| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹2.1 LAccepted-Finance VILLAGE PO JARWA SUB TEHSIL RONHAT DISTRICT SIRMOUR H P | SIRMAUR | HIMACHAL PRADESH | 173001 | ₹2.1 L | L-1 | Accepted-Finance Being 1st Lowest |
| 2 | L-2₹2.1 L+₹978.07 (0.47%)Rejected-Finance | ₹2.1 L+₹978.07 (0.47%) | L-2 | Rejected-Finance Being 2nd Lowest |
Tender Value
₹2.0 L
EMD Value
₹4,000
Closing Date
18 Aug 2026, 10:00 amClosed
EE Seraj
HPPWD Division Seraj at Janjehli
SH Construction of Retaining wall in wire crate at RD 0/380 to 0/401
2026_PWD_140838_5
4820-22 Dated 05.08.2026
Open Tender
Civil Works - Roads
Percentage
Janjehli
Please refer Tender documents.
11 documents required · 11 mandatory
₹350
₹4,000
29 Aug 2026
10 Aug 2026
18 Aug 2026
10 Aug 2026
18 Aug 2026
10 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation for structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material of disposal any lead and dressing of sides and bottom and backfilling in trenches with excavated suitable material ordinary soil including carriage of material within all leads and lifts and other incidental and as per the direction of the Engineer-in-Charge. . | 20.37 | Per Cubic Meter | 533.75 | ₹10,872.49 |
| 2 | Providing and laying of boulder apron laid in wire crates with 4mm (four millimetre) diametre G.I. wire conforming to IS: 280 and IS: 4826 in 100mm x 100mm (one hundred millimetre into one hundred millimetre) mesh (woven diagonally) including 10% (ten percent) extra for laps and joints laid with stones boulders weighting not less than 25 Kg. (twenty five kilogram) each as per drawing and technical specifications clause 1301 including carriage of material with in all leads and lifts and other incidentals and as per the direction of the Engineer-in-Charge. | 65.73 | Per Cubic Meter | 2,549.7 | ₹1,67,591.78 |
| 3 | Back filling behind abutment, wing wall and return wall complete as per drawing and technical specification clause 1204.3.8 including carriage of material with in all leads and lifts and other incidentals and as per the direction of the Engineer-in-Charge. | 17.64 | Per Cubic Meter | 1,198.5 | ₹21,141.54 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.16 MB
1.pdf
Tender Documents • 4.00 MB
BOQ_208966.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .