| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹58.4 LAccepted-AOC | ₹58.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹62.0 L+₹3.6 L (6.17%)Rejected-Finance HUMJAPURA NEAR RAM JANKI MANDIR BAHRAICH | ₹62.0 L+₹3.6 L (6.17%) | L2 | Rejected-Finance REJECTED DUE TO HIGHER RATE QUOTED |
| 3 | L3₹62.6 L+₹4.2 L (7.11%)Rejected-Finance GRAM SAKHAMAI BISAULI DISTRICT BADAUN UTTAR PRADESH | BISAULI | BADAUN | UTTAR PRADESH | ₹62.6 L+₹4.2 L (7.11%) | L3 | Rejected-Finance REJECTED DUE TO HIGHER RATE QUOTED |
| 4 | L4₹64.2 L+₹5.8 L (9.94%)Rejected-Finance | ₹64.2 L+₹5.8 L (9.94%) | L4 | Rejected-Finance REJECTED DUE TO HIGHER RATE QUOTED |
| 5 | L5₹65.3 L+₹6.9 L (11.8%)Rejected-Finance 00 BEHIND COURT PHALODI NAI SARAK PHALODI JODHPUR RAJASTHAN 342301 UDYAM RJ 22 0048153 | JODHPUR | RAJASTHAN | 342301 | ₹65.3 L+₹6.9 L (11.8%) | L5 | Rejected-Finance REJECTED DUE TO HIGHER RATE QUOTED |
Tender Value
₹74.7 L
EMD Value
₹5.7 L
Closing Date
18 Mar 2026, 12:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, Bahraich-Shrawasti Circle, P.W.D., Bahraich
Construction of Dariyaonpurwa Link Road in Km.-1 and 2(50) Under Rajya Sadak Nidhi Yojna in Financial Year 2025-26 with 05 year maintenance.
2026_CEDPW_1123540_4
905/8 Kam/e_Tendering/BRH-SWT Circle/2025-26 Dated - 28-02-2026
Open Tender
Civil Works - Roads
Fixed-rate
180 days
Bahraich
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,715
₹5.7 L
Yes
Bahraich
4 Jul 2026
11 Mar 2026
18 Mar 2026
11 Mar 2026
18 Mar 2026
11 Mar 2026
13 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5m. (5fts.) and lead upto 30m. (100fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-incharges upto a distance of 30m. (100 fts.) from the foundation trenches.. As Per SI No. 251. | 40 | Cum | 125 | ₹5,000 |
| 2 | Providing concrete for plain cement concrete 1:4:8 cement, fine sand and 40mm gauge brick ballast in open foundations complete As Per SI No. 275. | 2.3 | Cum | 4,400 | ₹10,120 |
| 3 | Providing and laying O.B.B. material underneath brick work in drain complete as per drawing and technical specifications Clause 1302 | 5.3 | Cum | 2,200 | ₹11,660 |
| 4 | Providing and laying reinforced cement concrete 600mm dia NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. | 15 | Rm | 2,400 | ₹36,000 |
| 5 | Providing and laying reinforced cement concrete 350mm dia NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. | 22.5 | Rm | 1,400 | ₹31,500 |
| 6 | Brick work with 150 class brick in cement mortor 1:4 cement and coarse sand in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work As Per SI No. 305 (b). | 13 | Cum | 6,000 | ₹78,000 |
| 7 | Pointing with cement mortar (1:3) on brick work in sub structure & super structure as per drawing and technical specification clauses 613.3, 1204 and 1208.4 | 30 | Sqm | 77 | ₹2,310 |
| 8 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 50 m as per Technical Specification Clause 301.5 | 4,300 | Cum | 104.5 | ₹4,49,350 |
| 9 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per (MORD) Technical Specification Clause 401. | 492 | Cum | 4,180 | ₹20,56,560 |
| 10 | Providing, laying, spreading and compacting stone aggregated of 45-63mm gauge sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smoth wheel 80-100 KN in stages to proper grade and camber, applying and brooming, stone screening / binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading as per (MORD) Technical Specification Clauses 405. | 295 | Cum | 5,010 | ₹14,77,950 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.13 MB
T_2.pdf
Tender Documents • 0.48 MB
BOQ_2093116.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .