Tender Value
₹75.0 L
EMD Value
₹1.5 L
Closing Date
8 Sept 2026, 3:00 pm
Deputy General Manager (Civil)
Contract Division BSPS
Construction of a 338 KL Capacity SMC (Sheet Molding Compound) Panel Water Tank at Surangani Colony
2026_NHPC_922520_1
Construction of a 338 KL Capacity SMC (Sheet Molding Compound) Panel Water Tank at Surangani Colony
Open Tender
Civil Works
Works
120 days
BSPS Surangani
Please refer Tender documents.
8 documents required · 8 mandatory
₹1,180
NHPC LTD
₹1.5 L
18 Aug 2026
18 Aug 2026
12 Sept 2026
18 Aug 2026
8 Sept 2026
18 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. : All kinds of soil. | 207.29 | Cum | 211.52 | ₹43,845.98 |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 14.73 | Cum | 6,114.72 | ₹90,069.83 |
| 3 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level: Thermo-Mechanically Treated bars of grade Fe-500 D or more. | 3,053.3 | Kg | 94.82 | ₹2,89,513.91 |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns,
etc. for mass concrete | 245.19 | Sqm | 267.11 | ₹65,492.7 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand) : 4 graded stone aggregate 20 mm nominal size) | 30.69 | Cum | 7,347.67 | ₹2,25,499.99 |
| 6 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand): 3 graded stone aggregate 20 mm nominal size) | 61.39 | Cum | 8,213.57 | ₹5,04,231.06 |
| 7 | Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone - III) : 6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. | 147.6 | sqm | 590.9 | ₹87,216.84 |
| 8 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:6 (1 cement : 6 coarse sand) | 34.58 | Cum | 6,551.74 | ₹2,26,559.17 |
| 9 | 12 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) | 232.93 | sqm | 213.3 | ₹49,683.97 |
| 10 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 5,958.95 | Kg | 106.93 | ₹6,37,190.52 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.15 MB
TendDocCW18.pdf
Tender Documents • 4.99 MB
BOQ_969436.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].