| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹51.1 LAccepted-AOC | ₹51.1 L | L1 | Accepted-AOC For Being L1 |
| 2 | L2₹51.7 L+₹55,287 (1.08%)Rejected-Finance CHAKRAJUMOLLA PAILAN KOLKATA 700 104 WEST BENGAL INDIA | 24 PARAGANAS SOUTH | WEST BENGAL | 700104 | ₹51.7 L+₹55,287 (1.08%) | L2 | Rejected-Finance Being L2 |
| 3 | L3₹58.1 L+₹7.0 L (13.6%)Rejected-Finance TARULIA KRISHNAPUR KOLKATA 700102 WEST BENGAL INDIA | 24 PARAGANAS NORTH | WEST BENGAL | 700102 | ₹58.1 L+₹7.0 L (13.6%) | L3 | Rejected-Finance Being L3 |
| 4 | L4₹1.1 Cr+₹55.5 L (108.7%)Rejected-Finance 214 2ND FLOOR SAMRUDDHI COMMERCIAL PREMISES CHINCHOLI BUNDER ROAD MINDSPACE MALAD WEST MUMBAI MAHARASHTRA 400064 | MUMBAI SUBURBAN | MAHARASHTRA | 400064 | ₹1.1 Cr+₹55.5 L (108.7%) | L4 | Rejected-Finance Being L4 |
| 5 | Rejected-Technical HARIYANA BHAWAN NEAR MAA SHARADA MANDIR CHOWK RAM NAGAR COLONY BOKARO JHARKHAND 827013 | BOKARO | JHARKHAND | 827013 | - | - | Rejected-Technical Technically Disqualified |
Tender Value
₹54.6 L
EMD Value
₹1.1 L
Closing Date
8 Dec 2023, 2:00 pmClosed
EXECUTIVE ENGINEER
IIM CALCUTTA, ENGINEERING DIVISION, JOKA, D.H Road, Kolkata 700104
External repairing and painting of the Lake View hostel building in IIMC Campus.
2023_IIMCT_781488_1
ED/IIMC/NIT/1/23-24/105
Open Tender
Civil Works
Item Rate
120 days
IIM Calcutta, Joka, D.H Road, Kolkata
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,500
IIMC CONSTRUCTION WORKS ACCOUNTS
₹1.1 L
Yes
IIM CALCUTTA, ENGINEERING DIVISION, JOKA
16 Jan 2024
17 Nov 2023
11 Dec 2023
17 Nov 2023
8 Dec 2023
17 Nov 2023
29 Nov 2023
Amount
Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.; upto 150 mm. thick.
Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars.
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in all floor as per relevant IS codes.
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (6mm nominal size) excluding shuttering and reinforcement,if any, in gound floor as per relevant IS codes.
Brick work with 1st class bricks in cement mortar (1:4). In superstructure, ground floor
Stripping off worn out plaster and raking out joints of walls, celings etc.
Taking out Mirzapur or glazed porcelain tiles carefully by chiselling from walls or floor including stacking serviceable material as directed.
Removal of rubbish, earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary, with sand and cement mortar 1:4, 20 mm thick plaster.
Applying 2 coats of bonding agent with synthetic multi-functional rubber emulsion having adhesive and water proofing properties by mixing with water in proportion (1 bonding agent : 4 water : 6 cement) as per Manufacturer's specification
Labour for Chipping of concrete surface etc.
Supplying, fitting and fixing 18 mm. to 22 mm. thick kota stone slab in wall, dado in 15 mm thick [avg] cement mortar (1:3) including making suitable arrangement to hold the stone properly by brass / copper hooks including pointing in cement mortar (1:2) (1 cement : 2 marble dust) with admixture of pigments matching the stone shade, including grinding and polishing all complete as per direction of Engineer-in-charge including cost of materials, labour, scaffolding, staging, curing complete. etc.
Supplying, fitting and fixing Black Stone slab used in Kitchen slab, alcove, wardrobe etc. laid and jointed with necessary adhesive Cement mortar (1:2) including grinding or polishing as per direction of Engineer-in -Charge in all Floor. Slab Thickness 20 to 25 mm.
Supplying& laying 25 mm designer chequered tiles of any shade and of approved quality as per IS: 1237: 1980 laid in patterns as directed in pavement, footpath including necessary underlay 25 mm thick average cement mortar (1:3) complete in all respect with all labour and materials [using cement slurry @ 4.4 kg/Sq.m at back side of tiles.
Applying decorative cement based paint of approved quality after preparing the surface including scraping the same thoroughly etc. One coat on new surface.
Scraping of moss, blisters etc. thoroughly from exterior surface of walls necessitating the use of scraper, wire brush etc.
Applying exterior grade Premium quality Acrylic primer having superior alkali and efflorescence resistance specially formulated properties of approved quality and brand on plastered or concrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface thoroughly, complete as per manufacturer's specification and as per direction of the EIC. One coat
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. Premium 100% Acrylic Emulsion
Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. one coat
Painting with best quality synthetic enamel paint of approved quality etc. On steel or other metal surface. Two coats (with any shade except white)
Supply of UPVC pipes (B Type) & fittings conforming to IS-13592-1992. Single Socketed 3 Meter Length. Dia 110 mm.
Labour for fitting and fixing U.P.V.C. pipes for above ground work including cost of jointing materials etc. fitting and fixing all necessary specials, cutting pipes, cutting holes in walls or R.C. floor where necessary and mending good all damages excluding the cost of masonry or concrete work, if necessary, but including the cost and fitting and fixing holder bat clamps (any floor) or for underground work including cutting trenches upto 1.5 metre and refilling the same complete as per direction of the Engineerin-charge. (Payment will be made on centre line measurement of the total pipeline including specials. Above ground. Dia 110 mm.
GAZI HARDWARES
SENCO ENTERPRISE
Oriental Integrated Facility Management Pvt Ltd
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .