Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical RAILWAY COLONY NOWGAM SRINAGAR JAMMU AND KASHMIR 190015 | BUDGAM | JAMMU AND KASHMIR | 190015 | Accepted-Technical As Per TEC report |
| 2 | Accepted-Technical ALLOCHI BAGH DISTT SRINAGAR J K | SRINAGAR | JAMMU AND KASHMIR | 190001 | Accepted-Technical As Per TEC report |
| 3 | Rejected-Technical | Rejected-Technical As Per TEC report |
| 4 | Rejected-Technical | Rejected-Technical As Per TEC report |
| 5 | Rejected-Technical | Rejected-Technical As Per TEC report |
Tender Value
₹2.4 Cr
EMD Value
₹4.7 L
Closing Date
6 Mar 2026, 5:00 pmClosed
ASHISH RANJAN
PCS COMPLEX GINGLE
Bituminous Carpeting of Internal Roads of Barrage at Boniyar
2026_NHPC_898574_1
NH/UPS/PCS/C-121R/NIQ-118/453 Dated 13/02/2026
Open Tender
Civil Works
Works
180 days
GINGLE BARAMULLA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,770
NHPC Limited Uri Power Station
₹4.7 L
Yes
24 Jul 2026
14 Feb 2026
12 Mar 2026
14 Feb 2026
6 Mar 2026
14 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Scarifying the existing bituminous road surface to a depth of 50mm and disposal of scarified material within all lifts and lead upto 1 km (by mechanical means) | 19,719.88 | Sqm | 5.25 | ₹1,03,529.37 |
| 2 | Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road / vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening /binding material to fill up interstices of coarse aggregate, watering and compacting to the required density. | 47.27 | Cum | 726.23 | ₹34,328.89 |
| 3 | Providing and applying tack coat using hot straight run bitumen of grade –VG-10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications. On W.B.M. @ 0.75 Kg/sqm. | 377.93 | Sqm | 55.95 | ₹21,145.18 |
| 4 | Providing and applying tack coat using hot straight run bitumen of grade –VG-10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications.On bitumen surface @ 0.50 Kg/sqm | 34,745.44 | Sqm | 42.22 | ₹14,66,952.48 |
| 5 | Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equipped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 40/50 mm compacted thickness with bitumen of grade VG-30@ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity. | 1,404.93 | Cum | 10,029.09 | ₹1,40,90,169.41 |
| 6 | Sand, stone aggregate below 40 mm nominal size By Mechanical Transport including loading, unloading and stacking complete. | 2,231.27 | Cum | 435.96 | ₹9,72,744.47 |
| 7 | Sand, stone aggregate above 40 mm nominal size By Mechanical Transport including loading, unloading and stacking complete | 47.27 | Cum | 473.92 | ₹22,402.2 |
| 8 | Tar Bitumen By Mechanical Transport including loading, unloading and stacking | 226.42 | Tonne | 957.83 | ₹2,16,871.87 |
| 9 | Painting runway / taxi track/ apron marking with adequate no. of coats to give uniform finish with road marking paint of superior make as approved by the Engineer-in-charge including cleaning the surface of all dirt, scales, oil, grease and other foreign material etc. and lining out complete.Two or more coat. | 1,102.13 | Sqm | 156.23 | ₹1,72,185.77 |
| 10 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 60.66 | Cum | 6,231.54 | ₹3,78,005.22 |
stage.html
html • 0.03 MB
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.20 MB
DTD.pdf
Tender Documents • 2.67 MB
BOQ_944496.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .