Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.8 LAccepted-Finance | ₹9.8 L | L1 | Accepted-Finance Responsive |
| 2 | L2₹10.4 LRejected-Finance | ₹10.4 L | L2 | Rejected-Finance Non Responsive |
| Sl No | Description | Qty | Unit | Anubir Singh L1 | Kheema Nand Devrari L2 |
|---|---|---|---|---|---|
| 1.00 | Excavation in foundation in all type of soil and rocks including lead, lift and disposal of surplus earth material as per direction of engineer - in -charge also including supply of all material labour T&p etc. required for proper complection of work for R/W, B/W | 29.51 | Cum. | 483.12 ₹2,566.21 | 512 ₹2,719.61 |
| 2.00 | Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, inbreast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction | 43.83 | Cum. | 4,528.16 ₹35,724.13 | 4,802 ₹37,884.54 |
| 3.00 | Random Rubble Stone Masonry laid dry in breast walls, retaining walls, parapets, scuppers, etc.including supply of all material, labour, T&P and royaltiies etc.(As per PWD Uttarakhand specifications) | 26.27 | Cum. | 2,512.71 ₹11,881.98 | 2,665 ₹12,602.12 |
| 4.00 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction | 57.3 | Cum. | 5,233.34 ₹53,976.67 | 5,550 ₹57,242.70 |
| 5.00 | Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) | 8.3 | Cum. | 1,139.39 ₹1,703.27 | 1,208 ₹1,805.84 |
| 6.00 | Providing and laying boulder apron for bed protection with stone boulders ofminimum size and weight as per Table 1300.1, no fragment weighing less than 25kg laid dry complete as per drawing and technical specifications Clause 1301 | 28.8 | Cum. | 1,693.89 ₹8,781.13 | 1,790 ₹9,279.36 |
| 7.00 | Providing concete for plain/reinforced concrete in open foundation complete as per drawing and technical specification clause 802,803,1202 and 120 P.C.C. Grade M10 Nominal mix(1:3:6) | 14.4 | Cum. | 8,813.97 ₹22,845.81 | 9,340 ₹24,209.28 |
| 8.00 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction | 7.2 | Cum. | 9,514.89 ₹12,331.30 | 10,000 ₹12,960 |
Tender Value
Refer Docs
EMD Value
₹20,000
Closing Date
16 May 2026, 3:00 pmClosed
Zonal Manager
C-11, Turner Road, Clement Town, Dehradun U.K- 248002
Restoration work at Tharali Dewal Mundoli to Tajput Lagga MR
2026_CCUK_147494_1
UT-03-170 Aapda
National Competitive Bid
Civil Works - Roads
90 days
Tharali
As per technical bid
3 documents required · 3 mandatory
₹3,540
ZONAL MANAGER ,NPCC Ltd
₹20,000
3 Jun 2026
7 May 2026
16 May 2026
7 May 2026
16 May 2026
7 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Excavation in foundation in all type of soil and rocks including lead, lift and disposal of surplus earth material as per direction of engineer - in -charge also including supply of all material labour T&p etc. required for proper complection of work for R/W, B/W | - | Cum. | 488 | - | Item1 |
| 2 | Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, inbreast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction | 1 | Cum. | 4,573.9 | ₹4,569.33 | Item2 |
| 3 | Random Rubble Stone Masonry laid dry in breast walls, retaining walls, parapets, scuppers, etc.including supply of all material, labour, T&P and royaltiies etc.(As per PWD Uttarakhand specifications) | - | Cum. | 2,538.1 | - | Item3 |
| 4 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction | 1 | Cum. | 5,286.2 | ₹5,280.91 | Item4 |
| 5 | Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) | 1 | Cum. | 1,150.9 | ₹1,149.75 | Item5 |
| 6 | Providing and laying boulder apron for bed protection with stone boulders ofminimum size and weight as per Table 1300.1, no fragment weighing less than 25kg laid dry complete as per drawing and technical specifications Clause 1301 | - | Cum. | 1,711 | - | Item6 |
| 7 | Providing concete for plain/reinforced concrete in open foundation complete as per drawing and technical specification clause 802,803,1202 and 120 P.C.C. Grade M10 Nominal mix(1:3:6) | - | Cum. | 8,903 | - | Item7 |
| 8 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction | - | Cum. | 9,611 | - | Item8 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.41 MB
SBD.pdf
Tender Documents • 1.57 MB
BOQ_230111.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid