Beam bottom's line, level & width should be checked.
Beam side's line , level & plumb should be checked.
Beam to beam measurements shall be checked as per architectural drawing.
Individual level & diagonal of each slab bay shall be checked.
Slab thickness level shall be marked with nails on the peripheral beam's outer side.
Slab thickness & beam depths should be checked
Support props for slab & beam bottoms should be in line & plumb, Bamboo bracing should be done at around 4' ht from floor level. Support props for double staging terraces shall be carefully checked.
Line of external/peripheral beam's side shall be checked & should be cross supported to avoid building out of sides.
Junctions of column & beam shall be checked & should be cross supported to avoid building out of sides.
De-shuttering oil shall be applied to beam/slab shuttering
Formwork of staircase shall be checked for dimensions of tread and riser, level of treads, plumb of risers.
Reinforcement shall be checked for beams and slab as per RCC drawing.
Proper cover for bottom/sides shall be checked for beams.
Proper cover shall be checked for slab.
Electrical points, electrical piping (conduits)/fan hooks shall be checked as per drawing.
Reduction of column as per drawing shall be done if any.
Proper no. of chairs shall be provided for slab.
Parapet (pardi) bars shall be left for balconies/staircase etc.
Ring (stirrups) shall be provided at the free end of each column reinforcement
Gaps between plates/planks should be filled. Taping should be done at ply joints in care of ply shuttering
Approval of architect and RCC consultant shall be taken prior to pouring.
Check the availability of required labour strength, mixer, lift, vibrators, masons, weigh batcher, diesel/petrol and plastics sheets etc. before start of concreting.
Hidden beams/inverted beams/cantilever beams should be checked.
Check for the sunk if any as per the approved drawings.
Packing below supports props should be avoided. If not, single wooden plank should be inserted as packing
In case of large slabs, position of concrete joints shall be decided in advance as per approval by RCC consultant.
Availability of raw material for concrete/RMC per grade of concrete, water. Electricity shall be checked in advance before the start of concreting.
Concreting shall be done for the beams first & then slabs.
Compaction of concrete shall be done by vibrators & tamping rods. (Spare vibrators with fuel shall be ensured.)
The top level of slabs shall be finished by the mason and no one should be allowed to walk on the fresh finished concrete.
Carpenter shall be present below the slab shuttering during concreting to ensure the tightness of the form work.
In case of rains, the finished concrete shall be covered with the big plastic sheets.
Cast 6 cube moulds for testing.
Curing the slab shall be done with pounding method by making ponds in cement & sand mortar(1.10) of size around 5'X5' curing of beams and slabs shall be done for 7 to 10 days or as directed by the consultant.
Date of casting and slab no shall be painted on the front side beam.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Labour Cooperative Societies shall submit only 50% of bid security for which the tenderers are required to upload Registration certificate issued by appropriate authority without which their offer will not be considered. Such firms should also declare that -" We are a Labour Cooperative Society and our Registration No. is .................... with .......................and hence required to deposit only 50% of Bid Security
Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' shall be exempted from payment of Bid Security on submission of Registration Certificate issued by appropriate authority. For such firms it is required to upload a copy of Registration Certificate issued by appropriate authority without which their offer will not be considered. Such firms should also declare that - I/We am/are a Startup firm registered by ........................ Department of Industrial Policy and Promotion (DIPP) and my registration number is ................ valid upto ...................... (Copy enclosed) and hence exempted from submission of Bid Security.
THE OFFERS WITHOUT EARNEST MONEY EXCEPT IN CASE OF EXEMPTION CLAIMED AS PER COMMERCIAL COMPLIANCE OF NIT WILL BE SUMMARILY REJECTED.
Rebuilding / Rehabilitation/ strengthening of bridges (up line) in connection with running of higher loads and higher speed (678,732,739,775,787,846 etc. bridges) & Replacement of Existing slab Bridge No. 366A, Ballast retainer replacement and widening of Major Bridge no. 391, UP line, Providing CC flooring, curtain wall, drop wall, inspection steps, pitching, standard bridge tablets & ballast retaining wall in bridge approaches on various major & minor bridges of Madar-Palanpur Section.
85-2026~NWR
85-2026
Open
Works - General
24 Months
Kota, Rajasthan
₹0
₹11.1 L
6 Jul 2026
11 Jun 2026
22 Jun 2026
5 items across 1 schedule · ₹48,03,803.4 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Pre Tamping Measurements (a) Establishment of main GNSS (DGPS Base) Point & reference point establishment at 150 meter maximum interval along the track. | Per Track KM | 165.00 | 5,410.01 | 8,92,651.65 |
| 2 | Pre Measurement of tamping with total station & prism Gedo trolley measure and store gauge. Cross elevation, chainage, shift and lift value at every 3 M i.e. every 5th sleeper interval along the track centre line and co-ordinates of track centre line at every 3M. to be submitted with track geometry (per km round) | Per Track KM | 165.00 | 9,479.17 | 15,64,063.05 |
| 3 | Construct target/Designs alignment with the good points of existing pre measurement profile in design software. To export data in ALC format with design alignment or measured reading in M/c and to provide track adjustment file with Ver extension and also to provide Geo Geometry file to profile to provide text file with slew, uplift and guage at every 3m i.e. every 5th sleeper interval for tamping machine operator during reference. | Per Track KM | 165.00 | 2,437.57 | 4,02,199.05 |
| 4 | Post tamping Measurements (a) Post Tamping measurements with total stations & prims Gedo trolley measure and store Guage. Cross elevation, Chainage, shift and lift value at every 3m i.e. Every 5th sleeper interval along the track centre line and co-ordinates of track centre line at every 3 mtr to submitted with track Geometry (per/km/round) | Per Track KM | 165.00 | 9,479.17 | 15,64,063.05 |
| 5 | Reporting (A) Report and ploting soft and Hard copies of slew and uplift report at every 3mtr/ 5 m i.e. every 5th sleeper interval compared with design vs pre profile report of offset distance from track centre to OHE, neighbouring track centre and platform point. | Per Track KM | 165.00 | 2,308.04 | 3,80,826.6 |
| Schedule total | ₹48,03,803.4 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .