| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.1 LAccepted-AOC | ₹11.1 L | L1 | Accepted-AOC below estimate rate |
| 2 | L2₹13.5 L+₹2.4 L (21.8%)Rejected-AOC | ₹13.5 L+₹2.4 L (21.8%) | L2 | Rejected-AOC Estimate rate |
| Sl No | Description | Qty | Unit | Eenam Electricals L2 | ELECTROTECH CONSTRUCTIONS L1 |
|---|---|---|---|---|---|
| 1.00 | Quoted Amount of BOQ1 in figures | 1 | Nos | 0 ₹11,43,234.76 | 3.1 ₹11,07,794.48 Lowest |
| 2.00 | GST Rate in percentage | 1 | Nos | 18 ₹2,05,782.26 Lowest | - |
Tender Value
₹11.4 L
EMD Value
₹28,600
Closing Date
13 Jul 2026, 5:00 pmClosed
Assistant Executive Engineer
Electrical sub division, Vazhathoppe,Idukki Colony PO,Idukki Dist.
LT RECONDUCTORING VIMALAGIRI AREA under Electrical Section,Painavu
2026_KSEB_857625_1
AEE,ESD-VZPE/T-12/2026-27 dated 24.06.2026
Open Tender
Electrical Works
Percentage
120 days
Vimalagiri
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
₹28,600
29 Jul 2026
25 Jun 2026
14 Jul 2026
27 Jun 2026
13 Jul 2026
27 Jun 2026
27 Jun 2026 - 8 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing Stay for LT poles
including digging & back
filling pit in ordinary soil. | 140 | No | 938.82 | ₹1,31,434.8 |
| 2 | Providing Strut using LT PSC pole including digging
and back filling pit in
ordinary soil. | 10 | No | 1,887.05 | ₹18,870.5 |
| 3 | Labour charges for loading
LT PSC pole from the
stacking place and unloading
the same at work site
(transportation by any
vehicle). | 114 | No | 478.82 | ₹54,585.48 |
| 4 | Providing Fly stay for LT
pole using LT PSC pole
including digging and back
filling pit in ordinary soil. | 4 | No | 3,062.14 | ₹12,248.56 |
| 5 | Erecting one LT PSC Pole in
position including digging &
back filling pit in ordinary
soil. | 100 | No | 2,017.73 | ₹2,01,773 |
| 6 | Additional rate for
excavation of one Pit for LT
Pole/LT Stay in Laterite | 20 | No | 217.45 | ₹4,349 |
| 7 | Additional rate for
excavation of one Pit for LT
Pole/LT Stay in Hard
Laterite. | 20 | No | 434.91 | ₹8,698.2 |
| 8 | Fitting one No. Section fuse
on LT line with dropping
cables, crimping sockets,
connecting with bolt & nut
etc. | 20 | No | 240.45 | ₹4,809 |
| 9 | Transporting poles by hired
vehicle to a distance upto
5km and carrying upto 4
numbers of poles excluding
loading& unloading charges | 28 | Trip | 3,142.26 | ₹87,983.28 |
| 10 | Installing One No. Insulation
piercing connector of size
Main :16 to 95 ,Tap:1.5 to 16
Sq.mm | 1,000 | E | 57.79 | ₹57,790 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
GTC.pdf
Other Document • 2.15 MB
TTC.pdf
Other Document • 1.52 MB
GCC.pdf
Tender Documents • 0.73 MB
BOQ_1449793.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .