The Director
Deep Bhavan,Directorate of Lighthouses and Lightships,P N Marg, Patel Colony,Jamnagar
maintenance and repair of staff Qtr, Power House , L H Tower and Compound wall at Gopnath Lighthouse Station
2021_DGLL_621509_1
4-DW(25)/90-IV (Re Tender)
Open Tender
Civil Works
Works
120 days
Gopnath Lighthouse
As per Tender
11 documents required · 11 mandatory
₹500
The Director of Lighthouses and Lightships
₹55,610
Jamnagar
4 Aug 2021
9 Mar 2021
9 Apr 2021
9 Mar 2021
8 Apr 2021
9 Mar 2021
15 Mar 2021
Amount
Providing and fixing 50 mm dia (3 Tier)GI Pipe ( C Class Heavy duty of brand TATA/JINDAL)Hand Railing as per drawing at all heights of Light House Tower including fabrication,finishing,supply,fixing in position ,all as directed and as per standard specifications including necessary specials such as T,Elbows,Crosses,base plate( with holes), nuts & bolts,flats etc.for all heights of lighthouse Tower including cost of all labours,materials tools & plants, scaffolding,transportation, safety measures etc complete as per instruction & direction of Engineer-In-Charge.
LightHouse Hand Railing of 1.0 m height consisting of 3 horizontal rows.
Providing and fixing carbon steel galvanised (minium coating 5 micron) dash fastener of 10 mm dia double threaded 6.8 grade (yield strength 480 N/mm2),counter sunk head,comprising of 10m dia polyamide PA 6 grade sleeve,including drilling of hole in frame,concrete/masonry surface, etc for lighthouse Tower Hand Railing(for all heights) & as per direction of Engineer-In-Charge.
Providing and laying cement concrete 1:1.5:3 (1 cement:1.5 coarse river sand:3 graded stone aggregate 20 mm nominal down size) RCC works for Lighthouse Tower (for all heights) including mixing, laying, compacting, vibrating, levelling, curing, etc all as per standard specification and as required including cost of all materials, tools & plants, labours, transportation , scaffolding and all other charges etc.complete but excluding the cost of reinforcement and shuttering.
Centering and shuttering (with shuttering oil)including strutting,propping etc and removal of form work for all heights including supply of all materials( binding wire,nails),labours,tools & plants,transportation,(lead& lift)scaffolding and all other charges etc.complete for all heights as per Instruction and direction of Engineer-In-Charge.
Providing and fixing Granite stone 12 to18 mm thick gang saw mirror polished ,premoulded and prepolished,machine cut for Lighthouse Tower Landing,Tread Riser & platforms of required size,approved shade,colour and texture laid over 20 mm thick base cement mortar(1:4(1 cement:4 coarse river sand),joints treated with white cement mixed with matching pigment,epoxy touch ups,including rubbing,curing,moulding and polishing to edges to give high gloss finish etc.complete at all levels including cost of all materials,labour,tools & plants,transportation and all other charges etc., complete as per standard specification ans as per Instruction & direction of Engineer-In-Charge.
Providing and Laying (water proofing)china mosaic flooring over terrace (after removing terrace topping)using broken pieces of full white/colour glazed tiles laid over 20 mm/as per require thick cement mortar in 1:4(1 cement:4 coarse sand) to maintain proper slope with water proofing compound on plain or curved,slope surface to be tampered to bring mortar cement cream up to surface with using white cement for filling of joints roughening of china mosaic is done after cleaning,preparing remove loose plaster with wire brush and water and all visible crakes a routed out/making V-Shape grooveand then filled with cement and water proofing chemical with cement slurry including the cost of all materials,labours,tools & plants and all other charges etc complete as per instruction and direction of Engineer-In-Charge.
Applying two or more coats of Synthetic Enamel Paint of approved 1 rst quality -High Glossy -Berger/Asian brand over a coat of primer for all heights of Light House Tower to give an even shade including throughly cleaning the surface to remove all dirt,dust ,mortar draps and other foreign matter etc., including cost of all materials,labours,brushes,transportation,scaffolding and ladder safety measures and all other charges etc.,complete as per instruction & direction of Engineer-In-Charge.
Applying One or more coats of Synthetic Enamel Paint of approved 1 rst quality Berger/Asian brand over existing surface of painted surface for Light House Tower and staff qtr door,window to give an even shade including throughly cleaning the surface to remove all dirt,dust ,mortar draps and other foreign matter etc., including cost of all materials,labours,brushes,transportation,scaffolding and ladder safety measures and all other charges etc.,complete as per instruction of Engineer-In-Charge.
Replacement of old broken glass panels with new 3.5/4 mm thk frosted /plane window glass panes fixed with clay,pins,teakwood beading etc including removing/disposing of old crack/damaged window glass up to all heights of bldgs /Light House Tower,all as directed and all as per standard specification, including cost of all materials,labours ,tools & plants,scafolding, ,transportation (including lead & lift) etc.complete as per instruction & direction of Engineer-In-Charge.
Applying Two or more coats of weather coat Exterior Emulsion Paint of approved brand & colour of top quality (BERGER(Antidust)/ASIAN(Apex Ultima)) on new/old wall surface( including coat of primer new/old surface) at all heights to give an even shade ,all as per standard specification and as directed including throughly brooming the surface to remove all dirt,dust,mortar draps ,loose paint and other foreign matter including the cost of all labour,materials,scafolding,tools & plants,transporttion (including lead & lift) etc complete as per instruction and direction of Engineer-In-Charge.
Providing & Fixing broken glass panes in uniform pattern on top of existing compound wall after plaster of 20 mm or more in 1:6 (1 cement:6 river sand) for fixing glass panes(with proper finish) after removing of existing paint and hacking the top surface(before plaster) top of compound wall including curing supply of all labours,materials,scaffolding,transportation ,tools,& plants and all other charges etc complete as per instruction& direction by the Engineer-In-Charge
Jungle Clearance including uprooting rank vegetation,grass,shrubs,saplings and trees girth up to 300 mm etc.(cutting & levelling)and disposal/removal of debris as directed,including supply of all labours,tools & plants and all other charges etc.complete as per instruction & direction of Engineer-In-Charge.
Brick work with burnt clay bricks of approved quality of class designation 7.5 in cement mortar 1:6 ( 1 cement : 6 river sand) for superstructure (up to all specified heights)as per standard specification and as directed including cost of all materials, transportation, scaffolding, labour, tools & plants,curing and all other charges etc.complete as per instruction & direction of Engineer-In-Charge.
15 mm thick cement plaster on Masonry/RCC work in cement mortar 1:4 (1 Cement :4 river sand) in line & level at all heights as per standard specifications and as directed including making of grooves/raindrip/patt wherever required,supply of all labours,tools & plants ,hacking(over RCC surface) curing,materials,tools & plants,scaffolding and all other charges etc complete as per instruction & direction of Engineer-In-Charge.
Providing and laying cement concrete 1:1.5:3 (1 cement: 1.5 coarse river sand: 3 graded stone aggregate 20mm nominal down size) -All work up to Plinth level for specified area including mixing laying,compacting,levelling,curing, etc.all as per standard speciffication and as required including cost of all materials,tools & plants, labours , transportation(lead & lifts),scaffolding and all other charges etc. complete but excluding the cost of reinforcement and shuttering etc complete as per instruction and direction of Engineer-In-Charge
Earth work in excavation( (Hydraulic excavator/manual means ) in trenches for foundation in all type of soils including back filling and disposal pf surplus excavated soil as directed within a lead of 500m all as per standard specifications and as directed including cost of all Labours, tools & plants and all other charges etc.complete.
All kind of soil not exceeding 30 cm in depth but exceeding 1.50 m in width as well as 10 sqm on plan.
Providing and Laying base P.C.C in CC 1:4:8 ( 1cement:4coarse river sand : 8 graded stone aggregate 20 mm nominal down size)All work up to Plinth level for concrete work (excluding shuttering) including mixing,laying,compacting,levelling,curing etc.,all as per standard specification and as required,including cost of all materials,tools & plants,labours,lead & lifts and all other charges etc complete.as per instruction and direction of Engineer-In-Charge.
Demolishing of RCC work manually/mechanical means including stacking of steel bars and disposal of 50.0 metres lead as per direction of Engineer-In-Charge for all heights including the cost of all labours,materials,scaffolding,tools ,plants,transportation (including lead & lift) from site etc complete.
Demolishing of Masonry work in cement mortar manually/by mechanically means including stacking of serviceable material and disposal of unserviceable material with in 50.0 metres lead as per direction of Engineer-In-Charge including the cost of all labours,materials,scaffolding,tools ,plants,transportation (including lead & lift) from site etc complete for all heights.
Providing and Applying white cement based putty of average thickness 1 mm,of approved brand and manufacturer over the plastered wall surface(old/new) to prepare the surface even and smooth etc complete for all heightsof Lighthouse Tower & staff Qtrs) as per direction of Engineer-In-Charge including supply of all labours/painters,tools & plants,materials,scaffolding,transportation and all other charges etc complete.
Applying Distemper(one or more coats) with 1rst quality acrylic distemper(Readymix)of (Asian/Berger brand)having VOC content less than 50 grams/ltr of approved brand and manufacture to give an even shade on old surface of staff qtrs & Lighthouse Tower for all heights including throughly brooming the surface to remove all dirt,dust,mortar draps and other foreign matter etc including cost of labour,materials,scaffolding,transportation etc complete. as per instruction & direction of Engineer-In-Charge.
Providing ,Laying & fixing PVC Pipes (6kg/sq.cm) of approved brand and manufacturer for rain water / sewer pipe line laid from roof of the building/kitchen/ toilet/ bathroom etc including providing necessary fixture & fittings like Tee,Shoe, Elbow, Socket,Bend (Long/Short/Shoe/Plug/plug bend,Y),PVC Cowl (wherever reuired chipping/ making of hole in walls & plugging of holes),Clamp at 1.00 m spacing,Screws (Brass),solution(excluding the cost of excavation) including the cost of all labours, materials,scafolding, tools,plants & transportation (including lead &lift) to site etc complete.for all heights.
100 mm dia pipe
50 dia pipe
Supplying Plumber for repair & maintenance of staff Qtrs plumbing accessories like shower with nose,pillar tap,bib cock(long & short body),geysor pipe,connector pipe,angle/stop cock, valve ,water supply & sewer line etc as per instruction & direction of Engineer -In- Charge which includines removing ,cleaning & refixing & testing of accessories with required materials like teflon tape etc for staff Qtrs & Office building .
Providing and fixing ISI marked flush door shutters(after removing old one) of Century/equivalent approved make conforming to IS: 2202(Part I) non decorative type,core of block board construction with frame of 1st class hard wood and well matched commercial 3 ply veneering with vertical grains or cross bands and face veneers on both faces of shutters 30 mm thick including ISI marked Stainless Steel butt hinges with necessary screws including supply of all labours (carpenter), materials, transportation, tools & plants etc complete as direction of Engineer-In -Charge for staff qtrs
Applying white/colour wash(one or more coats) over old surface to give an even shade up to all heights including throughly brooming the surface to remove all dirt,dust,mortar draps and other foreign matter etc including cost of labour,materials,scaffolding,transportation etc complete. as per instruction & direction of Engineer-In-Charge.
Repairing of cracks for wall surface of Lighthouse Tower & staff Qtrs after making U/V-shape groove size of 25x25 mm and then priming the surface with integral crystalline slurry @ 0.05 kg per running meter and while the surface is tacky then filling the groove up to top edge with crystalline mortar @ 1.50 kg per running meter .Once crystalline mortar is touch dry then finally applying two coats of integral crystalline slurry @ 0.05 kg per running meter per coat on treated surface etc complete as per instruction & direction of Engineer-In-Charge including cost of all labours,tools,plants,materials,curing etc ,complete.
Providing ,Supplying,Straightening,cutting,bending,binding and placing in position tested torr steel reinforcement/TMT bars of Grade Fe 500D of approved quality (TATA TISCON/SAIL/VIZAG)as per drawings and specification & as directed for all heights including supply of all labours,tools,materials(binding wire ,nails) etc.complete.( for staff qtrs ) etc.
Dismantling of old damaged Hand Railing of Lighthouse Tower ( Including RCC Pillars ) carefully without damaging existing structure including stacking of serviceable materials and disposal of unseriviceable materials with in lead of 500 m including all charges for labour,materials,tools & plants,safty measures , transportation and all other charges etc complete.as per Instruction &direction of Engineer-In-Charge.
Taking away the scrap reinforcement from dismantled RCC structure from the site on buy back by the contractor after stacking serviceable materials as proper and as directed at site and disposal of unserviceable materials with in a lead of 100 mtrs including the cost of all labour charges ,lift & lead loading and unloading, transportation, tools & plants,weighing charges and all other charges etc., complete as per Instruction &direction of Engineer-In- Charge.
Providing and Fixing Stainless Steel Angle flat(of approved quality) for damaged joints of door/window with brass screws including the cost of all labour,materials,tools,plants,transportation etc complete as per instruction & direction of Engineer-In-Charge.
Stainless Steel Angle flat of size 75x75 mm (for window)
Stainless Steel Angle flat of size 100x100 mm (for door)
Painting to Staff Qtr furniture (like cot,table chair,dinning table,T-Poi,Meat safe etc)with One or more coats of synthtic enamel paint of Asian/Berger brand (1rst quality)of approved colour including the cost of all labours,materials(paint,brush,sand paper etc),tools & plants ,lead ,lift (removing & placing as per direction) and all other charges etc.complete as per instruction & direction of Engineer-In-Charge.
Providing and fixing Netlon mesh for window/door/Vent. /Meat safe of staff qtrs and wherever directed including fixing with 1 st quality teak wood with screws including cost of all materials,labours,transportation,tools&plants etc complete for staff qtrs .,as per direction of Engineer -In-Charge.
Providing /Cutting and fixing 12 mm tk furniture ply of Century/equivalent brand for staff qtrs furniture including supply of all materials,carpenter/labour,tools &plants, transportation (lead &lift) and all other charges etc complete as per instruction and direction of Engineer-In-Charge.
Cleaning of Septic Tank including removing and fixing of top cover fo staff qtrs including supply of all labour,materials,tools,plants,(lead & lift) and all other charges etc complete as per instruction and direction of Engineer-In-Charge.
GHANSHMLAL BALUBHAI
namrataconstruction
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .