Executive Engineer (Civil), Construction Division, Gujarat Maritime Board, V C Fatak, Morbi
M and R to C1 and C3 Qtr. and other miscellaneous work at port Colony Mandvi
270453
15/2025-26
Open
Civil Works - Others
Works
Morbi
9 documents required · 9 mandatory
₹1,062
Yes
Executive Engineer (Civil), Construction Division, Gujarat Maritime Board, V C Fatak, Morbi - 363641
₹7,200
Yes
28 Jan 2026
28 Jan 2026
28 Jan 2026
11 Feb 2026
28 Jan 2026
Name of work: M and R to C1 & C3 Qtr. & other miscellaneous
work at port Colony Mandvi.
Amount put to tender
:: TENDER PAPER ::
Issue of tender documents (Start Date): Dt. 28/01/2026 from 18.00 hrs.
Submission of tender: Dt. 11/02/2026 up to 18.00 hrs.
Executive Engineer (C),
STANDARD BIDDING DOCUMENT
GUJARAT MARITIME BOARD
COMPLETE BIDDING DOCUMENT
Sr No Section Description Page No
1 Invitation for Bid (IFB)
2 Section -1 Instructions to Bidders
3 Section -2 Qualification Information
4 Section -3 Conditions of Contract
5 Section -4 Contract Data
6 Section -5 Technical Specification
7 Section -6 Form of Bid
8 Section -7 Bill of Quantities
9 Section -8 Securities and Other Forms
10 Section -9 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. On behalf of Chairman Gujarat Maritime Board, Executive Engineer (Civil), Gujarat
Maritime Board, PIU- Morbi invites bids for the construction of works detailed in the table.
The bidders may submit bids for any or all of the following works.
Name of Approxi Bid Cost of Period of #Class of
work mate security document completion Registration /
value of (Rs.) (Rs.) Category of
works contractor if
M and R to C1 6,08,826.05 7200/- 1062.00 03(Three) E2 class or
& C3 Qtr. & (Incl.GST) months above in public
Miscellaneous department of
work at port Government of
Colony Gujarat/India
1. https://www.nprocure.com free of cost till the Time and Date as mentioned on online NIT at
website https://www.nprocure.com.
2. However, Bidder who is submitting the Bid Online will have to pay the Bid Document
Fee/Tender Fee through Demand Draft only of any Schedule Bank payable at Morbi and in
favour of ‘Executive Engineer (Civil), Gujarat Maritime Board, Morbi. Once the Bid is received
online, Bid Document / Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid
Security / EMD shall be submitted in electronic format through online (by scanning) while
uploading the bid, this submission shall mean that bid document / tender fee and Bid Security
/ EMD has been received. Accordingly, the offer of only those shall be opened whose Bid
Document / Tender Fee and Bid Security / EMD have been received electronically. However,
for the purpose of realization of Demand Draft, and FDR / Bank Guarantee bidder shall send
the same in original through R.P.A.D. so as to reach to Executive Engineer (Civil), Construction
Division, Gujarat Maritime Board, V C Fatak, Morbi - 363641 (Telephone No. 02822- 234465)
(Fax No. 02822- 234465) within 7 Days from the last day of bid submission.
Penaltative action for not submitting Demand Draft / FDR / Bank Guarantee in original
to Executive Engineer / Tender Inviting Authority by bidder shall be initiated.
3. Bids received online, will be opened on the time, date and place as specified in the online NIT
at website https://www.nprocure.com in the presence of the bidders or their authorized
representatives, who wish to remain present.
If the office happens to be closed on the day of opening of the bids as specified, the bids will be
opened on the next working day at the same time and venue.
4. A pre bid meeting will be held on ………………………………at ………………………..hrs. at the office of
...........................................................................to clarify the issues and to answer questions on any
matter that may be raised at that stage as stated in clause 9.2 of ‘instructions to Bidders’ of the
bidding documents.
5. Bid Security (EMD) is equal to 1% of Estimated Amount put to bid / tender and should be
rounded off to the next thousand rupees.
6. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the tender
submission date and time. After the tender submission date and time, the bidder cannot
modify / edit / withdraw their submitted offer in any case. No written or online request
in this regard shall be granted.
B. Offers in physical form will not be accepted in any case.
C. Demand Draft purchased by the other then bidder and issued after the last date of
submission of Bids, will not be considered or accepted.
D. The cost incurred by the contractor for this offer for clarification or attending discussion,
conferences or site visits will not be reimbursed by the Employer or Engineer-in-Charge.
E. Conditional tender shall not be accepted.
F. Any changes, addition, alternation made in the prescribed form attached with tender are
liable to be rejected.
G. Any change in format or conditional Bank Guarantee will not be accepted and the bidder
will be considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the format
given in the checklist /qualification document / tender document.
I. It is mandatory for the bidders to supply each and every information as asked strictly in
electronic format at appropriate places only.
J. Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even if the bidder has been qualified in a similar or larger size of project in the past it shall
not be deemed to be a ground / reason for not giving required information for this work
L. Information supplied for earlier projects shall not be considered while evaluation of this
bid. The Government will not ask for any other information, unless it is found absolutely
necessary by the competent authority.
M. If found necessary, the contractor will be intimated for negotiation,
# For the works costing up to 7.5 crore (ROAD), 7.0 crore (BUILDING & BRIDGE)
kindly refer to SSR-10-2015-17-C dated 03-02-2017
Following documents shall be submitted in to the Tender opening authority through
RPAD, so as per schedule mentioned above
(i) Bid Security / EMD
(ii) Registration Certificate of Appropriate Class
(iii) Experience Certificate of similar work from any Central/State Govt./PSU/
Board/Nigam/Corporation:- 3A form to be submitted
Three similar completed works costing not less than the amount equal to 40(forty)
percent of the estimated cost; or Two similar completed works costing not less than
the amount equal to 50 (fifty) percent of the estimated cost or One similar completed
work costing not less than the amount equal to 80 (eighty) percent of the estimated
cost during last Five Years ending last day of month previous to the one in which
applications are invited
Similar Work means: Work of Repair/Maintenance of any Building
(iv) A solvency certificate of an amount equal to or above 20 percent of the
amount of work put to tender (i.e. Rs. 1,21,800/-or above) issued after dt.
01.01.2026. Such Solvency certificate should be issued by either schedule
bank or a nationalized bank
(v) GST Number/Certificate
(vi) PAN issued by Income tax department
INSTRUCTIONS TO BIDDERS
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. General D. Submission of Bids
1. Scope of Bid 8 19. Sealing & Marking of Bids
2. Source of Funds 8 20. Deadline for Submission of
3. Eligible Bidders 8 21. Late Bids
4. Qualification of the 8 22. Modification and
Bidder Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding 12 E. Bid Opening and Evaluation
7. Site Visit 12 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding 13 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding 13 27. Correction of Errors
10. Amendment of Bidding 14 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising 15 F. Award of Contract
13. Bid Prices 15 31. Award Criteria
14. Currencies of Bid and 16 32. Employer’s Right to Accept
Payment any Bid and to Reject any
15. Bid Validity 16 33. Notification of Award and
Signing of Agreement
16. Bid Security 16 34. Performance Security
17. Alternative Proposals By 17 35. Advance Payment and
Bidders Security
18. Format and Signing of Bid 17 36. Dispute Review Expert
37. Correct or Fraudulent
1. Scope of Bid
1.1 On behalf of Chairman Gujarat Maritime Board, Executive Engineer (C), Gujarat Maritime
Board, Morbi invites bids for the Construction of works (as defined in these documents
and referred to as ‘the works”) detailed in the table given in IFB. The bidders may
submit bids for any or all of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended
completion date specified in the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their
derivatives (bidder/ tenderer, bid / tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Gujarat Maritime Board.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
statement that the Bidder is neither associated, nor has been associated, directly or
indirectly, with the consultant or any other entity that has prepared the design,
specifications, and other documents for the Project or being proposed as Project
Manager for the Contract. A firm that has been engaged by the Employer to provide
consulting services for the preparation or supervision of the works, and any of its
affiliates, shall not be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
preliminary description of the proposed work method and schedule, including
drawings and charts, as necessary. The proposed methodology should include a
program of construction backed with equipment planning and deployment duly
supported with broad calculations and quality assurance procedures proposed to be
adopted justifying their capability of execution and completion of work as per
technical specifications, within stipulated period of completion.
4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on Applicant’s meeting all the following minimum pass/ fail
criteria regarding the Applicant’s general and particular experience, personnel and
equipment capabilities and financial positions, as demonstrated by the applicant’s
responses in the forms attached to the letter of application ( specified requirement for
joint ventures are given under para 4.6 below ) Subcontractors experience and
resources shall not be taken in to account in determining the applicants compliance
with the qualifying criteria
To qualify for more than one contract, the applicant must demonstrate having
experience and resources sufficient to meet the aggregate of the qualification criteria
for each contract given in paragraphs 4.5.4, 4.5.5 and 4.5.9 below
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year
Following enhancement factors will be used for the costs of works executed and the
financial figure to a common base value for works completed in India.
Year Financial Year Multiplying factor
Base year of inviting 2024-2025
Applicant should indicate actual figures of costs and amount for the works
executed by them without accounting for the above-mentioned factors.
In case the financial figures and value of completed works are in foreign
currency the above enhanced multiplying factors will not be applied. Instead, the
current market exchange rate (State Bank of India BC Selling rate as on the last date of
submission of the bid) will be applied for the purpose of conversion of the amount in
foreign currency into India rupees.
4.5.3. General Experience.
The Applicant shall meet with the following minimum criteria:
(a) Achieved a minimum annual financial turnover (defined as billing for works in
progress and completed in all classes of civil engineering construction works
only) in any one year, over the last five years (2019-20 to 2023-24) of the annual
value of contract / contracts applied for.
(b) Experience in successfully completing or substantially completing at least one
contract of highway (road and / or bridge works) airport runway of at least
percent of the value of proposed contract within the last five years (2019-20 to
The works may have been executed by the applicant as prime contractor or as a
member of a joint venture or as a nominated sub-contractor. As subcontractor,
he should have acquired the experience of execution of all major items of works
under the proposed contract. In case a project has been executed by a joint
venture, weight towards experience of the project would be given to each joint
venture in proportion to their financial participation in the joint venture.
Substantially completed works means those works which are at least 90 %
completed as on the date of submission (i.e. gross value of work done up to the
last date of submission is 90 % or more of the original contract price) and
continuing satisfactorily.
For these, a certificate from the employers shall be submitted along with the
application incorporating clearly the name of the work, contract value, billing
amount, date of commencement of works, satisfactory performance of the
contractor and any other relevant information.
4.5.4. Personnel Capabilities.
Availability for his work of personnel with adequate experience as required; as per
4.5.5. Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum suggested major
equipment to attain the completion of works in accordance with the prescribed
construction schedule are shown in the Appendix.
The bidders should, however, undertake their own studies and furnish with
their bid, a detailed construction planning and methodology supported with layout
and necessary drawings and calculations to allow the employer to review their
proposals. The numbers, types and capacities of each plant/equipment shall be shown
in the proposals along with the cycle time for each operation for the given production
capacity to match the requirements.
4.5.6. Financial Position
The Applicant should give undertaking that he has access to, or has available, liquid assets
(aggregate of working capital, cash in hand and uncommitted bank guarantees) and / or credit
facilities up to 25 percent of the value of the contract / contracts applied.
4.5.7. The audited balance sheets for the last five years should be submitted, which must
demonstrate the soundness of the applicant’s financial position, showing long – term
profitability including an estimated financial projection for the next two years If necessary,
the employer will make inquiries with the applicant’s bankers.
4.5.8. Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting
from contracts completed or under execution by him over the last five years. A consistent
history of awards against the Applicant or any partner of a joint venture may result in failure
of the applicant.
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified
Made misleading or false representation in the forms, statements submitted, and / or
Record of poor performance such as abandoning the work, rescinding of contract for
which the reasons are attributable to the non – performance of the contractor;
consistent history of litigation awarded against the applicant or financial failure due
to bankruptcy. The rescinding of contract of a joint venture on account of reasons
other than non – performance, such as Most Experienced partner of joint venture
pulling out, court directions leading to breaking up of a joint venture before the start
of work, which are not attributable to the poor performance of the contractor will,
however, not affect the qualification of the individual partners.
#4.6 JOINT VENTURE: (Maximum 3 Members i.e. 1 Lead & 2 Others)
(Applicable only for estimated project cost of 50 Crore and above)
4.6.1. Joint ventures must comply with the following requirement:
(a) Following are the minimum qualification requirements:
(i) The lead partner shall meet not less than 50 percent of all criteria given in para
4.5.3 & 4.5.6 above. The joint venture must collectively satisfy the criteria of para
4.5.3 & 4.5.6 above. The experience of the other joint venture partners shall be
considered if it is not less than 30 percent of the qualifying criteria in para 4.5.3 &
(ii) Individually each member must satisfy the requirements of para 4.5.7 & 4.5.8 above.
(b) Bid shall be signed so as to legally bind all partners, jointly and severally, and shall
be submitted with a copy of the joint venture agreement providing the joint and
several liabilities with respect to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its partners individually
or as a partner in any other joint venture. In case dissolution of a joint venture, each one
of the constituent firms may qualify if they meet all the qualification requirements, subject
to the written approval of the Employer.
4.7. Bid Capacity.
Applicants who meet the minimum qualification criteria will be qualified only if their
available bid capacity at the expected time of bidding is more than the total estimated
cost of the works. The available bid capacity will be calculated as under:
Assessed Available Bid Capacity = ( A*N*2-B), where
A = Maximum value of work executed in any one year during the last five years
(updated to the price level of the year indicated in appendix) taking into account
the completed as well as works in Progress.
B = Value at current price level of the existing commitments and ongoing works to be
completed during the next TWELVE months (period of completion of work for
which bids are invited ); and
N = Number of years prescribed for completion of the works for which the bids are
Note :- In Case of joint venture, the available bid capacity will be applied for each
partner to the extent of his proposed participation in the execution of
4.8 Even though the bidders meet the above qualifying criteria, they are subject to
be disqualified if they have:
- Made misleading or false representation in the forms, statements and
Attachments the submitted in proof the qualification requirements; and / or
- Record of poor performance such as abandoning the works, not properly
completing the contract, inordinate delay in completion, litigation history, or
financial failures etc.; and/ or
- Participated in the previous bidding for the same work and had quoted
unreasonably high bid prices and could not furnish rational justification to the
5. One bid per bidder
5.1. Each bidder shall submit only one bid for one package. A bidder who submits or
participates in more than one bid (other than as a subcontractor or in cases of
alternatives that have been permitted or requested) will cause all the proposals with
the bidder’s participation to be disqualified.
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation and submission of his Bid,
and the Employer will in no case be responsible and liable for those costs.
7.1. The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine
the Site of work and its surrounding and obtain all information that may be necessary
for preparing the Bid and entering into a contract for construction of the Works.
The costs of visiting the site shall be at the Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda
issued in accordance with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2. Volumes I, II, III and IV are available online and documents to be furnished by the
bidder in compliance to section 2 will be prepared by him and furnished as Volume- V
in two parts (refer clause 12).
8.3. The bidder is expected to examine carefully all instructions, conditions of contract,
contract data, forms, terms, and technical specifications, bill of quantities, forms,
Annexes and drawings in the Bid Document. Failure to comply with the requirements
of Bid Documents shall be at the bidder’s own risk. Pursuant to clause 26 hereof,
bids which are not substantially responsive to the requirements of the Bid Documents
shall be rejected.
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify
the Employer in writing or through E-mail at the Employer’s address indicated in the
invitation to bid. The Employer will respond to any request for clarification which he
received earlier than 15 days prior to the deadline for submission of bids. Employer’s
response will be published on website including a description of the enquiry but
without identifying its source.
9.2. Pre-bid meeting
9.2.1. The bidder or his official representative is invited to attend a pre-bid meeting which
will take place at the address, venue, time and date as indicated in the appendix.
9.2.2. The purpose of the meeting will be to clarify issues and to answer questions on any
matter that may be raised at that stage.
9.2.3. The bidder shall be required to submit any questions in writing or e-mail to reach
the Employer not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the
source of enquiry) and the responses given will be published without delay on the
tender website i.e. www.nprocure.com. Any modification of the bidding documents
listed in sub-Clause 8.1 which may become necessary as a result of the pre-bid
meeting shall be made by the Employer exclusively through the issue of an
Addendum pursuant to Clause 10 and not through the minutes of the pre-bid
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding
documents by issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The Employer
will assume no responsibility for the same.
10.3. To give prospective bidders reasonable time in which to take an addendum into
account in preparing their bids, the Employer may, at his discretion, extend as
necessary the deadline for submission of bids, in accordance with Sub-Clause
C. PREPARATION OF BIDS
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents Comprising the Bid
12.1. The bid be submitted by the bidder as Volume V of the bid document (refer Clause
8.1) shall be in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
(i) Bid Security in the form specified in Section
(ii) Qualification Information and supporting documents as specified in Section
(iii) Certificates, undertakings, affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 of these instructions
(v) Undertaking that the bid shall remain valid for the period specified in Clause
Part II shall be named “Financial Bid” and shall comprise
(i) Form of Bid as specified in Section
(ii) Priced Bill of Quantities for items specified in Section
12.2. The Bidder shall submit the details / information pertaining to each part i.e.
technical as well as financial and must be submitted online only.
12.3. Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
Invitation for Bids (IFB)
1 Instruction to Bidders Volume I
3 Conditions of Contract
4 Contract Data
5 Specifications Volume II
9 Drawings Volume IV
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on
the priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words)
for all items of the Works described in the Bill of Quantities along with total bid price
(Both in figures and words). Items for which no rate or price is entered by the bidder
will not be paid for by the Bill of Quantities.
13.3 All duties, taxes, and other levies except GST payable by the contractor under the
contract, or for any other cause shall be included in the rates, prices and total Bid Price
submitted by the Bidder. (GST will be paid extra)
13.5 The rates and prices quoted by the bidder are subject to adjustment during the
performance of the Contract in accordance with the provisions of Clause 47 of the
Condition of Contract (Irrespective of the time limit and Bid Amount)
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees.
All payments shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date
forbid submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer
may request that the bidders may extend the period of validity for a specified period.
A bidder may refuse the request without forfeiting his bid security. A bidder agreeing
to the request will not be required or permitted to modify his bid, but will be required
to extend the validity of his security for a period of the extension, and in compliance
with Clause 16 in all respects.
#16. Bid Security
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in
column 4 of the table of IFB for this particular work. This Bid security shall be in favor
of Employer as named in Appendix and may be in one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in Volume
III. (Bank Guarantee is applicable only for Bid Estimated Amount of 01 Crore and
above) and Bank Guarantee of Schedule and Private Banks shall be considered as per
GoG Finance Department’s Circular No. FD/MSM/e- file/4/2023/0057/D.M.O. Date
21/04/2023 or as per their latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank
approved by the Reserve Bank of India.
# A Valid Bid Security / EMD Exemption Certificate issued by (1) Road & Building
Department or (2) Narmada Water Resources, Water Supply and Kalpsar Department
of Govt of Gujarat. Exemption Certificate is applicable only when Registration
Certificate of Appropriate Class and Category of Approved Contractors is
required as eligible criteria of bidder.
16.2. Bank guarantees (and other instruments having fixed validity) issued as surety for
the bid shall be valid for 45 days beyond the validity of the bid i.e. total validity of
16.3. Any bid not accompanied by an acceptable Bid Security and not secured as indicated
in Sub-Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of the end
of the bid validity period specified in Sub-Clause
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed
the Agreement and furnished the required Performance Security.
16.6. The bid Security may be forfeited
(a) If the Bidder withdraws the bid after Bid opening during the period of Bid
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He will be intimated
maximum three times within the validity period for negotiation, If contractor does not
respond in time, his Bid Security (EMD) will be forfeited and his tender will be rejected.
Punitive action will be taken on such contractors. (As per GoG R&B Dept’s Gr. No.
17. Alternative Proposals by Bidders.
17.1. Bidders shall submit offers that fully comply with the requirements of the bidding
documents, including the conditions of contract (including mobilization advance or
time for completion), basic technical design as indicated in the drawing and
specifications. Conditional offers or alternative offers will not be considered further in
the process of tender evaluation.
18. Format and Signing of Bid
18.1. The Bidder shall prepare documents comprising the bid as described in Clause 12 of
these Instructions to bidder as the “Technical Bid “and “Financial Bid” in separate parts
to be uploaded.
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1. Complete Bids must be received online/ Physical form by the Employer at the tender
website/ Office Address specified above not later than the date indicated in appendix.
20.2. The Employer may extend the deadline for submission of bids by issuing an
amendment in accordance with Clause 10, in which case all right and obligation of the
Employer and the bidders previously subject to the original deadline will then be
subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1. Bidders may modify or withdraw their bids online before the deadline prescribed in
Clause 20 or pursuant to Clause
22.3. No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4. Withdrawal or modification of a bid between the deadline for submission of bids and
the expiration of the original period of bid validity specified in Clause 15.1 above or
as extended pursuant to Clause 15.2 may result in the forfeiture of the Bid security
pursuant to Clause
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant to
Clause 22, in the presence of the Bidders or their representatives who choose to attend
at time, date and the place specified in Appendix in the manner specified in Clauses
and 23.3, In the event of the specified date of Bid opening being declared a holiday for
the Employer, the Bids will be opened at the appointed time and location on the next
23.3. The “Technical Bid” shall be opened. The amount, form and validity of the bid security
furnished with each bid will be announced. If the bid security furnished does not
conform to the amount and validity period as specified in the invitation for bid (ref.
Column 4 and paragraph 3), and has not been furnished in the form specified in Clause
16, the technical bid will not be opened.
23.4. (i) Subject to confirmation of the bid security by the issuing Bank, the bids
accompanied with valid bid security will be taken up for evaluation with
respect to the Qualification information and other information furnished in
part I of the bid pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his Qualification
Documents with respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the clarification
(iv) Immediately (usually within 3 or 4 days), on receipt of these clarification the
Evaluation Committee will finalize the list of responsive bidders whose
financial bids are eligible for consideration.
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found
responsive in accordance with Clause 23.4(iv) will be announced. The bids of only
these bidders will be opened. The responsive Bidders’ names, the Bid prices, the total
amount of each bid, any discount and such other details as the Employer may consider
appropriate, will be announced by the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found responsive
in accordance with Clause 23.4(iv) will be announced. The bids of only these bidders
will be opened. The responsive Bidders’ names, the Bid prices, the total amount of
will be opened. The responsive Bidders’ names, the Bid prices, the total amount of
each bid, any discount, and such other details as the Employer may consider
appropriate, will be announced by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the
“Financial Bid” shall be in order of Estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and comparison of
Bids and recommendations for the award of a contract shall not be disclosed to
Bidders or any other persons not officially concerned with such process until the
award to the successful Bidder has been announced. Any effort by Bidder to influence
the Employer’s processing of Bids or award decisions may result in the rejection of his
25. Clarification of Financial Bids
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may,
at his discretion, ask any Bidder for clarification of his Bid, including breakdowns of
unit rates. The request for clarification and the response shall be in writing or by e-
mail, but no change in the price or substances of the Bid shall be sought, offered, or
permitted except as required to confirm the correction of arithmetic errors discovered
by the Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating
to his Bid opening to the contract is awarded. If the Bidder wishes to bring additional
information to the notice of the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decision may result in the rejection of the Bidders’ bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether
each Bid (a) meets the eligibility criteria defined in Clause 3 and 4; (b) has been
properly signed; (c) is accompanied by the required securities and; (d) is substantially
responsive to the requirements of the Bidding document. During the detailed
evaluation of the “Financial Bid”, the responsiveness of the bids will be further
determined with respect to the remaining bid conditions, i.e., priced bill of quantities,
technical specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms,
conditions and specifications of bidding documents, without material deviation or
reservation. A material deviation or reservation is one (a) which affects in any
substantial way the scope, quality, or performance of the Works; (b) which limits in
any substantial way, inconsistent with the Bidding documents, the Employer’s rights
or the Bidder’s obligations under the Contract; or (c) whose rectification would affect
unfairly the competitive position of other Bidders presenting substantially responsive
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer,
and may not subsequently be made responsive by correction or withdrawal of the non-
conforming deviation or reservation.
29. Evaluation and Comparison of Financial Bids
29.1. The Employer will evaluate and compare only the Bids determined to be substantially
responsive in accordance with Sub-Clause 26.2.
29.3. The Employer reserves the right to accept or reject any variation or deviation.
Variation and deviations and other factors, which are in excess of the requirements of
the Bidding documents or otherwise result in unsolicited benefits for the Employer,
shall not be taken in to account in Bid evaluation.
29.4. The estimated effect of the price adjustment conditions under Clause 47 of the
Conditions of Contact, during the period of implementation of the Contract, will not be
taken in to account in Bid evaluation.
29.5. If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer’s
estimate of the cost of work to be performed under the contract the Employer may
require the Bidder to produce detailed consistency of those prices with the
construction methods and schedule proposed. After evaluation of the price analyses,
the Employer may require that the amount of the performance security set forth in
Clause 34 be increased at the expense of the successful /bidder to a level sufficient to
protect the Employer against financial loss in the event of default of the successful
Bidder under the Contract.
29.6. A bid which contains several items in the bill of Quantities which are unrealistically
priced low and which cannot be substantiated satisfactorily by the bidder may be
rejected as non-responsive.
F. AWARD OF CONTRACT
31. Award Criteria
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid
has been determined.
(i) to be substantially responsive to the Bidding documents and who has offered
the lowest evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price
which is the lowest evaluation in any of the packages opened earlier than the
one consideration.
In no case, the contract shall be awarded to any bidder whose available bid
capacity is less than the evaluated bid price, even if the said bid is the lowest evaluated
bid. The contract will in such cases be awarded to the next lowest bidder at his
evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1. Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid,
and to cancel the Bidding process and reject all Bids, at any time prior to the award of
contract, without thereby incurring any liability to the affected bidder or Bidder or any
obligation to inform the affected Bidder or Bidders of the grounds for the Employer’s
33. Notification of Award and Signing of Agreement
33.1. The Bidder whose Bid has been accepted will be notified of the award by the Employer
prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by
registered letter. This letter (hereinafter and in the condition of contract called the
“Letter of Acceptance”) will state the sum that the Employer will pay the Contractor in
consideration of the execution, completion, and maintenance of the Works by the
Contractor as prescribed by the Contract (hereinafter and in the Contract called the
“Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to
the furnishing of a performance security in accordance with the provisions of Clause.
33.3. The Agreement will incorporate all agreements between the Employer and the
successful Bidder. It will be signed by the Employer and to the successful Bidder,
within 28 days following the notification of award along with the Letter of Acceptance.
Within 21 days of receipt, the successful Bidder will sign the Agreement and deliver it
to the Employer.
33.4. Upon the furnishing by the successful Bidder of the Performance Security, the
Employer will promptly notify the other Bidders that their Bids have been
34. Performance Security
34.1. (A) Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder shall
furnish to the Employer an irrevocable and unconditional guarantee from a Bank
in the form set forth in Section 8 (the “Performance Security”) for an amount equal
to 5% (five percent) of its Contract Price. In case of bids mentioned below, the
successful Bidder, along with the Performance Security,
Shall also furnish to the Authority an irrevocable and unconditional guarantee
from a Bank in the same form given at Section 8 towards an Additional
Performance Security (The “Additional Performance Security”) for an amount
calculated as under:
(a) If the Contract Price offered by the Selected Bidder is lower than 10% but
upto 20% of the Estimated Project Cost, then the Additional Performance
Security shall be calculated @ 20% of the difference in the (i) Estimated
Project Cost (as mentioned in Bid Document) - Minus 10% of the Estimated
Project Cost and (ii) Contract Price offered by the selected Bidder.
(b) If the Contract Price offered by the Selected Bidder is lower than 20% of
the Estimated Project Cost, then the Additional Performance Security shall
be calculated @ 30% of the difference in the (i) Estimated Project Cost (as
mentioned in Bid Document) - Minus 10% of the Estimated Project Cost
and (ii) Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of the
Performance Security.
(B) The Performance Security shall be valid beyond 60(sixty) days of the Defects
Liability Period and the Additional Performance Security shall be valid beyond
28 (twenty-eight) days of Project Completion Date.
34.2. If the performance security is provided by the successful Bidder in the form of a Bank
Guarantee, it shall be issued either (a) at the Bidder’s option, by a
Nationalized/Scheduled Indian bank or (b) by a foreign bank located in India and
acceptable to the Employer. As per GoG Finance Department’s Circular No.
FD/MSM/e-file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their latest
34.3. Failure of the successful Bidder to comply with the requirement of Sub-Clause
shall constitute sufficient grounds for cancellation of the award and forfeiture of the
35 Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated
in the Conditions of Contract, subject to maximum amount, as stated in the Contract
37. Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in completing for the contract
in question and will declare the firm ineligible, either indefinitely or for a stated
period of time, to be awarded a contract with National Highways Authority of India/
State PWD and any other agencies, if it at any time determines that the firm has
engaged in corrupt or fraudulent practices in completing for the contractor, or in
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the
Conditions of Contract.
APPENDIX TO ITB
Clause Reference
With respect to
1. The Name of the Employer is Executive Engineer (C), [ Cl.1.1]
Gujarat Maritime Board, V C Fatak, Morbi
2. The last five years.
3. This Annual Financial Turnover Amount is Rs. [Cl.4.5.3 (a)]
4. Value of Work is Rs.6,08,826.05
6. The cost of electric work is Rs NIL.
7. The cost of water supply / sanitary works is Rs.
8. Liquid assets and / or availability of credit facilities is [Cl.4.5.6 ]
9. Price level of the financial year …………… [Cl. 4.5.2]
10. The pre-bid meeting will take place at …………. [Cl. 9.2.1]
11. The technical Bid will be opened at the office of the
Executive Engineer (C),construction division,
Gujarat Maritime Board, Morbi on dt. 21/02/2026
12. Address of the Employer: Executive Engineer
(C),construction division, Gujarat Maritime Board,
V.C.para fatak, Morbi
14. The bid should be submitted latest by As [Cl. 20.1 &
stated on in NIT 20.2]
15. The bid will be opened at Executive Engineer [Cl. 23.1 ]
(C),construction division, Gujarat Maritime Board,
Morbi As stated
16. The Bank Draft in favor of Gujarat Maritime Board,
18. Escalation factors (for the cost of works [Cl.4.5.2]
executed and financial figure to a common base
value) for works completed
Year Financial Year Multiplying
Base year of inviting tender 2025-2026
#LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON CONTRACT WORK
[Reference CL. 4.5.5]
The contractors shall also give a list of machineries in his possession and which they
propose to use on the work.
Sr. Plant or Location Age of Make Capacity Approximate Remark
No. Machinery Machinery Value
List of Key Personnel to be deployed on Contract Work
(Reference Cl. 4.5.4)
# Employment of a qualified site Engineer by the Contractor.
The Contractor shall employ full-time technically qualified staff during the execution of this
work as under: -
1. Two graduate Civil Engineers and three diploma Civil Engineers when cost of the work
to be executed is more than Rs.50 lakhs.
2. One graduate & two Diploma, Civil Engineers when the cost of the work to be executed
is more than Rs.15 lakhs but less than Rs.50 lakhs.
3. Minimum one Diploma Civil Engineer when the cost of work is less than Rs.15 lakhs but
more than Rs.5 lakhs.
4. Minimum two Diploma Civil Engineers for the work when the cost of work to be
executed is less than Rs. 5 lakhs. The Engineer so employed for the Government work
must have sufficient experience to handle the work independently. Such an Engineer
shall have to stay at the site of work and he shall not be entrusted with other duty except
In case the contractor or partner of the contractor firm is a Civil Graduate Engineer,
Employment of a separate Engineer will not be necessary provided that the Engineer
partner himself attends the execution of the work on the site.
Within 15 days of issue of work-order the Contractor will have to furnish to the Deputy
Executive Engineer-in-charge of the work the Name, Qualifications, copy of mark sheet,
Color Photograph and the appointment order issued such engineers engaged for this
contract work. If 15 days after issue of work order such designated Site Engineers do
not resume or do not remain present on site of work, the recovery at the rate of
Rs.15,000-00 per month per Engineer will be made from the bills/deposit/dues of the
contractor. Such recovery shall be non-refundable.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for the
purpose of post qualification as provided for in Clause 4 of the Instruction to Bidders. This
information will not be incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder
Place of registration
Principal place of business
Power of attorney of signatory of Bid
1.2 Total value of Civil engineering constructions 2023-2024
Work performed in the last five years 2022-2023
(in Rs. Lakhs) 2021-2022
15.2.1 Work performed as prime contractor, work performed in the past as a nominated sub-
contractor will also be considered the sub-contract involved execution of all main
items of work described in the bid documents, provided further that all other
qualification criteria are satisfied (in the same name) on works of a similar nature over
the last five years** and in current year before the submission of the bid.
Project Name of Description Contract Value of Date Stipulated Actual date Remark
Name the of work No. contract of period of of explaining
Employer (Rs. issue completion completion* reasons for
Crore) of delay &
order Completed
*Attach certificate(s) from the Engineer(s)in-charge
** Immediately preceding the financial year in which bids are received.
#1.3.2 Quantities of work executed as prime contractor, work performed, in the past as a
nominated sub-contractor, will also be considered provided the sub-contract involved
execution of all main items of work described in the bid document, provided, further
that all other qualification criteria are called (in the same name and style) in the last
five years** and in current year before the submission of the bid.
Year Na Name of Quantity of work performed (Cum/MT) Remarks*
me the Cement Masonry Earth Bituminous (indicate
of Employer Concrete Works Work contract Ref)
1.4 Information on Bid Capacity (works for which bids have been submitted and works
which are yet to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Description Place Contract Name & Value Stipulated Value of Anticipated
of works & No. Address Contract Period of Works* of
State of (Rs. Cr) Completion remaining completion
*Attach certificate (s) from the Engineer(s) in-charge
** Immediately preceding the financial year in which bids are received.
1.5 Availability of key items of Contractors Equipment for carrying out the works (Ref.
Clause 4.5.5). The Bidder should list all the information requested below.
Item of Requirement Availability Proposals Remarks
Equipment NO Capacity Owned/ Nos/. Age/ (from
Leased to be Capacity Conditions whom to
1.6 Qualifications and experience of key personnel required for administration and
execution of the contract. Attach biographical data. Refer also to Sub Clause 9.1 of the
Conditions of Contract.
Position Name Qualification Year of Year of
Experience experience in
(General) the proposed
Project Manager
1.7 Proposed sub-contract and firms involved
Sections of the Value of Sub- Sub-Contractor Experience in
works Contractor (Name & similar work
Attach copies of certificates on possession of valid license for executing water
supply/ sanitary work/ building electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss statements,
auditors’ reports (in case of companies/corporations), etc. List them below and attach
1.9 Evidence of access to financial resources to meet the qualification requirements: cash
in hand, lines of credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders bankers who may
provide references if contacted by the Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party Employer Cause of Amount Remarks
(ies) Dispute Involved showing
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to
Bidders. (Name of Consultant engaged for project preparations is *................................. )
1.13 Proposed work method and schedule. The Bidder should attach descriptions,
drawings and charts as necessary to comply with the requirements of the Bidding
documents. (Refer ITB Clause 4.1)
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
* Fill the name of Consultant
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR
AVAILABILITY OF CREDIT FACILITIES
(CLAUSE 4.5.6 OF ITB)
BANK CERTIFICATE
This is to certify that M/s. is a reputed company
with a good financial standing.
If the contract for the work, namely is awarded to the
above firm, we shall be able to provide overdraft/credit facilities to the extent of
Rs. to meet their working capital requirements for executing the above
during the contract period.
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
_ have not abandoned any work of
Government of Gujarat/Government of India/any Board or Corporation under
Government of Gujarat/Government of India nor any contract awarded to us for
such works have been rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by
the Department to verify this statement or regarding any (our) competence and
general reputation.
4. The Undersigned understands and agrees that further qualifying information may
be requested, and agrees to furnish any such information at the request of the
Department/ Project implementing agency.
(Signed by an Authorized Officer of the Firm)
Title of Officer
I, the undersigned do hereby undertake ......... that our firm
up to 25% of the value of the work during implementation of the contract.
(Signed by an Authorized officer of the firm)
Title of officer
CONDITIONS OF CONTRACT
Conditions of Contract
Table of Contents
A General Page D. Cost Control
1 Definitions 37 37 Bill of Quantities
2 Interpretation 38 38 Changes in the Quantities
3 Language and Law 39 39 Variations
4 Engineer’s Decisions 39 40 Payments for Variations
5 Delegations 39 41 Cash Flow Forecasts
6 Communications 39 42 Payment Certificates
7 Sub-Contractors 39 43 Payments
8 Other Contractors 39 44 Compensations Events
9 Personnel 40 45 Tax
10 Employer’s & Contractor Risk 40 46 Currencies
11 Employers Risks 40 47 Price Adjustment
12 Contractor’s Risk 40 48 Retention
13 Insurance 40 49 Liquidated damages
14 Site Investigations Reports 41 50 Bonus
15 Queries about the Contract 41 51 Advance Payment
16 Contractors to Construct the 41 52 Securities
17 The Works to be Completed By 41 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 41 54 Cost of Repair
20 Discoveries 42 E. Finishing the Contract
21 Possession of the Site 42 55 Completion
22 Access to the Site 42 56 Taking Over
23 Instructions 42 57 Final Account
24 Disputes 42 58 Operating and Maintenance
25 Procedure for Disputes
26 Deleted 43 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 44 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted 44 F.Special Conditions of
30 Delays Ordered by The 44 63 Labour
Engineer 64 Compliance with labour
31 Management Meetings 45 65 Arbitration
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions
of Contract but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities forming
part of the Bid
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified by
the Engineer in accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to execute,
complete and maintain the Works till the completion of Defects Liability Period.
It consists of the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which
comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the
Work has been accepted by the Employer.
The Contractor’s Bid is the completed Bidding document submitted by the
Contractor to the Employer and includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and
calculated from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the
The Engineer is the person named in the Contract Data (or any other
competent person appointed and notified to the contractor to act in replacement of
the Engineer) who is responsible for supervising the Contractor, administering the
Contract, certifying payments due to the Contractor, issuing and valuing Variations
to the Contract, awarding extensions of time, and valuing the Compensations Events.
Equipment is Contractor’s machinery and vehicles brought temporarily to
the site to construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s
Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is specified in the
Contract Data. The Intended Completion Date may be revised only by the Engineer by
issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for
incorporation in the works.
Plant is any integral part of the work which is to have mechanical, electrical,
electronic or chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding
documents and are factual interpretive reports about the surface and subsurface
conditions at the site.
Specifications means the Specifications of the works included in the Contract
and any modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor
shall commence execution of the works. It does not necessarily coincide with any of
the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the
Contractor to carry out a part of the work in the Contract which includes work on the
Temporary Works are works designed, constructed, installed, and removed
by the Contractor which are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct, install,
and turn over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male
also means female or neuter and the other way around. Heading have no
significance. Words have their normal meaning under the language of the
Contract unless specifically defined. The Engineer will provide instructions
clarifying queries about Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the
Conditions of Contract to the Works, the Completion date, and Intended
Completion Date apply to any Section of the Works (other than references to
the Completion Date and Intended Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the following order
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming part of the
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are stated in
the Contract Data.
4. Engineers Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual
matters between the Employer and the Contractor in the role representing the
5.1 The Engineer may delegate any of his duties and responsibilities to other
people after notifying the Contractor and may cancel any delegation after
notifying the Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are
effective only when in writing. A notice shall be effective only when it is
delivered (in terms of Indian Contract Act).
7. Sub-Contracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in
contract data, with the approval of the engineer but may not assign the Contract
without the approval of the Employer in writing. Subcontracting shall not alter
the Contractor’s obligations. Sub-contracting of supply or specific items of
work is not allowed.
7.2 The sub-contractor must be registered in appropriate class and category for the
part of work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities and the Employer between the dates given in the Schedule
of other Contractor. The Contractors shall as refer to in the Contract Data, also
provide facilities and services for them as described in the Schedule. The
employer may modify the schedule of other contractors and shall notify the
contractor of any such modifications.
9.1 The Contractor shall employ the key personnel named in the Schedule of Key
Personnel as referred to in the Contract Data to carry out the functions stated
in the Schedule or other personnel approved by the Engineer. The Engineer will
approve any proposed replacement of key personnel only if their qualifications,
abilities, and relevant experience are substantially equal to or better than those
of the personnel listed in the Schedule.
9.2 If the engineer asks the Contractor to remove a person who is a member of the
Contractor Staff or his work force stating the reasons the Contractor shall
ensure that the person leaves the Site within seven days and has no further
connection with the work in the Contract.
10. Employer’s and Contractors Risks
10.1 The Employer carries the risk which these Contract states are Employer’s
risks, and the Contractor carries the risks which these Contracts states are
Contractors risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far as
they directly affect the execution of the Works, the risks of war, hostilities,
invasion, act of foreign enemies, rebellion, revolution, insurrection or military
or usurped power, civil war, riot commotion or disorder (unless restricted to
the Contractor’s employees), and contamination from any nuclear fuel or
nuclear waste or radioactive toxic explosive.
12. Contractor’s Risks
12.1 All risks of loss of or damages to physical property and of personal injury and
death which arise during and in consequence of the performance of the
Contract other than the excepted risks are the responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start date to the end of the Defects
Liability Period, in the amounts and deductibles stated in the Contract data for
the following events which are due to the Contractor’s risks:
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and
Equipment) in connection with the Contract; and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to
the Engineer for the Engineer’s approval before the Start Date. All such
insurance shall provide for compensation to be payable in the types and
proportions of currencies required to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required,
the Employer may affect the insurance which the Contractor should have
provided and recover the premiums the Employer has paid from payments
otherwise due to the Contractor or, if no payment is due, the payment of the
premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made without the approval
of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site Investigation reports
referred to in the Contract Data, supplemented by any information available to
15. Queries about the Contract data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance with the
specification and Drawings.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and
shall carry out the Works in accordance with the programme submitted by the
Contractor, as updated with the approval of the Engineer, and complete them
by the Intended Completion date
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed
Temporary works to the Engineer, who is to approve them if they comply with
the Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility for design
of the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of the
Temporary works where required.
18.5 All Drawings prepared by the Contractors for the execution of the temporary
or permanent work are subject to prior approval by the Engineer before their
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly
discovered on the site is the property of the Employer. The contractor is to
notify the engineer of such discoveries and carry out the Engineer’s
instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the Contractor. If
possession of a part is not given by the date stated in the Contract Data the
Employer is deemed to have delayed the start of the relevant activities and this
will be a Compensation Event.
21.2 If within 25% of the time limit of the project, 80% of possession of the site is
not handed over to the Contractor, then contractor/ Employer may fore-close
the contract. Contractor/Employer has to foreclose the work within 30 days
after lapse of 25%-time limit and after 30 days foreclosure option will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the
Engineer access to the Site, to any place where work in connection with the
Contract is being carried out or is intended to be carried out and to any place
where materials or plants are being manufactured/ fabricated/ assembled for
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to
works which comply with the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s accounts
and records relating to the performance of the Contractor and to have them
audited by auditors appointed by the Employer, if so required by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the
decision was wrongly taken, the decision shall be referred to Superintending
Engineer(Higher Authority)within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the matter
for conciliation within 15 days from the decision given by the Superintending
Engineer of concerned Project Implementation Unit.
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer of concerned Project
Implementation Unit, both the parties have to refer to the Chief Engineer
concern for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied
with the decision of the #Superintending Engineer, both the parties have
to refer to the #Secretary, Roads & Building Department, Government of
Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process, he may refer the
dispute to Gujarat Public Works Contract Dispute Arbitration Tribunal. If the
Contractor fails to refer a claim / dispute to the Higher Authority within
days of the notification of the Engineer's decision, the Contractor shall not be
entitled to any additional payment/claim if he doesn’t follow the above
sequence in stipulated time and he should not stop the work.
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the arbitration
procedure stated in the Special Conditions of Contract.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to the
Engineer for approval a Programme showing the general methods,
arrangements orders, and timing for all the activities in the works along with
monthly cash flow forecast.
27.2 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing
of the remaining work including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated
programme at intervals no longer than the period stated in the Contract data.
If the Contractor does not submit an updated programme within this period,
the Engineer may withhold the amount stated in the Contract data from the
next payment after the date on which the overdue programme has been
27.4 The Engineer’s approval of the programme shall not alter the Contractor’s
obligations. The Contractor may revise the programme and submit it to the
Engineer again at any time. A revised programme is to show the effect of
Variations and Compensations events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a compensation
Event occurs or a Variation is issued which makes it impossible for completion
to be achieved by the Intended Completion Date without the Contractor taking
steps to accelerate the remaining work and which would cause the Contractor
to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended
Completion Date within 35 days of the Contractor asking the Engineer for a
decision upon the effect of a compensation event or Variation and submitting
full supporting information. If the Contractor has failed to give early warning of
a delay or has failed to cooperate in dealing with a delay, the delay by this
failure shall not be considered in assessing the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the
contractor for extension of Intended Completion Date refer to the Employer his
decision. The employer shall in not more than 21 days communicate to the
engineer the acceptance or otherwise of the Engineer’s decision. If the
employer fails to give his acceptance, the Engineer shall not grant the extension
and the contractor may refer the matter under Clause
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any
activity within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a
management meeting. The business of a management meeting shall be to
review the plans for remaining work and to deal with matters raised in
accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is to
provide copies of his record to those attending the meeting and to the
Employer. The responsibility of the parties for actions to be taken is to be
decided by the Engineer either at the management meeting or after the
management meeting and stated in writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific
likely future events or circumstances that may adversely affect the quality of
the work, increase the Contract price or delay the execution of works. The
Engineer may require the contractor to provide an estimate of the expected
effect of the future event or circumstance on the contract price and completion
date. The estimate is to be provided by the Contractor as soon as reasonably
32.2 The Contractor shall cooperate with the Engineer in making and considering
proposals for how the effect of such an event or circumstance can be avoided
or reduced by anyone involved in the work and in carrying out any resulting
instruction of the Engineer.
C. QUALITY CONTROL
# 33. Identifying Defects/ Defect liability period
33.1 : Defect liability period : The contractor shall be responsible to make good and
remedy at his own expense any defect which may develop or may be noticed before
the period mentioned hereunder from the certified date of completion. The
Engineer in charge shall give the contractor a notice in writing about the defects
and the contractor shall make good the same within 15 days of receipt of the notice.
In the case of failure on the part of the contractor, the Engineer- in-charge may
rectify or remove or re-execute the work at the risk & cost of the contractor. The
Engineer-in-charge shall be entitled to appropriate the whole or any part of the
amount of security deposit towards the expenses, if any, Incurred by him in
rectification, removal or re-execution. The Defects Liability period shall be as under
two years from the certificate date of completion.
(a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall
be 3 Months from the certified date of completion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put
tender), the period shall be 12 (Twelve) months from the certified date of
completion or one monsoon, whichever is later.
(c) For major projects costing more than Rs. 1 crore, the period shall be 36 Months
from the certified date of completion which should include three monsoons.
(d) For original building works the defect liability period will be 4 years or elapse
of 4 monsoon period following date of possession of building taken over by user
agency following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September shall be
treated as the last date.
Modified vide R & B D Circular No. PAC-11-102008-2076-N dated 31/8/2009,
PRCH/102013(2976) 2759-N, Dated 27/05/2013 and Circular
No.TNC/10/2016/Clause 17A (Correction/(1)C Dated 12/05/2016]
33.2 Free maintenance guarantee period for works of Road/Bridge construction
(a) For resurfacing work of road free maintenance guarantee period one year
from the date of completion.
(b) In case of widening of the road/strengthening of the road/bridge, the
contractor shall have to give four years free maintenance guarantee from
the certified date of completion. During this period the contractor shall visit
the site every six months along with the concerned Section Officer / Deputy
Executive Engineer and will examine the work already carried out in this
contract like road work, jungle cutting, side shoulders, side gutter, road
furniture, patta etc. and will prepare Km. wise inspection report duly signed
by all concerned and any defect observed shall be done within 15 days by
the contractor at his risk and cost as per the direction of Engineer in charge.
The contractor needs to do videography of these visits and require to
submit at the time of release of FMG. If B.T. the surface during the
maintenance period of 4 years is worn out then agency shall have to provide
renewal coating as per tender item as directed by the Engineer-in- charge.
The amount equivalent to 5% of each running bill shall be withheld and will
be released after the free maintenance guarantee period (i.e. 4 years) is
However, this amount shall be released against fixed deposit or bank
guarantee pledged in the name of Executive Engineer after completion
certificate of work is issued.
(1) The flakiness and elongation index (combined) for coarse aggregates under
no circumstances shall exceed the allowable limit set forth in the relevant
clause for the material in question.
(2) 2% of the amount eligible for the payment of bituminous items shall be
withheld till the miscellaneous items like earthwork in embankment /
cutting for side shoulders, side gutters, kilometer / indicator / guard stones,
sign boards etc. are completed in all respect by the contractor. After
completion of the miscellaneous items, the above said 2% withheld amount
shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as
per Govt. letter No.: SSR/10/2015-16/26/C, Dtd. 26/11/15 for the work
costing more than Rs. 5.00 Crore.
(4) Setting up of adequate laboratory & deployment of quality engineers.
The contractor shall have to set up the laboratory with adequate equipment.
Till the setting up of adequate laboratory is completed & reported of this to
the engineer (subject to due verification by engineer’s representative) by
contractor in writing, Rs.2,00,000/- shall be withheld. The qualified quality
Engineer shall be deployed exclusively for this contract by the contractors.
If quality Engineer is not deployed by contractor within one month after the
date of work order, the amount equivalent to Rs.20,000 per month shall be
recovered till the actual deployment of quality engineer. The amount so
recovered towards the deployment of quality engineers shall not be
(5) Asphalt work will have to be cross checked as per G.R. No.:
RGN/60/2006/35/C, dtd.31/05/07 before final bill is paid.
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall maintain, at his own
risk and cost, the existing lane(s) of the road so that the traffic worthiness
and safety thereof are at no time materially inferior as compared to their
condition 10 (ten) days prior to the date of the Agreement, and shall
undertake the necessary repair and maintenance works for this purpose;
provided that the Contractor may, at his cost, interrupt and divert the flow
of traffic if such interruption and diversion is necessary for the efficient
progress of works and conforms to Good Industry Practice; provided
further that such interruption and diversion shall be undertaken by the
Contractor only with the prior written approval of the Executive Engineer
which approval shall not be unreasonably withheld. For the avoidance of
doubt, it is agreed that the Contractor shall at all times be responsible for
ensuring safe operation of the road.
33.3 The Engineer shall check the Contractor’s work and notify the Contractor of any
defects that are found. Such checking shall not affect the Contractor’s
responsibilities the Engineer may instruct the Contractor to search for a Defect and
to uncover and test any work that the Engineer considers may have a Defect.
34.1 If the engineer instructs the Contractor to carry out a test not specified in the
Specification to check whether any work has a Defect and the test shows that it
does, the Contractor shall pay for the test and any samples. If there is no defect
the test shall be a Compensation Event.
34.2 All testing charges for shall be borne by contractor as per instruction of
department (GMB) and various codal provisions /Govt Circulars .
34.3 Agency has to establish testing laboratory on site for the various test to be
carried out in the work for this purpose agency shall construct a pukka
laboratory building with all facility on site at location specified by the engineer
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects before the end
of the defects Liability Period, which begins at Completion and is defined in the
contract data. The Defects Liability Period shall be extended for as long as
Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified
defect within the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in the
Engineer’s notice, the Engineer will assess the cost of having the Defect
corrected, and the Contractor will pay this amount.
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions, installation,
testing and commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor is
paid for the quantity of the work done at the rate in the Bill of Quantities for
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to the
original specifications , drawings, designs and instructions that may appear to
him to be necessary or advisable during the progress of the work and the
contractor shall be bound to carry out the work in accordance with any
instruction in this connection which may be given to him in writing signed by
the Engineer and such alteration shall not invalidate the contract and any
additional work which the contractor may be directed to do in the manner
above specified as part of the work shall be carried out by the contractor on the
same conditions in all respects on which he agreed to do the main work and at
the same rate as are specified in the tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the tender
by more than 130%, the contractor will be paid for the quantity in excess of
130%, at the rate entered in the SOR of the year during which the excess in
quantity is first executed.
39.1 All Variations shall be included in updated programmes produced by the
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no rate is
specified in this contract, then such class of work shall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to
the one involving additional or altered class of work; where there are more
than one comparable items, the item of the contract which is nearest in
comparison with regard to class or classes of the work involved shall be
selected and the decision of the Superintending Engineer of concerned
Project Implementation Unit as to the nearest comparable item shall be final
and binding on the contractor.
(ii) If the rate cannot be derived in accordance with (i) above, such class of works
shall be carried out at the rate entered in the Schedule of Rates of the division
for the year in which the tender was received, increased or decreased by the
percentage by which the tender amount is more or less as compared to the amount
arrived at the rates in the “Schedule of Rates” of the Division in the year in which the
tender was received. If the Schedule of rates of the Division does not contain all the
items, the percentage increase or decrease of the tender shall be calculated
considering such items which were included in the “Scheduled Rates” of the division
for the year and for materials consumed on such item the rate to be charged would be
the basic rate taken into account for fixing the rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work
shall be carried out at the rate decided by the competent authorities on the
basis of detailed rate analysis after hearing the contractor before a Committee
of of two Superintending Engineers- Superintending Engineer (Civil)- Head
Quarter circle and Superintending Engineer of concerned Project
Implementation Unit.
40.2 If the additional or altered work, for which no rate is entered in the “Schedule
of Rates” of the Division is ordered to be carried out before the rate is agreed
upon, then the contractor shall within seven days of the date of receipt by him
of the order to carry out the work, inform the Engineer-in-charge of the rate,
which it is his intention to charge for such class of work and if the Engineer in
charge does not agree to this rates, he shall by notice in writing be at liberty to
cancel his order to carry out such class of work and arrange to carry it out in
such manner as he may consider it advisable, provided always that if the
contractor shall commence work or incur any expenditure in regard thereof
before the rates shall have been determined as lastly herein before mentioned,
then in such cases he shall only be entitled to be paid in respect of the work
carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate or rates as shall
be fixed by the Engineer-in-charge. In the event of the dispute, the decision of
the Superintending Engineer of the of concerned Project Implementation Unit
shall be final.
Where, however, the work is to be executed according to the designs,
drawings and specifications recommended by the contractor and accepted by
the competent authority, the alternation above referred to shall be within the
scope of such designs, drawings and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in the
proportion that the increase in the cost occasioned by alterations bears to the
cost of the original work and the certificate of the Engineer-in-charge as to such
proportion shall be final and conclusive.
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the engineer with
an updated cash flow forecast.
42. Payment certificates.
42.1 The Contractor shall submit to the Engineer monthly statements of the
estimated value of the work completed less the cumulative amount certified
42.2 The Engineer shall check the Contractor’s monthly statement within 14 days
and certify the amount to be paid to the Contractor after taking in to account
any credit or debit for the month in question in respect of materials for the
works in the relevant amounts and under conditions set forth in sub-clause
32.3 of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of the
items in the Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations and
compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce
the proportion of any item previously certified in any certificate in the light of
later information
43.1 Payments shall be adjusted for deductions for advance payments, retention,
other recoveries in terms of the contract and taxes at source, as applicable
under the law. The Employer shall pay the Contractor the amounts certified by
the Engineer within 28 days of the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the contract to
the Contractor will be made by the Employer. Hence, it is the responsibility of
the contractor to pay the GST to the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not be
paid by the Employer and shall be deemed covered by other rates and prices in
44. Compensation events
44.1 The following are compensation Events unless they are caused by the
(a) The Employer does not give access to a part of the Site by the site
Possession date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being completed
beyond the Intended Completion Date then Authority will approve EOT with
eligible contractual price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on
due date of bid submission except GST. However, any subsequent changes in
the tax structure by Government after due date of bid submission will be
compensated (+/-) on availability or submission of actual documentation.
Contractor will have to intimate Engineer regarding changes occurred in the
tax structure after bid submission. If the contractor fails to provide such
information and if any financial obligation may arise due to change in tax
structure, same will be recovered from the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the
contractor to pay the GST to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
47. Price Adjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of
labour, materials, fuels and lubricants in accordance with the following
principles and procedures and as per formula given in the contract data:
(a) The price adjustment shall apply for the work done from the start date given
in the contract data up to end of the initial intended completion date or
extensions granted by the Engineer and shall not apply to the work carried
out beyond the stipulated time for reasons attributable to the contractor.
(b) The price adjustment shall be determined during each month from the
formula given in the contract data.
(c) Following expressions and meanings during to the work done during each
R = Total value of work done during the month. It would include the amount
of secured advance granted, if any, during the month less the amount of
secured advance recovered, if any during the month. It will exclude value
for works executed under variations for which price adjustment will be
worked separately based on the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor
is not covered by the provisions of this or other clause in the contract, the unit
rates and prices included in the contract shall be deemed to include amounts
to cover the contingency of such other rise or fall in costs.
48.1 The Employer shall retain from each payment due to Contractor the proportion
stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is
48.2 On Completion of the whole of the Works half the total amount retained is
repaid to the Contractor and half when the Defects Liability Period has passed
and the Engineer has certified that all Defects notified by the Engineer to the
Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention
money with an “on demand” Bank guarantee.
In case, Contractor requests for refund of the Retention Money deducted
by the Employer under the provision of this clause, Employer shall consider the
said request of the Contractor provided that the refund hereunder shall be
made in tranches of not less than 1% (One Percent) of the Contract Price and
Contractor furnishes an irrevocable and unconditional Bank guarantee for an
equal amount substantially in the format of Bank Guarantee for Performance
Guarantee enclosed with SBD and valid up to 60 day beyond the scheduled /
extended Defects Liability Period. On completion of the whole works, the
contractor has however an option to submit a fresh irrevocable and
unconditional Bank Guarantee for an amount equal to 5% of the total value of
work executed substantially in the format of Bank Guarantee for Performance
Guarantee enclosed with SBD and valid up to 60 days beyond the Defect
Liability Period and yet refund the Retention Money Bank Guarantee submitted
for refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per
day stated in the Contract Data for each day that the Completion Date is later
than the Intended Completion Date (for the whole works or the milestone as
stated in the contract data). The total amount of liquidated damages shall not
stated in the contract data). The total amount of liquidated damages shall not
exceed the amount defined in the Contract Data. The Employer may deduct
liquidated damages from payment due to the Contractor. Payment of liquidated
damages does not affect the Contractor’s liabilities.
49.2 If the Intended Completion Date is extended after liquidated damages have
been paid, the Engineer shall correct any overpayment of liquidated damages
by the Contractor by adjusting the next payment certificate. The Contractor
shall not be entitled for any interest on the over payment calculated from the
date of payment to the date of repayment.
49.3 If the contractor fails to comply with the time for completion as stipulated in
the tender, then the contractor shall pay to the employer the relevant sum
stated in the Contract Data as Liquidated damages for such default and not as
penalty for everyday or part of day which shall elapse between relevant time
for completion and the date stated in the taking over certificate of the whole of
the works on the relevant section, subject to the limit stated in the contract
The employer may, without prejudice to any other method of recovery
deduct the amount of such damages from any monies due or to become due to
the contractor. The payment or deduction of such damages shall not relieve
the contractor from his obligation to complete the works on from any other of
his obligations and liabilities under the contract.
49.4 If, before the Time for Completion of the whole of the Works or, if applicable
any Section, a Taking Over Certificate has been issued for any part of the Works
or of a Section, the liquidated damages for delay in completion of the remainder
of the Works or of that Section shall, for any period of delay after the date stated
in such Taking-Over-Certificate, and in the absence of alternative provisions in
the Contract, be reduced in the proportion which the value of the part so
certified bears to the value of the whole of the Works or Section, as applicable.
The provisions of this Sub-clause shall only apply to the rate of liquidated
damages and shall not affect the limit thereof.
50.1 If the contractor achieves completion of the whole of the works prior to the
intended Completion Date prescribed in Contract Data the Employer shall pay
to the contractor a sum stated in Contract Data as bonus for every completed
month but subjected to maximum amount as stated in Contract Data;
which shall elapse between the date of completion of all items of works as
stipulated in the contract, including variations ordered by the Engineer and the
time prescribed in Clause
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time
limit of the works is equal or more than 6 months. The bonus would be paid as
% of Time Saved % of Initial Contract Price
entitled for Bonus
Less than 10% 0%
51. Advance Payment.
51.1 The Employer shall make advance payment (not to be paid less than two
installments except in special circumstances for which the reason to be
Recorded in writing) to the Contractor of the amounts stated in the Contract
Date by the date stated in the Contract Date, against provision by the Contactor
of an Unconditional Bank Guarantee in a form and by a bank acceptable to the
Employer in amounts and currencies equal to be at least 110% of the advance
payment. The guarantee shall remain effective until the
advance payment has been repaid, but the amount of the guarantee shall be
progressively reduced by the amounts repaid by the Contractor. The
Mobilization advance would be deemed as interest bearing advance at an
interest rate of 10 % to be compounded, quarterly.
51.2 The Contractor is to use the advance payment only to pay for Equipment, plant
and Mobilization expenses required specifically for execution of the Works. The
Contractor shall demonstrate that advance payment has been used in this way
by supplying copies of invoices or other documents to the engineer.
51.3 The advance payment shall be repaid by deduction proportionate amount from
payments otherwise due to the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No account shall be taken of the
advance payment or its repayment in assessing valuations of work done,
variations, price adjustments, Compensation Events, or Liquidated damages.
52.1 The performance Security (including additional security for unbalanced bids)
shall be provided to the Employer no later than the date specified in the Letter
of Acceptance and shall be issued in an amount and form and by a bank or
surety acceptable to the Employer, and denominated in Indian Rupees. The
performance Security shall be valid until a date 60 days from the date of expiry
of Defects Liability Period and the additional security for unbalanced bids shall
be valid until a date 28 days from the date of issue of the certificate of
54. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the Works
between the Start date and the end of Defects Correction periods shall be
remedied by the Contractor at the Contractor’s cost if the loss or damages arises
from the Contractor’s acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion
of the works and the Engineer will do so upon deciding that the work is
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the
Engineer issuing a certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of the total
amount that the Contractor considers payable as full and final settlement of all
claims under the Contract for items before the end of the Defects Liability
Period. The Engineer shall issue a Defect Liability Certificate and certify any
final payment that is due to the Contractor within 56 days of receiving the
Contractor's account if it is correct and complete. If it is not, the Engineer shall
issue within 56 days a schedule that states the scope of the corrections or
additions that are necessary. If the Final Account is still unsatisfactory after it
has been resubmitted, the Engineer shall decide on the amount payable to the
Contractor and issue a payment certificate, within 56 days of receiving the
Contractor’s revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of excesses
and savings in final account is observed, the Engineer/Employer shall be at
liberty to restrict the final payment of BOQ items to the lowest amount
evaluated of the bids considering the final quantities and the rates quoted
including the rebates if any. Payment of variation items shall however be made
at the rates approved by the Employer, within 90 days from the physical
completion of work.
58. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals are required,
the Contractor shall supply them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates
stated in the Contract data, or they do not receive the Engineer’s approval, the
Engineer shall withhold the amount stated in the Contract Data from payments
due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party
causes a fundamental breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the
1. The contractor stops work for 28 days when no stoppage of work is shown
on the current programme and the stoppage has not been authorized by the
2. The Engineer instructs the Contractor to delay the progress of the Works
and the instructions is not withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into liquidation
other than for a reconstructions or amalgamation
4. A payment certified by the Engineer is not paid by the Employer to the
Contractor within 56 days of the date of the Engineer’s certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a
fundamental breach of Contract and the Contractor fails to correct it within
a reasonable period of time determined by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the number of days
for which the maximum amount of liquidated damages can be paid as
defined in the Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged in corrupt
or fraudulent practices in competing for or in executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the offering,
giving, receiving or soliciting of anything of value to influence the action of a
public official in the procurement process or in contract execution. “Fraudulent
practice” means a misrepresentation of facts in order to influence a
procurement process or the execution of a contract to the detriment of the
borrower, and includes collusive practice among Bidders (prior to or after bid
submission) designed to establish bid prices at artificial non-competitive levels
and to deprive the Borrower of the benefits of free and open competition.
59.3 When either party to the Contract gives notice of a breach of contract to the
Engineer for a cause other than those listed under Sub Clause 59.2 above, the
Engineer shall decide whether the breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by
the Contractor, the Engineer shall issue a Certificate for the value of the work
done less advance payments received up to the date of the issue of the
certificate, less other recoveries due in terms of the contract, less taxes due to
deducted at source as per applicable law and less the percentage to apply to the
work not completed as indicated in the Contract data. Additional Liquidated
Damages shall not apply. If the total amount due to the Employer exceeds any
Damages shall not apply. If the total amount due to the Employer exceeds any
payment due to the Contractor the difference shall be a debt payable to the
60.2 If the Contract is terminated at the Employer’s convenience or because of a
fundamental breach of Contract by the Employer, the Engineer shall issue a
certificate for the value of the work done, the cost of balance material brought
by the contractor and available at site, the reasonable cost of removal of
equipment, repatriation of the Contractor’s personnel employed solely on the
works, and the Contractor’s cost of protecting and securing the Works and less
advance payment received up to the date of the certificate, less other recoveries
due in terms of the contract and less taxes due to deducted at source as per
applicable law.
61.1 All materials on the Site, Plant Equipment’s, Temporary Works and Works are
deemed to be property of the Employer, if the Contract is terminated because
of a Contractor’s default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other event
entirely outside the control of either the Employer or the Contractor the
Engineer shall certify that the Contract has been frustrated. The Contractor
shall make the Site safe and stop work as quickly as possible after receiving this
certificate and shall be paid for all work carried out before receiving it and for
any work carried out afterwards to which commitment was made.
F. SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make
his own arrangements for the engagement of all staff and labour, local or other,
and for their payment of housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer
a return in detail, in such form and at such intervals as the Engineer may
prescribe, showing the staff and the numbers of the several classes of labour
from time to time employed by the Contractor on the site and such other
information as the Engineer may require.
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his sub-
contractor shall abide at all times by all existing labour enactments and rules
made thereunder, regulations, notification and bye laws of the State or central
Government or local authority and any other labour law (including rules),
regulations, bye laws that may be passed or notifications that may be issued
under any labour law in future either by the State or the Central Government
or the local authority. Salient features of some of the major labour laws that are
applicable to the construction industry are given below. The Contractor shall
keep the Employer indemnified in case any action is taken against the Employer
by the competent authority on account of contravention of any of the provisions
of any Act or rules made thereunder, regulations or notifications including
amendments. If the Employer is caused to pay or reimburse, such amounts as
may be necessary to cause or observe, or for observance of the provisions
stipulated in the notifications/bye laws/Acts/Rules/regulations including
amendments, if any, on the part of the Contractor, the Engineer/employer shall
have the right to deduct any money due to the Contractor including his amount
of performance security. The Employer/Engineer shall also have the right to
recover from the Contractor any sum required or estimated to be required for
making good the loss or damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be
treated as the employees of the Employer at any point to time.
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS APPLICABLE TO
ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS WORK
A) Workmen Compensation Act 1923 :- The Act provides for compensation in case
of injury by accident arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee under the
Act on satisfaction of certain conditions on separation if an employee has
completed 5 years service or more on death, the rate of 15 days wages for every
completed year of service. The Act is applicable to all establishments employing
or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952:- The Act Provides for
monthly contributions by the employer plus workers @ 10% or 8.33% The
benefits payable under the Act are :
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951 :- The Act provides for leave and some other benefits
to women employees in case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides for
certain welfare measures to be provided by the Contractor to contract labour and
in case the Contractor fails to provide, the same are required to be provided, by the
Principal Employer by Law. The principal Employer is required to take Certificate
of Registration and the Contractor is required to take license from the designated
Officer. The Act is applicable to the establishments or Contractor of Principal
Employer, if they employ 20 or more contract labour.
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the Act, if
the employment is a scheduled employment. Construction of Building, Roads,
Runways are scheduled employment.
G) Payments of wages Act 1936:- It lays down as to by what date the wages are to
be paid, when it will be paid and what deductions can be made from the wages of
H) Equal remunerations Act 1979 :- The Act provides for payment of equal wages
for work of equal nature to Male and Female workers and for not making
discrimination against female employees in the matter of transfer, training and
promotions etc.
I) Payments of Bonus Act 1965 :- The Act is applicable to all establishments
employing 20 or more employees. The Act provides for payments of annual bonus
subject to a minimum of 8.33% of wages and maximum of 20 % of wages to
employees drawing Rs. 3500/- per month or less. The bonus to be paid to
employees getting Rs, 2500/- per month or above Rs. 3500/- per month shall be
worked out by taking wages as Rs. 2500/- per month only. The Act does not
apply to certain establishments. The newly set-up establishments are exempted
for five years in certain circumstances. Some of the State Governments have
reduced the employment size from 20 to 10 for the purpose of applicability of this
J) Industrial Disputes Act 1947 :- The Act lays down the machinery and procedure
for resolutions of Industrial disputes, in what situations a strike or lock-out
becomes illegal and what are the requirements for laying off or retrenching the
employees or closing down the establishment.
K) Industrial employment (standing Orders) Act 1946 :- It is applicable to all
establishments employing 100 or more workmen (employment size reduced by
some of the State and Central Government to 50). The Act provides for laying
down rules governing the conditions of employment by the Employer on matters
provided in the Act and get the same certified by the designated Authority.
L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade
unions of workmen and employers. The Trade Unions registered under the Act
have given certain immunities from civil and criminal liabilities.
M) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits
employment of children below 14 years of age in certain occupations and process
and provides for regulation of employment of children in all other occupations
and processes. Employment of Child labour is prohibited in Building and
Construction Industry.
N) Inter – State Migrant workmen’s (Regulation of Employment & Conditions of
service) Act 1979:- The Act is applicable to an establishment which employs 5 or
more inter-state migrant workmen through an intermediary (who has recruited
workmen in one state for employment in the establishment situated in another
state).The inter-state migrant workmen, is an establishment to which this Act
becomes applicable, are required to be provided certain facilities such as housing,
medical aid, traveling expenses from home upto the establishment and back, etc.
O) The Building and Other Construction workers (Regulation of employment
and Conditions of Service) Act 1996 and the Cess Act of 1996:- All the
establishments who carry on any building or other constructions work and
employ 10 or more workers are covered under this Act.
All such establishments are required to pay cess at the rate not exceeding 2% of
the cost of construction as may be modified by the government. The Employer of
the establishment is required to provide safety measures at the Building or
construction work and other welfare measures, such as canteens, First Aid
facilities, Ambulance, Housing accommodations for workers near the workplace
etc. The Employer to whom the Act applies has to obtain a registration certificate
from the Registering Officers appointed by the Government.
P) Factories Act 1948 :- The Act lays down the procedure for approval of plans
before setting up a factory, health and safety provisions, welfare provisions,
working hours, annual earned leave and rendering information regarding
accidents or dangerous occurrences to designated authorities. It is applicable to
premises employing 10 persons or more with aid of power or 20 or more persons
without the aid of power engaged in the manufacturing process.
Q) Royalty charges-The contractor shall pay the royalty to the competent
authority as per rule. The royalty charges paid shall be borne by the
contractor and shall not be reimbursed by the Employer.
R) Following Pollution control Acts and amendments made thereof from
time to time shall be applicable.
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental management
plan for best energy use, waste management, the reduction of pollution as
in EMS (Environmental Management system)ISO-14001-
65. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the decision
was wrongly taken, the decision shall be referred to Superintending
Engineer of concerned Project Implementation Unit (Higher Authority)
within 14 days of the notification of the Engineer's decision. If the issue is not
resolved, any party can refer the matter for conciliation within 15 days from
the decision given by the #Superintending Engineer of concerned Project
Implementation Unit.
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer, of concerned Project
Implementation Unit both the parties have to refer to the #Chief Engineer
concerned for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with
the decision of the Superintending Engineer, both parties have to refer to
the #Secretary, Roads & Building Department, Government of Gujarat for
the conciliation process.
If the dispute is not resolved through the conciliation process,
contractor may refer the dispute to Gujarat Public Works Contract Dispute
Arbitration Tribunal. If the Contractor fails to refer a claim / dispute to the
Higher Authority within 14 days of the notification of the Engineer's
decision, the Contractor shall not be entitled to any additional
payment/claim if he doesn’t follow the above sequence in stipulated time.
However, during such period, he would not stop the work in any case.
Clause Reference With
respect To section
Item marked “N/A” do not apply to this Contract.
1. The Employers is [CL.1.1]
Name: Executive Engineer (C ) Construction division, Gujarat maritime
Address: Gujarat Maritime Board, near Visipara fatak, Morbi
Name of authorized Representative
2. The Engineer is Executive Engineer (C ),
Name of Authorized Representative: Executive Engineer (C ),Deputy
Executive Engineer, Additional Assistant Engineer
3. The Defects Liability Period is o n e years from the date of [CL.1.1&33]
4. The Start Date shall be 1st days for the date of issue of the Notice [CL.1.1]
to proceed with the work.
5. The Intended Completion Date for the whole of the works is [CL.1.1,17&2]
Three months after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period from the start date
Milestone 1 i.e. 25 % 30 days.
Milestone 2 i.e. 50 % 60 days.
Milestone 3 i.e. 75 % 90 days.
Milestone 4 i.e. 100 % 120 days
6. The Site is located at Mandvi [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of Miscellaneous Civil Works [CL.1.1]
Site clearance; setting – out and layout; widening of existing
carriageway and strengthening including camber corrections;
construction of new road/ Parallel service road; bituminous pavements
remodeling/construction of Junctions, intersections, bus bays, lay-bays;
supplying and placing of drainage Channels, flumes, guard posts and
guard other related items; construction/extension of cross drainage
works, bridge, approaches and other related stones; protective works
for roads/bridge; all aspects of quality assurance of various
components of the works; rectification of The defects in the completed
works during the Defects Liability Period; submission of “As- built’’
drawings and any other related documents; and other item of work as
may be required to be carried out for completing the work in
accordance with the drawings and the provisions of the contract and to
(B) Bridge Works
Site clearance; setting out, provision of foundations, piers abutments and
bearing; prestressed/reinforced cement concrete superstructure;
wearing coat, hand railings, expansion joints, approach slabs, drainages
spouts/ downtake pipes, arrangements for fixing light posts, water
mains, utilities etc; provision of suitably designed protective works;
providing wing/return walls; provision of road markings, road signs etc.;
all aspects of quality assurance; clearing the site and handing over the
works on completion; rectification of the defects during the Defects
Liability Period and submission of “As-built” drawings and other related
documents; and other items of work as may be required to be carried out
for completing the works in accordance with the drawings and the
provisions of the contract and to Insure safety
(C) Other Items [CL.1.1]
Any Other Items as required to fulfill all contractual obligations as per the Bid
10. The following documents also form part of the Contract: [CL.2.3(9)]
As per clause 2-3 Addendum/ Corrigendum/ undertaking given by
contractor, if any
11. The law which applies to the Contract is the law of Union of India [CL.3.1]
12. The language of the Contract documents is English [CL.3.1]
13. Limit of subcontracting 25% of the Initial Contract Price [CL.7.1]
14. The Schedule of Other Contractors [CL.8]
15. The Schedule of Key Personnel As per Annex – II to Section I [CL.9]
16. The minimum insurance cover for physical property, injury and death [CL13]
is Rs. 5 lakhs per occurrence with the number of occurrences limited to
four. After each occurrence, the contractor will pay an additional
premium necessary to make insurance valid for four occurrences
17. Site Investigation report [CL.14]
18. The Site Possession dates shall be the date of the issuance of work order [CL.21]
19. The period for submission of programme for approval of the engineer [CL. 27.1]
shall be 21 days from the issue of Letter of Acceptance.
20. The period between program updates will be 30 days. [CL.27.3]
21. The amount to be withheld for late submission of an updated programme shall be
22. The following events shall also be Compensation Events Substantially adverse ground
conditions encountered during the
course of execution of work not provided for in the bidding document.
(i) Removal of underground utilities detected subsequently
(ii) Significant changes in classification of soil requiring additional mobilization by
the contractor, e.g. ordinary soil to rock excavation,
(iii) Removal of unsuitable material like marsh, debris dumps, etc. not caused
by the contractor.[CL. 27.3]
(iv) Artesian conditions
(v) Seepage, erosion landslide
(vi) River training requiring protection of permanent work
(vii)Presence of historical, archeological or religious structures,
monuments interfering with the works
(viii) Restriction of access to ground imposed by civil, judicial, or
military authority
23. The currency of the Contract is Indian Rupees [CL. 46]
24. The formula (e) for adjustment of prices are as under: [CL.47]
• If any of the commodities like Cement, Steel or Bitumen are not
found applicable in a work, the weight component of that
commodities {i.e. ‘Cement’ (Pc), ‘Steel’ (Ps) or ‘Bitumen' (Pb) as
indicated in SBD for the purpose of Price Adjustment} shall be
clubbed with the weight component of ‘Other Material’ (Pm), such
that the gross % weight of the components shall remain as 100% .
R = value of work as defined in Clause 47.1 of Conditions of Contract
Adjustment for labour component
(i) Price adjustment for increase or decrease in the cost due to
labour shall be paid in accordance with the following formula:
VL = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for local
L0 = The consumer price index for industrial workers for the
State on 28 days preceding the scheduled date of opening
of technical Bids as published by Labour Bureau, Ministry
of Labour, Government of India
Li = The consumer price index for industrial workers for the State
for the month under consideration as published by the
Labour Bureau, Ministry of Labour, Government of India.
Pl = Percentage of labor component of the work.
Adjustment for cement component.
(ii) Prices adjustment for increase or decrease in the cost of
cement procured by the contractor
Vc = Increase or decrease in the cost of work during the
month under consideration due to changes in rates
C0 = The all India wholesale price index for Ordinary Portland
Cement on 28 days preceding the scheduled date of
opening of technical bid as published by the Office of
the Economic Adviser,
Department for Promotion of Industry and Internal
Trade, Ministry of Commerce & Industry.
Ci = The all India average wholesale price index for Ordinary
Portland Cement for the month under consideration as
published by Office of the Economic Adviser, Department
for Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Pc = Percentage of cement component of the work
Adjustment for steel component
(iii) Price adjustment for increase or decrease in the cost of steel procured by the
contractor shall be paid in accordance with the following formula
Vs= Increase or decrease in the cost of work during the month under consideration
due to changes in the rates for steel
So= The all India wholesale price index for steel (Mild Steel - Long Products
Rebars) on 28 days preceding the date of opening of Bids as published by the
Office of the Economic Adviser, Department for Promotion of Industry and
Internal Trade, Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel - Long Products
Rebars) for the month under consideration as published by Office of the
Economic Adviser, Department for Promotion of Industry and Internal
Trade, Ministry of Commerce & Industry.
Ps = Percentage of steel component of the work
Note : For the application of this clause, the index of Mild Steel- Long
products Rebars has been chosen to represent the steel group.
Adjustments of bitumen component
(iv) Price adjustment for increase in the cost of bitumen shall be paid in
accordance with the following formula
Vb = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for bitumen.
Bo = The official retail price of bitumen at the IOC depot at the nearest
centre on the day 28 days prior to the scheduled date of opening of
Bi = The official retail price of bitumen of IOC depot at the nearest centre
for the 15th day of the month under consideration.
Pb = Percentage of bitumen component of the work
Adjustment of POL (fuel and lubricant) component
(v) Price adjustment for increase or decrease in cost of POL (fuel and
lubricant) shall be paid in accordance with the following formula
Vf = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for fuel and lubricants.
Fo = The official retail price of High Speed Diesel (HSD) at the existing
consumer pumps of IOC at the nearest centre on the day 28 prior to the
date of opening of Bids.
Fi = The official retail price of HSD at the existing consumer pumps of
IOC at the nearest centre for the 15th day of the month of the under
Pf = Percentage of fuel and lubricants component of the work
Note: For the application of this clause, the price of High-Speed diesel Oil has
been chosen to represent the fuel and lubricants group.
Adjustment for Construction Machinery
(vi) Price adjustment for increase or decrease in the cost of plant and
Machinery spare procured by the Contractor shall be paid in accordance
with the following formula
Vp= Increase or decrease in the cost of work during the month under
consideration due to changes in rates for plant and machinery spares
P0 = The all India wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month
under consideration as published Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Pi = The all India average wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month
under consideration as published Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Pp = Percentage of plant and machinery spares component of the work.
Note: For the application of this clause, index of Heavy Machinery and parts
has been chosen to represent the Plant and Machinery Spares group
Adjustment of other materials Component
(vii) Price adjustment for increase or decrease in cost of local materials other
than cement, steel, bitumen and POL procured by the contractor shall
be paid in accordance with the following formula
Vm = Increase or decrease in the cost of work during the month under
consideration due to change in rates for local materials other than
cement, steel, bitumen and POL.
M0 = The All Indian wholesale price index (all commodities) on 28 days
preceding the scheduled date of opening of technical Bids, as published
by the Office of the Economic Adviser, Department for Promotion of
Industry and Internal Trade, Ministry of Commerce & Industry.
Mi= The All India wholesale price index (all commodities) for the month
under consideration as published by the Office of the Economic
Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Pm = Percentage of local material components (other than cement,
steel, bitumen and POL) of the work.
The following percentage will govern the price adjustment for the
entire contract:
2. Cement – Pc ……%
25. The proportion of payments retained (retention money) shall be 6% {CL. 48}
from each bill subject to a maximum of 5% of final contract price.
26. Amount of Liquidated damages for For Whole of work {CL.49}
delay in completion of works (1/2000)th of the Initial contract
price, rounded off to the nearest
Thousand, per day. For sectional
Completion (wherever specified In
item 6 of Contract data) (1/2000)th of
initial contract price for #5 km
Section, rounded off to the nearest
thousand per day.
27. Maximum limit of liquidated damages 10 percent of the Initial {CL. 49}
For delay in completion work Contract Price rounded off to
the nearest thousand
28. Amount of Bonus for early completion Amount of bonus for early
Completion of work shall be given
as per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances Amount (Rs.) Conditions to
i Mobilization 10% of the contract On submission of unconditional
Price Bank Guarantee. (to be drawn
before the end of 20% of the
contract period). The contractor
may furnish four bank guarantees
of 2.5 % of each valid for the full
ii Equipment 90% for new and 50% of After equipment is brought to site
depreciated value for old (provided the Engineer is
equipment. Total amount satisfied That the equipment is
equipment. Total amount satisfied That the equipment is
will be subject to a required for performance of the
maximum of 5% of the contract) and on submission of
Contract Price unconditional Bank Guarantee for
amount of advance
iii Secured Deleted
Brought to site
(The advance payment will be paid to the Contractor no later than 28 days after
fulfillment of the above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the interim
payments certified by the Engineer under the Contract. Deduction shall commence
in the next Interim Payment Certificate following that in which the
total of all such payments to the Contractor has reached not less than 20 percent of
the Contract Price or 6 (six) months from the date of payment of first installment
of advance, whichever period concludes earlier, and shall be made at the rate of
percent (collectively for both Mobilization Advance and Equipment Advance)
of the amounts of all Interim Payment Certificate until such time as the loan has
been repaid, always provided that the loan shall be completely repaid prior to the
expiry of the original time for completion pursuant to Clause 17 and
33. The securities shall be for the following minimum amounts equivalent {CL. 52}
As a percentage of the Contract Price:
Performance Security for 5 percent of contract price plus Rs. …………….. (to be
decided after evaluation of the bid) as additional security in terms of ITB Clause
The standard form of Performance security acceptable to the Employer shall be an
unconditional Bank Guarantee of the type as presented in Section 8 of the Bidding
34. The Schedule of Operating and maintenance Manuals…..N/A. {CL. 58}
35. The date by which “as– built” drawings (in scale as directed) in 2 sets {CL. 58} are
required within 28 days of the issue of certificate of completion of the whole or
section of the work, as the case may be.
36. The amount to be withheld for failing to supply “as built” drawings {CL. 58} by the
Date required is Rs ................... Lakhs.
37. The following events shall also be fundamentals breach of contract: {CL.59.2} “The
Contractor has contravened Sub- clause 7.1 and Clause 9 of GCC”
38. The percentage to apply the value of the work not completed representing {Cl 60}
the Employer’s additional cost for completing the Works shall be 20 per cent.
TECHNICAL SPECIFICATION
• Material Specifications
• General Specifications
• Item Specifications
MATERIAL SPECIFICATIONS
General instruction for material and workmanship
All material and workmanship shall be according to the latest Indian Standard Specifications in
addition to the specification given below. Relevant IS specifications shall be followed for matters not
covered by these specifications. Wherever the above specifications and IS codes are silent, the
construction shall be carried out according to sound engineering practice and as per the instruction
1.1 Water shall not be salty brackish and shall be clean, reasonably clear and free objectionable
quantities of slit and traces of oil add injurious alkalies, salts organic matter and other deleterious
material which will either weaken the mortar of concrete or cause efflorescence or attack the steel
in R.C.C. Container for transport, storage and handling of water shall be clean. Water shall conform
to the standard specified in I.S. 456-1978.
1.2 If required by the Engineer-in-Charge it shall be tested by comparison with distilled water.
Comparison shall be made by means of standard cement tests for soundness time of setting
and mortar strength as specified in I.S. 269-1976. Any indication of unsoundness, charge in
time of setting by 30 minutes or more or decrease of more than 1 per cent in strength of mortar
prepared with water sample when compared with the results obtained with mortar prepared
with distilled water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It shall
be free of elements, which significantly affect the hydration reaction or otherwise interfere
with the hardening of mortar or concrete during currying or those which produce
objectionable stains or other unsightly deposits on concrete or mortar surfaces.
1.4 Hard and bitter water shall not be used for curing.
1.5 Portable water will generally found suitable for curing mortar or concrete.
2.1 Lime shall be hydraulic lime as per I.S. 712-1973 Necessary tests shall be carried out as per
I.S. 6932 (Parts I to X)
2.2 The following field tests for limes are to be carried out.
2.3 A very rough idea can be formed about the type of lime by its visual examination i.e. fat lime
bears pure white color, lime in form of porous lumps of dirty white color indicates quick lime and
solid lumps are the unburnt lime stone.
2.4Acid tests for determining the carbonate contain in lime Excessive amount of impurities and
rough determination of class of lime.
