Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 LAccepted-AOC | ₹2.4 L | L1 | Accepted-AOC Lowest Quoted |
| 2 | L2₹2.5 LRejected-Finance | ₹2.5 L | L2 | Rejected-Finance Highest quoted |
| Sl No | Description | Qty | Unit | ARUNSAM S L2 | Joji L1 |
|---|---|---|---|---|---|
| 1.00Appendix A-Premonsoon Cleaning Thettiyar for 2km from Technopark Phase-2 | |||||
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 4,200 | sqm | 18.59 ₹78,078 | 17.71 ₹74,382 |
| 1.00 | 50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete. | 43 | each | 386.04 ₹16,599.72 | 367.89 ₹15,819.27 |
| 1.00 | 2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth | 1 | each | 563.04 ₹563.04 | 536.57 ₹536.57 |
| 1.00 | OD33494/2025-2026: Removal of accumulated waste and deposited silt including plastic and organic waste etc in or under
water from the thodu by mechanical means or manual means with all lead and lift including
disposal of the removed accumulated plastic waste, earth,silt,clay,mud etc , complete as per the
directions of the Engineer in charge for fulfilling the final objective of removing all obstructions
and to ensure free flow of water in the thodu, and convenyance /carriage charge for rubbish/silt
collected from site to contractors own dumping area as without causing damages to
enivornment or society | 292.5 | cum | 361.12 ₹1.1 L | 344.14 ₹1.0 L |
| 1.00 | OD33495/2025-2026:Engaging man mazdoor for various works to execute the work as per direction of departmental officers at site. | 48 | each | 1,110 ₹53,280 | 1,054.22 ₹50,602.56 |
Tender Value
₹2.5 L
EMD Value
₹6,349
Closing Date
12 Nov 2025, 5:00 pmClosed
Assistant Executive Engineer
Assistant Executive Engineer Minor Irrigation Sub Division Opposite Museum Police station Observatory Hills Thiruvananthapuram 695033
GENERAL-Urban flood 2025-Emergency Cleaning Work 2025-26-Pre-monsoon cleaning work for Thettiyar thodu from Technopark phase-2 to phase-3.-General Civil Work
2025_Irrig_819805_1
IRR/IA/TR/1149/2025_5_1_1/1
Open Tender
Civil Works - Water Works
30 days
Trivandrum Corporation
Please refer Tender documents.
7 documents required · 7 mandatory
₹560
Yes
₹6,349
Yes
6 Jan 2026
6 Nov 2025
14 Nov 2025
6 Nov 2025
12 Nov 2025
6 Nov 2025
Amount
Appendix A-Premonsoon Cleaning Thettiyar for 2km from Technopark Phase-2
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete.
2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth
OD33494/2025-2026: Removal of accumulated waste and deposited silt including plastic and organic waste etc in or under water from the thodu by mechanical means or manual means with all lead and lift including disposal of the removed accumulated plastic waste, earth,silt,clay,mud etc , complete as per the directions of the Engineer in charge for fulfilling the final objective of removing all obstructions and to ensure free flow of water in the thodu, and convenyance /carriage charge for rubbish/silt collected from site to contractors own dumping area as without causing damages to enivornment or society
OD33495/2025-2026:Engaging man mazdoor for various works to execute the work as per direction of departmental officers at site.
ARUNSAM S (BID ID -2436316)
Bidder Name
ARUNSAM S
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1374381.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.06 MB
viewsbd.pdf
Tender Documents • 1.65 MB
Additionaldocuments.pdf
Additional Documents • 0.90 MB
BOQ_1374381.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid