Loading…
Loading…
Tender Value
₹31.9 Cr
EMD Value
₹31.9 L
Closing Date
3 Sept 2026, 6:10 pm
Chief Executive Officer, GUJSAIL
Development of Heliport and Allied Building Facilities Including E&M Works at Dwarka, Gujarat.
331114
AVN/2026-27/Development of Heliport and Allied Building Facilities Including E&M Works at Dwarka.
Open
Aviation
Works
Ahmedabad
₹17,700
Gujarat State Aviation Infrastructure Company Limited
₹31.9 L
4 Aug 2026
4 Aug 2026
4 Aug 2026
3 Sept 2026
4 Aug 2026
Name of Work: - Development of Heliport and Allied
Building Facilities Including E&M Works at Dwarka,
GOVERNMENT OF GUJARAT
Gujarat State Aviation Infrastructure Company Ltd.
This is a generic SBD to be used for Civil and E&M works. Each user/concern
department needs to examine and put up their particular bidding requirement like;
qualification criteria, contract Data etc., marked at [#] while finalizing their own bidding
Sr. No. Section Description Page No
1 Invitation for Bid (IFB)
2 Section -1 Instructions to Bidders
3 Section -2 Qualification Information
4 Section -3 Conditions of Contract
5 Section -4 Contract Data
6 Section -5 Technical Specification
7 Section -6 Form of Bid
8 Section -7 Bill of Quantities
9 Section -8 Securities and Other Forms
10 Section -9 Drawings
11 Section -10 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The Gujarat State Aviation Infrastructure Company Ltd invites bids for the construction
of works detailed in the table. The bidders may submit bids for any or all of the following
Package Name of work Approximate Bid security Cost of Period of #Class of
No. value of works (Rs.) document completion Registration
(Rs.) excluding /Category of
GST contractor if
01 Development of Heliport at 31,92,89,798/- 31,93,000/- 17,700/- 18 Months AA Class
Dwarka, Gujarat including category
pavement facilities such as FATO,
Parking Aprons, Connecting Special
Taxiways, Perimeter Road, Category
Approach Road, Car Parking and class–I
building facilities such as
Passenger Terminal Building (PTB) (Road) &
cum ATC Tower, Fire Station, AA Class
Electrical Substation, Pump
Room/Underground Tank, Security
Hut, Watch Towers under Phase-1 Category
development. Class-I
2. Prospective/Interested bidder may download the Bid Documents from website
https://tender.nprocure.com free of cost till the Time and Date as mentioned on online NIT at
website https://tender.nprocure.com.
3. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee /
Tender Fee through Demand Draft only of any Schedule Bank payable at Ahmedabad and in
favour of “Gujarat State Aviation Infrastructure Company Ltd”. Once the Bid is received
online, Bid Document / Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid
Security / EMD shall be submitted in electronic format through online (by scanning) while
uploading the bid, this submission shall mean that bid document / tender fee and Bid Security
/ EMD has been received. Accordingly, the offer of only those shall be opened whose Bid
Document / Tender Fee and Bid Security / EMD have been received electronically. However,
for the purpose of realization of Demand Draft, and FDR / Bank Guarantee bidder shall send
the same in original through R.P.A.D. so as to reach to ‘Chief Executive Officer, GUJSAIL
Complex Near SVPI Airport Ahmedabad within 3 Days from the last day of bid submission.
Penaltative action for not submitting Demand Draft / FDR / Bank Guarantee in original to
Executive Engineer / Tender Inviting Authority by bidder shall be initiated.
Bids received online, will be opened on the time, date and place as specified in the online NIT at website
https://tender.nprocure.com in the presence of the bidders or their authorized representatives, who
wish to remain present. If the office happens to be closed on the day of opening of the bids as specified, the
bids will be opened on the next working day at the same time and venue.
4. A pre bid meeting will be held on ……../XX/2026 at 12:00 hrs. (Tentatively) at the office of
GUJSAIL Complex, Nr. Torrent Sub Station, SVPI Airport, Ahmedabad – 380004 to clarify the
issues and to answer questions on any matter that may be raised at that stage as stated in
9.2 of ‘instructions to Bidders’ of the bidding documents.
5. Bid Security (EMD) is equal to 1% of Estimated Amount put to bid / tender and should be
rounded off to the next thousand rupees.
6. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the tender
submission date and time. After the tender submission date and time, the bidder cannot
modify / edit / withdraw their submitted offer in any case. No written or online request in
this regard shall be granted.
B. Offers in physical form will not be accepted in any case.
C. Demand Draft purchased by the other then bidder and issued after the last date of
submission of Bids, will not be considered or accepted.
D. The cost incurred by the contractor for this offer for clarification or attending discussion,
conferences or site visits will not be reimbursed by the Employer or Engineer-in-Charge.
E. Conditional tender shall not be accepted.
F. Any changes, addition, alternation made in the prescribed form attached with tender are
liable to be rejected.
G. Any change in format or conditional Bank Guarantee will not be accepted and the bidder
will be considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the format
given in the checklist /qualification document / tender document.
I. It is mandatory for the bidders to supply each and every information as asked strictly in
electronic format at appropriate places only.
J. Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even if the bidder has been qualified in a similar or larger size of project in the past, it
shall not be deemed to be a ground / reason for not giving required information for this
L. Information supplied for earlier projects shall not be considered while evaluation of this
bid. The Government will not ask for any other information, unless it is found absolutely
necessary by the competent authority.
M. If found necessary, the contractor will be intimated for negotiation.
For the works costing up to 7.5 crore (ROAD), 7.0 crore (BUILDING & BRIDGE) kindly refer to
For the works costing more than 7.5 crore for Road Works and 7.0 crore for Building and
Bridge Works following documents shall be submitted in electronic format only through
online by scanning and the (i) Bid Document Fee / Tender Fee (ii) Bid Security / EMD
should be sent in original to the Tender opening authority through RPAD, so as to reach the
Chief Executive Officer within 3 days from last day of submission of Bid.
(i) Bid Document Fee / Tender Fee
(ii) Bid Security / EMD or Valid EMD Exemption Certificate of Appropriate Class of
Registration of Approved Contractors
(iii) Registration Certificate of Appropriate Class "AA" & Sp. Cat-I (Road) & AA Class Special
Category Class-I (Building)Experience As mentioned in General Experience Criteria.
(iv) Bank Solvency of current calendar year i.e. 2026. (20% of estimated cost)
(vi) Page No. (38) Bank Certificate compulsory.
(vii) Undertaking for Investment and For Validity are compulsory.
(viii) Other Documents, as required as per Tender documents (As per NIT)
(ix) Valid Plant Certificate (Batch Mx Plant) issud by S.E / E.E. Mechanical
INSTRUCTIONS TO
SECTION 1: INSTRUCTIONS TO BIDDERS
TABLE OF CLAUSES
Page No. Page No.
A. General D. Submission of Bids
1. Scope of Bid 8 19. Sealing & Marking of Bids
2. Source of Funds 8 20. Deadline for Submission of
3. Eligible Bidders 8 21. Late Bids
4. Qualification of the Bidder 8 22. Modification and
Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding 12 E. Bid Opening and Evaluation
7. Site Visit 13 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding 14 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding 14 27. Correction of Errors
10. Amendment of Bidding 15 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising the Bid 16 F. Award of Contract
13. Bid Prices 16 31. Award Criteria
14. Currencies of Bid and 17 32. Employer’s Right to Accept
Payment any Bid and to Reject anyor
15. Bid Validity 17 33. Notification of Award and
Signing of Agreement
16. Bid Security 17 34. Performance Security
17. Alternative Proposals By 18 35. Advance Payment and
Bidders Security
18. Format and Signing of Bid 19 36. Dispute Review Expert
37. Correct or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction
of works (as defined in these documents and referred to as ‘the works”)
detailed in the table given in IFB. The bidders may submit bids for any or all
of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the
intended completion date specified in the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their
derivatives (bidder/ tenderer, bid / tender, bidding/ tendering, etc.) are
2. Source of Funds
2.1 The expenditure on this project will be met from the Budget of Govt. of
Gujarat sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification
Information, a statement that the Bidder is neither associated, nor has been
associated, directly or indirectly, with the consultant or any other entity
that has prepared the design, specifications, and other documents for the
Project or being proposed as Project Manager for the Contract. A firm that
has been engaged by the Employer to provide consulting services for the
preparation or supervision of the works, and any of its affiliates, shall not be
eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification
Information, a preliminary description of the proposed work method and
schedule, including drawings and charts, as necessary. The proposed
methodology should include a program of construction backed with
equipment planning and deployment duly supported with broad
calculations and quality assurance procedures proposed to be adopted
justifying their capability of execution and completion of work as per
technical specifications, within stipulated period of completion.
4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on Applicant’s meeting all the following
minimum pass/ fail criteria regarding the Applicant’s general and
particular experience, personnel and equipment capabilities and
financial positions, as demonstrated by the applicant’s responses in
the forms attached to the letter of application (specified requirement
for joint ventures are given under para 4.6 below) Subcontractors
experience and resources shall not be taken in to account in
determining the applicants compliance with the qualifying criteria
To qualify for more than one contract, the applicant must
demonstrate having experience and resources sufficient to meet the
aggregate of the qualification criteria for each contract given in
paragraphs 4.5.4, 4.5.5 and
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year
Following enhancement factors will be used for the costs of works
executed and the financial figure to a common base value for works
completed in India.
Year Financial Year Multiplying factor
Base year of inviting tender 2026-2027
Applicants should indicate actual figures of costs and amount for the
works executed by them without accounting for the above-mentioned
In case the financial figures and value of completed works are in
foreign currency the above enhanced multiplying factors will not be
applied. Instead, the current market exchange rate (State Bank of
India BC Selling rate as on the last date of submission of the bid) will
be applied for the purpose of conversion of the amount in foreign
currency into India rupees.
4.5.3. General Experience
The Applicant shall meet with the following minimum criteria:
(a) Achieved a minimum annual financial turnover (defined as billing for works in
progress and completed in all classes of civil engineering construction works
only) in any one year, over the last five years of the annual value of contract /
contracts applied for.
(b) Experience in successfully completing at least one contract of “Rigid/ Flexible
Pavement works in Airfield, National Highways / Expressways, Harbor pavements
State Highways” on Item rate / Percentage rate tender mode basis during last
(Five) years ending select day of month previous to the one in which tenders are
invited, at least 40 percent of the value of proposed contract within the last five
(Road & Utility Work value for This Project is 14,66,88,240.70/-) Their 40 percent
would be 5,86,75,297)
(c) Experience in completion of at least one contract of “Construction of Administrative
Building or any other Government Building Works” on Item rate / Percentage rate
tender mode basis during last 05 (Five) years ending select day of month previous to
the one in which tenders are invited, at least 40 percent of the value of proposed
contract within the last five years.”
(Main Building and Electric Work for This Project is 17,26,01,557.33/-) Their
Percent would be 6,90,40,623)
(Both Criteria Mandatory)
The works may have been executed by the applicant as prime contractor or as a
member of a joint venture or as a nominated sub-contractor. As subcontractor,
he should have acquired the experience of execution of all major items of works
under the proposed contract. In case a project has been executed by a joint
venture, weight towards experience of the project would be given to each joint
venture in proportion to their financial participation in the joint venture.
Substantially completed works means those works which are at least 90 %
completed as on the date of submission (i.e. gross value of work done up to the
last date of submission is 90 % or more of the original contract price) and
continuing satisfactorily.
For these, a certificate from the employers shall be submitted along with the
application incorporating clearly the name of the work, contract value, billing
amount, date of commencement of works, satisfactory performance of the.
4.5.4. Personnel Capabilities.
Availability for his work of personnel with adequate experience as
required; as per Appendix.
4.5.5. Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum
suggested major equipment to attain the completion of works in
accordance with the prescribed construction schedule are shown in
The bidders should, however, undertake their own studies and furnish
with their bid, a detailed construction planning and methodology
supported with layout and necessary drawings and calculations to
allow the employer to review their proposals. The numbers, types and
capacities of each plant/equipment shall be shown in the proposals
along with the cycle time for each operation for the given production
capacity to match the requirements.
4.5.6. Financial Position
The Applicant should give undertaking that he has access to, or has
available, liquid assets (aggregate of working capital, cash in hand and
uncommitted bank guarantees) and / or credit facilities up to
percent of the value of the contract / contracts applied.
4.5.7. The audited balance sheets for the last five years should be submitted,
which must demonstrate the soundness of the applicant’s financial
position, showing long – term profitability including an estimated
financial projection for the next two years. If necessary, the employer
will make inquiries with the applicant’s bankers.
4.5.8. Litigation History
The Applicant should provide accurate information on any litigation or
arbitration resulting from contracts completed or under execution by him
over the last five years. A consistent history of awards against the Applicant
or any partner of a joint venture may result in failure of the applicant.
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be
disqualified if they have:
Made misleading or false representation in the forms, statements
submitted and / or Record of poor performance such as abandoning the
work, rescinding of contract for which the reasons are attributable to the
non – performance of the contractor; consistent history of litigation
awarded against the applicant or financial failure due to bankruptcy. The
rescinding of contract of a joint venture on account of reasons other than
non – performance, such as Most Experienced partner of joint venture
pulling out, court directions leading to breaking up of a joint venture before
the start of work, which are not attributable to the poor performance of the
contractor will, however, not affect the qualification of the individual
#4.6 JOINT VENTURE: NOT APPLICABLE (Maximum 3 Members i.e. 1 Lead
& 2 Others) (Applicable only for estimated project cost of 50 Crore and
4.6.1. Joint ventures must comply with the following requirements:
(a) Following are the minimum qualification requirements:
(i) The lead partner shall meet not less than 50 percent of all criteria
given in para 4.5.3 & 4.5. above. The joint venture must collectively
satisfy the criteria of para 4.5.3 & 4.5.6 above. The experience of the
other joint venture partners shall be considered if it is not less than
percent of the qualifying criteria in para 4.5.3 & 4.5.6 above.
(ii) Individually each member must satisfy the requirements of para 4.5.7 &
(b) Bid shall be signed so as to legally bind all partners, jointly and severally,
and shall be submitted with a copy of the joint venture agreement
providing the joint and several liabilities with respect to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its
partners individually or as a partner in any other joint venture. In case
dissolution of a joint venture, each one of the constituent firms may qualify
if they meet all the qualification requirements, subject to the written
approval of the Employer.
4.7. Bid Capacity
Applicants who meet the minimum qualification criteria will be qualified
only if their available bid capacity at the expected time of bidding is more
than the total estimated cost of the works. The available bid capacity will be
calculated as under:
Assessed Available Bid Capacity = ( A*N*2-B), where
A = Maximum value of work executed in any one year during the last five
years (updated to the price level of the year indicated in appendix)
taking into account the completed as well as works in Progress.
B = Value at current price level of the existing commitments and ongoing
works to be completed during the next ____(period of
completion of work for which bids are invited); and
N= Number of years prescribed for completion of the works for which
the bids are invited.
Note :- In Case of joint venture, the available bid capacity will be
applied for each partner to the extent of his proposed
participation in the execution of the work.
4.8 Even though the bidders meet the above qualifying criteria, they are
subject to be disqualified if they have:
- Made misleading or false representation in the forms, statements and
Attachments the submitted in proof the qualification requirements; and
- Record of poor performance such as abandoning the works, not properly
completing the contract, inordinate delay in completion, litigation
history, or financial failures etc.; and/ or
- Participated in the previous bidding for the same work and had quoted
unreasonably high bid prices and could not furnish rational justification
to the employer.
- Have Been blacklisted or placed In the Negative List by any Govt.
Organization In the past 5 years from the date of bid submission.
5. One bid per bidder
5.1. Each bidder shall submit only one bid for one package. A bidder who
submits or participates in more than one bid (other than as a subcontractor
or in cases of alternatives that have been permitted or requested) will cause
all the proposals with the bidder’s participation to be disqualified.
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation and
submission of his Bid, and the Employer will in no case be responsible and
liable for those costs.
7.1. The Bidder, at the Bidder’s own responsibility and risk, is encouraged to visit
and examine the Site of work and its surroundings and obtain all
information that may be necessary for preparing the Bid and entering into a
contract for construction of the Works. The costs of visiting the site shall be
at Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below,
and addenda issued in accordance with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2. Volumes I, II, III and IV are available online and documents to be furnished
by the bidder in compliance to Section 2 will be prepared by him and
furnished as Volume-V in two parts (refer clause 12).
8.3. The bidder is expected to examine carefully all instructions, conditions of
contract, contract data, forms, terms, technical specifications, bill of
quantities, forms, Annexes and drawings in the Bid Document. Failure to
comply with the requirements of Bid Documents shall be at the bidder’s
own risk. Pursuant to clause 26 hereof, bids which are not substantially
responsive to the requirements of the Bid Documents shall be rejected.
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents
may notify the Employer in writing or through E-mail at the Employer’s
address indicated in the invitation to bid. The Employer will respond to
any request for clarification which he received earlier than 15 days prior
to the deadline for submission of bids. Employer’s response will be
published on website including a description of the enquiry but without
identifying its source.
9.2. Pre-bid meeting
9.2.1. The bidder or his official representative is invited to attend a pre-bid
meeting which will take place at the address, venue, time and date as
indicated in the appendix.
9.2.2. The purpose of the meeting will be to clarify issues and to answer
questions on any matter that may be raised at that stage.
9.2.3. The bidder shall be required to submit any questions in writing or e-mail
to reach the Employer not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying
the source of enquiry) and the responses given will be published without
delay on the tender website i.e. tender.nprocure.com. Any modification of
the bidding documents listed in sub-Clause 8.1 which may become
necessary as a result of the pre-bid meeting shall be made by the
Employer exclusively through the issue of an Addendum pursuant to
Clause 10 and not through the minutes of the pre-bid meeting.
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for
disqualification of a bidder.
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the
bidding documents by issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The
Employer will assume no responsibility for the same.
10.3. To give prospective bidders reasonable time in which to take an
addendum into account in preparing their bids, the Employer may, at his
discretion, extend as necessary the deadline for submission of bids, in
accordance with Sub-Clause 20.2 below.
C. PREPARATION OF BIDS
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents Comprising the Bid
12.1. The bid to be submitted by the bidder as Volume V of the bid document
(refer Clause 8.1) shall be in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
(i) Bid Security in the form specified in Section
(ii) Qualification Information and supporting documents as specified in
(iii) Certificates, undertakings, affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 of these instructions
(v) Undertaking that the bid shall remain valid for the period specified
Part II shall be named “Financial Bid” and shall comprise
(i) Form of Bid as specified in Section
(ii) Priced Bill of Quantities for items specified in Section
12.2. The Bidder shall submit the details / information pertaining to each part
i.e. technical as well as financial and must be submitted online only.
12.3. Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
Invitation for Bids (IFB)
1 Instruction to Bidders Volume I
3 Conditions of Contract
4 Contract Data
5 Specifications Volume II
9 Drawings Volume IV
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1,
based on the priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line-item total (both in figures
and words) for all items of the Works described in the Bill of Quantities
along with total bid price.
(Both in figures and words). Items for which no rate or price is entered into
by the bidder will not be paid for by the Bill of Quantities.
13.3 All duties, taxes, and other levies except GST payable by the contractor
under the contract, or for any other cause shall be included in the rates,
prices and total Bid Price submitted by the Bidder. (GST will be paid extra)
13.5 The rates and prices quoted by the bidder are subject to adjustment during
the performance of the Contract in accordance with the provisions of
Clause 47 of the Condition of Contract (Irrespective of the time limit and
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian
Rupees. All payments shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the
deadline date forbid submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the
Employer may request that the bidders may extend the period of validity
for a specified period. A bidder may refuse the request without forfeiting
his bid security. A bidder agreeing to the request will not be required or
permitted to modify his bid, but will be required to extend the validity of his
security for a period of the extension, and in compliance with Clause 16 in
16. Bid Security
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as
shown in column 4 of the table of IFB for this particular work. This Bid
security shall be infavor of Employer as named in Appendix and may be in
one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in
Volume III. (Bank Guarantee is applicable only for Bid Estimated Amount
of 01 Crore and above) and Bank Guarantee of Schedule and Private
Banks shall be considered as per GoG Finance Department’s Circular
NoFD/MSM/e-file/4/2023/4020/DMO Date 11/04/2024 or as per their
latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign
Bank approved by the Reserve Bank of India.
# A Valid Bid Security / EMD Exemption Certificate issued by (1) Road & Building
Department or (2) Narmada Water Resources, Water Supply and Kalpsar
Department of Govt of Gujarat. Exemption Certificate is applicable only when
Registration Certificate of Appropriate Class and Category of Approved
Contractors is required as eligible criteria of bidder.
16.2. Bank guarantees (and other instruments having fixed validity) issued as
surety for the bid shall be valid for 45 days beyond the validity of the bid
i.e. total validity of 120+45 = 165 Days.
16.3. Any bid not accompanied by an acceptable Bid Security and not secured
as indicated in Sub-Clauses 16.1 and 16.2 above shall be rejected by the
Employer as non-responsive.
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of
the end of the bid validity period specified in Sub-Clause 15.1.
16.5 The Bid Security of the successful bidder will be discharged when the
bidder has signed the Agreement and furnished the required Performance
16.6. The bid Security may be forfeited:
(a) If the Bidder withdraws the bid after Bid opening during the period of
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He
will be intimated maximum three times within the validity period for
negotiation, If contractor does not respond in time, his Bid Security
(EMD) will be forfeited, and his tender will be rejected. Punitive
action will be taken on such contractors. (As per GoG R&B Dept’s Gr.
17. Alternative Proposals by Bidders
17.1. Bidders shall submit offers that fully comply with the requirements of the
bidding documents, including the conditions of contract (including
mobilization advance or time for completion), basic technical design as
indicated in the drawing and specifications. Conditional offers or alternative
offers will not be considered further in the process of tender evaluation.
18. Format and Signing of Bid
18.1. The Bidder shall prepare documents comprising the bid as described in
Clause 12 of these Instructions to bidder as the “Technical Bid “and
“Financial Bid” in separate parts to be uploaded.
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1. Complete Bids must be received online by the Employer at the tender
website specified above not later than the date indicated in appendix.
20.2. The Employer may extend the deadline for submission of bids by issuing an
amendment in accordance with Clause 10, in which case all right and
obligation of the Employer and the bidders previously subject to the
original deadline will then be subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1. Bidders may modify or withdraw their bids online before the deadline
prescribed in Clause 20 or pursuant to Clause
22.3. No bid shall be modified or withdrawn after the deadline for submission of
22.4. Withdrawal or modification of a bid between the deadline for submission
of bids and the expiration of the original period of bid validity specified in
Clause 15.1 above or as extended pursuant to Clause 15.2 may result in
the forfeiture of the Bid security pursuant to Clause
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made
pursuant to Clause 22, in the presence of the Bidders or their
representatives who choose to attend at time, date and the place specified
in Appendix in the manner specified in Clauses 20 and 23.3, In the event of
the specified date of Bid opening being declared a holiday for the Employer,
the Bids will be opened at the appointed time and location on the next
23.3. The “Technical Bid” shall be opened. The amount, form and validity of the
bid security furnished with each bid will be announced. If the bid security
furnished does not conform to the amount and validity period as specified
in the invitation for bid (ref. Column 4 and paragraph 3), and has not been
furnished in the form specified in Clause 16, the technical bid will not be
23.4. (i) Subject to confirmation of the bid security by the issuing Bank, the
bids accompanied with valid bid security will be taken up for
evaluation with respect to the Qualification information and other
information furnished in part I of the bid pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his
Qualification Documents with respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the
clarification letter.
(iv) Immediately (usually within 3 or 4 days), on receipt of these
clarifications the Evaluation Committee will finalize the list of
responsive bidders whose financial bids are eligible for
23.6 At the time of opening of “Financial Bid”, the names of the bidders were
found responsive in accordance with Clause 23.4(iv) will be announced. The
bids of only these bidders will be opened. The responsive Bidders’ names,
the Bid prices, the total amount of each bid, any discount and such other
the Bid prices, the total amount of each bid, any discount and such other
details as the Employer may consider appropriate, will be announced by
the Employer at the opening.
23.7 The time of opening of “Financial Bid”, the names of the bidders were
found responsive in accordance with Clause 23.4(iv) will be announced. The
bids of only these bidders will be opened. The responsive Bidders’ names,
the Bid prices, the total amount of each bid, any discount, and such other
the Bid prices, the total amount of each bid, any discount, and such other
details as the Employer may consider appropriate, will be announced by
the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening
of the “Financial Bid” shall be in order of Estimated amount of Bids from
highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the
information disclosed to those present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and
comparison of Bids and recommendations for the award of a contract shall
not be disclosed to Bidders or any other persons not officially concerned
with such process until the award to the successful Bidder has been
announced. Any effort by Bidder to influence the Employer’s processing of
Bids or award decisions may result in the rejection of his Bid.
25. Clarification of Financial Bids
25.1. To assist in the examination, evaluation, and comparison of Bids, the
Employer may, at his discretion, ask any Bidder for clarification of his Bid,
including breakdowns of unit rates. The request for clarification and the
response shall be in writing or by e- mail, but no change in the price or
substances of the Bid shall be sought, offered, or permitted except as
required to confirm the correction of arithmetic errors discovered by the
Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any
matter relating to his Bid opening to the contract is awarded. If the Bidder
wishes to bring additional information to the notice of the Employer, it
should do so in writing.
25.2. Any effort by the Bidder to influence the Employer in the Employer's bid
evaluation, bid comparison or contract award decision may result in the
rejection of the Bidders’bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detailed evaluation of "Technical Bid", the Employer will
determine whether each Bid (a) meets the eligibility criteria defined in
Clause 3 and 4; (b) has been properly signed; (c) is accompanied by the
required securities and; (d) is substantially responsive to the requirements
of the Bidding document. During the detailed evaluation of the “Financial
Bid”, the responsiveness of the bids will be further determined with respect
to the remaining bid conditions, i.e., priced bill of quantities, technical
specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the
terms, conditions and specifications of bidding documents, without material
deviation or reservation. A material deviation or reservation is one (a) which
affects in any substantial way the scope, quality, or performance of the
Works; (b) which limits in any substantial way, inconsistent with the Bidding
documents, the Employer’s rights or the Bidder’s obligations under the
Contract; or (c) whose rectification would affect unfairly the competitive
position of other Bidders presenting substantially responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the
Employer, and may not subsequently be made responsive by correction or
withdrawal of the non-conforming deviation or reservation.
29. Evaluation and Comparison of Financial Bids
29.1. The Employer will evaluate and compare only the Bids determined to be
substantially responsive in accordance with Sub-Clause 26.2.
29.3. The Employer reserves the right to accept or reject any variation or
deviation. Variation and deviations and other factors, which are in excess
of the requirements of the Bidding documents or otherwise result in
unsolicited benefits for the Employer, shall not be taken in to account in Bid
29.4. The estimated effect of the price adjustment conditions under Clause 47 of
the Conditions of Contact, during the period of implementation of the
Contract, will not be taken in to account in Bid evaluation.
29.5. If the Bid of the successful Bidder is seriously unbalanced in relation to the
Engineer’s estimate of the cost of work to be performed under the contract
the Employer may require the Bidder to produce detailed consistency of
those prices with the construction methods and schedule proposed. After
evaluation of the price analyses, the Employer may require that the amount
of the performance security set forth in Clause 34 be increased at the
expense of the successful /bidder to a level sufficient to protect the
Employer against financial loss in the event of default of the successful
Bidder under the Contract.
29.6. A bid which contains several items in the bill of Quantities which are
unrealistically priced low, and which cannot be substantiated satisfactorily
by the bidder may be rejected as non-responsive.
F. AWARD OF CONTRACT
31. Award Criteria
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder
whose Bid has been determined.
(i) to be substantially responsive to the Bidding documents and who
has offered the lowest evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid
price which is the lowest evaluation in any of the packages opened
earlier than the one consideration.
In no case, the contract shall be awarded to any bidder whose available bid
capacity is less than the evaluated bid price, even if the said bid is the
lowest evaluated bid. The contract will in such cases be awarded to the next
lowest bidder at his evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1. Notwithstanding Clause 31, the Employer reserves the right to accept or
reject any Bid, and to cancel the Bidding process and reject all Bids, at any
time prior to the award of contract, without thereby incurring any liability
to the affected bidder or Bidder or any obligation to inform the affected
Bidder or Bidders of the grounds for the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1. The Bidder whose Bid has been accepted will be notified of the award by
the Employer prior to expiration of the Bid validity period by cable, telex or
facsimile confirmed by registered letter. This letter (hereinafter and in the
condition of contract called the “Letter of Acceptance”) will state the sum
that the Employer will pay the Contractor in consideration of the execution,
completion, and maintenance of the Works by the Contractor as prescribed
by the Contract (hereinafter and in the Contract called the “Contract
33.2 The notification of award will constitute the formation of the contract,
subject only to the furnishing of performance security in accordance with
the provisions of Clause.
33.3. The Agreement will incorporate all agreements between the Employer and
the successful Bidder. It will be signed by the Employer and to the
successful Bidder, within 28 days following the notification of award along
with the Letter of Acceptance. Within 21 days of receipt, the successful
Bidder will sign the Agreement and deliver it to the Employer.
33.4. Upon furnishing by the successful Bidder of the Performance Security, the
Employer will promptly notify the other Bidders that their Bids have been
34. Performance Security
(A) Within 10 (Ten) days of receipt of Letter of Acceptance, the
successful Bidder shall furnish to the Employer an irrevocable and
unconditional guarantee from a Bank in the form set forth in
Section 8 (the “Performance Security”) for an amount equal to 5%
(five percent) of its Contract Price. In case of bids mentioned
below, the successful Bidder, along with the Performance Security,
shall also furnish to the Authority an irrevocable and
unconditional guarantee from a Bank in the same form given at
Section 8 towards an Additional Performance Security (The
“Additional Performance Security”) for an amount calculated as
(a) If the Contract Price offered by the Selected Bidder is lower
than 10% but upto 20% of the Estimated Project Cost, then the
Additional Performance Security shall be calculated @ 20% of
the difference in the (i) Estimated Project Cost (as mentioned in
Bid Document) - Minus 10% of the Estimated Project Cost and
(ii) Contract Price offered by the selected Bidder.
(b) If the Contract Price offered by the Selected Bidder is lower
than 20% of the Estimated Project Cost, then the Additional
Performance Security shall be calculated @ 30% of the
difference in the (i) Estimated Project Cost (as mentioned in Bid
Document) - Minus 10% of the Estimated Project Cost and (ii)
Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of
Performance Security.
(B) The Performance Security shall be valid beyond 60 (Sixty) days from
the stipulated date of completion of the project and the Additional
Performance Security shall be valid beyond 28 (twenty-eight) days of
Project Completion Date.
Performance Security shall become refundable/releasable within
15 days after certified project completion date subject to
Fulfillment of contractual obligation and settlement of all dues and
34.1. If the performance security is provided by the successful Bidder in the
form of a Bank Guarantee, it shall be issued either (a) at the Bidder’s
option, by a Nationalized/Scheduled Indian bank or (b) by a foreign bank
located in India and acceptable to the Employer. As per GoG Finance
Department’s Circular No. FD/ MSM/e-file/4/2023/0057/D.M.O. Date
21/04/2023 or as per their latest amendment.
34.2. Failure of the successful Bidder to comply with the requirement of Sub-
Clause 34.1 shall constitute sufficient grounds for cancellation of the
award and forfeiture of the Bid Security.
35 Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as
stipulated in the Conditions of Contract, subject to maximum amount, as
stated in the Contract Data.
37. Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder
recommended for award has engaged in corrupt or fraudulent practices in
completing for the contract in question and will declare the firm ineligible,
either indefinitely or for a stated period of time, to be awarded a contract
with National Highways Authority of India/ State PWD and any other
agencies, if it at any time determines that the firm has engaged in corrupt
or fraudulent practices in completing for the contractor, or in execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause
59.2 of the Conditions of Contract.
APPENDIX TO ITB
Clause Reference with respect to Section –I
1. The Name of the Employer is Gujarat State [ Cl.1.1]
Aviation Infrastructure Company Ltd
2. The last five years.
3. This Annual Financial Turnover Amount is Rs. [Cl.4.5.3 (a)]
4. Value of Work is Rs. 31,92,89,798.00/-
6. The cost of electric work is Rs. 6,44,22,245.41/-
7. The cost of Utilities and Site Development is
8. Liquid assets and/or availability of credit facilities
is Rs.7,98,22,450/- (25% of Contract amount) [Cl. 4.5.2]
9. Price level of the financial year 2026-2027 [Cl. 9.2.1]
10. The pre-bid meeting will take place at Ahmedabad.
(As Mentioned Above)
11. The technical Bid will be opened at the GUJSAIL
Complex, SVPI Airport, Ahmedabad. on dt.
12. Address of the Employer : GUJSAIL Complex, SVPI
Airport, Ahmedabad
Deleted [Cl. 20.1 & 20.2]
14. The bid should be submitted at the latest by as
stated on online NIT [Cl. 23.1 ]
15. The bid will be opened at GUJSAIL Complex, SVPI
Airport, Ahmedabad as stated on online NIT.
16. The Bank Draft in favor of Gujarat State Aviation
Infrastructure Company Limited Payable at
18. Escalation factors (for the cost of works executed [Cl.4.5.2]
and financial figure to a common base value) for
works completed
Year Financial Year Multiplying factor
Base year of inviting tender 2026- 2027
LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON
[Reference CL. 4.5.5]
The contractors shall also give a list of machinery in his possession and which
they propose to use on the work.
Sr. Plant or Location Age of Make Capacity Approximate Remark
No. Machinery Machinery Value
List of Key Personnel to be deployed on Contract
Work (Reference Cl. 4.5.4)
# Employment of a qualified site Engineer by the Contractor.
The Contractor shall employ full-time technically qualified staff during the
execution of this work as under: -
1. Two graduate Civil Engineers and three diploma Civil Engineers when cost of
the work to be executed is more than Rs.50 lakhs.
2. One Master/Graduate Civil Engineer as a Project manager having work
experience of 12 to 15 years (7+ Year Experience in Road Work)
3. One graduate Civil Engineers as a Material and Quality Control Engineer
having work experience of 5 Years Exp. / 10 Years Exp.
4. One Plant Engineer from B.E/Diploma Mechanical having 05 Years’
5. One graduate & two Diploma, Civil Engineers, when the cost of the work to
be executed is more than Rs.15 lakhs but less than Rs.50 lakhs.
6. Minimum one Diploma Civil Engineer when the cost of work is less than Rs.15
lakhs but more than Rs.5 lakhs.
7. Minimum two Diploma Civil Engineers for the work when the cost of work to
be executed is less than Rs. 5 lakhs. The Engineer so employed for the
Government work must have sufficient experience to handle the work
independently. Such an Engineer shall have to stay at the site of work, and he
shall not be entrusted with other duty except this work.
In case the contractor or partner of the contractor firm is a Civil Graduate
Engineer, Employment of a separate Engineer will not be necessary provided
that the Engineer partner himself attends the execution of the work on the
Within 15 days of issue of work-order the Contractor will have to furnish to
the Chief Executive Officer-in-charge of the work the Name, Qualifications,
copy of marksheet, Colour Photograph and the appointment order issued
such engineers engaged for this contract work. If 15 days after issue of work
order such designated Site Engineers do not resume or do not remain present
on site of work, the recovery at the rate of Rs. 15,000-00 per month per
Engineer will be made from the bills/deposit/dues of the contractor. Such
recovery shall be non-refundable.
QUALIFICATION INFORMATION
AND OTHER FORMS
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for
the purpose of post qualification as provided in Clause 4 of the Instruction to
Bidders. This information will not be incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder(Attach Copy)
Place of registration
Principal place of business
Power of attorney of signatory of Bid(Attach)
1.2 Total value of Civil engineering constructions 2025-2026
Work performed in the last five years 2024-2025
(in Rs. Lakhs) 2023-2024
1.3.1 Work performed as prime contractor, work performed in the past as a
nominated sub-contractor will also be considered the sub-contract
involved execution of all main items of work described in the bid
documents, provided further that all other qualification criteria are satisfied
(in the same name) on works of a similar nature over the last five years**
and in current year before the submission of the bid.
Project Name of Description Contract Value of Date Stipulated Actual date Remark
Name the of work No. contract of period of of explaining
Employer (Rs. issue completion completion* reasons for
Crore) of delay &
order Completed
*Attach certificate(s) from the Engineer(s)in-charge
** Immediately preceding the financial year in which bids are received.
#1.3.2 Quantities of work executed as prime contractor, work performed, in the
past as a nominated sub-contractor, will also be considered provided the
sub-contract involved execution of all main items of work described in the
bid document, provided, further that all other qualification criteria are
called (in the same name and style) in the last five years** and in current
year before the submission of the bid.
Year Name Name of Quantity of work performed (Cum/MT) Remarks*
of the the Cement Masonry Earth Bituminous (indicate
work Employer Concrete Works Work contract Ref)
1.4 Information on Bid Capacity (works for which bids have been submitted
and works which are yet to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Description Place Contract Name & Value Stipulated Value of Anticipated
of works & No. Address Contract Period of Works* of
State of (Rs. Cr) Completion remaining completion
*Attach certificate (s) from the Engineer(s) in-charge
** Immediately preceding the financial year in which bids are received.
1.5 Availability of key items of Contractors Equipment for carrying out the
works (Ref. Clause 4.5.5). The Bidder should list all the information
requested below.
Item of Requirement Availability Proposals Remarks
Equipment No. Capacity Owned/ Nos/. Age/ (from whom
Leased to be Capacity Conditions tobe
procured purchased
1.6 Qualifications and experience of key personnel required for administration
and execution of the contract. Attach biographical data. Refer also to Sub
Clause 9.1 of the Conditions of Contract.
Position Name Qualification Year of Year of
Experience experience in
(General) the proposed
Project Manager
1.7 Proposed sub-contract and firms involved
Sections of the Value of Sub- Sub-Contractor Experience in
works Contractor (Name & similar work
Attach copies of certificates on possession of valid license for executing water supply/
sanitary work/ building electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss
statements, auditors’ reports (in case of companies/corporations), etc. List
them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification
requirements: cash in hand, lines of credit, etc. List them below and attach
copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders
bankers who may provide references if contacted by the Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party Employer Cause of Amount Remarks
(ies) Dispute Involved showing
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the
instruction to Bidders. (Name of Consultant engaged for project
1.13 Proposed work method and schedule. The Bidder should attach
descriptions, drawings and charts as necessary to comply with the
requirements of the Bidding documents. (Refer ITB Clause 4.1)
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
* Fill the name of Consultant
SAMPLE FORMAT FOR EVIDENCE OF
ACCESS TO OR AVAILABILITY OF CREDIT
(CLAUSE 4.5.6 OF ITB)
BANK CERTIFICATE
is a reputed company with a good financial standing.
If the contract for the work, namely
awarded to the above firm, we shall be able to provide overdraft/credit facilities to
their working capital requirements for executing the above during the contract
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the
required attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
_ have not abandoned
any work of Government of Gujarat/Government of India/any Board or
Corporation under Government of Gujarat/Government of India nor any
contract awarded to us for such works have been rescinded, during last
five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person,
firm or corporation to furnish pertinent information deemed necessary
and requested by the Department to verify this statement or regarding
any (our) competence and general reputation.
4. The Undersigned understands and agrees that further qualifying
information may be requested, and agrees to furnish any such
information at the request of the Department/ Project implementing
(Signed by an Authorized Officer of the
Title of Officer
I, the undersigned do hereby undertake that our firm M/s
__________________________________would invest a minimum cash up to 25%
of the value of the work during implementation of the contract.
(Signed by an Authorized officer of the firm)
Title of officer
CONDITIONS OF CONTRACT
Conditions of Contract
Table of Contents
A General Page D. Cost Control Page
1 Definitions 43 37 Bill of Quantities
2 Interpretation 44 38 Changes in the Quantities
3 Language and Law 45 39 Variations
4 Engineer’s Decisions 45 40 Payments for Variations
5 Delegations 45 41 Cash Flow Forecasts
6 Communications 45 42 Payment Certificates
7 Sub-Contractors 45 43 Payments
8 Other Contractors 46 44 Compensations Events
9 Personnel 46 45 Tax
10 Employer’s & Contractor Risk 46 46 Currencies
11 Employers Risks 46 47 Price Adjustment
12 Contractor’s Risk 46 48 Retention
13 Insurance 47 49 Liquidated damages
14 Site Investigations Reports 47 50 Bonus
15 Queries about the Contract 47 51 Advance Payment
16 Contractors to Construct the 47 52 Securities
17 The Works to be Completed by 48 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 48 54 Cost of Repair
20 Discoveries 48 E. Finishing the Contract
21 Possession of the Site 48 55 Completion
22 Access to the Site 49 56 Taking Over
23 Instructions 49 57 Final Account
24 Disputes 49 58 Operating and Maintenance
25 Procedure for Disputes
26 Deleted 50 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 50 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted 51 F. Special Conditions of Contract
30 Delays Ordered by The 51 63 Labour
31 Management Meetings 51 64 Compliance with labour
32 Early Warning 51 65 Arbitration
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the
Conditions of Contract but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities
forming part of the Bid
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified
by the Engineer in accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to
execute, complete and maintain the Works till the completion of Defects
Liability Period. It consists of the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which
comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the
Work has been accepted by the Employer.
The Contractor’s Bid is the completed Bidding document submitted by the
Contractor to the Employer and includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and
calculated from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the
The Engineer is the person named in the Contract Data (or any other
competent person appointed and notified to the contractor to act in
replacement of the Engineer) who is responsible for supervising the
Contractor, administering the Contract, certifying payments due to the
Contractor, issuing and valuing Variations to the Contract, awarding
extensions of time, and valuing the Compensations Events.
Equipment is Contractor’s machinery and vehicles brought temporarily to
the site to construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s
Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is
specified in the Contract Data. The Intended Completion Date may be
revised only by the Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor
for incorporation in the works.
Plant is any integral part of the work which is to have mechanical,
electrical, electronic or chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding
documents and are factual interpretive reports about the surface and
subsurface conditions at the site.
Specifications means the Specifications of the works included in the
Contract and any modification or addition made or approved by the
The Start Date is given in the Contract Data. It is the date when the
Contractor shall commence execution of the works. It does not necessarily
coincide with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with
the Contractor to carry out a part of the work in the Contract which
includes work on the Site.
Temporary Works are works designed, constructed, installed, and
removed by the Contractor which are needed for construction or
installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct,
install, and turn over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means
plural, male also means female or neuter and the other way around.
Headings have no significance. Words have their normal meaning
under the language of the Contract unless specifically defined. The
Engineer will provide instructions clarifying queries about Conditions
2.2 If sectional completion is specified in the Contract Data, references
in the Conditions of Contract to the Works, the Completion date,
and Intended Completion Date apply to any Section of the Works
(other than references to the Completion Date and Intended
Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the
following order of priority
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming
part of the Contract.
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are
stated in the Contract Data.
4. Engineers’ Decisions
4.1 Except where otherwise specifically stated, the Engineer will
decide contractual matters between the Employer and the
Contractor in the role representing the Employer.
5.1 The Engineer may delegate any of his duties and responsibilities to
other people after notifying the Contractor and may cancel any
delegation after notifying the Contractor.
6. Communications
6.1 Communications between parties which are referred to in the
conditions are effective only when in writing. A notice shall be
effective only when it is delivered (in terms of Indian Contract Act).
7. Sub-Contracting
7.1 The Contractor may subcontract any portion of work, up to a limit
specified in contract data, with the approval of the engineer but may
not assign the Contract without the approval of the Employer in
writing. Subcontracting shall not alter the Contractor’s obligations.
Sub-contracting of supply or specific items of work is not allowed.
7.2 The sub-contractor must be registered in appropriate class and
category for the part of work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other
contractors, public authorities, utilities and the Employer between
the dates given in the Schedule of other Contractor. The Contractors
shall as refer to in the Contract Data, also provide facilities and
services for them as described in the Schedule. The employer may
modify the schedule of other contractors and shall notify the
contractor of any such modifications.
9.1 The Contractor shall employ the key personnel named in the
Schedule of Key Personnel as referred to in the Contract Data to
carry out the functions stated in the Schedule or other personnel
approved by the Engineer. The Engineer will approve any proposed
replacement of key personnel only if their qualifications, abilities,
and relevant experience are substantially equal to or better than
those of the personnel listed in the Schedule.
9.2 If the engineer asks the Contractor to remove a person who is a
member of the Contractor Staff or his work force stating the reasons
the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the work in the
10. Employer’s and Contractors Risks
10.1 The Employer carries the risk which these Contract states are
Employer’s risks, and the Contractor carries the risks which these
Contracts states are Contractor’s risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in
so far as they directly affect the execution of the Works, the risks of
war, hostilities, invasion, act of foreign enemies, rebellion,
revolution, insurrection or military or usurped power, civil war, riot
commotion or disorder (unless restricted to the Contractor’s
employees), and contamination from any nuclear fuel or nuclear
waste or radioactive toxic explosive.
12. Contractor’s Risks
12.1 All risks of loss of or damages to physical property and of personal
injury and death which arise during and in consequence of the
performance of the Contract other than the excepted risks are the
responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and
the Contractor, insurance cover from the Start date to the end of
the Defects Liability Period, in the amounts and deductibles stated
in the Contract data for the following events which are due to the
Contractor’s risks:
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant,
Materials andEquipment) in connection with the Contract;
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the
Contractor to the Engineer for the Engineer’s approval before the
Start Date. All such insurance shall provide for compensation to be
payable in the types and proportions of currencies required to
rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and
certificates required, the Employer may affect the insurance which
the Contractor should have provided and recover the premiums the
Employer has paid from payments otherwise due to the Contractor
or, if no payment is due, the payment of the premiums shall be a
13.4 Alterations to the terms of an insurance shall not be made without
the approval of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site
Investigation reports referred to in the Contract Data, supplemented
by any information available to the Bidder.
15. Queries about the Contract data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance
with the specification and Drawings.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start
Date and shall carry out the Works in accordance with the program
submitted by the Contractor, as updated with the approval of the
Engineer, and complete them by the Intended Completion date.
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing
the proposed Temporary works to the Engineer, who is to approve
them if they comply with the Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility
for design of the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of
the Temporary works where required.
18.5 All Drawings prepared by the Contractors for the execution of the
temporary or permanent work are subject to prior approval by the
Engineer before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the
20. Discoveries
20.1 Anything of historical or other interest or of significant value
unexpectedly discovered on the site is the property of the Employer.
The contractor is to notify the engineer of such discoveries and carry
out the Engineer’s instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the
Contractor. If possession of a part is not given by the date stated in
the Contract Data the Employer is deemed to have delayed the start
of the relevant activities and this will be a Compensation Event.
21.2 If within 25% of the time limit of the project, 80% of possession of
the site is not handed over to the Contractor, then contractor/
Employer may fore-close the contract. Contractor/Employer has to
foreclose the work within 30 days after lapse of 25%-time limit and
after 30 days foreclosure option will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized
by the Engineer access to the Site, to any place where work in
connection with the Contract is being carried out or is intended to
be carried out and to any place where materials or plants are being
manufactured/ fabricated/ assembled for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer
pertaining to works which comply with the applicable laws where
the site is located.
23.2 The Contractor shall permit the Employer to inspect the
Contractor’s accounts and records relating to the performance of
the Contractor and to have them audited by auditors appointed by
the Employer, if so required by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer
was either outside the authority given to the Engineer by the Contract
or that the decision was wrongly taken, the decision shall be referred
to Managing Director, GUJSAIL (Higher Authority) within 14 days of
the notification of the Engineer's decision. If the issue is not resolved,
any party can refer the matter for conciliation within 15 days from the
decision given by the Managing Director, GUJSAIL.
(a) For the work up to Rs.100 Cr., if any of the parties is not
satisfied with the decision of the Managing Director, GUJSAIL,
both the parties have to refer to the Secretary, Civil Aviation
Department, Government of Gujarat concern for the conciliation
(b) For the work more than Rs.100 Cr., if any of the parties is not
satisfied with the decision of the Managing Director, GUJSAIL,
both the parties have to refer to the Secretary, Civil Aviation
Department, Government of Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process, he may
refer the dispute to Gujarat Public Works Contract Dispute Arbitration
Tribunal. If the Contractor fails to refer a claim / dispute to the Higher
Authority within 14 days of the notification of the Engineer's decision,
the Contractor shall not be entitled to any additional payment/claim if
he doesn’t follow the above sequence in stipulated time and he
should not stop the work.
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the Arbitration
procedure stated in the Special Conditions of Contract.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall
submit to the Engineer for approval a Programme showing the
general methods, arrangements orders, and timing for all the
activities in the works along with monthly cash flow forecast.
27.2 An update of the Programme shall be a programme showing the
actual progress achieved on each activity and the effect of the
progress achieved on the timing of the remaining work including
any changes to the sequence ofthe activities.
27.3 The Contractor shall submit to the Engineer, for approval an
updated programme at intervals no longer than the period stated in
the Contract data. If the Contractor does not submit an updated
programme within this period, the Engineer may withhold the
amount stated in the Contract data from the next payment after the
date on which the overdue programme has been submitted.
27.4 The Engineer’s approval of the programme shall not alter the
Contractor’s obligations. The Contractor may revise the programme
and submit it to the Engineer again at any time. A revised
programme is to show the effect of Variations and Compensations
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a
compensation Event occurs or a Variation is issued which makes it
impossible for completion to be achieved by the Intended
Completion Date without the Contractor taking steps to accelerate
the remaining work and which would cause the Contractor to incur
additional cost.
28.2 The Engineer shall decide whether and by how much to extend the
Intended Completion Date within 35 days of the Contractor asking
the Engineer for a decision upon the effect of a compensation event
or Variation and submitting full supporting information. If the
Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not
be considered in assessing the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from
the contractor for extension of Intended Completion Date refer to
the Employer his decision. The employer shall in not more than
days communicate to the engineer the acceptance or otherwise of
the Engineer’s decision. If the employer fails to give his acceptance,
the Engineer shall not grant the extension, and the contractor may
refer the matter under Clause
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or
progress of any activity within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to
attend a management meeting. The business of a management
meeting shall be to review the plans for remaining work and to deal
with matters raised in accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings
and is to provide copies of his record to those attending the meeting
and to the Employer. The responsibility of the parties for actions to
be taken is to be decided by the Engineer either at the management
meeting or after the management meeting and stated in writing to
all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of
specific likely future events or circumstances that may adversely
affect the quality of the work, increase the Contract price or delay
the execution of works. The Engineer may require the contractor to
provide an estimate of the expected effect of the future event or
circumstance on the contract price and completion date. The
estimate is to be provided by the Contractor as soon as reasonably
32.2 The Contractor shall cooperate with the Engineer in making and
considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the
work and in carrying out any resulting instruction of the Engineer.
C. QUALITY CONTROL
#33. Identifying Defects/ Defect liability period
33.1 : Defect liability period: The contractor shall be responsible to make
good and remedy at his own expense any defect which may develop
or may be noticed before the period mentioned here under from the
certified date of completion. The Chief Executive Officer shall give
the contractor a notice in writing about the defects and the
contractor shall make good the same within 15 days of receipt of the
notice. In the case of failure on the part of the contractor, the
Engineer- in-charge may rectify or remove or re-execute the work at
the risk & cost of the contractor. The Engineer-in-charge shall be
entitled to appropriate the whole or any part of the amount of
security deposit towards the expenses, if any, Incurred by him in
rectification, removal or re-execution. The Defects Liability period
shall be as under….
(a) For all works costing up to Rs. 50,000 (amount put to tender), the
period shall be 3 Months from the certified date of completion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore
(amount put tender), the period shall be 12 (Twelve) months from
the certified date of completion or one monsoon, whichever is later.
(c) For major projects costing more than Rs. 1 crore, the period shall
be 36 Months from the certified date of completion which should
include three monsoons. (For Pavement Works).
(d) For original building works the defect liability period will be 4 years
or elapse of 4 monsoon period following date of possession of
building taken over by user agency following the certified date of
completion, whichever is later. (For Building Works).
For the purpose of deciding the monsoon period, the 30 th
September shall be treated as the last date.
Modified vide R & B D Circular No. PAC-11-102008-2076-N dated
Circular No. TNC/10/ 2016/Clause 17A (Correction/(1)C Dated
33.2 Free maintenance guarantee period for works of Road/Bridge
(a) For resurfacing work of road free maintenance guarantee period
one year from the date of completion.
(b) In case of widening of the road/strengthening of the
road/bridge, the contractor shall have to give four years free
maintenance guarantee from the certified date of completion.
During this period the contractor shall visit the site every six
months along with the concerned Section Officer / Deputy
Executive Engineer and will examine the work already carried
out in this contract like road work, jungle cutting, side shoulders,
side gutter, road furniture, patta etc. and will prepare Km. wise
inspection report duly signed by all concerned and any defect
observed shall be done within 15 days by the contractor at his
risk and cost as per the direction of Chief Executive Officer. The
contractor needs to do videography of these visits and require to
submit at the time of release of FMG. If B.T. the surface during
the maintenance period of 4 years is worn out then agency shall
have to provide renewal coating as per tender item as directed
by the Engineer-in-charge. The amount equivalent to 5% of each
running bill shall be withheld and will be released after the free
maintenance guarantee period (i.e. 4 years) is over.
However, this amount shall be released against fixed deposit or
bank guarantee pledged in the name of Executive Engineer after
completion certificate of work is issued.
(1) The flakiness and elongation index (combined) for coarse
aggregates under no circumstances shall exceed the allowable
limit set forth in the relevant clause for the material in question.
(2) 2% of the amount eligible for the payment of bituminous items
shall be withheld till the miscellaneous items like earthwork in
embankment / cutting for side shoulders, side gutters, kilometer
/ indicator / guard stones, sign boards etc. are completed in all
respect by the contractor. After completion of the miscellaneous
items, the above said 2% withheld amount shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd.
(3) Videography for the surface under Maintenance Guarantee is to
be done as per Govt. letter No.: SSR/10/2015-16/26/C, Dtd.
26/11/15 for the work costing more than Rs. 5.00 Crore.
(4) Setting up adequate laboratory & deployment of quality
The contractor shall have to set up the laboratory with adequate
equipment. Till the setting up of adequate laboratory is
completed & reported of this to the engineer (subject to due
verification by engineer’s representative) by contractor in
writing, Rs. 2,00,000/- shall be withheld. The qualified quality
Engineer shall be deployed exclusively for this contract by the
contractors. If quality Engineer is not deployed by contractor
within one month after the date of work order, the amount
equivalent to Rs.20,000 per month shall be recovered till the
actual deployment of quality engineer. The amount so recovered
towards the deployment of quality engineers shall not be
(5) Asphalt work will have to be cross checked as per G.R.
No.: RGN/60/ 2006/35/C, dtd.31/05/07 before final bill is
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall
maintain, at his own risk and cost, the existing lane(s) of the
road so that the traffic worthiness and safety thereof are at
no time materially inferior as compared to their condition
(ten) days prior to the date of the Agreement and shall
undertake the necessary repair and maintenance works for
this purpose; provided that the Contractor may, at his cost,
interrupt and divert the flow of traffic if such interruption
and diversion is necessary for the efficient progress of works
and conforms to Good Industry Practice; provided further
that such interruption and diversion shall be undertaken by
the Contractor only with the prior written approval of the
Executive Engineer which approval shall not be unreasonably
withheld. For the avoidance of doubt, it is agreed that the
Contractor shall at all times be responsible for ensuring safe
operation of the road.
33.3 The Engineer shall check the Contractor’s work and notify the
Contractor of any defects that are found. Such checking shall not
affect the Contractor’s responsibilities the Engineer may instruct
the Contractor to search for a Defect and to uncover and test
any work that the Engineer considers may have a Defect.
34.1 If the engineer instructs the Contractor to carry out a test not
specified in the Specification to check whether any work has a
Defect and the test shows that it does, the Contractor shall pay
for the test and any samples. If there is no defect the test shall
be a Compensation Event.
34.2 #1% of the amount of work done should be deducted from R.A.
Bill of the contractor for testing the quality of material
workmanship, irrespective of actual charges.
34.3 Agency has to establish testing laboratory on site for the various
test to be carried out in the work for this purpose agency shall
construct a pukka laboratory building with all facility on site at
location specified by the Chief Executive Officer.
34.4 Agency has to carried out testing 80% in NABL approved
laboratory and 20% in Gov. Laboratory for the various test to
be carried out in the work.
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects
before the end of the defects Liability Period, which begins at
Completion and is defined in the contract data. The Defects
Liability Period shall be extended for as long as Defects remain
to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall
correct the notified defect within the length of time specified by
the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time
specified in the Engineer’s notice, the Engineer will assess the
cost of having the Defect corrected, and the Contractor will pay
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions,
installation, testing and commissioning work to be done by the
37.2 The bill of Quantities is used to calculate the Contract price. The
Contractor is paid for the quantity of the work done at the rate in
the Bill of Quantities for each item.
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition
to the original specifications , drawings, designs and instructions
that may appear to him to be necessary or advisable during the
progress of the work and the contractor shall be bound to carry out
the work in accordance with any instruction in this connection which
may be given to him in writing signed by the Engineer and such
alteration shall not invalidate the contract and any additional work
which the contractor may be directed to do in the manner above
specified as part of the work shall be carried out by the contractor
on the same conditions in all respects on which he agreed to do the
main work and at the same rate as are specified in the tender for the
Except that when the quantity of any item exceeds the quantity as in
the tender by more than 130%, the contractor will be paid for the
quantity in excess of 130%, at the rate entered in the SOR of the
year during which the excess in quantity is first executed.
39.1 All Variations shall be included in updated programmes produced by
the Contractor.
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for
which no rate is specified in this contract, then such class of work
shall be carried out as below.
(i) At the rate derived from the item within the contract which is
comparable to the one involving additional or altered class of work;
where there are more than one comparable items, the item of the
contract which is nearest in comparison with regard to class or
classes of the work involved shall be selected and the decision of the
Superintending Engineer as to the nearest comparable item shall be
final and binding on the contractor.
(ii) If the rate cannot be derived in accordance with (i) above, such
class of works shall be carried out at the rate entered in the
Schedule of Rates of the division for the year in which the tender
was received, increased or decreased by the percentage by which
the tender amount is more or less as compared to the amount
arrived at the rates in the “Schedule of Rates” of the Division in the
year in which the tender was received. If the Schedule of rates of
the Division does not contain all the items, the percentage increase
or decrease of the tender shall be calculated considering such items
which were included in the “Scheduled Rates” of the division for the
year and for materials consumed on such item the rate to be
charged would be the basic rate taken into account for fixing the
rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such
class of work shall be carried out at the rate decided by the
competent authorities on the basis of detailed rate analysis after
hearing the contractor before a Committee of two Superintending
Engineers stationed at the same place or the nearest place.
40.2 If the additional or altered work, for which no rate is entered in the
“Schedule of Rates” of the Division is ordered to be carried out
before the rate is agreed upon, then the contractor shall within
seven days of the date of receipt by him of the order to carry out the
work, inform the Engineer-in-charge of the rate, which it is his
intention to charge for such class of work and if the Chief Executive
Officer does not agree to this rates, he shall by notice in writing be
at liberty to cancel his order to carry out such class of work and
arrange to carry it out in such manner as he may consider it
advisable, provided always that if the contractor shall commence
work or incur any expenditure in regard thereof before the rates
shall have been determined as lastly herein before mentioned, then
in such cases he shall only be entitled to be paid in respect of the
work carried out or expenditure incurred by him prior to the date of
the determination of the rate as aforesaid according to such rate or
rates as shall be fixed by the Engineer-in-charge. In the event of the
dispute, the decision of the Superintending Engineer of the Circle
shall be final.
Where, however, the work is to be executed according to the
designs, drawings and specifications recommended by the
contractor and accepted by the competent authority, the alternation
above referred to shall be within the scope of such designs, drawings
and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in
the proportion that the increase in the cost occasioned by
alterations bears to the cost of the original work and the certificate
of the Engineer-in-charge as to such proportion shall be final and
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the
engineer with an updated cash flow forecast.
42. Payment certificates
42.1 The Contractor shall submit to the Chief Executive Officer monthly
statements of the estimated value of the work completed less the
cumulative amount certified previously.
42.2 The Chief Executive Officer shall check the Contractor’s monthly
statement within 14 days and certify the amount to be paid to the
Contractor after taking into account any credit or debit for the
month in question in respect of materials for the works in the
relevant amounts and under conditions set forth in sub-clause
of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Chief
Executive Officer.
42.4 The value of work executed shall comprise the value of the
quantities of the items in the Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations
and compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate
or reduce the proportion of any item previously certified in any
certificate in the light of later information
43.1 Payments shall be adjusted for deductions for advance payments,
retention, other recoveries in terms of the contract and taxes at
source, as applicable under the law. The Employer shall pay the
Contractor the amounts certified by the Engineer within 28 days of
the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the
contract to the Contractor will be made by the Employer. Hence, it is
the responsibility of the contractor to pay the GST to the Authority
43.3 Items of the works for which no rate or price has been entered in
will not be paid by the Employer and shall be deemed covered by
other rates and prices in the Contract.
44. Compensation events
44.1 The following are compensation Events unless they are caused by
the Contractor:
(a) The Employer does not give access to a part of the Site by the
site possession date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being
completed beyond the Intended Completion Date then Authority
will approve EOT with eligible contractual price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes
prevailing on due date of bid submission except GST. However, any
subsequent changes in the tax structure by the Government after
due date of bid submission will be compensated (+/-) on availability
or submission of actual documentation. Contractor will have to
intimate Engineer regarding changes occurred in the tax structure
after bid submission. If the contractor fails to provide such
information and if any financial obligation may arise due to change
in tax structure, same will be recovered from the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility
of the contractor to pay the GST to the Authority concerned.
46.1 All payment shall be made in Indian Rupees.
47. Price Adjustment- APPLICABLE
47.1 Contract price shall be adjusted for increase or decrease in rates and
price of labour, materials, fuels and lubricants in accordance with
the following principles and procedures and as per formula given in
the contract data:
(a) The price adjustment shall apply for the work done from the
start date given in the contract data up to end of the initial
intended completion date or extensions granted by the Engineer
and shall not apply to the work carried out beyond the stipulated
time for reasons attributable to the contractor.
(b) The price adjustment shall be determined during each month
from the formula given in the contract data.
(c) Following expressions and meanings during to the work done
during each month.
= Total value of work done during the month. It would include
the amount of secured advance granted, if any, during the
month less the amount of secured advance recovered, if any
during the month. It will exclude value for works executed
under variations
for which price adjustment will be worked separately based on
the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to
the contractor is not covered by the provisions of this or other
clause in the contract, the unit rates and prices included in the
contract shall be deemed to include amounts to cover the
contingency of such other rise or fall in costs.
48.1 The Employer shall retain from each payment due to Contractor the
proportion stated in the Contract Data until Completion of the
whole of the Works.
48.2 On Completion of the whole of the Works half the total amount
48.2 On Completion of the whole of the Works half the total amount
retained is repaid to the Contractor and half when the Defects
Liability Period has passed and the Engineer has certified that all
Defects notified by the Engineer to the Contractor before the end
of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute
retention money with an “on demand” Bank guarantee.
In case, Contractor requests for refund of the Retention Money
deducted by the Employer under the provision of this clause,
Employer shall consider the said request of the Contractor provided
that the refund hereunder shall be made in trenches of not less than
1% (One Percent) of the Contract Price and Contractor furnishes an
irrevocable and unconditional Bank guarantee for an equal amount
substantially in the format of Bank Guarantee for Performance
Guarantee enclosed with SBD and valid up to 60 day beyond the
scheduled / extended Defects Liability Period. On completion of the
whole works, the contractor has however an option to submit a
fresh irrevocable and unconditional Bank Guarantee for an amount
equal to 5% of the total value of work executed substantially in the
format of Bank Guarantee for Performance Guarantee enclosed with
SBD and valid up to 60 days beyond the Defect Liability Period and
yet refund the Retention Money Bank Guarantee submitted for
refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the
rate per day stated in the Contract Data for each day that the
Completion Date is later than the Intended Completion Date (for the
whole works or the milestone as stated in the contract data). The
total amount of liquidated damages shall not exceed the amount
total amount of liquidated damages shall not exceed the amount
defined in the Contract Data. The Employer may deduct liquidated
damages from payment due to the Contractor. Payment of
liquidated damages does not affect the Contractor’s liabilities.
49.2 If the Intended Completion Date is extended after liquidated
damages have been paid, the Engineer shall correct any
overpayment of liquidated damages by the Contractor by adjusting
the next payment certificate. The Contractor shall not be entitled for
any interest on the over payment calculated from the date of
payment to the date of repayment.
49.3 If the contractor fails to comply with the time for completion as
stipulated in the tender, then the contractor shall pay to the
employer the relevant sum stated in the Contract Data as Liquidated
damages for such default and not as penalty for everyday or part of
day which shall elapse between relevant time for completion and
the date stated in the taking over certificate of the whole of the
works on the relevant section, subject to the limit stated in the
The employer may, without prejudice to any other method of
recovery, deduct the amount of such damage from any monies due
or to become due to the contractor. The payment or deduction of
such damage shall not relieve the contractor from his obligation to
complete the works on from any other of his obligations and
liabilities under the contract.
49.4 If, before the Time for Completion of the whole of the Works or, if
applicable any Section, a Taking Over Certificate has been issued for
any part of the Works or of a Section, the liquidated damages for
delay in completion of the remainder of the Works or of that Section
shall, for any period of delay after the date stated in such Taking-
Over-Certificate, and in the absence of alternative provisions in the
Contract, be reduced in the proportion which the value of the part
so certified bears to the value of the whole of the Works or Section,
as applicable. The provisions of this Sub-clause shall only apply to
the rate of liquidated damages and shall not affect the limit thereof.
50.1 If the contractor achieves completion of the whole of the works
prior to the intended Completion Date prescribed in Contract Data
the Employer shall pay to the contractor a sum stated in Contract
Data as bonus for every completed month but subjected to
maximum amount as stated in Contract Data; which shall elapse
between the date of completion of all items of works as stipulated in
the contract, including variations ordered by the Engineer and the
time prescribed in Clause
50.2 Bonus shall be paid only to works amounting to above INR 5 crore
with time limit of the works is equal or more than 6 months. The
bonus would be paid as under: NOT APPLICABLE
% of Time Saved % of Initial Contract Price
entitled for Bonus
Less than 10% 0%
51. Advance Payment: NOT APPLICABLE
The Employer shall make advance payment (not to be paid less than
two installments except in special circumstances for which the
reason to be Recorded in writing) to the Contractor of the amounts
stated in the Contract Date by the date stated in the Contract Date,
against provision by the Contactor of an Unconditional Bank
Guarantee in a form and by a bank acceptable to the Employer in
amounts and currencies equal to be at least 110% of the advance
payment. The guarantee shall remain effective until the advance
payment has been repaid, but the amount of the guarantee shall be
progressively reduced by the amounts repaid by the Contractor. The
Mobilization advance would be deemed as interest bearing advance
at an interest rate of 10 % to be compounded, quarterly.
51.1 The Contractor is to use the advance payment only to pay for
Equipment, plant and Mobilization expenses required specifically for
execution of the Works. The Contractor shall demonstrate that
advance payment has been used in this way by supplying copies of
invoices or other documents to the engineer.
51.2 The advance payment shall be repaid by deduction proportionate
amount from payments otherwise due to the Contractor, following
the schedule of completed percentages of the Works on a payment
basis. No account shall be taken of the advance payment or its
repayment in assessing valuations of work done, variations, price
adjustments, Compensation Events, or Liquidated damages.
52.1 The performance Security (including additional security for
unbalanced bids) shall be provided to the Employer no later than the
date specified in the Letter of Acceptance and shall be issued in an
amount and form and by a bank or surety acceptable to the Employer
and denominated in Indian Rupees. The performance Security shall be
valid until a date 60 days from the certified date of completion of the
project and the additional security for unbalanced bids shall be valid
until a date 28 days from the date of issue of the certificate of
completion of the work.
Performance and Additional Performance Security shall become
refundable/releasable within 15 days after project certified
completion date subject to fulfillment of contractual obligation and
settlement of all dues and claims.
54. Cost of Repairs
54.1 Loss or damage to the Works or Materials to be incorporated in the
Works between the Start date and the end of Defects Correction
periods shall be remedied by the Contractor at the Contractor’s cost
if the loss or damages arises from the Contractor’s acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of
Completion of the works, and the Engineer will do so upon deciding
that the work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven
days of the Engineer issuing a certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account
of the total amount that the Contractor considers payable as full and
of the total amount that the Contractor considers payable as full and
final settlement of all claims under the Contract for items before the
end of the Defects Liability Period. The Engineer shall issue a Defect
Liability Certificate and certify any final payment that is due to the
Contractor within 56 days of receiving the Contractor's account if it
is correct and complete. If it is not, the Engineer shall issue within
days a schedule that states the scope of the corrections or additions
that are necessary. If the Final Account is still unsatisfactory after it
has been resubmitted, the Engineer shall decide on the amount
payable to the Contractor and issue a payment certificate, within
days of receiving the Contractor’s revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of
excesses and savings in final account is observed, the
Engineer/Employer shall be at liberty to restrict the final payment of
BOQ items to the lowest amount evaluated of the bids considering
the final quantities and the rates quoted including the rebates if any.
Payment of variation items shall however be made at the rates
approved by the Employer, within 90 days from the physical
completion of work.
58. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals
are required, the Contractor shall supply them by the dates stated in
the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by
the dates stated in the Contract data, or they do not receive the
Engineer’s approval, the Engineer shall withhold the amount stated
in the Contract Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the
other party causes a fundamental breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited
to the following:
1. The contractor stops work for 28 days when no stoppage of
work is shown on the current programme and the stoppage has
not been authorized by the Engineer
2. The Engineer instructs the Contractor to delay the progress of
the Works and the instructions is not withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into
liquidation other than for a reconstruction or amalgamation.
4. A payment certified by the Engineer is not paid by the Employer
to the Contractor within 56 days of the date of the Engineer’s
5. The Engineer gives Notice that failure to correct a particular
Defect is a fundamental breach of Contract and the Contractor
fails to correct it within a reasonable period of time determined
by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the
number of days for which the maximum amount of liquidated
damages can be paid as defined in the Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged
in corrupt or fraudulent practices in competing for or in
executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the
offering, giving, receiving or soliciting of anything of value to
influence the action of a public official in the procurement process
or in contract execution. “Fraudulent practice” means a
misrepresentation of facts in order to influence a procurement
process or the execution of a contract to the detriment of the
borrower and includes collusive practice among Bidders (prior to or
after bid submission) designed to establish bid prices at artificial
non- competitive levels and to deprive the Borrower of the benefits
of free and open competition.
59.3 When either party to the Contract gives notice of a breach of
contract to the Engineer for a cause other than those listed under
Sub Clause 59.2 above, the Engineer shall decide whether the
breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the
Contract for convenience.
60. Payment upon Termination
If the Contract is terminated because of a fundamental breach of
Contract by the Contractor, the Engineer shall issue a Certificate for
the value of the work done less advance payments received up to
the date of the issue of the certificate, less other recoveries due in
terms of the contract, less taxes due to deducted at source as per
applicable law and less the percentage to apply to the work not
completed as indicated in the Contract data. Additional Liquidated
Damages shall not apply. If the total amount due to the Employer
Damages shall not apply. If the total amount due to the Employer
exceeds any payment due to the Contractor the difference shall be a
debt payable to the Employer.
60.1 If the Contract is terminated at the Employer’s convenience or
because of a fundamental breach of Contract by the Employer, the
Engineer shall issue a certificate for the value of the work done, the
cost of balance material brought by the contractor and available at
site, the reasonable cost of removal of equipment, repatriation of
the Contractor’s personnel employed solely on the works, and the
Contractor’s cost of protecting and securing the Works and less
advance payment received up to the date of the certificate, less
other recoveries due in terms of the contract and less taxes due to
deducted at source as per applicable law.
61.1 All materials on the Site, Plant Equipment, Temporary Works and
Works are deemed to be property of the Employer, if the Contract is
terminated because of a Contractor’s default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other
event entirely outside the control of either the Employer or the
Contractor, the Engineer shall certify that the Contract has been
frustrated. The Contractor shall make the Site safe and stop work as
quickly as possible after receiving this certificate and shall be paid
for all work carried out before receiving it and for any work carried
out afterwards to which commitment was made.
B. SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract,
make his own arrangements for the engagement of all staff and
labour, local or other, and for their payment of housing, feeding and
The Contractor shall, if required by the Engineer, deliver to the
Engineer a return in detail, in such form and at such intervals as the
Engineer may prescribe, showing the staff and the numbers of the
several classes of labour from time to time employed by the
Contractor on the site and such other information as the Engineer
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his sub-
contractor shall abide at all times by all existing labour enactments
and rules made thereunder, regulations, notification and bye laws of
the State or central Government or local authority and any other
labour law (including rules), regulations, bye laws that may be
passed or notifications that may be issued under any labour law in
future either by the State or the Central Government or the local
authority. Salient features of some of the major labour laws that are
applicable to the construction industry are given below. The
Contractor shall keep the Employer indemnified in case any action is
taken against the Employer by the competent authority on account
of contravention of any of the provisions of any Act or rules made
thereunder, regulations or notifications including amendments. If
the Employer is caused to pay or reimburse, such amounts as may
be necessary to cause or observe, or for observance of the
provisions stipulated in the notifications/bye laws/Acts/
Rules/regulations including amendments, if any, on the part of the
Contractor, the Engineer/employer shall have the right to deduct
any money due to the Contractor including his amount of
performance security. The Employer / Engineer shall also have the
right to recover from the Contractor any sum required or estimated
to be required for making good the loss or damage suffered by the
The employees of the Contractor and the Sub-Contractor in no case
shall be treated as the employees of the Employer at any point to
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS APPLICABLE
TO ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS
A) Workmen Compensation Act 1923 :- The Act provides for compensation
in case of injury by accident arising out of and during the course of
B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee
under the Act on satisfaction of certain conditions on separation if an
employee has completed 5 years’ service or more on death, the rate of
15 days wages for every completed year of service. The Act is applicable
to all establishments employing 10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952:- The Act
Provides for monthly contributions by the employer plus workers @
10% or 8.33% The benefits payable under the Act are :
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951 :- The Act provides for leave and some
other benefits to women employees in case of confinement or
miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides
for certain welfare measures to be provided by the Contractor to
contract labour and in case the Contractor fails to provide, the same are
required to be provided, by the Principal Employer by Law. The principal
Employer is required to take Certificate of Registration and the
Contractor is required to take license from the designated Officer. The
Act is applicable to the establishments or Contractor of Principal
Employer, if they employ 20 or more contract labour.
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less
than the Minimum Wages fixed by appropriate Government as per
provisions of the Act, if the employment is a scheduled employment.
Construction of Building, Roads, Runways are scheduled employment.
G) Payments of wages Act 1936:- It lays down as to by what date the
wages are to be paid, when it will be paid and what deductions can
be made from the wagesof the workers.
H) Equal remunerations Act 1979 :- The Act provides for payment of
equalwages for work of equal nature to Male and Female workers and
for not making discrimination against female employees in the matter
of transfer, training and promotions etc.
Payments of Bonus Act 1965 :- The Act is applicable to all
establishments employing 20 or more employees. The Act provides for
payments of annual bonus subject to a minimum of 8.33% of wages
and maximum of 20% of wages to employees drawing Rs. 3500/- per
month or less. The bonus to be paid to employees getting Rs, 2500/-
per month or above Rs. 3500/- per month shall be worked out by
taking wages as Rs. 2500/- per month only. The Act does not apply
to certain establishments. The newly set-up establishments are
exempted for five years in certain circumstances. Some of the State
Governments have reduced the employment size from 20 to 10 for the
purpose of applicability of this Act.
I) Industrial Disputes Act 1947 :- The Act lays down the machinery and
procedure for resolutions of Industrial disputes, in what situations a
strike or lock-out becomes illegal and what are the requirements for
laying off or retrenching the employees or closing down the
J) Industrial employment (standing Orders) Act 1946 :- It is applicable to
all establishments employing 100 or more workmen (employment size
reduced by some of the State and Central Government to 50). The Act
provides for laying down rules governing the conditions of employment
by the Employer on matters provided in the Act and get the same
certified by the designated Authority.
K) Trade Unions Act 1926:- The Act lays the procedure for registration of
trade unions of workmen and employers. The Trade Unions registered
under the Act have given certain immunities from civil and criminal
L) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits
employment of children below 14 years of age in certain occupations
and process and provides for regulation of employment of children in
all other occupations and processes. Employment of Child labour is
prohibited in Buildingand Construction Industry.
M) Inter – State Migrant workmen’s (Regulation of Employment &
Conditions of service) Act 1979:- The Act is applicable to an
establishment which employs 5 or more inter-state migrant workmen
through an intermediary (who has recruited workmen in one state for
employment in the establishment situated in another state).The inter-
state migrant workmen, is an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as
housing, medical aid, traveling expenses from home upto the
establishment and back, etc.
N) The Building and Other Construction workers (Regulation of
employment and Conditions of Service) Act 1996 and the Cess Act of
1996:- All the establishments who carry on any building or other
constructions work and employ 10 or more workers are covered under
All such establishments are required to pay cess at the rate not
exceeding 2% of the cost of construction as may be modified by the
government. The Employer of the establishment is required to provide
safety measures at the Building or construction work and other welfare
measures, such as canteens, First Aid facilities, Ambulance, Housing
accommodations for workers near the workplace etc. The Employer to
whom the Act applies has to obtain a registration certificate from the
Registering Officers appointed by the Government.
O) Factories Act 1948 :- The Act lays down the procedure for approval of
plans before setting up a factory, health and safety provisions, welfare
provisions, working hours, annual earned leave and rendering
information regarding accidents or dangerous occurrences to
designated authorities. It is applicable to premises employing
persons or more with aid of power or 20 or more persons without the
aid of power engaged in the manufacturing process.
P) Royalty charges-The contractor shall pay the royalty to the
competent authority as per rule. The royalty charges paid shall be
borne by the contractor and shall not be reimbursed by the
Q) Following Pollution control Acts and amendments made thereof
from time to time shall be applicable.
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental management
plan for best energy use, waste management, and the reduction of
pollution as in EMS (Environmental Management system)ISO-14001-
65. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
65.1 If the Contractor is of the view that a decision taken by the Engineer
was either outside the authority given to the Engineer by the
Contract or that the decision was wrongly taken, the decision shall
be referred to Managing Director, GUJSAIL, (Higher Authority)
within 14 days of the notification of the Engineer's decision. If the
issue is not resolved, any party can refer the matter for conciliation
within 15 days from the decision given by the Managing Director,
1. For the work up to Rs.100 Cr., if any of the parties are not
satisfied with the decision of the Managing Director, GUJSAIL
both the parties have to refer to the Secretary, Civil Aviation
Department, Government of Gujarat for the conciliation process.
2. For the work more than Rs.100 Cr., if any of the parties is not
satisfied with the decision of the Superintending Engineer, both
parties have to refer to the #Secretary, Civil Aviation,
Government ofGujarat for the conciliation process.
If the dispute is not resolved through the conciliation process,
contractor may refer the dispute to Gujarat Public Works
Contract Dispute Arbitration Tribunal. If the Contractor fails to
refer a claim / dispute to the Higher Authority within 14 days of
the notification of the Engineer's decision, the Contractor shall
not be entitled to any additional payment/claim if he doesn’t
follow the above sequence in stipulated time. However, during
such period, he would not stop the work in any case.
Clause Reference With
respect to section
Item marked “N/A” do not apply to this Contract.
1. The Employers is [CL.1.1]
Name: Gujarat State Aviation Infrastructure Company Limited
Address: GUJSAIL Complex, Near SVPI Airport Ahmedabad.
Name of authorized Representative (will be intimated later)
2. The Engineer is Chief Executive Officer
Name of Authorized Representative : NA
3. The Defects Liability Period is 3 Year Including 3 Monsoon For [CL.1.1&33]
Pavement Works and 04 Years for Building Works from the date of
completion. [CL.1.1]
4. The Start Date shall be 1st days for the date of issue of the Notice to
proceed with the work.
5. The Intended Completion Date for the whole of the works is
18 Months after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period from the start date
Milestone 1 i.e. 25 % 135 days.
Milestone 2 i.e. 50 % 270 days.
Milestone 3 i.e. 75% 405 days.
Milestone 4 i.e. 100% 540 days.- DETAILS
6. The Site is located at Dwarka, District Devbhumi Dwarka [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The work consists of Development of Heliport at Dwarka, Gujarat [CL.1.1]
including pavement facilities such as FATO, Parking Aprons,
Connecting Taxiways, Perimeter Road, Approach Road, Car Parking
and building facilities such as Passenger Terminal Building (PTB) cum
ATC Tower, Fire Station, Electrical Substation, Pump
Room/Underground Tank, Security Hut, Watch Towers under Phase-1
development. with items as per B.O.Q. The works shall, inter alia,
include the following, as Specified or as directed:
Site clearance; setting – out and layout; widening of existing
carriageway and strengthening including camber corrections;
construction of new road/ Parallel service road; bituminous
pavements remodeling / construction of Junctions, intersections, bus
bays, lay-bays; supplying and placing of drainage Channels, flumes,
guard posts and guard other related items; construction/extension of
cross drainage works, bridge, approaches and other related stones;
protective works for roads/bridge; all aspects of quality assurance of
various components of the works; rectification of The defects in the
completed works during the Defects Liability Period; submission of
“As- built’’ drawings and any other related documents; and other
item of work as may be required to be carried out for completing
the work in accordance with the drawings and the provisions of the
contract and to ensure safety.
(B) Bridge Works
Site clearance; setting out, provision of foundations, piers abutments and
bearing; prestressed/reinforced cement concrete superstructure; wearing
coat, hand railings, expansion joints, approach slabs, drainages spouts/
downtake pipes, arrangements for fixing light posts, water mains, utilities
etc; provision of suitably designed protective works; providing wing/return
walls; provision of road markings, road signs etc.; all aspects of quality
assurance; clearing the site and handing over the works on completion;
rectification of the defects during the Defects Liability Period and
submission of “As-built” drawings and other related documents; and
other items of work as may be required to be carried out for completing
the works in accordance with the drawings and the provisions of the
contract and to Insure safety
(C) Other Items (ELECTRICAL WORKS)
Any Other Items as required to fulfill all contractual obligations as per the Bid
documents. [CL.2.3(9)]
10. The following documents also form part of the Contract:
As per clause 2-3
11. The law which applies to the Contract is the law of Union of India
12. The language of the Contract documents is English
13. Limit of subcontracting NOT APPLICABLE [CL.7.1]
14. The Schedule of Other Contractors
15. The Schedule of Key Personnel As per Annex – II to Section I
16. The minimum insurance cover for physical property, injury and death is [CL13]
Rs. 5 lakhs per occurrence with the number of occurrences limited to
four. After each occurrence, the contractor will pay an additional
premium necessary to make insurance valid for four occurrences always.
17. Site Investigation report- Annexed to the Tender Document
18. The Site Possession date shall be first day of work order
19. The period for submission of programme for approval of the engineer [CL. 27.1]
shall be 21 days from the issue of Letter of Acceptance.
20. The period between program updates will be 23 days.
21. The amount to be withheld for late submission of an updated program
shall be Rs.1.00 lakhs
22. The following events shall also be Compensation Events: [CL. 27.3]
(i) Substantially adverse ground conditions encountered during the
course of execution of work not provided for in the bidding
(ii) Removal of underground utilities detected subsequently
Significant changes in classification of soil requiring additional
mobilization by the contractor, e.g. ordinary soil to rock
(iii) Removal of unsuitable material like marsh, debris dumps,
etc. not caused by the contractor.
Artesian conditions
(iv) Seepage, erosion landslide
(v) River training requiring protection of permanent work
(vi) Presence of historical, archeological or religious structures,
monuments interfering with the works
(vii) Restriction of access to ground imposed by civil, judicial, or
military authority.
23. The currency of the Contract is Indian Rupees [CL. 46]
24. The formula (e) for adjustment of prices are as under: Applicable [CL.47]
If any of the commodities like Cement, Steel or Bitumen are not found
applicable in a work, the weight component of that commodities {i.e.
‘Cement’ (Pc), ‘Steel’ (Ps) or ‘Bitumen' (Pb) as indicated in SBD for the
purpose of Price Adjustment} shall be clubbed with the weight
component of ‘Other Material’ (Pm), such that the gross % weight of
the components shall remain as 100% .
R = value of work as defined in Clause 47.1 of Conditions of Contract
ADJUSTMENT FOR LABOUR COMPONENT
(i) Price adjustment for increase or decrease in the cost due to labour
shall be paid in accordance with the following formula:
VL = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for local labour
L0 = The consumer price index for industrial workers for the State on
28 days preceding the scheduled date of opening of technical Bids
as published by Labour Bureau, Ministry of Labour, Government
Li = The consumer price index for industrial workers for the State
for the month under consideration as published by the Labour
Bureau, Ministry of Labour, Government of India.
PL = Percentage of labor component of the work.
ADJUSTMENT FOR CEMENT COMPONENT
(ii) Prices adjustment for increase or decrease in the cost of cement
procured by the contractor
Vc = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for cement.
C0 = The all India wholesale price index for Ordinary Portland
Cement on 28 days preceding the scheduled date of opening of
technical bid as published by the Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Ci = The all India average wholesale price index for
Ordinary Portland Cement for the month under consideration as
published by Office of the Economic Adviser, Department for
Promotion of Industry and Internal Trade, Ministry of Commerce
Pc = Percentage of cement component of the work
ADJUSTMENT FOR STEEL COMPONENT
(iii) Price adjustment for increase or decrease in the cost of steel
procured by the contractor shall be paid in accordance with
the following formula:
Vs= Increase or decrease in the cost of work during the month under
consideration due to changes in the rates for steel
So= The all India wholesale price index for steel (Mild Steel - Long
Products Rebars) on 28 days preceding the date of opening of
Bids as published by the Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel -
Long Products Rebars) for the month under consideration as
published by Office of the Economic Adviser, Department for
Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Ps = Percentage of steel component of the work
Note : For the application of this clause, the index of Mild Steel-
Long products Rebars has been chosen to represent the steel
ADJUSTMENTS OF BITUMEN COMPONENT
(iv) Price adjustment for increase in the cost of bitumen shall be paid in
accordance with the following formula
Vb = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for bitumen.
Bo = The official retail price of bitumen at the IOC depot at the nearest
centre on the day 28 days prior to the scheduled date of opening of
Bi = The official price of bitumen of IOC depot at the nearest center:
For the first 15 days of the month under consideration, the
price declared on the 1st day of that month.
For the remaining days of the month under consideration, the
rate declared on the 16th day of that month.
Pb = Percentage of bitumen component of the work
ADJUSTMENT OF POL (FUEL AND LUBRICANT) COMPONENT
(v) Price adjustment for increase or decrease in cost of POL (fuel and
lubricant) shall be paid in accordance with the following formula
Vf = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for fuel and
Fo = The official retail price of High Speed Diesel (HSD) at the
existing consumer pumps of IOC at the nearest centre on the day
prior to the date of opening of Bids.
Fi = The official retail price of HSD at the existing consumer pumps
of IOC at the nearest centre for the 15th day of the month of the
under consideration.
Pf = Percentage of fuel and lubricants component of the work
Note: For the application of this clause, the price of High-Speed
diesel Oil has been chosen to represent the fuel and lubricants
ADJUSTMENT FOR CONSTRUCTION MACHINERY
(vi) Price adjustment for increase or decrease in the cost of plant and
Machinery spare procured by the Contractor shall be paid in accordance
with the following formula
Vp= Increase or decrease in the cost of work during the month
underconsideration due to changes in rates for plant and machinery
P0 = The all India wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month
under consideration as published Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Pi = The all India average wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month
under consideration as published Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Pp = Percentage of plant and machinery spares component of the
Note: For the application of this clause, index of Heavy Machinery
and parts has been chosen to represent the Plant and Machinery
ADJUSTMENT OF OTHER MATERIALS COMPONENT
(vii) Price adjustment for increase or decrease in cost of local materials other
than cement, steel, bitumen and POL procured by the contractor shall
be paid in accordance with the following formula
Vm = Increase or decrease in the cost of work during the month
under consideration due to change in rates for local materials other
than cement, steel, bitumen and POL.
M0 = The All-Indian wholesale price index (all commodities) on
days preceding the scheduled date of opening of technical Bids, as
published by the Office of the Economic Adviser, Department for
Promotion of Industry and Internal Trade, Ministry of Commerce
Mi= The All India wholesale price index (all commodities) for the
month under consideration as published by the Office of the
Economic Adviser, Department for Promotion of Industry and
Internal Trade, Ministry of Commerce & Industry.
Pm = Percentage of local material components (other than
cement, steel, bitumen and POL) of the work.
THIS Percentage COMPONENT CHANGE
BEFORE ONLINE TENDERING. AS THIS ARE
UNDER CALCULATIONS.
The following percentage will govern the price adjustment for the
entire contract:
1 Labour –PL 5%
Cement – Pc 90 %
6 Plant & Machinery Spares Pp
7 Other Materials – Pm
25. The proportion of payments retained (retention money)
shall be 5% from each bill subject to a maximum of
5 % of final contract price.
26. Amount of Liquidated damages for For Whole of work
{CL.49} delay in completion of works (1/2000)th of the
Initial contract price, rounded off to the
nearest Thousand, per
day. For sectional
Completion (wherever
specified In item 6 of
Contract data) (1/2000)th
of initial contract price for
#5 km Section, rounded
off to the nearest
thousand per day.
27. Maximum limit of liquidated damages
10 percent of the Initial {CL. 49}
For delay in completion work Contract Price rounded off to
the nearest thousand
28. Amount of Bonus for early completion NOT APPLICABLE
completion of work
shall be given as
29. Maximum limit of bonus for early Not Applicable
the Contract {CL. 50} Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances Amount (Rs.)
Conditions to be
i Mobilization 10% of the contract value Not Applicable
ii Equipment 90% for new and 50% of Not Applicable
depreciated value for old
equipment. Total amount
equipment. Total amount
will be subject to a
maximum of 5% of the
iii Secured Deleted
Advance for non-perishable material Brought
(The advance payment will be paid to the Contractor no later than 28 days
after fulfillment of the above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the
interim payments certified by the Engineer under the Contract.
Deduction shall commence in the next Interim Payment Certificate
following that in which the total of all such payments to the Contractor
has reached not less than 20 percent of the Contract Price or 6 (six)
months from the date of payment of first installment of advance,
whichever period concludes earlier, and shall be made at the rate of
percent (collectively for both Mobilization Advance and Equipment
Advance) of the amounts of all Interim Payment Certificate until such
time as the loan has been repaid, always provided that the loan shall be
completely repaid prior to the expiry of the original time for completion
pursuant to Clause 17 and
33. The securities shall be for the following minimum amounts
equivalent {CL. 52} As a percentage of the Contract Price:
Performance Security for 5 percent of contract price plus Rs. ………………..
(to be decided after evaluation of the bid) as additional security in terms
of ITB Clause 29.5.
The standard form of Performance security acceptable to the Employer
shall be an unconditional Bank Guarantee of the type as presented in
Section 8 of the Bidding Documents.
34. The Schedule of Operating and maintenance Manuals…..N/A. {CL. 58}
35. The date by which “as– built” drawings (in scale as directed) in 2 sets
{CL. 58} are required within 28 days of the issue of certificate of
completion of the whole or section of the work, as the case may be.
36. The amount to be withheld for failing to supply “as built” drawings
{CL. 58} by the Date required is Rs 5 Lakhs.
37. The following events shall also be fundamentals breach of contract:
{CL.59.2} “The Contractor has contravened Sub- clause 7.1 and Clause
38. The percentage to apply the value of the work not completed
representing {Cl 60} the Employer’s additional cost for completing the
Works shall be 20 per cent.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Dwarka Heliport Tender Volume SBD 23 july 2026.pdf
Dwarka Heliport Tender Volume-II (Technical Specifications).pdf
Dwarka Heliport Tender Volume-III.pdf
Drawing 01 to 39.pdf
Drawing 39 to 77.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].