2.5Storage shall comply with I.S.712-1973. The slaked lime, if stored shall be kept in a weather
proof and damp-proof shed with impervious floor and sides to protect it against rain, moisture,
weather and extraneous materials mixing with it. All lime that has been damaged in any way shall
be rejected and all rejected materials shall be removed from site of work.
2.6Field testing shall be done according to I.S. 1624-1974 to show the acceptability of materials.
Cement shall be ordinary Portland slag cement as per I.S.269-1976 or Portland slag cement as per I.S.
M-4 White Cement
4.1 The white cement shall confirm I.S. 8042-E-1978.
M-5 Coloured Cement
5.1 Coloured cement shall be with white of gray Portland cement as specified in the item of the
5.2 The pigments used for coloured cement shall be of approved quality and shall not exceed 10%
of cement used in the mix. The mixture of pigment and cement shall be properly ground to
have a uniform colour and shade. The pigments shall have such properties as to provide for
durability under exposure to sunlight and weather. The pigments shall have such properties
as to provide for durability under exposure to sunlight and weather.
5.3 The pigment shall have the property such that it is neither affected by the cement nor
detrimental to it.
6.1 Sand shall be natural sand, clean, well graded, hard strong, durable and gritty particles free
from injurious amounts of dust, clay kankar nodules, soft or flaky particles shale, alkali salts organic
matter, loam. Mica or other deleterious substances and shall be got approved from the Engineer-In-
Charge. The sand shall not contain more contain more than 8 percent of silt as determined by field
test. If necessary the sand shall be washed to make it clean.
6.2 Coarse Sand : The fineness modulus of coarse sand shall not be less than 2.5 and shall not
exceed 3.0. The sieve analysis of coarse shall be as under :
I.S.Sieve Percentage by weight I.S. Sieve Percentage by weight Designation
passing sieve Designation passing sieve
2.36 mm 90 to 100 300 Micron 5-70
The fineness modulus shall not exceed 1.0. The sieve analysis of fine sand shall be as under:
I.S. Sieve Percentage by weight I.S. Sieve Percentage by weight
Designation passing sieve Designation passing sieve
7.1 Grit shall consist of crushed or broken stone and be hard, strong, dense, durable, clean of proper
gradation and free from skin or coating likely to prevent proper adhesion of mortar. Grit shall
generally be cubical in shape and as far as possible flaky elongated pieces shall be avoided. It shall
generally comply whit the provisions of I.S. 383-1970. Unless special stone of particular quarries is
mentioned grit shall be obtained from the best black trap or equivalent hard stone as approved by
the Engineer-in-charge. The grit shall have no deleterious with cement.
7.2 The crushing strength of grit will be such as to allow the concrete in which it used to build-up the
specified strength of concrete.
7.3 The necessary tests for grit shall be carried out as per the requirements of I.S. 2386- (parts-I to
VIII) 1963, as per instructions of the Engineer-in-charge. The necessity of test will be decided by
the Engineer-in-charge.
M-08 Lime Mortar
8.1 Lime: Lime shall conform to specification M-2 Water: Water shall conform to specification M-1
Sand : Sand shall conform to specification M-6.
8.2 Proportion of Mix:
8.2.1 Motor shall consist of such proportions of slaked lime and sand as may be specified in item.
The slaked lime and sand shall be measured by volume.
8.3 Preparation of mortar:
8.3.1 Lime mortar shall be prepared by wet process as per I.S. 1635-1971. Power driven mill shall
be used for preparation of lime mortar. The slaked lime shall be placed in the mill in an even
layer and ground for 180 revolutions with sufficient water. Water shall be added as required
during grinding (care being taken not to add more water) that will bring the mixed material to
a consistency of stiff paste. Thoroughly wetted sand shall then be added evenly and the mixture
ground for another 180 revolutions.
8.4.1 Mortar shall always be kept damp, protected from sun and rain till used up, covering it by
tarpaulin or open sheds.
8.5.1 All mortar shall be used as soon as possible after grinding. It should be used on the day on
which it prepared. But in no case mortar made earlier than 36 hours shall be permitted for
M- 9Brick Bats Aggregate
9.1 Brick bat aggregate shall be broken from well burnt or slightly over burnt and dense bricks. It
shall be homogeneous in texture, roughly cubical in shape, clean and free from dirt of any other
foreign material. The brick bats shall be of 40 mm, 50mm size unless otherwise specified in the item.
The under burnt of over burnt brick bats shall not be allowed.
9.2The brick bats shall be measured by suitable boxes or as directed.
10.1The brick shall be hand or machine molded and made from suitable soils and kiln burnt. They
shall be free from cracks and flaws and nodules of free lime they shall have smooth rectangular faces
with sharp corners and shall be uniform colour.
The bricks shall be molded with a frog of 100mm. X 40mm. and 10mm. to 20mm. deep on one of its
flat sides. The bricks shall not break when thrown on the ground from a height of 600mm.
10.2The size of modular bricks shall be 190mm. X 90mm. X 90mm.
10.3The size of the conventional bricks shall be as under :
10.4Only bricks of one standard size shall be used on one work. The following tolerances shall be
permitted in the conventional size adopted in a particular work.
Length ± 1/8” (3.0 mm.) Width ± 1/16” (1.50mm.) Height ± 1/16” (1.50mm.)
10.5 The crushing strength of the bricks shall not be less than 35 Kg./Sq. Cm. The average water
absorption shall not be more the 20 percent by weight. Necessary tests for crushing strength and
water absorption etc. shall be carried out as per I.S. 3495 (Part-I to IV) –
11.1 The stone shall be of the specified variety such as Granite /Trap Stone/ Quartzite or any other
type of good hard stones. The stones shall be only from the approved quarry and shall be hard sound,
durable and free from defects like cavities, cracks, sand holes, flaws injurious veins, patches of loose
or soft materials etc. and weathered portions and other structural defects or imperfections tending
to affect their soundness and strength. The stone with round surface shall not be used. The
percentage of water absorption shall not be more than 5% of day weight. When tested in accordance
with I.S.1124-1974. The minimum crushing strength of stone shall be 200 Kg./Sq. Cm. unless
otherwise, specified.
11.2The samples of the stone to be used shall be got approved before the work is started.
11.3The Khanki facing stone shall be dressed by chisel as specified in the item for khanki facing in
required shape and size. The face of the stone shall be so dressed that the busing on the exposed face
shall not project by more than 40mm from the general wall surface and on face to be plastered it shall
not project by more than 19 mm nor shall it have depressions more than 10 mm. from the average
M-1 2Laterite Stone
1 2.1Laterite stone shall be obtained from the approved quarry. It shall be compacted in texture
sound, durable and free from soft patch. It shall have minimum crushing strength of 100 Kg/Sq. Cm
in ites dry condition. I shall not absorb water more than 20% of its own weight, when immersed for
24 hours in water. After quarrying, the stone shall be allowed to weather for some time before using
12.2The stone shall be dressed into regular rectadngular block so that all faces are free from
waviness and unevenness, and the edges true and square.
12.3Those types of stone in which white clay occurs should not be used.
12.4Special corner stones shall be provide where so directed.
M-13 Mild Steel Bars
1 3.1Mild steel bars reinforcement for R.C.C. work shall conform to I.S. 432 (Part-II) 1966 and shall
be of tested quality. It shall also comply with relevant part of I.S. 456-1978.
13.2All the reinforcement shall be clean and free from dirt, paint, grease, mill scale or loose or thick
rust at the time of placing.
13.3For the purpose of payment, the bar shall be measured correct up lto 10 mm. length and weight
payable worked out at the rate specified below.
1. 6 mm 0.22 Kg./Rmt 8 20 mm 2.47 Kg./Rmt
2. 8 mm 0.39 Kg./Rmt 9 22 mm 2.98 Kg./Rmt
3. 10 mm 0.62 Kg./Rmt 10 25 mm 3.85 Kg./Rmt
4. 12 mm 0.89 Kg./Rmt 11 28 mm 4.83 Kg./Rmt
5. 14 mm 1.21 Kg./Rmt 12 32 mm 6.31 Kg./Rmt
6. 16 mm 1.58 Kg./Rmt 13 36 mm 7.99 Kg./Rmt
7. 18 mm 2.00 Kg./Rmt 14 40 mm 9.86 Kg./Rmt
M-14 High Yield Strength Steel Deformed Bars
14.1 High yield strength steel deformed bars shall be either cold twisted other rolled and shall
conform to I.S. 1786-1966 and I.S. 1139-1966 respectively.
14.2Other provisions and requirements shall conform to specification no. M-16 for Mild Steel Bars.
M-15 High Tensile Steel Wires
15.1 The high tensile wires for use in prestressed concrete work shall conform to I.S. 2090-1962.
15.2 The tensile strength of the high tensile steel bars shall be as specified in the item. In absence of
the given strength the minimum strength shall be taken as per Para 6-1 of the I.S. 1785-1962. Testing
shall be done as per I.S. requirements.
1 5.3The high tensile steel shall be free from loose mill scale, rust, oil, grease, or any other harmful
matter. Cleaning of steel bars may be carried out by immersion insolvent solution. Wire brushing or
passing through a pressure box containing Carborudum.
15.4The high tensile wire shall be obtained from manufactures in coils having diameter not less than
350 times the diameter of wire itself so that wire springs back straight on being uncoiled.
M-16 Mild Steel Binding Wire
16.1 The mild steel wire shall be of 1.63mm or 1.22 mm.,{ 16to 18 gauge ) diameter and shall conform
rust to I.S. 280-1972.
16.2The use of black will be permitted for biding reinforcement bars. It shall be free from rust oil
paint, grease, loose mill scale or any other undesirable coating which may prevent adhesive of cement
M-17 Structural Steel
17.1 All structural Steel conform to I.S. 226-1985. The steel shall be free from the defects mentioned
in I.S. 226-1975 and shall have a smooth finish. The material shall be –free from loose mill scale. Rust
pits or other defects affecting the strength and durability. River bars shall conform to I.S. 1148-1973
17.2When the steel is supplied by the contractor test certificate of the manufacturers shall be
obtained according to I.S. according to I.S. 226-1975 and other relevant Indian Standards.
M-18 Galvanized Iron Sheets
18.1 The Galvanized iron sheets shall be plain or corrugated sheet of gauges as specified in item.
The G.I. Sheets shall conform to I.S. 277-1977. The sheets shall be undamaged in carriage and
handling either by rubbing off of zinc coating or otherwise. They shall have clean and bright surface
and shall be free from dents, bends, holes, rust or white powdery deposit.
18.2 The length and width of G.I. sheet shall be directed as per site condition.
M-19: Galvanized Iron Valleys gutter, ridge
19.1 The G.I. ridges and hips shall be of plain galvanized sheets Class-3 of the thickness as specified
in item. Theses shall be 600 mm, in width and property bent up to shape without damage to
the sheets in process of bending.
19.2 Valleys gutters and flashings shall also be of galvanized sheet of thickness as specified in item
Valleys shall be 900 mm, wide overall and flashing shall be 380 mm. wide overall. They shall
be bent to the required shape without damage to the sheet in the process of bending.
M-20 Asbestos Cement Sheets
20.1Asbestos cement sheets plain, corrugated of semi-corrugated shall conform to I.S. 459-1970.
The thickness of the sheets shall be as specified in the item. The sheets shall be free from all defects
such as cracks, holes, and deformities chipped edges or otherwise damaged.
M-21 Ridges & Hips :
21.1 Ridges and hips shall be of same thickness as that of A.C. sheets. The types, of ridges of ridges
shall be suitable for the type of sheets and location.
21.2 Other accessories to be used in roof such as flashing pieces eaves filler pieces, valley gutters,
nor the light and ventilator curves, barge boards etc., shall be of standard manufacture and shall be
suitable for the type of sheets and location.
M-22 Mangalore Pattern Roof Tiles
22.1. The Mangalore pattern tiles shall conform to I.S. 654-1972 for Class AA or Class A type as
specified in item Samples of the tiles to be provided shall be got approved from the Engineer-
in-charge. Necessary tests shall be carried out as directed.
M-23 Shuttering
23.1 The shuttering shall be either of wooden planking of 30 mm minimum thickness with or
without steel lining or of steel plates stiffened by steel angles. The shuttering shall be supported on
battens and beams and props of vertical bellies properly cross-braced together so to make the
centering rigid. In places of bullies props, brick pillar of adequate section built in mud mortar may
23.2 The formwork shall be sufficiently strong and shall have camber. so that it assumes correct
shape after deposition of the concrete and shall be able to resist forces caused by vibration of live
load of men work in over it and other incidental loads associated with it. The shuttering shall have
smooth and even surface and its joints shall permit leakage of cement grout.
23.3 If at any stage of work during or after placing concrete in the structure. The formwork sags or
bulges out beyond the required shape of the structure, the concrete shall be removed and work
redone with fresh concrete and adequately the complete formwork shall be got inspected by and got
approved form the Engineer-in-charge. before the reinforcement bars are placed in position.
23.4 The props shall consist to having 100 mm. minimum diameter measured at mid length and
mm at thin end shall be placed as per design requirement. These shall rest squarely on wooden sole
plates 40 mm thick and minimum bearing area of 0-10 sq. m. laid on sufficiently hard base.
23.5 Double wedges shall further be provided between the sole plate and the wooden props so as to
facilitate tightening and easing of shuttering without jet king the concrete.
23.6 The timber used in shuttering shall not be so dry as to absorb water from concrete and swell
or bulge nor so green or wet as to shrink after erection. The timber shall be properly sawn and
planed on the sides and the surface coming in contact with concrete. Wooden formwork with metal
sheet lining or steel plates stiffened by steel angles shall be permitted.
23.7 As far as practicable, clambs shall be used to hold the forms together and use of nails and spikes
23.8 The surface of timber shuttering that would come in contact with concrete shall be well wetted
and coated with soap. solution before the concreting is done. Alternatively coat of raw linseed oil or
oil of approved manufacture may be applied in place of soap solution. In case of steel shuttering
either soap solution or raw linseed oil shall be applied after thoroughly cleaning the surface. Under
no circumstances black or burnt oil shall be permitted.
23.9 The shuttering for beams and slabs shall have camber of 4 mm. per meter (1 in 250) or as
directed by the Engineer-in-charge so as to offset the subsequent deflection. For cantilevers, the
camber at free end shall be 1/50 of the projected length or as directed by the Engineer-in-charge.
M-24 Expansion Joints –Permoulded filler
24.1 The item provides for expansion joints in R.C.C. Frames structure for internal joints, as well as
exposed joints, with the use of promoulded bituminous joints filler.
24.2 Premoulded bituminous joints filler i.e. performed strip of expansion joints filler shall not get
deformed or broken by twisting bending or other handling when exposed to atmospheric condition.
Pieces of joints filler that have been damaged shall be rejected.
24.3 Thickness of the per-moulded joints filler shall be 25 mm. unless otherwise specified.
24.4 Premoulded bituminous joints filler shall conform to I.S. 1838-1961.
M-25 Expansion Joints –Copper strips & hold fasts
25.1 The item provide for expansion joints in R.C.C. frames structure for internal joints, as well as
exposed joints, with use of premoulded bituminous joints filler.
25.2 Copper sheet shall be of 1.25 mm. width and or 1.25 mm. width and the “U” shape in the middle
Copper strip shall have holdfast of 3mm diameter copper rod fixed to the plate soldered on strip at
intervals of about 30 cm or as shown in the drawing or as directed. The width of each flange(
horizontal side ) of the expansion joints, in the copper plate shall be of 25 mm.
26.1 The teak wood shall be of good quality as required for the item to be executed. When the kind
of wood is not specifically mentioned, good Indian teak wood as approved shall be used.
26.2 Teak wood shall generally be free from large, loose dead or cluster knots flaws shakes, wraps
twists, bends or any other defects, It shall generally be uniform in substance and of straight fibres,
as far as possible. It shall be free from rot decay, harmful fungi and other defects of harmful nature
which will affect the strength, durability or its usefulness for the purpose for which it is required.
The color shall be uniform as far as possible. Any effort like paining using any adhesive materials
made to hide the defects shall render the pieces liable to rejection by the Engineer-in-charge.
26.3 All scantlings, plunks etc., shall be straight lines and planes in the direction of grains and of
uniform thickness.
26.4 The tolerance in the dimensions shall be allowed at the rate of 1.5 mm per face to be plande.
M-27 First Class teak wood
27.1 First class teak wood shall have no individual hard and sound knots, more than 6 sq. cm. in
size and the aggregate area of such knots shall not be more than 1% of area of piece. The timber
shall be closed grained.
M-28 Second Class Teak Wood:
28.1 No individuals hard and sound knots shall be more than 15 sq.cms. In size and aggregates area
of such knots shall be not exceed 2% of the area of piece.
M-29.A Non-Teak wood
29.1 The non-teak wood shall be chemically treated. seasoned as per I.S. Specifications and of good
quality. The type of wood shall be got approved before collecting the same on site. Fabrication of
wooden members shall be started only after approval.
29.2 For this purpose wood of Bio. Kalai, Sires, Saded, Behda, Jamun, Sisco, will be used for door
where as only Kalai, Sires, Halda, Kalam etc. will be permitted for shutters after proper seasoning
and chemical treatment.
29.3 The non-teak wood shall be free from large, loose dead of cluster knots, flows, shakes, wraps,
bends or any other defects, It shall be uniform in substances and of straight fibers as far as possible.
It shall be free from rots, decay, harmful fungi and other defects of nature which will effect the
strength, durability or its usefulness for the purpose for which it is required. The colour of wood
shall be uniform as far as possible. The scantlings planks etc. shall be saw in straight lines and planes
in the direction of grain and of uniform thickness. The department will use the Agency to produce
certificate from Forest Department in event of Dispute and the decision of the Department shall be
final and binding to the contractor. The tolerance in the dimension shall be allowed at 1.5 mm. per
face to be planed.
M-30 Wooden flush door shutters (solid core)
30.1 The solid core type flush door shutters shall be of decorative or non-decorative type as
specified in the drawing. The size and thickness of the shutter shall be as specified in drawings
or as directed. The timber species for core shall be used as per I.S. 2202 (part-I) 1980. The
timber shall be free from decay and insect attack. Knots and knot holes less than half the width
of cross-section of the members in which they occur may be permitted. Pitch pockets, pitch
streaks and harmless pinholes shall be permissible except in the exposed edges of the core
members. The commercial plywood cross-bands shall conform to I.S. 303-1275.
30.2 The face panel of the shutters shall be formed by gluing by the hot press process on both faces
of the core with either plywood or cross-bands and face veneers. The hopping, rebating
opening of glazing venation etc., shall be provided it specified in the drawing.
30.3 All edges of the door shutters shall be square. The shutters shall be free from twist or wrap in
its plane. Both faces of the shutters shall be sand papered to smooth even texture.
30.4 The shutters shall be tested for-
(1) End immersion test: The test shall be carried out as per I.S.2202 (part-1) 1980. There
shall be no delamination at the end of the test.
(2) Knife Test : The face panel when tested in accordance with I.S. 1659-1979 shall pass the
(3) Glue adhesion test: The flush door shall be tested for glue adhesive test in accordance
with I.S.2202 (part-I) 1980. The shutters shall be considered to have passed the test if no
delamination occurred in the assembly glue lines between the plywood face and the style
and rail. Delamination at the corner shall be measured corner shall be measured
continuously around the corner. Delamination at the knots, knothole and other
permissible wood defects shall not be considered in assessing the sample.
30.5 The tolerance in size of solid core type flush door shall be as under.
In Normal thickness ± 1.2 mm. In Nominal height ± 3 mm.
30.6 The thickness of the shutter shall be uniform throughout with a permissible variation of not
more than 0.8 mm. when measured at any two points.
M-31 Aluminium doors, windows ventilators
31.1 Alluminium alloy used in the manufacture of extruded window sections shall conform to I.S.
designation HWA-WP of I.S. 733-1975 and also to I.S. Designation WVG-WP of I.S. 1285-1975.
The section shall be as specified in the drawing and design. The fabrication shall be done as
31.2 The hinges shall be cast or extruded aluminum hinges of same type as in window but of larger
31.3 The hinges shall normally be of 50 mm. projecting type. Non-projecting type of hinges may
also be used if directed. The handles of door shall be provided. In double shutter door, the
first closing shutter shall have concealed aluminium alloy bolt at top and bottom.
M-32 Rolling Shutters
32.1 The rolling shutters shall conform to I.S. 6248-1979. Rolling shutters shall be supplied of
specified type with accessories. The size of the rolling shutters shall be specified in the
drawings. The shutters shall be specified in the drawings. The shutters shall be constructed
with interlocking lath sections formed from cold rolled steel strips not less than 0.9-mm. thick
and 80 mm. wide for shutters up to 3.5 mm. width not less than 1.25 mm. thick and 80 mm.
wide for shutter 3.5 mm. in width and above unless otherwise specified.
32.2 Guide channels shall be of mild steel deep channel section and of rolled pressed or built up
(fabricated) joint less construction. The thickness of sheet used shall not be less than
32.3 Hood covers shall be made of M.S. Sheets not less than 0.90 mm. thick. For shutters having
width 3.5 meters and above, the thickness of M.S. sheet for the hood cover shall be not less
32.4 The spring shall be of best quality and shall be manufactured from tested high tensile spring
steel wire of strip of adequate strength to balance the shutters in all position. The spring pipe
shaft etc., shall be supported on strong M.S. of malleable C.I. brackets. The brackets shall be
fixed on or under the lintel as specified with rawl plugs and screws bolts etc.
32.5 The rolling shutters shall be of self-rolling up to 8 Sq.m. clear area without ball bearing and
up to 12 Sq.m. clear area with ball bearing. If the rolling shutters are of larger, then gear
operated type shutters shall be used.
32.6 The locking arrangement shall be provided at the bottom of shutter at both ends. The shutters
shall be opened from outside.
32.7 The Shutters shall be completed with door suspension shafts, looking arrangements, pulling
hooks, handles and other accessories.
M-33 Collapsible Steel Gate
33.1 The collapsible steel gate shall be in one or two leaves and size as per approved drawings or
as specified. The gate shall be fabricated from best quality mild steel channels, flats etc. Either
steel pulleys or ball bearings shall be provided in every double channel. Unless otherwise
specified the particulars of collapsible gate shall be as under.:
(a) Pickets : These shall be of 20 mm. M.S. channels of heavy sections unless otherwise shown on
drawing. The distance center to center of pickets shall be 12 cms. with and opening or 10 cms.
(b) Pivoted M.S. flats shall be 20 mm X 6 mm.
(c) Top and bottom guides shall be from tee of flat iron of approved size.
(d) The fittings likes stoppers fixing, locking cleats, brass handles and cast iron rollers shall be of
approved design and size.
M-34 Welded Steel Wire Fabric
34.1 Welded steel wire fabric for general purpose shall be manufactured from cold drawn steel
wire “as drawn” or galvanized steel conforming to I.S. 226-1975 with longitudinal and
transverse wire securely connected at every intersection by a process of electrical resistance
welding and conforming to I.S.4948-1974. It shall be fabricated and finished in workman like
manner and shall be free from injurious defects and shall be rust proof. The type of mesh shall
be oblong or square as directed. The mesh sizes and sizes if wire for square as well as oblong
welded steel wire fabric shall be as directed. The steel wire fabric in panels shall be in one
whole piece in each panel as far as stock sizes permit.
M-35 Expanded Metal Sheets
35.1 The expanded metal sheets shall be free from flaws joints broken strands laminations and
other harmful surface defects. Expanded metal steel sheet shall conform to I.S.412-1975,
except that blank sheets need not be with guaranteed mechanical properties. The size of the
diamond mesh of expanded metal and dimensions of strands (width and thickness) shall be as
specified. The tolerance on nominal weight of expanded metal sheets shall be of ± 10 percent.
35.2 Expanded metal in panels shall be in one whole piece in each panel as far as stock sizes permit.
The expanded metal sheets shall be coated with suitable protective coating to prevent
M-36 Mild Steel Wire (Wire Gauze Jail)
36.1 Mild steel wire may be galvanized as indicated. All finished steel wire shall be well cleanly
drawn to the dimensions, and size of wire as specified in item. The wire shall be sound free
from splits surface flaws, rough jagged and imperfect edges and other harmful surface defects
and shall conform to I.S.280-1978.
37.1 The plywood for general purpose shall conform I.S.303-17-1975.
Plywood is made by cementing together than boards or starts of wood into panels. There are
always an odd number of layers, 3, 5, 7, 9, ply etc. The plies are placed so that grain of each
layer is at right angels to the grain in the adjacent layer.
37.2 The chief advantages of plywood over a single board of the same thickness is the more uniform
strength of the plywood, along the length and width of the plywood and grater resistance to
cracking and splitting with change in moisture content.
37.3 Usually synthetic resins are used to giing, phenolic resions are usually cured in a hot press
which compressesand simultaneously heats the plies between hot plates which maintain a
temperature of 90 degree C to 140 degree C and a pressure of 11 to 14 Kg/ Sq.Cm. on the wood.
The time of heating may be anything from 2 to 60 minutes depending up on thickness.
37.4 When water glue are used the wood absorbs so much water that the finished plywood must
be dried caregully, When, synthetic resigs are used as adhesive the finished plywood must be
exposed toan atomosphere of controlled humadity untill the proper amount of moisture has
37.5 According to I.S. 303-1975 the plywood for general purpose shall be of the gradesnamely
BWR, WWR and CWR, depending upto the adhesive used for bonding the veneers, and it will
be further classified in to six types namely AA,AB,AC, BB,BC, and CC based on the quality of the
two faces each face being of three kind namely A, Band C After pressing, the finished plywood
should be reconditioned to a moisture content not less than 8 percent and not more than
37.6 Thickness of plywood Boards.
Board Thickness Board Thickness Board Thickness Board Thickness
3 ply 3 mm 5ply 5 mm 7 ply 9 mm 9 ply 16 mm
6 mm 8 mm 9-ply 13 mm 11 ply 25 mm
38.1 All glass shall be of the beif quality, free from specks, bubbles, smokes veins, air hole
blisters, and other defects. The kind of glass to be used shall be as mentioned in the item or
specification or in the special provision or as shown in detailed drawings. Thickness of glass panes
shall be uniform. The specification of different kinds of glass shall be as under,
38.2. Sheet Glass
38.2.1. In absence of any specified thickness or weight in the item or detailed specifications of the
item of work, sheet glass shall be weighing 73.5 Kg./Sq. m. for panes upto 600mm x 600mm.
38.2.2 For panes larger than 600mm x600 mm and up to 800 mm x 800 mm the glass weighing not
less than 8.75 Kg/Sq.m. shall be used. For bigger panes up to 900 mm x 900 mm glass
weighing not less than 8.75 Kg./Sq. m. shall be used. For bigger panes up to 900 mmx 900 mm
glass weighing not less than 11.25 Kg/Sq.m. shall be used.
38.2.2.1 Shee glass shall be patent-flattened glass of best quality and for glazing and framing
purposes shall conform to I.S. : 1761-1960. Sheet glass of the specified colors shall be used.
If so shown, on detailed drawing or so specified. For important building and for panes with
any dimension over 900 mm plate glass of specified thickness shall be used.
38.3 Plate Glass :
38.3.1 When plate glass is specified it shall be polished patent plate glass of best quality it shall have
both the surface ground. flat and parallel and polished to obtained clear undisturbed vision
and reflection. The plate glass shall be of the thickness mentioned in the item or as shown in
the detailed drawing or as specified. In absence of any specified thickness. the thickness of
plate glass to be supplied shall be 6 mm and a tolerance of 0.20 mm. shall be admissible.
38.4 Obscured Glass :
38.4.1 This type of glass transmits light so that vision is partially or almost completely obscured.
Glass shall be plain rolled, figured, ribbed of fluted, or frosted glass as may be specified as
required. The thickness and type of glass shall be as per details on drawings or as specified or
38.5 Wired Glass :
38.5.1 Glass shall be with wire netting embedded in a sheet planet glass. Electrically welded 13 mm.
Georgian square mesh shall be used. Thickness of glass shall not be less than 6 mm. Wired
glass shall be of type and thickness as specified.
M-39 Acrylic Sheets
39.1 Acrylic sheets shall be of thickness as specified in the item and of unspecified shape and size
as the case may be panels may be flat or curved. It should be light in weight. It shall be colourless
or coloured or opaque as specified in the item. Colourless sheet shall be as transparent as the
finest optical glass. Its light transmission rate shall be about 95% Transparency shall not be
affected for the sheets of larger thickness. It shall be extremely resistant to sunlight weather and
now temperatures.
It shall not sow any significant yellowing or change in physical properties or loss of light
transmission over a longer period of use. The sheet shall be impact resistant also. Sheets should
be of such quality that they can be cut, bent jointed as desired Solution for the joints shall be used
as per the requirement of manufacturer.
M-40 Particle board
40.1 The particleboards used for ace panels shall of best quality free from any defects. The
particleboards shall be made with phenol aldehyde adhesive. The particleboards shall
conform I.S.3087-1965. “Specification for wood particle board for general purpose” The size
and the thickness shall be as indicated.
M-41 Expanded polystyrene or framed sty roper slabs
41.1 The expanded polystyrene ceiling boards and tiles shall be of approved make and shall be of
sizes, thickness, finish and colour as indicated. It shall be of high density and suitable for use
as insulating material. The insulating material shall be like slab of Thermo Cole etc.
M-42 Resign bonded fibre glass
42.1 The resign bonded fiberglass tiles or rolls shall be of approved make and shall be of sizes,
thickness and finish as indicated.
42.2 For test of Mineral wool thermal insulation Blanket I.S. 3144-1965 shall be followed.
42.3 Insulation wool blanket shall be with the following coverings on one or both sides as indicated
(1) Bituminized Hessian Kraft paper suitable for use in position where moisture has to be
(2) Hessian cloth or Kraft paper for keeping out dust.
(3) G.I. wire netting, suitable for surfaces to be plastered over.
M-43 Fixtures and fastenings
43.1.1 The fixtures and fastenings, that is butt hinges tee and strap hinges sliding door bolts, tower
bolts, door latch, bath-room latch, handles, door stoppers, casement window fasteners,
casement stays and ventilators catch shall be made of the metal as specified in the item or its
43.1.2 They shall be of iron, brass, aluminum chromium plated iron, chromium plated brass, copper
oxidized iron, copper oxidized brass or anodized aluminum as specified.
43.1.3The fixtures shall be heavy medium or light type. The fixtures and fastenings shall be smooth
before finished and shall be such as will ensue ease of operations.
43.1.4 The samples of fixtures and fastenings shall be got approved as regards, quality and shape
before providing them in position.
43.1.5 Brass and anodized aluminum fixtures and fastenings shall be bright finished.
43.2 Holdfasts :
43.2.1 Holdfasts shall be made from mild steel flat 30 cm. length and one of the holdfasts shall be
bent at right angle and two nos. of 6 mm. diameter holes, shall be made in it for fixing it to the
frame with screws. At the other end, the holdfast shall be forked and bent at right angles in
opposite directions.
43.3 Butt hinges
43.3.1 Railway standard heavy type butt hinges shall be used when so specified.
43.3.2 Tee and strap hinges shall be manufactured from M.S. Sheet.
43.4 Siding door bolts (Aldrops) :
43.4.1 The aldrops as specified in the item shall be used and shall be got approved.
43.5 Tower bolts (Barrel Type) :
43.5.1 Tower bolts as specified in the item shall be used and shall be got approved.
43.6 Door Latch :
43.6.1 The size of door latch shall be taken as the length of latch.
43.7 Bathroom Latch :
43.7.1 Bathroom latch shall be similar to tower bolt.
The size of the handles shall be determined by the inside grip length of the handles. Handles
shall have a base plate of length 50 mm. more than the size of the handle.
43.9 Door Catch :
43.9.1 Door stoppers shall be fixed at a height of about 900 mm. from the floor level such that one
part of the catch is fitted on the inside of the shutter and the other part is fixed in the wall with
necessary wooden plug arrangements for appropriate fixity. The catch shall be fixed 20 mm.
inside the face of the door for easy operation of catch.
43.10 Door Stoppers :
43.10.1 Door catch shall be fixed at a height to about 900mm. from the floor level such that one
part of the catch is fitted on the inside of the shutter and the other part is fixed in the wall with
necessary wooden plug arrangements for appropriate fixity. The catch shall be fixed 20 mm.
inside the face for the door for easy operation of catch.
43.11 Wooden Door Stop with hinges :
43.11.1 Wooden door stop of size 100 mm. X 60 mm. X 40 mm. shall be fixed on the doorframe
with a hinges of 75-mm. sizes and at a height of 900 mm. from the floor level. The wooden
doorstop shall be provided with 3 coats of approved oil paint.
43.12 Casement Window Fastener :
43.12.1 Casement window fastener for single leaf window shutter shall be left or right handed
43.13 Casement stays (Straight Ped Stay) :
43.13.1 The stays shall be made from a channel section having three holes at appropriate
position so that the window can be opened either fully or partially as directed. Size of the stay
shall be 250 mm. to 300 mm. as directed.
43.14 Ventilator Catch :
43.14.1 The pattern and shape of the catch shall be as approved.
43.15.1 The base and socket plate shall be made from minimum 3 mm. thick plate and
projected pivot shall not be less than 12 mm. diameter and 12 mm. length and shall be firmly
riveted to the base plate in case of iron pivot and in single place plate in the case of brass pivot.
44.1. (A) Oil paints :
44.1.1 Oil paints shall be of the specified colour and as approved. The ready mixed paints shall only
be used. However, if ready mixed paint of specified shade or tint is not available white ready
mixed paint with approved strainer will be allowed. In such a case the contractor shall ensure
that the shade of the paint so allowed shall be uniform.
44.1.2 All the paints shall meet with the following general requirements.
(i) Paint shall not show excessive setting in a freshly opened full can and shall easily be
redispresed with a paddle to a smooth homogeneous state. The paint shall show no curdling,
livering, caking or colour separation and shall be free from lumps and skins.
(ii) The paint as received shall brush easily, possesses good leveling properties and show no
running or sagging tendencies.
(iii) The paint shall not skin within 48 hours in a three quarters filled closed container.
(iv) The paint shall dry to a smooth uniform finish free from roughness, grit unevenness and other
M.45 French Polish :
45.1 The French polish of required tint and shade shall be prepared with the below mentioned
ingredients and other necessary materials.
(i) Denatured spirit of approved quality (ii) Chandras (iii) Pigment.
45.2 The French polish so prepared shall conform to I.S. 348-1968.
M.46 Marble chips for marble mosaic terrazzo
46.1 The marble chips shall be of approved quality and shades. It shall be hard, sound, dense and
homogeneous in texture with crystalline and coarse grains. It shall be uniform in colour and
free from stains cracks, decay and weathering.
46.2 The size of various colours of marble chips ranging from the smallest up to 20 mm. shall be
used where the thickness of top wearing layer in 6 mm. size. The marble chips of approved
quality and colours only as per grading as decided by the Engineer-in-charge shall be used for
mosaic tiles or works.
46.3 The marble chips shall be machine crushed. They shall be free from foreign matter, dust etc.
Except as above, the chips shall conform to I.S.2114-1962.
M.47 Flooring Tiles :
47.1(A) Plain Cement tiles :
47.1.1 The plain cement tiles shall be of general-purpose type. These are the tiles in the manufacture
of which no pigments are used. Cement used in the manufacture of tiles shall be as per Indian
47.1.2 The tiles shall be manufactured from a mixture of cement and natural aggregates by pressure
process. During manufacture the tiles shall be subjected to pressure of not less than
Kg/Sq. Cm. The proportion of cement to aggregate in the backing of the tiles shall be not less
than 1:3 by weight. The wearing face through the tiles are plain cement, shall be provided with
stone chips 1 to 2 mm. size. The proportions of cement aggregate in the wearing layer of the
tiles shall be three parts of cement to one parts chip by weight. The minimum thickness of
wearing layer shall be 3 mm. The colour and texture of wearing layer shall be uniform
throughout its face and thickness. On removal from mould, the tiles shall be kept in moist
condition, condition continuously at least for seven days and subsequently, if necessary, for
such long period as would ensure their conformity to requirements of I.S.1237-1980
regarding strength resistance to wear and water absorption.
47.1.3 Thewearing face of the tiles shall be plane free from projections, depressions and cracks and
shall be reasonably parallel to the back face of the tile. All angles shall be right angles and all
edges shall be sharp and true.
47.1.4 The size of tiles generally be square shapes 24.85 Cm. X 24.85 Cm. or 25 Cm X 25 Cm. The
thickness of tiles shall be 20 mm.
47.1.5 Tolerance of length and breadth shall be plus of minus one millimeter. Tolerance on thickness
shall be plus 5m.m.
47.1.6 The tiles shall satisfy the tests as regards transverse strength, resistance to wear and water
absorption as per I.S.1237-1980.
47.2(B) Plain Coloured Tiles :
47.2.1 The tiles shall have the same specification as for plain cement tiles as per (A) above expect
that they shall have a plain wearing surface wherein pigments are used. They shall conform
47.2.2 The pigments used for colouring cement shall not exceed 10 percent by weight of cement used
in the mix. The pigments, synthetic or otherwise, used for colouring tiles shall have permanent
colour and shall not contain materials detrimental to concrete.
47.2.3 The colour of the tiles shall be specified in the item or as directed.
47.3(C) Marble mosaic tiles :
47.3.1 These tiles have same specification as per plain cement tiles except the requirements as stated
47.3.2 The marble mosaic tiles shall conform to I.S.1237-1980. The wearing face of the tiles shall be
mechanically ground and filled. The wearing face of tiles shall be free from projections
depressions and cracks and shall be reasonably parallel to the back face of the tiles. All angles
shall be right angles and all edges shall be sharp and true.
47.3.3 Chips used in the tiles be from smallest upto 20 mm. size. The minimum thickness of wearing
layer of tiles shall be 6 mm. For pattern of chips to be had on the wearing face, a few samples
with or without their full size photographs as directed shall be approved by the Engineer-in-
Charge, for approval.
47.3.4 Any particular samples if found suitable shall be approved by the Engineer-in-Charge, or he
may ask for a few more samples to be presented. The samples halls have to be made by the
contractor, till a suitable sample is finally approved for use in the work. The Contractor shall
ensure that the tiles supplied for the work shall be in conformity with the approved sample
only, in terms of its dimensions thickness of backing layer and wearing surface, materials,
ingredients, colour, shade, chips, distributions, etc. required.
47.3.5 The tiles shall be prepared from cement conforming to Indian Standards or coloured Portland
cement generally depending upon the colour of tiles to be used or as directed.
47.4(D) Chequered Tiles :
47.4.1 Chequered tiles shall be plain cement tiles or marble mosaic tiles. The former shall have the
same specification as per (A) above and the latter as per marble mosaic tiles as per (C) except
as mentioned below.
47.4.2 The tiles shall be of nominal size of 250 mm. X 250 mm. or as specified. The center-to-center
distance of chequer shall not be less then 25 mm. and not more than 50 mm. The overall
thickness of the tile shall be 22 mm.
47.4.3 The grooves in the chequers shall be uniform and straight. The depth of the grooves shall not
be less than 3 mm. The chequered tiles shall be plain coloured or mosaic as specified. The
thickness of the upper layer measured from the top of the chequers shall not be less than
mm. The tiles shall be given the first grinding with machine before delivery to site.
47.4.4 Tiles shall conform or relevant I.S. 1237-1980.
47.5(E) Chequered Tiles For Stair Cases :
47.5.1 The requirements of these tiles shall be the same as chequered tiles as per (D) above except
in following respects :
(1) The length of a tile including note shall be 300 mm. (2) The minimum thickness shall be
28 mm. (3) The nosing shall have also the same wearing layer as at the top. (4) The
nosing edge shall be rounded. (5) The front portion of the tile for a minimum length of 75mm.
from and including the nosing shall have grooves running parallel to nosing and at centers not
exceeding 25 mm. Beyond that the tiles shall have normal chequer pattern.
M.48 Rough Kotah Stone
48.1 The kotah stones shall be hard even sound and regular in shape and generally uniform in
colour. The colour of the stone shall generally be green. Brown coloured shall not be allowed
for use. They shall be without any soft veins, cranks of flaws.
48.2 The size of the stones to be used for flooring shall be size 600mm X 600mm and/or size
600mm X 450mm. as directed. However smaller sizes will be allowed to be used to the extent
of maintaining required pattern. Thickness shall be as specified.
48.3 Tolerance of minus 30 mm. on accounts of chisel dressing of edges shall be permitted for
length as well as breadth. Tolerance in thickness shall be ± 3 mm.
48.4 The edges of stones shall be truly chiseled and table rubbed with coarse sand before paving.
All angles and edges of the stones of shall be true, square and free from chipping and surface
shall be true and plain.
48.5 When machine cut edges are specified, the exposed and the edges at joints shall be machine
cut. The thickness of the exposed machine cut edges shall be uniform.
M.49 Polished Kotah Stones
49.1 Polished kotah stone shall have the same specification as per rough kotah stone except as
mentioned below.
49.2 The stones shall have machine polished surface. When brought on site, the stones shall be
single polished or double polished depending upon its use. The stones for paving shall
generally be single polished. The stones to be used for dedo, skirting, sink, veneering, sills,
steps, etc. where machine polishing after the stones are fixed in site is not possible shall be
double polished.
M.50 Dholpur Stone Slab
50.1 Dholpur stone slab shall be of best quality as approved by the Engineer-in-Charge. The stone
slab shall be without any veins, cracks, and flaws. The stone slab shall be even sound and
durable regular in shapes and of uniform colour.
50.2 The size of the stone shall be as specified in the item or detailed drawing or as approved by
the Engineer-in-Charge. The thickness stone shall be as specified in the item of work with the
permissible tolerance of plus or minus 2 mm. The provision in respect of polishing as for
polished kotah stone shall apply to polished Dholpur stone also. All angles and edges of the
face of the stone slab shall be fine chiselled or polished as specified in the item of work and all
the four edges shall be machine cut. All angles and edges of the stone slab shall be true and
50.3 The sample of stone shall be got approved by the Engineer-in-Charge for a particular work. It
shall be ensured that the stones to be used in a particular work shall not differ much in shade
or tint from the approved sample.
M.51 Marble Slab
51.1 Marble slab shall be white or of other and of best quality as approved by the Engineer-in-
51.2 Slabs shall be hard, close, uniform and homogeneous in texture. They shall have even
crystalline grain and free from defects and cracks. The surface shall be machine polished to an
even and perfect plane surface and edges machine cut true and square. The rear face shall be
rough to provide key for the mortar.
51.3 Marble slabs with natural veins, if selected shall have to be laid as per the pattern given by the
Engineer-in-Charge. Size of the slab shall be minimum 460 mm. X 450 mm. and preferably
600 mm. X 600 mm. However, smaller sizes will be used shall be allowed to be used to the
extent of maintaining required pattern.
51.4 The slab shall not be thinner than the specified thickness at its thinnest part. A few specimen
of finished slab to be used shall be deposited by the Contractor in the office for reference.
51.5 Except as above the marble slabs shall conform to I.S.1130-1969.
M.52 Granite Stone Slab
52.1 Granite shall be of approved colour and quality. The stone shall be hard, even sound and
regular in shape and generally uniform in colour. It shall be without any soft veins, cracks of
52.2 The thickness of the stone shall be specified in items.
52.3 All exposed faces shall be double polished to tender truly smooth and even reflecting surface.
The exposed edges and corners shall be rounded off as directed. The exposed edges shall be
machine cut and shall have uniform thickness.
M.53 P.V.C. Flooring
53.1 P.V.C. sheets for P.V.C. floor covering shall be of homogenous, flexible type conforming to I.S.
3462-1966. The PVC covering shall neither develop any toxic effect while put to use nor shall
give off any disagreeable odor.
53.2 Thickness of flexible type covering tiles shall be as specified in the description of the item.
53.3 The flexible type shall be backed with Hessian or other woven fabric. The following tolerances
shall be applicable on the nominal dimensions of the rolls or tiles :
(a) Thickness ± 0.15 mm.
(b) Length or Width :
(1) 300 mm. Square tiles ± 0.20 mm. (3) 900 mm. Square Tiles ± 0.60 mm.
(2) 600 mm. Square tiles ± 0.40 mm. (4) Sheets and roll ± 0.10 percent
53.4 Adhesive :
53.4.1 The adhesive for PVC flooring shall be of the type and make recommended by the
manufactures of PVC sheets/tiles.
M.54 Facing Tiles
54.1 The facing tiles (burnt clay facing bricks) shall be free from cracks, and nodules of free lime.
They shall be thoroughly burnt and shall have plane rectangular faces with parallel sides and
sharp straight right-angled faces. The texture of the finished surface that will be exposed
when in place shall confirm to an approved sample consisting not less than for stretcher bricks
each representing the texture desired. The facing tiles shall have a pleasing appearance,
sufficient resistance to penetration by rain and greater durability than common bricks. The
tiles shall conform to I.S. 2691-1972.
54.2 The standard size of facing brick tiles shall be 19 X 9 X 4 cms. The facing brick tiles shall be
provided with frog which shall conform to I.S. 11077-1976.
54.3 The permissible tolerance in dimensions specified above shall be as follows:
M-55 Cement Mortar
55.1 Water shall conform to specification M-1 Cement: Cement shall conform to specifications M-3
Sand: Sand shall conform to M-6.
55 2.Proportion of Mix
55 2.1.Cement and sand shall be mixed to specified proportion, sand being measured by measuring
boxes, the proportion of cement will be by volume on the basis of 50 kg/Bag of cement being equal
to 0.0342 Cu.m. The mortar may be hand mixed of machine mixed as directed.
55 3.Proportion of Mortar:
55 3.1.In hand mixed mortar, cement and sand in the specified proportions shall be thoroughly
mixed dry on a clean impervious platform by turning over at least 3 times or more till a homogeneous
mixture of uniform colour is obtained. Mixing platform shall be so arranged that no deleterious
extraneous material shall get mixed with mortar or mortar shall flow out. While mixing, the water
shall be gradually added and thoroughly mixed to form a stiff plastic mass of uniform colour so that
each particle of sand shall be completely covered with a film of wet cement. The water cement ratio
shall be adopted as directed.
55 3.2.The mortar so prepared shall be used within 30 minutes of adding wate. Only such quantity
of mortar shall be prepared as can be used within 30 minutes.
M-56 Stone Coarse Aggregate For Nominal Mix Concrete
561. Coarse aggregate shall be of machine crushed stone of black trap or equivalent and be hard
strong, dense, durable, clean and free from skin and coating likely to prevent proper adhesion of
56 2.The aggregate shall generally be cubical in shape. Unless special sto9nes of particular quarries
are mentioned aggregates shall be machine crushed from the best black, trap or equivalent hard stone
as approved. Aggregate shall have no deleterious reaction with cement. The size of the coarse
aggregate for plain cement and ordinary reinforced cement concrete shall generally be as per the
table given below. However, in case of reinforced cement concrete the maximum limit may be
restricted to 6 mm. less than the minimum lateral clear distance between bars or 6 mm. less than the
cover whichever is smaller.
I. S. Sieve Percentage passing for single I. S. Sieve Percentage passing for
Designation Designation Single Sized aggregates
Note: This percentage may be varied somewhat by the Engineer-in-charge when considered
necessary for obtaining better density and strength of concrete.
563. The grading test shall be taken in the beginning and at the change of source of materials. The
necessary tests indicated in I.S. 383-1970 and 456-1978 shall have to be carried out to ensure the
acceptability. The aggregates shall be stored separately and handled in such a manner as to prevent
the intermixing of different aggregates. If the aggregates are covered with dust, they shall be washed
with water to make them clean.
M-57 Black Trap or Equivalent Hard Stone Coarse
57.1 Aggregate For Design Mix Concrete. Coarse aggregate shall be of machine crushed stone of black
trap or equivalent hard stone and be hard, strong, dense, durable, clean and free from skin and
coating likely to prevent proper adhesion of mortar.
57.2 The aggregates shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned, aggregates shall be machine crushed from the best, black trap or equivalent hard
stones as approved. Aggregate shall have no deleterious with cement.
57 3.The necessary tests indicated in I.S. 383-1970 and I.S.456-1978 shall have to be carried out to
ensure the acceptability of the material.
57 4.If aggregate is covered with dust it shall be washed with water to make it clean.
GENERAL SPECIFICATIONS
1.1 Indian Standard
All materials used in the works shall be of the best quality of their respective kinds and as
specified herein, obtained from sources and suppliers approved by the Engineer-in-Charge
(EIC) or his authorized representative and shall conform to the latest edition of Indian
Standard issued by the Bureau of Indian Standards. All materials shall comply strictly with
the tests prescribed hereinafter or where with the requirements of the latest issues of the
relevant Indian Standards. Standards issued elsewhere may be used only when appropriate
Indian Standards are not available and are subject to approval of EIC.
1.2 Inspection, Sampling and Testing
All materials used in the works shall be subjected to inspection and tests. Samples of all
materials proposed to be employed in the permanent works shall be submitted to the EIC for
approval before they are brought to the site.
Samples provided to the EIC or his AR for their retention are to be in labeled boxes suitable
for storage. Materials or workmanship not corresponding in character and quality with
approved samples will be rejected by the EIC.
Samples required for approval and testing must be supplied in sufficient time to allow for
testing and approval, due to allowance being made for the fact that if the first samples are
rejected, works arising from the late submission of samples will not be acceptable as reason
for delay in the completion of the works.
Materials shall be tested leaving the manufacture's premises, quarry or sources where
possible. Materials shall also be tested on the site and they may be rejected if found not
suitable or not in accordance with the specifications notwithstanding the results of tests at the
manufacturer's works or elsewhere or of test certificates or of any approval given earlier. The
contractors shall provide all assistance, instruments, machinery, labour and materials as are
normally required for examining, measuring and testing any work.
1.3 Dispatch of Materials
No materials shall be used in the works unless they have first been approved by EIC. Materials
shall not be dispatched from the manufacturer's works to the site without written authority
from the EIC or his AR.
1.4 Test Certificate
All manufacturer's certificate of test, proof sheets, mill sheets etc. showing that the materials
have been tested in accordance with the requirement of this specification, the appropriate
Indian Standard or other relevant standard specifications are to be supplied free of charge, on
request to the EIC or his AR.
1.5 Source of materials
The contractor shall indicate to the EIC the source of all materials to be used in the work with
relevant test data sufficiently in advance, and the approval of the EIC for the same shall be
obtained at least 45 days before the scheduled commencement of the work. If the contractor
proposes to obtain materials from a different source, he shall notify the EIC for his approval,
at least 45 days before such materials are to be used with relevant test data.
1.6 Name of Manufacturers and Copies of Orders
Before ordering any materials or any description for the works, the Contractor shall submit
for the approval of the EIC, the names of the makers and suppliers proposed and any other
detail required by the EIC and shall afterwards send to the EIC copies in quadruplicate of the
orders given by the Contractor for the materials.
1.7 Storage of Materials
All materials used in the work shall be stored on racks, supports, in bins, under cover, etc. as
appropriate to prevent deterioration or damage from any cause whatsoever to the entire
satisfaction of the EIC or his AR and as amplified in the succeeding clauses.
1.8 Record and Usage of Materials
The contractor shall maintain a detailed record of all materials received on the site or in his
stores or storage and working areas in the vicinity of the site and shall make such records
available to the EIC at such time as the letter may reasonably require.
Materials shall wherever possible and practicable be used on the order in which they arrive
on the site and in the stores on storage and working areas in the vicinity of the site.
1.9 Notice for Inspection of Materials
Where the EIC or his AR shall give notice to the contractor that materials are to be inspected
off the site, the contractor shall, having regard to the location of the materials and the nature
of the inspection, test or examination required, give to the EIC or his AR when such materials
are ready for inspection, test or examination either during manufacture, fabrication etc. or on
completion, such notice as the EIC may reasonably require to enable the inspection, test or
examination to be made. Delay to the works arising from the late submission of such notice
will not be acceptable as reason for delay to the completion of works.
1.10 Use of Permanent Materials for Temporary works
Materials for the permanent works shall not be used for temporary works unless otherwise
approved in writing by the EIC. Granting of such permission shall not prejudice the right of
the EIC to reject materials so used which have become unfit for use in the permanent works.
1.11 Cost of Sampling and Testing
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Technical bid.docx.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .