| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹31.2 CrAdmitted-Finance 26 2 SHAKTI NAGAR PAOTA C ROAD JODHPUR | JODHPUR | JODHPUR | RAJASTHAN | L1 | Admitted-Finance | ||
| 2 | L2₹31.8 Cr+₹57.0 L (1.83%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹34.3 Cr+₹3.1 Cr (9.97%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | L4₹36.9 Cr+₹5.7 Cr (18.4%)Admitted-Finance | L4 | Admitted-Finance |
Tender Value
₹39.4 Cr
EMD Value
₹50 L
Closing Date
9 Oct 2025, 6:00 pmClosed
Addl. Chief Engineer, PWD Zone-I Jodhpur
Addl. Chief Engineer, PWD Zone-I Jodhpur
Widening and Strengthening of Mertacity to Kherapa (NH-62) Via Gotan-Asop-Palari Ranavatan Road (SHW-86A) Km. 37/0 to 63/0 and 67/0 to 76/0. (Job No.CRIF/1059/RJ/2023-24)
2025_CEPWD_500160_1
Short Term NIT No.23/2025-26 of ACE PWD Zone-I Jodhpur
Open Tender
Civil Works
Percentage
425 days
Jodhpur
Please refer Tender documents.
7 documents required · 7 mandatory
₹5,000
Executive Engineer, PWD District Dn.I Jodhpur
₹50 L
Addl. Chief Engineer, PWD Zone-I Jodhpur
10 Dec 2025
11 Sept 2025
10 Oct 2025
12 Sept 2025
9 Oct 2025
12 Sept 2025
18 Sept 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | PART (A) : EARTH WORK, GRAVELLING & WMM WORK Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material up to a lead of 1000m including removal and disposal of top organic soil not exceeding in 150 mm thickness as per MoRTH specification clause 201 By mechanical Means. In area of light jungle | 10.5 | Hect. | 16,335 | ₹1,71,517.5 |
| 2 | Earth work in excavation, including stacking/disposal of surplus material with all lifts and lead upto 495 metres, exclusive of compensation of earth [MoRTH specification : Clause 301 to 305] In ordinary Soil Mechanically by power shovel, including mechanical loading and carriage by tipper/dumper (6T capacity) | 1,90,080 | Cum | 40 | ₹76,03,200 |
| 3 | Extra for laying earth as per specification for compaction in 200 mm thick loose layers and dressing [MoRTH Specification Clause 305.3.5]. a) BY MECHANICAL MEANS, using Motor Grader, from earth in stock piles with all lead and lift but excluding rolling and watering. | 1,90,080 | Cum | 25 | ₹47,52,000 |
| 4 | b) Extra for watering the earth to bring the earth upto required O.M.C excluding rolling | 1,90,080 | Cum | 18 | ₹34,21,440 |
| 5 | Extra for rolling to specification with Power Roller, 8-10 tonne when earth is at suitable moisture content with dry field density not less than 100 % of maximum dry density (Ordi-nary Procter test).excluding watering. | 1,90,080 | Cum | 26 | ₹49,42,080 |
| 6 | Carriage of Sand, bajri, ballast, stone, boulders, kankar & gravelly material includind loading & unloading Add for each subsequent Km. Lead above 1 KM. Upto 3 KM. | 47,520 | Cum | 107.98 | ₹51,31,209.6 |
| 7 | Lead above 1 KM. Upto 9 KM. | 77,220 | Cum | 125.95 | ₹97,25,859 |
| 8 | Lead above 1 KM. Upto 3 KM. | 35,640 | Cum | 107.98 | ₹38,48,407.2 |
| 9 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 1000 metres, stacking serviceable and unserviceable materials separately as per MORTH specification clause 202. By Mechanical Means : Bituminous courses | 1,873.2 | Cum | 238 | ₹4,45,821.6 |
| 10 | Providing laying, spreading and compacting specified graded crushed stone in sub-base course including premixing the material at OMC in wet mix plant, carriage of mixed material, laying in uniform layers with motor grader, F.E.loader on a prepared surface and compacting with vibratory compactor to achieve the desired density including all material, labour, mach-nery, lighting barricading and maintenance of diversion complete.[MoRTH specification Clause 401] includiong 20 Km lead. For Grading I Material | 81,534.5 | Cum | 690 | ₹5,62,58,805 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.58 MB
SBD_CRIF_JOB_1059_D1.pdf
Tender Documents • 11.08 MB
BOQ_891513.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .