| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.4 LAccepted-AOC | L1 | Accepted-AOC AOC | |
| 2 | l2₹12.8 L+₹43,031.20 (3.47%)Rejected-Finance | l2 | Rejected-Finance L2 | |
| 3 | L3₹14.9 L+₹2.5 L (20.1%)Rejected-Finance | L3 | Rejected-Finance L3 | |
| 4 | L4₹15.1 L+₹2.7 L (21.4%)Rejected-Finance | L4 | Rejected-Finance L4 | |
| 5 | L5₹15.4 L+₹3.0 L (24.2%)Rejected-Finance 67 AASANI BAS PALANA PALANA BIKANER BIKANER RAJASTHAN 334402 UDYAM RJ 08 0063520 | BIKANER | RAJASTHAN | 334402 | L5 | Rejected-Finance L5 |
| Sl No | Description | Qty | Unit | S R CONTRACTORS L1 | M/S SAVERA BUILDCON L9 | M/S PRABHAT CONTRACTOR AND ENGINEERS L4 | M/S M W CONSTRUCTIONS L6 | M/S STAR BUILD SOLUTION L2 | Shah Alam L8 | R.A.V. BUILDERS AND CONSULTANT L7 | IQRAR AHMAD CONTRACTOR L3 | S S CONSTRUCTION COMPANY L5 | M/S DIVINE BLESSED ENTERPRISES L10 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Earth work in excavation of foundation in ordinary soil i/c all lead & reqd lifts with proper compaction as per site requirement and proper disposel of excavated surplus earth as directed by engineer in charge including cost of all labour T&P etc. required for proper completion of work | 140.19 | CUM | 60 ₹8,411.4 | 60 ₹8,411.4 | 40 ₹5,607.6 Lowest | 57.12 ₹8,007.65 | 40 ₹5,607.6 Lowest | 57.8 ₹8,102.98 | 40 ₹5,607.6 Lowest | 90 ₹12,617.1 | 52.7 ₹7,388.01 | 60 ₹8,411.4 |
| 2.00 | Laying of cement concrete M10 A40 (1:3:6) with Cement, Coarse Sand, Stone Grit (A-40) laid in foundation of abutment including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete or as directed By for proper completion of work Engineer-in-charge | 20.88 | CUM | 3,400 ₹70,992 Lowest | 5,800 ₹1,21,104 | 4,800 ₹1,00,224 | 4,889.49 ₹1,02,092.55 | 5,200 ₹1,08,576 | 5,068.32 ₹1,05,826.52 | 4,500 ₹93,960 | 4,500 ₹93,960 | 4,621.17 ₹96,490.03 | 5,900 ₹1,23,192 |
| 3.00 | Laying of Cement Concrete in M7.5 A40 (1:4:8) mix with Cement, Coarse Sand, Stone Grit (A-40) including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | 12 | CUM | 3,500 ₹42,000 Lowest | 5,600 ₹67,200 | 4,600 ₹55,200 | 4,849.99 ₹58,199.88 | 5,000 ₹60,000 | 4,907.73 ₹58,892.76 | 4,000 ₹48,000 | 4,000 ₹48,000 | 4,474.69 ₹53,696.28 | 5,700 ₹68,400 |
| 4.00 | Ist class Brick work in 1:4, Cement Coarse Sand mortar in warping including cost of all material labour T&P etc. complete for proper completion of work | 84.65 | CUM | 4,850 ₹4,10,552.5 | 5,800 ₹4,90,970 | 5,300 ₹4,48,645 | 4,970.99 ₹4,20,794.3 | 4,900 ₹4,14,785 | 5,030.17 ₹4,25,803.89 | 5,900 ₹4,99,435 | 4,800 ₹4,06,320 | 4,488.68 ₹3,79,966.76 Lowest | 5,800 ₹4,90,970 |
| 5.00 | Struck Pointing in 1:2 Cement mortor including cost of all material, labour, T&P, Curing etc complete for proper completion of work | 72.32 | SQM | 70 ₹5,062.4 | 100 ₹7,232 | 100 ₹7,232 | 86.85 ₹6,280.99 | 50 ₹3,616 Lowest | 87.89 ₹6,356.2 | 100 ₹7,232 | 90 ₹6,508.8 | 80.13 ₹5,795 | 100 ₹7,232 |
| 6.00 | Providing centering & shuttering for bridge slab, bed block, dirt wallcement concrete work in foundation and transitions i/c all cost of labour & T&P etc complete for proper completion of work | 82.98 | SQM | 350 ₹29,043 | 650 ₹53,937 | 500 ₹41,490 | 575.4 ₹47,746.69 | 450 ₹37,341 | 582.25 ₹48,315.11 | 250 ₹20,745 Lowest | 400 ₹33,192 | 530.87 ₹44,051.59 | 650 ₹53,937 |
| 7.00 | Laying of reinforeced cement concrete in M20 A20 (1:1.5:2) mix with Cement, Coarse Sand, Stone Grit (A-20) in slab including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | 13.17 | CUM | 5,800 ₹76,386 | 7,100 ₹93,507 | 6,300 ₹82,971 | 5,928.39 ₹78,076.9 | 6,200 ₹81,654 | 6,145.28 ₹80,933.34 | 6,800 ₹89,556 | 6,600 ₹86,922 | 5,603.05 ₹73,792.17 Lowest | 7,200 ₹94,824 |
| 8.00 | Laying of reinforeced cement concrete in M25 A20 (1:1:2) mix Cement, Coarse Sand (A-20) in dirt wall and bed block including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | 8.15 | CUM | 5,800 ₹47,270 | 7,200 ₹58,680 | 6,400 ₹52,160 | 6,105.28 ₹49,758.03 | 6,600 ₹53,790 | 6,328.59 ₹51,578.01 | 7,000 ₹57,050 | 6,500 ₹52,975 | 5,770.18 ₹47,026.97 Lowest | 7,400 ₹60,310 |
| 9.00 | S/L of two coat tar Felt Painting including cost of all material, labour, T&P complete for proper completion of work | 5.7 | SQM | 50 ₹285 | 35 ₹199.5 | 41.65 ₹237.41 | 34.98 ₹199.39 | 20 ₹114 Lowest | 35.4 ₹201.78 | 30 ₹171 | 300 ₹1,710 | 32.27 ₹183.94 | 40 ₹228 |
| 10.00 | Providing & Fixing 20mm thick Expansion Joint with angle iron both side & M.S. plate carring & filling of filler material of bitumin soil dust & Coarse Sand (F.M. Not less than 2.00), etc complete for proper completion of work | 15.4 | RM | 1,200 ₹18,480 | 1,500 ₹23,100 | 700 ₹10,780 | 1,571.76 ₹24,205.1 | 1,000 ₹15,400 | 1,590.45 ₹24,492.93 | 1,500 ₹23,100 | 500 ₹7,700 Lowest | 1,450.14 ₹22,332.16 | 1,500 ₹23,100 |
Tender Value
₹18 L
EMD Value
₹36,000
Closing Date
2 Apr 2026, 5:00 pmClosed
EEMGCCD4 AMROHA
EEMGCCD4 AMROHA
Construction Of V.R.B At Km. 5.315 Of Dhakiya Dy. under Project M.G.C. Stage-II IN DIST MORADABAD
2026_UPIDC_1130901_11
09/EE/2025-26
Open Tender
Civil Works - Canal
Item Rate
AMROHA
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹36,000
11 May 2026
27 Mar 2026
3 Apr 2026
27 Mar 2026
2 Apr 2026
27 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Earth work in excavation of foundation in ordinary soil i/c all lead & reqd lifts with proper compaction as per site requirement and proper disposel of excavated surplus earth as directed by engineer in charge including cost of all labour T&P etc. required for proper completion of work | |||||
| 2Laying of cement concrete M10 A40 (1:3:6) with Cement, Coarse Sand, Stone Grit (A-40) laid in foundation of abutment including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete or as directed By for proper completion of work Engineer-in-charge | |||||
| 3Laying of Cement Concrete in M7.5 A40 (1:4:8) mix with Cement, Coarse Sand, Stone Grit (A-40) including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | |||||
| 4Ist class Brick work in 1:4, Cement Coarse Sand mortar in warping including cost of all material labour T&P etc. complete for proper completion of work | |||||
| 5Struck Pointing in 1:2 Cement mortor including cost of all material, labour, T&P, Curing etc complete for proper completion of work | |||||
| 6Providing centering & shuttering for bridge slab, bed block, dirt wallcement concrete work in foundation and transitions i/c all cost of labour & T&P etc complete for proper completion of work | |||||
| 7Laying of reinforeced cement concrete in M20 A20 (1:1.5:2) mix with Cement, Coarse Sand, Stone Grit (A-20) in slab including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | |||||
| 8Laying of reinforeced cement concrete in M25 A20 (1:1:2) mix Cement, Coarse Sand (A-20) in dirt wall and bed block including cost of all material, labour, T&P, Machanical Mixing, Curing etc complete for proper completion of work | |||||
| 9S/L of two coat tar Felt Painting including cost of all material, labour, T&P complete for proper completion of work | |||||
| 10Providing & Fixing 20mm thick Expansion Joint with angle iron both side & M.S. plate carring & filling of filler material of bitumin soil dust & Coarse Sand (F.M. Not less than 2.00), etc complete for proper completion of work | |||||
stage.html
html • 0.08 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.93 MB
TD11.pdf
Tender Documents • 2.70 MB
BOQ_2109874.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .