Tender Value
₹25.9 L
EMD Value
₹51,800
Closing Date
21 Oct 2026, 6:00 pm5d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
EE PWD DIV. BUNDI
EE PWD DIV. BUNDI
A/R to Raktya Bheruji
2026_CEPWD_603840_4
EE PWD DIV. BUNDI NITNO-09/2026-27
Open Tender
Civil Works
Percentage
90 days
BUNDI
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
500 EE PWD DIV. BUNDI
₹51,800
Yes
12 Oct 2026
12 Oct 2026
23 Oct 2026
12 Oct 2026
21 Oct 2026
12 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation for Structures Earthwork in excavation for structures as per drawing and MoRTH specifications Clause 304.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. Hard rock (blasting prohibited) | 44.02 | Cum | 331 | ₹14,570.62 |
| 2 | Excavation for Structures Earthwork in excavation for structures as per drawing and MoRTH specifications Clause 304.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. Ordinary soil Upto 3 m depth | 46.2 | Cum | 137 | ₹6,329.4 |
| 3 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 10 Nominal mix 1:3:6 | 34.85 | Cum | 2,584 | ₹90,052.4 |
| 4 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 R.C.C. grade M 25 | 144.56 | Cum | 3,266 | ₹4,72,132.96 |
| 5 | Stone masonry in cement mortar for substructure complete as per drawing & MoRTH specification Clauses 1402, 1405 & 2200 and including Weepholes as per MoRTH specifications Clauses 2706 Random rubble masonry In 1:3 cement mortar | 81 | Cum | 3,082 | ₹2,49,642 |
| 6 | Back filling behind abutment, wing wall and return wall in 150mm layers, with mechanical compaction, complete with all lead and lift as per drawing and technical specification as per MoRTH Specification : Clause : 304 Gravelly material | 54 | Cum | 513 | ₹27,702 |
| 7 | Plastering with cement mortar (1:4), 20 mm thick on Stone work. | 144 | Sqm | 132 | ₹19,008 |
| 8 | Supplying, fitting, and placing HYSD bar reinforcement (Primary Steel) in Foundation, Substructure and superstructure at any level complete as per drawing and MoRTH specifications Clauses 1009,1600 and 2302 | 2.54 | Tonne | 80,077 | ₹2,03,395.58 |
| 9 | Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 2905. 1000 mm dia | 22.5 | Rmt | 3,864 | ₹86,940 |
| 10 | Dry Lean Cement Concrete Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a fully automatic computerised batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. | 76.55 | Cum. | 2,418 | ₹1,85,097.9 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.21 MB
Tendernotice_2.pdf
PDF • 1.40 MB
Tendernotice_3.pdf
PDF • 11.56 MB
BOQ_1070895.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .