Loading…
Loading…
Tender Value
₹1.5 Cr
EMD Value
₹3.1 L
Closing Date
22 Jun 2026, 4:15 pm6d left
xen west
jda jodhpur
Road strengthening work from Nahar Road to Chopasni Road.
2026_JDAJO_567462_4
JoDA/Nit-03/West/2026-27
Open Tender
Civil Works
365 days
jda jodhpur
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,000
secretary jda jodhpur and md risl jaipur
₹3.1 L
Yes
12 Jun 2026
12 Jun 2026
23 Jun 2026
12 Jun 2026
22 Jun 2026
12 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRTH Specification Clause 201. By Mechanical Means In area of non-thorny jungle | 1.2 | Hect. | 10,374 | ₹12,448.8 |
| 2 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3 | 432 | Cum. | 25 | ₹10,800 |
| 3 | Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by Mechanical Means Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by mechanical means including a lead upto 30 m | 432 | Cum | 26 | ₹11,232 |
| 4 | Haulage of materials by tipper excluding cost of loading, unloading and stacking Case-II: Unsurfaced Gravel Road | 605 | Tone | 18.5 | ₹11,192.5 |
| 5 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400-12 & 400-13 and MoRTH Specification Clause 406 By Mechanical Means with a lead of 1 Km. For All Rajasthan except Bikaner, Churu, Hanumangarh and Sri Ganganagar | 300 | Cum | 1,044 | ₹3,13,200 |
| 6 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base(WBM/WMM) using truck mounted sprayer including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per MoRTH Specification Clause 502 | 309 | Sqm | 28 | ₹8,652 |
| 7 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.30 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per MoRTH Specification Clause 503. | 1,01,455 | Sqm | 8.75 | ₹8,87,731.25 |
| 8 | Providing and laying bituminous macadam with Drum type hot mix plant using crushed aggregates of grading as per Table 500-7 premixed with bituminous binder, transported to site with all leads laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per MoRTH Specification Clause 504 Bitumen (VG-30) | 337 | Cum. | 6,100 | ₹20,55,700 |
| 9 | Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder minimum @ 5.2 & 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH Specifications Clause 507 complete in all respects For All Rajasthan except Bikaner and Sri Ganganagar for Grading-II(13 mm nominal size) Bitumen (VG-30) | 674 | Cum. | 7,241 | ₹48,80,434 |
| 10 | Providing concrete for plain/reinforced concrete in open foundations
complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 15 Nominal mix (1:2.5:5) | 216 | Cum | 2,809 | ₹6,06,744 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.97 MB
Binder1.pdf
Tender Documents • 1.58 MB
BOQ_1009374.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid