| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 LAccepted-Finance NARIKULAM HOUSE KANJOOR KANJOOR ERNAKULAM DISTRICT | KANJOOR | ERNAKULAM | KERALA | ₹2.1 L | L1 | Accepted-Finance L1 |
| 2 | L2₹2.3 LAccepted-Finance | ₹2.3 L | L2 | Accepted-Finance L2 |
| Sl No | Description | Qty | Unit | DAISY JOSE L1 | VISHNU K K L2 |
|---|---|---|---|---|---|
| 1.00Appendix A | |||||
| 1.00 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 19.2 | cum | 218.99 ₹4,204.61 | 232.12 ₹4,456.70 |
| 1.00 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 1.61 | cum | 2,139.39 ₹3,450.84 | 2,267.75 ₹3,657.88 |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 4.95 | cum | 6,742.96 ₹33,377.65 | 7,147.53 ₹35,380.27 |
| 1.00 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 78.81 | sqm | 328.24 ₹25,870.24 | 347.93 ₹27,422.10 |
| 1.00 | 4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 15.64 | cum | 7,109.88 ₹1.1 L | 7,536.47 ₹1.2 L |
| 1.01 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.68 | cum | 7,850.57 ₹5,299.13 | 8,321.6 ₹5,617.08 |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 86.4 | kilogram | 95.57 ₹8,257.25 | 101.29 ₹8,751.46 |
| 1.01 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.96 | cum | 8,915.45 ₹8,558.83 | 9,450.38 ₹9,072.36 |
| 1.01 | 13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) | 46.98 | sqm | 269.71 ₹12,670.98 | 285.89 ₹13,431.11 |
Tender Value
₹2.5 L
EMD Value
₹6,261
Closing Date
15 Jun 2026, 4:30 pmClosed
Assistant Execuitive Engineer
Assistant Execuitive Engineer MINOR IRRIGATION SUBDIVISION ALUVA
Construction of canal
2026_Irrig_855308_1
IRR/IA/TR/6014/2025_5_1_1/1
Open Tender
Civil Works - Canal
270 days
Thottuiva
Please refer Tender documents.
10 documents required · 10 mandatory
₹555
Yes
₹6,261
Yes
17 Jun 2026
10 Jun 2026
16 Jun 2026
10 Jun 2026
15 Jun 2026
10 Jun 2026
10 Jun 2026 - 15 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1Appendix A | ||||||
| 1.001 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 1 | cum | - | - | BI01010001010000000000000515BI0100001114 |
| 1.002 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | - | cum | - | - | BI01010001010000000000000515BI0100001115 |
| 1.003 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | - | cum | - | - | BI01010001010000000000000515BI0100001116 |
| 1.004 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 1 | sqm | - | - | BI01010001010000000000000515BI0100001117 |
| 1.005 | 4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 1 | cum | - | - | BI01010001010000000000000515BI0100001118 |
| 1.006 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - | BI01010001010000000000000515BI0100001119 |
| 1.007 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | - | kilogram | - | - | BI01010001010000000000000515BI0100001120 |
| 1.008 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - | BI01010001010000000000000515BI0100001121 |
| 1.009 | 13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) | 1 | sqm | - | - | BI01010001010000000000000515BI0100001122 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_1445524.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
Preliminaryagmt.pdf
Tender Documents • 0.06 MB
PAY.pdf
Tender Documents • 0.04 MB
BOQ_1445524.xls
BOQ • 0.30 MB
viewsbd.pdf
Tender Documents • 2.62 MB
Download all tender documents and submit your bid