MATERIALS USED ON THE NO.
POLES AND NUMBERING WITH COST OF PAINT AS PER STANDARD
SPECIFICATION BUT EXCLUDING ERECTION OF GUY SET AND
ERECTION OF DOUBLE POLE STRUCTURE OF 10 METERS 270 KG PSC
POLES INCLUDING EXCAVATION OF PITS & REFILLING OF EARTHING,
FIXING OF CHANNELS, SUPPORTING ANGLES,CLAMPS, ANTI-CLIMBING
31 DEVICES DANGER BOARDS,INSULATORS ETC.COMPLETE AND NO.
PAINTING OF FABRICATED MATERIALS USED ON THE POLES AND
NUMBERING WITH COST OF PAINT AS PER STANDARD SPECIFICATION
BUT EXCLUDING ERECTION OF GUY SETS AND EARTHING.
STRINGING OF 100MM2 ACSR/100MM2 AAAC CONDUCTOR FOR ONE
32 11/22KV & LT LINES INCLUDING FIXING OFINSULATORS, BINDING
JUMPERING ETC. KM
STRINGING OF ABC OF FOLLOWING SIZES INCLUDING FITTING OF ALL
ACCESSORIES I.E. SPECIAL DESIGN SUSPENSIION/TENSION CLAMP.
FIXING OF CROSSARM, LT SHACKLE INSULATOR, & DIRECTED BY
ENGINEER-IN-CHARGE.
STRINGING OF ABC OF FOLLOWING SIZES INCLUDING FITTING OF ALL
ACCESSORIES I.E. SPECIAL DESIGN SUSPENSIION/TENSION CLAMP.
FIXING OF CROSS ARM, LT SHACKLE INSULATOR, ETC. FOR FIXING OF
MESSENGER WIRE COMPLETE, AS REQUIRED & DIRECTED BY
ENGINEER-IN-CHARGE.
STRINGING OF 11KV ABC OF FOLLOWING SIZES IN RURAL/URBAN
AREA INCLUDING FIXING OF CROSS ARM, SSPECIAL DESIGN
SUSPENSION/TENSION CLAMP, BINDING TO PIN INSULATOR,
35 PREPARING SHCKLE POINT JUMPERS ETC. AS REQUIRED AND MTR
DIRECTED BY ENGINEER-IN-CHARGE.
STRINGING OF ABC OF FOLLOWING SIZES INCLUDING FIXING OF ALL
36 ACCESSORIES. MTR
ERECTION OF DOUBLE POLE STRUCTURES WITH MOUNTING OF AB
SWITCH, HG FUSES, TRANSFORMERS, LIGHTENING ARRESTORS,
DISTRIBUTION BOX OF 10 METERS 270 KG AND PSC POLES
INCLUDING EXCAVATION OF PITS AND REFILLING OF EARTH, CARTING
OF TRANSFORMERS FROM STORES TO SITE, FIXING OF CHANNELS,
37 SUPPORTING ANGLES,BRACINGS CROSS ARMS CLAMPS, NO.
ANTICLIMBING DEVICES DANGER BOARDS, CONDUCTOR AND CABLE
WIRING ETC.COMPLETE AND PAINTING OF FABRICATED MATERIALS
USEDON THE POLES AND NUMBERING WITH COST OF PAINT AS PER
STANDARD SPECIFICATION BUT EXCLUDING ERECTION OFGUY SETS
Sign & Stamp of the Bidder P a g e 58 |
ERECTION OF DOUBLE POLE STRUCTURES FOR CTPT UNIT (PSC POLE)
(ERECTION OF DOUBLE POLE STRUCTURES WITH CTPT,LIGHTENING
ARRESTORS, OF 8 METERS 200 KG AND PSC POLES INCLUDING
EXCAVATION OF PITS AND REFILLING OF EARTH,CARTING OF CTPT
FROM STORES TO SITE, FIXING OF CHANNELS, SUPPORTING
ANGLES,BRACINGS CROSS ARMS CLAMPS, ANTICLIMBING DEVICES
DANGER BOARDS,CONDUCTOR AND CABLE WIRING ETC.COMPLETE
AND PAINTING OF FABRICATED MATERIALS USE ON THE POLES AND
NUMBERING WITH COST OF PAINT AS PER STANDARD SPECIFICATION
BUT EXCLUDING ERECTION OF GUY SETS AND EARTHING.)
ERECTION OF SINGLE POLE SHACKLE POINT ON PSC POLE 8 Mt ./200
KG (ERECTION OF PSC POLES OF 8 MT./200 KG INCLUDING
EXCAVATION OF PIT AND REFILLING OF EARTH, FIXING OFCROSS
ARMS, TOP FITTING CLAMPS ANTI-CLIMBING DEVICES, INSULATORS
ETC. COMPLETE AND PAINTING OF FABRICATED MATERIALS USED ON
THE POLES AND NUMBERING WITH COST OF PAINT AS PER STANDARD
SPECIFICATION BUT EXCLUDING ERECTION OF GUY SET AND
ERECTION OF SINGLE POLE SHACKLE POINT ON STEEL POLE (9 TO
(ERECTION OF STEEL POLES OF 9 TO 11 METERS INCLUDING
EXCAVATION OF PIT AND REFILLING OF EARTH, FIXING OF CROSS
40 ARMS, TOP FITTING CLAMPS ANTI-CLIMBING DEVICES, DANGER NO.
BOARD, INSULATORS ETC. COMPLETE AND PAINTING OF STEEL POLE,
FABRICATED MATERIALS USED ON THE POLE AND NUMBERING WITH
COST OF PAINT AS PER STANDARD SPECIFICATION BUT EXCLUDING
ERECTION OF GUY SET ANDEARTHING.
ERECTION OF SINGLE POLE SHACKLE POINT ON STEEL POLE (13 MTR)
(ERECTION OF STEEL POLES OF 13 METERS INCLUDING EXCAVATION
OF PIT AND REFILLING OF EARTH, FIXING OF CROSS ARMS, TOP
FITTING CLAMPS ANTI-CLIMBING DEVICES, DANGER BOARD,
INSULATORS ETC. COMPLETE AND PAINTING OF STEEL POLE,
FABRICATED MATERIALS USED ON THE POLE AND NUMBERING WITH
COST OF PAINT AS PER STANDARD SPECIFICATION BUT EXCLUDING
ERECTION OF GUY SET ANDEARTHING.
ERECTION OF DOUBLE POLE STRUCTURE OF 13 MTR STEEL POLE
(ERECTION OF DOUBLE POLE STRUCTURE WITH MOUNTING OF AB
SWITCH, DO FUSES TRANSFORMERS, LIGHTENING ARRESTORS,
DISTRIBUTION BOX 13 METERS STEEL POLES EXCAVATION OF PITS
AND REFILLING OF EARTH CARTING OF TRANSFORMERS FROM
42 STRORE TO SITE, FIXING OF CHANNELS SUPPORTING ANGLES, NO.
BRANCING, CROSS ARMS,CLAMPS, ANTI-CLIMBING DEVICES, DANGER
BOARDS, CONDUCTOR AND CABLE WIRING ETC. COMPLETE AND
PAINTING OF POLES FABRICATED MATERIALS USED ON THE POLES
AND NUMBERING AS PER STANDARD SPECIFICATION ERECTION OF
GUY SET AND EARTHING.
ERECTION OF DOUBLE POLE STRUCTURES FOR CTPT UNIT (GIRDER
(ERECTION OF DOUBLE POLE STRUCTURES WITH MOUNTING OF
CTPT, LIGHTENING ARRESTORS,9 TO 11 METERS STEEL POLES
43 INCLUDING EXCAVATION OF PITS AND REFILLING OF EARTH,CARTING NO
OF CTPT FROM STORES TO SITE, FIXING OF CHANNELS, SUPPORTING
ANGLES, BRACINGS CROSS ARMS, CLAMPS, ANTICLIMBING DEVICES,
DANGER BOARDS,CONDUCTOR AND CABLE WIRING ETC. COMPLETE
AND PAINTING OF POLES FABRICATED MATERIALS USE ON THE POLES
Sign & Stamp of the Bidder P a g e 59 |
AND NUMBERING AS PER STANDARD SPECIFICATION BUT EXCLUDING
ERECTION OF GUY SETS AND EARTHING.)
PROVIDING SINGLE PHASE SERVICE CONNECTION (FOR SOLAR
GENERATION METER, HIGH RISE BUILDING, COMPLEX ETC.)WITH
PVC 2.5/4.0 MM2 TWIN CORE CABLE FROM COMMON BUS BAR TO
METERING POINT INCLUDING FIXING OF METER Et COMPLETE WORK
AS PER STANDARD SPECIFICATION BUT EXCLUDING COST OF
PROVIDING THREE PHASE 4 WIRE SERVICE CONNECTIONS (FOR
SOLAR GENERATION METER, HIGH RISE BUILDING, COMPLEX ETC.)
WITH PVC 4MM2/10MM2 FOUR CORE CABLE FROM BUS BAR TO
METERING POINT INCLUDING FIXING OF METER Et COMPLETE WORK
AS PER STANDARD SPECIFICATION BUT EXCLUDING COST OF
RECOVERY PROPOSED FOR NOT PROVIDING AB SWITCH Et LT DISTRIBUTION BOX.
DURING THE ERECTION OF TRANSFORMER CENTER, IF AB SWITCH IS
46 NOT PROVIDED THEN AMOUNT RS.833.00 SHALL BE RECOVER FROM NO
THE BILL OF E/O TRANSFORMER CENTER OF CONTRACTOR.
DURING THE ERECTION OF TRANSFORMER CENTER, IF LT
DISTRIBUTION BOX IS NOT PROVIDED THEN AMOUNT RS.450.00
SHALL BE RECOVER FROM THE BILL OF E/O TRANSFORMER CENTER
Sealing of LT Stud of Transformers with use of 2 inch Diameter &
inch length PVC Pipe around the bushing with wiring connection to
48 the bushing with M-seal. (3 Stud Per Transformer) (The material NO.
required for this work will have to be purchase by the contractor).
NOTE: 75% LABOUR CHARGE WILL BE DEDUCTED IF PAINTING IS NOT DONE.
Sign & Stamp of the Bidder P a g e 60 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
LABOUR RATE FOR MAINTENANCE WORK OF HT LINE.(Excluding of GST)
All Rates are with transportation charges / All material including - M.S. Nut-Bolts of all size will be
supplied by PGVCL / Paints Et Colour to be purchased by the contractors.
HT -LINE MAINTENANCEWORK.
Item Unit Rate for
1 Replacement of V-X-Arm with transportation, etc. (+) Painting. Set
2 Straightening of tilted V-X -Arm, Top fitting / LT X-Arm/ Tapping
3 Dismantling of Old V-X-Arm with Top fitting / LT X-Arm/
Tapping Angle from existing pole.
4 Fixing of V-X-Arm with Top / LT - X- Arm/ Tapping Angle on
existing necked pole with colour
5 Re-fixing & Changing height of V-X-Arm / LT-X-Arm / Tapping
Angle Projection Brackets.
6 Dismentaling of Old deteriorated/Broken PSC Pole with all
Fabrication - with crediting fabrication at field store and staking No.
of pole safely on road side.
6-A Dismentaling of existing re-usable PSC Pole with all Fabrication
- with crediting fabrication at field store and staking of pole No.
safely on road side.
7 Dismentaling Of Old Deteriorated/Broken/ Rail Pole / Tubular
Pole With All Fabrication – With Crediting Fabrication At Field No.
Store And Staking Of Pole Safely On Road Side.
7-A Dismentaling Of existing M.S.Girder Pole with entire length
intact and Re-Usable With All Fabrication - With Crediting
Fabrication At Field Store And Staking Of Pole Safely On Road
8 -do- but D.P. Structure set of PSC Poles Set
9 -do- but D.P. Structure set of PSC Poles (if intact and re-usable) Set
10 Dismantling Of Old Deteriorated/Broken D.P. Structure Set Of
M.S.Girder Poles
10-A Dismantling Of intact and Re-Usable D.P. Structure Set Of
M.S.Girder Poles
11 Replacement of 11 KV Pin Insulator with providing new double
12 Replacement of old 11 KV Pin Insulator by new 22 KV Pin
Insulator with rod and providing double pin bindings and check No.
13 Re-Pin binding with cleaning of 11 KV / 22 KV Pin Insulator. No.
14 Replacement of old 11 KV Disc Insulator by New one with
15 Providing 11 KV double disc insulator with binding etc. No.
16 Replacement of Old jumpers and Providing new double
jumpers with 8" binding and PVC pipe etc.
Sign & Stamp of the Bidder P a g e 61 |
17 Replacement of existing A.C.S.R./All Alu. Conductor up to 55 Per cond.
mm2 by new one/ Coated conductor with pin binding including
transportation and crediting to store etc.
18 Replacement of existing 11 KV conductor by 0.1 A.C.S.R./ AAAC Per cond.
DOG conductor with new double pin binding. Per Km
19 Re-stringing of 11 KV A.C.S.R./AAAC Conductor & L.T. Line 1 Wire per
conductor/ Coated conductor (All size) with new double pin
binding between two locations.
20 Re-stringing of 11 KV Aerial Bunch Cable (All size) between two
21 Removal / Dismantling of ex. HT / LT Line conductor (All Size)
22 Straightening of tilted PSC Poles /Girder Poles. No.
23 Dismantling of guy set comp. with rod (If possible) etc. Set
24 Re-tightening in all respect of loose guy set. Set
25 Providing new guy insulator and tightening of guy set /
26 Trimming/ Cutting of tree branches as per instruction.
Cutting of bigger size of tree branches/whole tree obstructing
28 Providing 11 KV projection brackets in place of old V-X- Arm Set
29 Providing H.T. / L.T. projection brackets (Combined) in place of
ex. Old V-X Arm / L.T. X-Arm etc.
30 Providing LT projection brackets in place of old L.T. X-Arm etc. Set
31 Dismantling of exist. HT / LT projection brackets Set
32 Providing bracing angle set in ex. D.P. ( 4-Angles) Set
33 Straightening of tilted D.P. Set ( PSC / Girder pole) etc. with
refilling of stones, moram etc.
34 Laying of 11 KV power cable from 70mm2 to 225mm2 with
exaction of 3 Feet depth cable trench and refilling the same
with providing bricks layers and refilling the same with sand /
moram up to ground level as per specification.
35 -do-, additional cable in same tranche with additional bricks for
separating both cables
36 Re-activation of earthing of poles No.
37 Repairing and providing HT / LT Guarding with straightening of
G.I. Wire & providing lacings at 1 Mtr. dist. As per specification Per Mtr.
with using I - Rod etc.
38 Providing name of 11 KV fdr in "Gujarati" only on PSC / Girder
Poles with providing back ground colour on poles with two
coats of colour and size of letters to be 2 to 3" in approved ISI No.
colour (Asian Apeolite, Three Mengo including all materials.
39 Providing Pole No with S/S code No, S/Dn Code No. / Feeder
Code No. / T.C. Code No. etc. with back ground colour and
height of letters to be 2 to 3" I.S.I. approved colour (A.A.
Mengo) including all materials.
Sign & Stamp of the Bidder P a g e 62 |
40 Providing New 11 KV A.B./ G.O. Switch with fabrications and
insulated colour code jumpers / bindings lug etc.
41 Providing new 11 KV D.O. Fuse with fabrication and insulated
colour code jumpers / binding / lugs etc
42 Replacement of old 11 KV A.B. / G.O. Switch with providing
new insulated colour code jumpers / bindings / lugs etc.
43 Replacement of old 11 KV D.O. Fuse unit comp. No.
44 Providing C.C. ex. HT / LT Line Poles, Guy Sets etc. as per sp. with all
materials by contractors including cement in 1:2:4 ratio as per
specifications it also includes excavation & relevant works and
45 Providing Muffing in stone masonry in cement mortar 1:5 for X'mers as per
sp. with all materials by contractors including cement without excavation Cmt.
46 Only colour work on ex. Items. ( 2 coats ) of red oxide colour and two coats of silver
colours I.S.I. Asian Acolyte 3 mango colour to be used.
47 V-X-Arm / Tapping Channel or Angle with all fitting. No.
48 L.T. -X-Arm + '-do- No.
49 H.T. /L.T. Proj. brackets complete Set
50 H.T. Proj brackets Set
51 L.T. Proj. brackets Set
53 M.S. Girders 100x116 / Rail & Angle & Tubular Poles (9 to
54 M.S. Girders poles (150x150x11 to 13 Mtrs.) No.
55 D.P. Structure + All fabrications.
(PSC Poles)-without Bracing
56 D.P. Structure + All fabrications.
(PSC Poles)-with bracing
57 '-do- Transformer Structure set - PSC/Girder Pole. Set
58 Providing of XLPE hard coating on 34 mm2 AAAC conductor
with 3 mm coating.
59 Providing of XLPE hard coating on 55 mm2 AAAC conductor
with 3 mm coating.
60 Cost of drum in which party will return the Hard Core XLPE
coated conductor.
Sign & Stamp of the Bidder P a g e 63 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Labour Rates For Maintenance Work Of HT Line. (Excluding Of GST)
All Rates are with transportation charges / All material including - M.S. Nut-Bolts of all size
will be supplied by PGVCL / Paints a Colour to be purchased by the contractors.
HT -LINE MAINTENANCEWORK.
Sr. Item Unit Rate for
61 Straightening of Transformer Centre No.
62 HT ABC Dismantling Mtr.
(1)3x95mm2+1x8Omm2
(2)3x7Omm2+1x7Omm2
63 Erection of Naked PSC Poles of 8 Mt./200 KG No.
64 Erection of Naked Steel Poles of 9 to 11 Mtr No.
65 Erection of Naked Steel Poles of 13 Mtr No.
66 Fixing of Pin Insulator with Pin rod with binding No.
67 Fixing of Disc Insulator with H/W with Binding No.
68 Dismantling of Pin Insulator With Rod No.
69 Dismantling of Disc Insulator With H/W No.
70 Dismantling of DP Angle/Channel with all fabraction, insulating materials No.
etc. and crediting in Field/Divisional Store.
71 Fixing of L Top No.
72 Re-Fixing of Top fitting in Proper position No.
73 Replacement of Top Fitting No.
74 Refitting of LA No.
75 Converting pin point to Shackle Point including Dismentaling arestringing Location
76 Plumbing of PSC pole with straightening at tension point No.
77 Carting of PSC Pole at Destination morethan 5 Kms with prior No.
approval of EE of Division
78 Petrolling of LT/HT Line Et Submission of Summary Report Per Pole
79 Untie the kintting of the old AB Cable Mtr
80 D Type Jumper Per Pole
81 Replacement of D.O.Fuse Set
82 Burning of Thread of LT/HT line including cost of oil bamboo etc. Span
No Dismantled items should be credited in divisional store/RSO.
Sign & Stamp of the Bidder P a g e 64 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Labour Rates For Maintenance Work Of LT Line Service Connection. (Excluding Of GST)
All Rates are with transportation charges / All material including - M.S. Nut-Bolts of all size
will be supplied by PGVCL / Paints a Colour to be purchased by the contractors.
L.T. LINE AND SERVICE CONNECTION MAINTENANCE WORK.
Item. Unit Rate for
1 Replacement of LT X-Arm comp. & crediting in Store. Set
Replacement of LT Pin or shackle insulator by new one with
double binding and claiming etc.
3 Replacement of old deteriorated C - clamp No.
4 Re-binding of L.T. Pin / shackle insulator. No.
5 Providing spacer between L.T. Line conductor with binding etc. No.
Providing cage type loop guard in vertical L.T. Line with using PVC
real insulator etc.
Replacement of old jumpers by new thick insulator colour code
7 jumpers for bare conductor with using PVC Pipe and providing 8" No.
long binding on each jumpers.
Providing junction box or M.S. Box with wooden plate inside on pole with clamp etc.
8 including fixing of K.K. Fuses up to 63 Amp & Neutral link with giving cable connections
on poles and in fuses.
8.c More Than 5 Fuse with respect to item No. 8.b Per fuse
Replacement & Laying of O/H L.T. - PVC Cable for road / H.T. Line
/ P&T Line / Crossing with using G.I. Wire No. 8/10 & PVC Real & One
Egg insulators etc. with connection of Lugs, etc. up to 70 sq.mm Span
Replacement & Laying of O/H L.T. - PVC Cable for road / H.T. Line
/ P&T Line / Crossing with using G.I. Wire No. 8/10 & PVC Real & One
Egg insulators etc. with connection of Lugs, etc. for 95 sq.mm & Span
11 Replacement of service lines with MMB & meters with all accessories as under:
1 Phase Connection
Replacement of service lines with Meter Box & meters by using
11.a G.I. Wire No. 8/10, Real insulator at the distance of 1.0 Mtr., two No.
nos. of egg insulator, wall fast, service angle, PVC Service pipe
etc. at equal vertical distance with giving connections of service.
11.aa -do-without meter box and meter No.
Sign & Stamp of the Bidder P a g e 65 |
3 Phase Connection
Replacement of service lines with Meter Box & meters by using
11.b G.I. Wire No. 8/10, Real insulator at the distance of 1.0 Mtr. two No.
nos. of egg insulator, wall fast, service angle, PVC Service pipe
etc. at equal vertical distance with giving connections of service.
11.bb --do-- without meter box and meter No.
12 Labour charge for replacement of Meter Box without meter.
12.a 1 Phase Conn. No.
12.b 3 Phase Conn. No.
13 Labour charge for replacement / providing of meter and Meter Box
13.a 1 Phase Conn. No.
13.b 3 Phase Conn. No.
14 Replacement of meter / providing only
14.a 1 Phase Conn. No.
14.b 3 Phase Conn. No.
15 Labour charge for installation of 3 phase Meter Box & 3 phase Meter on T.C. complete
in all respect including carting of materials from respective store as per instruction of
engineer in-charge.
15.a In City Area Set
15.b In Rural Area Set
16 Providing leads of service wires on L.T. Line with 8 to 10 turns with insulation and 8 to
10 turns of bare wire with L.T. Line conductor and providing insulated PVC tape on it.
16.a Per 1 Phase S/C. 13.13
16.b Per 3 Phase S/C. 23.34
17 Stringing of Twin wire No. 35 41.82
18 Single Phase Meter, SMC & Service Shifting Work 448.05
19 Providing Pole SMC BUS-BAR
(Providing leads of service wires on on BUS BAR per service)
20 Providing Dropper(4mm/6mm Cable) 29.87
21 LT ABC Dismantling
22 LT ABC Dismantling
(1) 1x35rnm2 + 1x25mm2
23 LT ABC Re-stringing 95.58
Note: Dismantled items should be credited in divisional store/RSO.
Sign & Stamp of the Bidder P a g e 66 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Labour Rates For Maintenance Work Of Transformer Center. (Excluding Of GST)
All Rates are with transportation charges / All material including - M.S. Nut-Bolts of all size will
be supplied by PGVCL / Paints a Colour to be purchased by the contractors.
TRANSFORMER MAINTENANCE WORK.
Item Unit Rate for
Replacement of old jumpers by new insulated cover cable
1 jumper/biding/lugs etc. etc. from L.A. to D.O. fuse or D.O. fuse to No
Replacement of old 200 KVA & above distribution box complete
with making all connections with crimping of lugs, tapping, neutral
Replacement of old up to 100 KVA distribution box complete with
making all connections (i.e.25,63,100)
Dismentling of existing distribution transformer center up to 100 KVA with all
fabrication and crediting the old material in sub-Division/Division store (With
Girder pole Set
Dismentling of existing distribution transformer center above 100 KVA with all
fabrication and crediting the old material including Distribution Transformer
5 in sub-Division/Division store.
Girder pole Set
Dismantling of Transformer Centre (8 Mtr PSC Pole)
(without Transformer) with crediting of fabrication at
store a stacking of pole safely on road side or Crediting to
Departmental Store
Note: Dismantled items should be credited in divisional store/RSO.
Sign & Stamp of the Bidder P a g e 67 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Labour Rates Disconnection & Reconnection For Work Of Transformer Center. (Excluding Of
All Rates are with transportation charges / All material including - M.S. Nut-Bolts of all size will
be supplied by PGVCL / Paints a Colour to be purchased by the contractors.
DISCONNECTION AND RECONNECTION WORK.
Sr. No. Item Unit
Disconnection & Reconnection from LT Pole Single Phase S/C
City Area(Disconnection & Reconnection) (Payment will be No
made after receipt of RC Charges)
City Area(Only Disconnection ) No.
Rural Area(Disconnection & Reconnection) (Payment will be No.
made after receipt of RC Charges)
Rural Area(Only Disconnection ) No.
Disconnection & Reconnection from LT Pole Three Phase S/C
1 City Area(Disconnection & Reconnection) (Payment will be No
made after receipt of RC Charges)
City Area(Only Disconnection ) No.
Rural Area - Other than Ag. (Disconnection & Reconnection) No.
(Payment will be made after receipt of RC Charges)
Rural Area - Other than Ag. (Only Disconnection) No.
Rural Area - Ag. Connection (Disconnection & Reconnection) No.
(Payment will bemade after receipt of RC Charges)
Rural Area - Ag. Connection (Only Disconnection) No.
Dismantling and removal of service line from pole and crediting in store Single Phase
2 Dismantling and removal of service line from pole and crediting in store Three Phase
Rural Area - Other than Ag. No.
Rural Area - Ag. Connection No.
Sign & Stamp of the Bidder P a g e 68 |
PASCHIM GUJARAT VIJ COMPANY LIMITED
Labour Rates For Laying of 11 KV Underground Cable
(The Labour rates are excluding of GST)
Description Unit
Excavation of trench 0.5 metre wide and 1 metre deep for laying of HT/LT
underground cable of size up to 300mm2 PILC or XLPE. (The cable should be
laid on bed of sand and to cover cable with half round RCC pipe 6" internal
dia. And length of 1 metre along with each bottom and top.) The entire
trench thereafter should be refilled with earth duly rammed up to ground
level as per drawing No. PGVCL/Tech/UG Cable/01/2014-15.
Excavation of trench 0.75 metre wide and 1 metre deep for laying of double
HT/LT underground cable of size up to 300mm2 PILC or XLPE. (The cable
should be laid on bed of sand and to cover cable with half round RCC pipe
6" internal dia. And length of 1 metre along with each bottom and top.) The
entire trench thereafter should be refilled with earth duly rammed up to
ground level as per drawing No. PGVCL/Tech/UG Cable/02/2014-15.
Laying / re-laying of cable in cable trench and from ground level to Pole
structure for providing outdoor cable joints.
Laying / re-laying XLPE/PILC cable by digging of pits, removal of old cable
and laying of new cable on sand bed as per item No.1 above.
Widening & refilling with earth duly rammed the trench for laying additional
No. of cable. For Item No.1 above.
Add: Charges for digging of Tar road for laying of cables over and above
digging of pit in normal soil as per Sr.No.1.
Laying of underground 11 KV XLPE Cable by push and pool method (Manual)
through with HDPE Pipe 140mm diameter, 6mm thickness or 6" or 4"
7 diameter GI Pipe without damaging surface of the rod by Horizontal boring Metre
/ drilling method (excluding cost of HDPE Pipe or 6" or 4" GI Pipe) as per
drawing and specification.
Laying of underground 11 KV XLPE Cable by push and pool method (by
Horizontal directional machine) through with HDPE Pipe 140mm diameter,
8 6mm thickness or 6" or 4" diameter GI Pipe without damaging surface of the Metre
rod by Horizontal boring / drilling method (excluding cost of HDPE Pipe or
6" or 4" GI Pipe) as per drawing and specification.
Moulding of cable joints (straight joints, indoor and outdoor) for PILC Cable
- labour charges.
Moulding of cable joints (straight joints, indoor and outdoor) for XLPE Cable
- labour charges, for Urban area.
Moulding of cable joints (straight joints, indoor and outdoor) for XLPE Cable
- labour charges, for Rural area.
Moulding of cable joints (straight joints, indoor and outdoor) for LT PVC
Supply of HDPE pipe for laying 11 KV XLPE Cable 140mm diameter and 6mm
thickness as per IS:
Sign & Stamp of the Bidder P a g e 69 |
Supply of HDPE pipe for laying 11 KV XLPE Cable 100mm diameter and 6mm
thickness as per IS:
Supply of half round RCC Hume pipe 6" internal diameter and length of
Supply of medium grade GI Pipe of size 6" diameter (including clamping the
cable with Pole)
Supply of medium grade GI Pipe of size 4" diameter (including clamping the
cable with Pole)
Supply of RCC Hume Pipe of 6" internal diameter for laying cable for double
circuit and road crossing.
Supply of sand 0.300 X 0.500 X 1.00 metre (layer at bottom of cable trench
approx. 0.15 CMT) as per Drg. No. PGVCL/Tech/UG Cable/01/2014-15
Supply of sand 0.300 X 0.750 X 1.00 metre (layer at bottom of cable trench
approx. 0.225 CMT) as per Drg. No. PGVCL/Tech/UG Cable/02/2014-15
Rate of Route Marker:
Providing, supplying & fixing route marker of C.C. 1:2:4, 150mm X 150mm
X 750mm concrete stone (PGVCL marked with approved yellow colour)
21 embedded in earth at least 300mm below the ground level and 450mm No.
above ground level at distance approximately 100 metre or as directed by
Engineer-In-Charge (this includes material and labour charges for
excavation and refilling.)
Dismantling of Under Ground Cable (Excavation and Refilling Earth
credited to store without cutting the cable.)
Total Estimated Tender Cost Rs. 10,00,000=00
In Word (Ten lakh Rs only)
’ h&> upr[ikt kim p).J.v).s).a[l,k>pn)ni> BivY) krvi t]yir C&>.
’ h&> upr[ikt kim p).J.v).s).a[l,k>pn)ni> BivY)––––––– % a[in mi> krvi t]yir C&>.
’ h&> upr[ikt kim p).J.v).s).a[l,k>pn)ni> BivY)––––––– % l[S mi> krvi t]yir C&>.
ki[ºT^ikTrn) sh): Biv Byi< tir)K:
Sign & Stamp of the Bidder P a g e 70 |
SECTION VIII: Technical Specifications
TECHNICAL SPECIFICATIONS FOR THE WORK TO BE CARRIED OUT For erection work 11 KV and L.T.
Distribution lines and Transformer Centres
The work should be strictly as per specifications and approved designs of the PGVCL. The inferior and
unsatisfactory work is liable for rejection and to be rectified at the cost of contractor. The work will have to
be carried out as per programmed laid down by department and under the entire instruction of engineer-in-
Charge and contractor should employ supervisor who could supervise the works through out and he should
remain present on site. No tools & Tackles will be supplied by the department.
(A) Erection of HT and LT Lines:
Site clearing and tree branches trimming which come in the way of line will be done by the contractor at
his cost. The Company will assist the contractor in getting necessary permission for tree cutting etc. Any
claim for compensation in above respect will have to be borne by contractor.
(B) Fixing: Pole Position:
The Points of pole structures, guys and earthing will be fixed by the department and will be shown to the
contractor. He should adhere to these locations in all circumstances unless directed by the department to
make any change. The Poles from One site to other site or at proposed locations must be carted by loading
on Tractor or Hand-Cart. The Poles shall not be carted by toeing/Dragging with Tractor or Cart or with any
(C) Pole setting:
Where poles are set in good solid ground the depth of pit shall be 1/6th of the height of the pole and for
grounds of any other nature. The pit must be size of 2 X 2 X 5 feet. The poles and guys must not be set at
the edge of cuts/at shore/embankment where the soil is liable to be washed or eroded out of such setting
should be avoided. While back filling, earth must be packed tight and in no case earth be dumped to greater
depth more than four inches without being rammed, hard before the next layer is thrown in. Extra earth
should be packed around the poles and rammed.
The cost of damage done to the pole during erection will be recoverable from the contractor. No pole,
which is out of plumb or out of alignment shall be accepted. The pole will be in his safe custody till erected
and he is liable to compensate to the Company the full cost of pole along with supervision charges, if the
pole is broken during erection, or stolen from his custody. He should be able to render full account of the
poles entrusted to him whenever the Supervising Officer demands to scrutinizes the same.
(D) Erection of Complete single Pole Structure
Erection of single pole structure comprises of shifting of pole from the stacking place in the village,
excavation of pit, erection in position (with base plate where required), of 8/10 meter PSC poles / 9 to
meter Steel Pole or any other suitable pole, fitting of clamps and cross arms and fabricated materials, fixing
of caution board, anti-climbing device etc. complete as per drawing and specification inclusive of painting,
numbering. Generally vertical formation will be used on each pole. However horizontal formation will have
to be used in special circumstances as per instruction at Engineer in change.
(E) Double Pole (D. P.) Structure
Double poles structure such as for HT line tapping, Railway crossing, any other HT/LT or telephone line
crossing, terminal structure for distribution transformer centre comprises of Excavation suitable pits and
refilling of earth, erection in position of two Nos. of 8/10 meter PSC
poles / 9 to 13 meter Steel Pole or any other suitable pole, fitting of clamps, cross arms, bracing cross arm
bracing etc. as per drawing/ standards with mounting D.O. fuses/A.B. switches/HT metering equipment’s
etc., painting, Pole numbering, fixing of caution Board and anti-climbing devices.
The D.P. must be properly aligned and must be in plumb. Special structure if included will be erected as
per drawing supplied. Each Shackle Points must have “D” type Jumpers only.
(F) Stringing of conductors
Sign & Stamp of the Bidder P a g e 71 |
This includes stringing of stranded and solid bare conductor with fitting of necessary HT/LT pin and strain
insulators, binding on insulators, jumpers, the jointing in HT line will be done by twisting sleeve joints as
per standard practice. Care must be taken in handling the conductor to protect against cuts, scratches or
kinks. The conductor must not be drawn over rough or rocky ground, when it is liable to be damaged.
AAA/ACSR conductors must be drawn on wooden or aluminium pulley only. Wastage and cutting should
be avoided as far as possible. Not more than 3 % sag will be accepted in the materials account. The sag
and spans will be maintained as per drawing/standard. The cross arms insulators must be so fixed that
neither tilts nor bands from position. The sagging should be uniform for all conductors and uneven sagging
will not be allowed. The ground clearance to be maintained as per IE Rules 2010 Clause No. 58 as
mentioned below.
For lines of voltage not exceeding 650 Volts 5.8 Meters
Across a street For lines of voltage exceeding 650 Volts but not
exceeding 33 kV
For lines of voltage not exceeding 650 Volts 5.5 Meters
Along any street For lines of voltage exceeding 650 Volts but not
exceeding 33 kV
For lines of voltage up to and including 11,000 If bare - 4.6 Meter
Elsewhere than Volts If insulated- 4.0 Meter
along or across
any street For lines of voltage exceeding 11,000 Volts but
not exceeding 33 kV
An overhead line shall not cross over an existing building as far as possible and no building shall be
constructed under an existing overhead line.
Where an overhead line of voltage not exceeding 650 V passes above or adjacent to or terminates on
any building, the following minimum clearances as per IE Rules 2010 Clause No. 60 from any
accessible point, on the basis of maximum sag, shall be observed, namely:-
(i) for any flat roof, open balcony, varandah roof and lean-to-roof and Pitched Roof-
(a) when the line passes above the building a vertical clearance of highest part of building immediately
under such line 2.5 meters from the highest point,
(b) When the line passes adjacent to the building a horizontal clearance of 1.2 meters from the nearest
(ii) Where an overhead line of voltage exceeding 650 V passes above or adjacent to or terminates on any
building, the following minimum clearances as per IE Rules 2010 Clause No. 61 from any accessible
point, on the basis of maximum sag, shall be observed, namely:-
(a) when the line passes having voltage 650 V and up to and including 33000 V above the building a
vertical clearance of highest part of building immediately under such line 3.7 meters from the
(b) When the line having voltage 650 V and up to and including 11000 V passes adjacent to the building
a horizontal clearance between nearest Conductor and any part of such building on the basis of
maximum deflection of wind must be 1.2 meters
(iii) Minimum clearances in meters between lines crossing each other as per IE 2010 Clause No. 69 are as
1 Low and Medium 2.44 3.05 4.58 5.49
Sign & Stamp of the Bidder P a g e 72 |
In case of illegal construction / structure on the line under erection, the same is to be put in written notice
to the Engineer-In-charge.
(G) Erection of Stay Set:
The erection of stay set comprises of anchor rod, turn buckle, eye bolt and excavation of suitable pit size
of 2 X 2 X 5 foot, fixing of stay clamp on pole, binding of GI stay wire. The stay insulators must be inserted
in the stay wire on all stays as per drawing. The wrapping of the Guy wire strands at both ends the stay
insulator must be even and must presents neat appearance and good workmanship. No stay should be
left loose but should be tight and straight to withstand in say cyclone or sand storm, the item includes
refilling of earth and painting of fabrication material. If stays are not required to be concreted, a pre
casted cement concrete block will be supplied by the department from his division store which the
contractor will have to transport at his own cost to the site of work and will have to use for fixing of
anchor rod at site.
A pits of 2 X 2 X 5 foot is to be dig about 4 foot away from the pole on which earthing is required to be
carried out. The earthing pipe/earthing plate/earthing coil supplied by the company shall be used as per
specification and drawing. GI wire no. 8 SWG for earthing should be bolted with earthing pipe/earthing
plate/earthing coil. G. I. Wire must be passed through PVC rigid Pipe which must be buried at least
Meter in ground and to be kept 2.0 Meters above ground along the Pole. The earthing are to be done at
place as indicted in the pole schedule or as selected by the field Engineer. The coke and salt will have to
be supplied by the contractor at his cost. Erection of earthing should be carried out under the supervision
of the Engineer in charge or nominated Supervisors. At least 20 KG of salt and 20 KG of coal per earth on
alternate layers (as per drawing) will be used by contractor. No amount will be paid if the work is not
done in accordance with these specifications.
The guarding will have to provide at crossing of lines, telephone line crossing, road crossing and any
accident prone places as indicated by the Engineer in Charge. The work comprises of fixing of guard cross
arms, eye bolts, guard cradle as per design, GI cross lacing wires complete. Any special type of guarding
if required will be designed by the department. Binding cross arms must be used where the HT line
crosses the road. The ground clearance, line to line clearances etc. to be maintained as per IE Rules
69 and 70. The poles for road crossing may be concreted as instructions of the Engineer In-charge. The
work has to be carried out as instructions of the Engineer In-charge.
(J) Painting and Numbering:
Rail poles and girder poles shall be given one coat of approved red-lead paint and two coats of approved
aluminium paint. All fabricated material will also be painted with two coats of approved aluminium paint
and there should be sufficient interval between every coat of painting in order to allow for drying. The
bolts and must shall be dipped in anticorrosive oil before insertion. The lower portion of steel poles up
foot above ground level shall be cleaned of all dust and rust. This surface should be given a base coat of
red lead and an additional coat of black bituminous paint before inserting in the ground. The good quality
paint will be supplied by the contractor and should be of I.S.I mark and will be got approved from
Executive Engineer, prior to starting work.
Name of the feeder and pole number has to be written on all the poles in English/Gujarati as per
instruction of Engineer In-charge. The colour of back ground and name/number must be of contras
colour. Prior to apply Colour for Numbering on P.S.C poles, it should be properly cleaned and all
accumulations of earth, dirt etc. should be removed.
(K) Concreting:
Unless Specified concreting is to be done for Girder Poles/Guys only. No any PSC Pole/Guys to be
concreted without any special reason. The Concreting of PSC Poles must be approved by concerned
Executive Engineer prior to execution as per Tender Condition mentioned under Section III Clause No.
2 and sub clause No. 8. Certificates for special Reason and approvals must be submitted with detail Bill.
Sign & Stamp of the Bidder P a g e 73 |
Cement concrete for any pole / stay should be carried out as per specification given by Engineer In-Charge
as and where required. Concreting should be with one part of cement, two part of specified quality sand
and four parts of well burnt Brice bats (1:2:4). The mixture should be prepared on GI sheet and should
be free from the dust. Cement, river sand and metal should be used by contractor at his own cost. The
finishing coat of cement plaster shall be applied on outer surface Concreting and boxing for smoothness.
The normal size of concreting of pole shall be 2 X 2 X 2 Feet (0.226 cmt) & that for stay 2 x 2x 1 Feet
(0.113 cmt). In case of Boxing for pole, it shall be 18” dia. x 3 feet (h) (2’ above and 1' below ground)
(L) Distribution Transformer Centre:
The distribution transformer centre (10 KVA to 200 KVA) will be of outdoor type on two poles structures
as per standard drawing and 5 KVA Transformers are to be on Single Pole. This work include erection of
special two pole structure as per Item No. 2 and fixing of all fabricated material for support of line, L.A.,
HG Fuse/AB Switch, Transformer, LT Dist. Box, cable wiring, anti-climbing devices etc. The works includes
of transportation and hoisting of transformer, numbering and painting of all fabricated materials. For
transformer having capacity of 100 KVA and above MS channel shall be utilize which will be supplied by
the company. Three Earthing are to be provided on each Transformers.
1) Earthing of LA on One side.
2) Earthing of all Metal Parts from Top angle and Transformer Body and Dist. Box on other side.
3) For neutral, two separate Earth wire on both side of Transformer and to be common at ground.
All three earthing are to be done as in Delta Formation as shown in the attached Drawing. All earthing
wires are to be connected by proper size of lug and bolted at each earthing points properly. The Earthing
of Transformer Body must be done with lug only. Looping or winding with Earthing Bolt on Transformer
Body is not allowed. Earthing wire Lugs are to be brought by Contractors. No any extra cost will be paid
for this material.
Extra payment for hard soil or rock is payable as per SOR as per committee report to be formed to
decide hard soil or rock which shall consists of Concerned SDO, Deputy Engineer (Tech) and Executive
The cost of damage done to the transformer while erection/Transportation is recoverable from
Before starting the work (new, alteration or addition) and during the works the contractor must obtain
line clear wherever necessary for the concerned officer of this office of other Office. For any damage
done to the Men, Materials and/or property due to non-observance of rules, the contractor will be solely
Sign & Stamp of the Bidder P a g e 74 |
SECTION IX: Drawings
Sign & Stamp of the Bidder P a g e 75 |
Sign & Stamp of the Bidder P a g e 76 |
Sign & Stamp of the Bidder P a g e 77 |
Arrangement of Transformer
Sign & Stamp of the Bidder P a g e 78 |
Earthing Arrangement for Transformer Centre
Sign & Stamp of the Bidder P a g e 79 |
Arrangements of Guy
1. Guy Clamp 2. Turn Buckle and Eye Bolt 3. Guy Insulator
4. Guy Wire 5. Guy Rod 6. Guy Pit (2 X 2 X 5 ft.)
7. θ 30 to 40 Deg.
Sign & Stamp of the Bidder P a g e 80 |
Sign & Stamp of the Bidder P a g e 81 |
Sign & Stamp of the Bidder P a g e 82 |
Double Pole (D.P.) Structure
Sign & Stamp of the Bidder P a g e 83 |
Guarding under 11 KV Line
Sign & Stamp of the Bidder P a g e 84 |
Guarding under LT Line
Sign & Stamp of the Bidder P a g e 85 |
LT Line Horizontal Formation and Clearances (415 V)
Sign & Stamp of the Bidder P a g e 86 |
LT Line Vertical Formation and Clearances (415 V)
Sign & Stamp of the Bidder P a g e 87 |
LT Line Horizontal Formation and Clearances (230 V)
Sign & Stamp of the Bidder P a g e 88 |
LT Line Vertical Formation and Clearances (230 V)
Sign & Stamp of the Bidder P a g e 89 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.