| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹52.3 LAdmitted-Finance | -9.35% | ₹52.3 L | L1 | Admitted-Finance |
| 2 | L2₹53.7 LAdmitted-Finance | -7.00% | ₹53.7 L | L2 | Admitted-Finance |
| 3 | L3₹54.3 LAdmitted-Finance | -5.99% | ₹54.3 L | L3 | Admitted-Finance |
| 4 | L4₹54.9 LAdmitted-Finance | -4.95% | ₹54.9 L | L4 | Admitted-Finance |
Tender Value
₹57.7 L
EMD Value
₹1.2 L
Closing Date
6 Apr 2026, 5:00 pmClosed
GM-CIVIL
MAIN ADMINISTRATIVE BUILDING, SECTOR-6, NOIDA
M/o Village (Renovation of Pond in village Shadhra Sector-141) Noida
2026_NOIDA_1128447_1
43/GM(C)/ SM (WC-8)/ET/2025-26
Open Tender
Civil Works - Others
180 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,832
NOIDA
₹1.2 L
22 Apr 2026
20 Mar 2026
7 Apr 2026
20 Mar 2026
6 Apr 2026
20 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | |||||
| 2Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. | |||||
| 3Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 20 mm nominal size) | |||||
| 4Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately). All works upto plinth level | |||||
| 5Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately). All works above plinth level upto floor V level (DSR-18/5.37.2) | |||||
| 6Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | |||||
| 7Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete. | |||||
| 8Centering and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. | |||||
| 9Centering and shuttering including strutting, propping etc. and removal of form for : Lintels, beams, plinth beams, girders, bressumers and cantilevers. | |||||
| 10Brick work with F.P.S. bricks of class designation 150 in superstructure above plinth level upto floor V level in all shapes and sizes in :Cement mortar 1:4 (1 cement : 4 coarse sand)Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. | |||||
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.21 MB
TD43.pdf
Tender Documents • 2.30 MB
BOQ_2104711.xls
BOQ • 0.27 MB
Capability-43.xls
Additional Documents • 0.04 MB
Download all tender documents and submit your bid