Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC L1 |
| 2 | Rejected-Technical | - | - | Rejected-Technical L3 |
| 3 | Rejected-Technical | - | - | Rejected-Technical L2 |
| 4 | Rejected-Technical | - | - | Rejected-Technical L4 |
Tender Value
₹1.2 Cr
EMD Value
₹50,000
Closing Date
29 Mar 2023, 4:00 pmClosed
Superintending Engineer
PH Circle, KWA,Kozhikode
AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-KOVOOR ZONE-Extension and Replacement of Distribution pipeline and Providing FHTC in Corporation Roads Wards 21 - Chevayur and ward 23- Nellikkode
2023_KWA_568891_1
SE/PHC/KKD/128/2022-23
Open Tender
Civil Works - Others
Item Rate
180 days
Kozhikode Corporation
7 documents required · 7 mandatory
₹5,515
₹50,000
12 May 2023
23 Mar 2023
30 Mar 2023
23 Mar 2023
29 Mar 2023
23 Mar 2023
Amount
Appendix A :- Pipe Laying
100.59.1:Cutting the bituminous / concrete roads with cutting machine for a minimum depth of 200mm along the sides of proposed alignment of the pipe to be laid without causing any damage to other utilities, including the charges for hire and conveyance of tools and plant, cost of consumables and charges for lighting, watching, ribbon fencing, caution boards, traffic diversion, and as per the direction of departmental officers etc. complete, before carrying out the demolition of bituminous / concrete road by mechanical means and carrying out the excavation.
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
100.9.9:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 110 mm nominal outside diameter pipes.
100.12.9:Conveying and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc., but excluding cost of pipes and fittings for External work: 100mm diameter nominal bore.
100.31.1.2:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 100mm diameter, Class I.
100.32.1:Conveying and fixing C. I. Single Acting Air Valve of approved quality with bolts, nuts, rubber insertions etc., complete, but excluding the cost of air valve (tail pieces, if required, will be paid separately): 25mm Single Acting Air Valve.
100.98.1008:Engaging Coolie.
Appendix - B :- Cost of Materials
100.98.237:Supply of PVC Pipe, 10kg/cm2, 110mm Dia.
OD185894/2022-2023:Supply of 100 mm GI pipe
100.98.458:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 100mm.
100.98.440:Supply of CI Air Valve, Conforming to IS 14848 - 2000, Single Orifice, Small Orifice Type S1, Size 25mm.
OD185895/2022-2023:Add 3% cost of PVC pipes for specials
OD185896/2022-2023:Add 5 % for specials for GI pipe
Appendix -C :- Providing FHTCs
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
100.60.13.3.2:Providing 20mm (3/4 inch) house connection with 15mm water meter from existing PVC / HDPE mains up to 110 mm dia., up to a length of 5m using 25mm ( 3/4 inch ) PE Pipe, PE80, PN16, Conforming to IS 4984: 2016 or later edition and PP PN 16 Compression / GM / Brass specials viz. brass ferrule, brass hexagonal nipple, GM full way wheel valve, bend, MTA, FTA, couplers, PVC Service Saddle of suitable size etc. and connecting with the mains, testing the joints etc. complete including trenching and refilling in all kinds of soil up to a depth of 1.50m for main line tracing and trench of average cross section 0.3m x 0.75m for laying connection pipe and service pipe, fixing water meter, lighting, watching, providing caution boards, traffic control etc. complete including cost of materials, hire for tools, cost of consumables and labour charges,including the cost of tested Class B Multijet water meter and weather with ISI mark resistant PP / PE meter box of minimum size 300mm x 200mm x 150mm, but excluding charges for cutting the concrete / tarred / bituminous roads etc, and as per the direction of the departmental officers.
OD249296/2022-2023:Reinstating House Connections
100.60.15.1.1:Providing additional length of house connection pipe using 20 mm (1/2 inch) PE Pipe, PE80, PN16, Conforming to IS 4984: 2016 or later edition and PN16 specials and testing the joints etc., by trenching and refilling in all kinds of soil with trench of average cross section 0.3m x 0.75m for laying of connection pipe and service pipe, lighting, watching, providing caution boards, traffic control etc., including cost of materials, hire for tools, cost of consumables and labour charges etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads etc., and as per the directions of the department officers.
100.60.12.4.1:Providing 15mm PVC Tap in the water meter assembly for 20mm connection, using 25mm Indian Standard Class 6 uPVC pipes and specials including cost of materials, consumables, hire charges for tools and labour charges etc. complete and as per the direction of departmental officers.
OD185897/2022-2023:Providing and Fixing Water Tap post using 75 mm PVC 6 kg/cm2 pipe including cost of pipe, End cap, fixing in concrete
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Appendix - D :- Construction of Valve Chamber, Interconnection and Allied works
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD185893/2022-2023:Making Tee connection from 63/75/90/110/140/160 mm dia PVC pipe line to the proposed line by cutting and providing suitable size PVC tee, the charges including all provisions for BT cutting, earth work excavation in all classes of soil, bailing out water, fencing, labour for controlling, traffic and valves,, providing and filling quarry muck in the trenches etc. complete
OD186108/2022-2023:providing surface box with protection tube of 200mm pvc10kg/cm2 pipe 75cm in length, for sluice valves, Airvalves etc
Road Reformation Works
3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m <br> Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3
4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) <br> (A) By Mix in Place Method <br> Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. <br> (i) For Grading I Material
4.9:Wet Mix Macadam <br> Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. <br> By Mechanical Means with 1 km lead
5.1.2a:Prime Coat <br> Medium porosity :- Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.90- 1.2 kg/sqm using mechanical means as per Technical Specification Clause 502.
5.2.1a:Tack Coat<br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
5.9.2.2a:20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder - Bitumen S-65 <br> Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508. <br> Case - II By Mechanical Means :- (II) Bitumen (S-65)
5.12.B.2.2a:Seal Coat - Mechanical Means - Type B - Bitumen S-65 <br> Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 <br> B. By Mechanical Means :- Case - II : Type B <br> (II) Bitumen (S-65)
PRABEESH CONSTRUCTIONS
JITHIN GOPINATH K
PRABEESH KUMAR C
Bidder Name
JITHIN GOPINATH K
PRABEESH KUMAR C
M ABDUL NAZER
PRABEESH CONSTRUCTIONS
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_839680.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .