| 1.00CONSTRUCTION OF TOILET | ||||
| 1.00 | 2.9.1:Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinary rock | 1.93 | cum | 300 ₹577.50 |
| 1.00 | OD269194/2024-2025:Laterate masonry with neatly dressed laterate stone of size 35x20x20 cm or nearest
size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc.
(Modified 50.6.7.1) | 4.03 | cum | 5,100 ₹20,563.20 |
| 1.00 | OD269192/2024-2025:Laterate masonry with neatly dressed laterate stone of size 35x20x20 cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | 4.81 | cum | 5,400 ₹25,968.60 |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | 0.27 | cum | 6,000 ₹1,620 |
| 1.00 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 7.9 | sqm | 750 ₹5,925 |
| 1.01 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 1.8 | sqm | 650 ₹1,170 |
| 1.01 | 5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for:
Edges of slabs and breaks in floors and wallsUnder 20 cm wide | 13 | metre | 400 ₹5,200 |
| 1.01 | 5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size). | 1.43 | cum | 11,000 ₹15,763 |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 100.3 | kilogram | 90 ₹9,026.64 |
Tender Value
₹1.7 L
EMD Value
₹4,237
Closing Date
14 Mar 2025, 10:00 amClosed
ASSISTANT ENGINEER
O/O the AEE,LSGD,KARADUKKA BLOCK
TOILET CONSTRUCTION
2024_LSGD_709980_33
TN/02/2024-25/AE/LIDEW/KDK
Open Tender
Civil Works - Buildings
180 days
BEDADUKKA
Please refer Tender documents.
7 documents required · 7 mandatory
₹555
Yes
₹4,237
Yes
17 Apr 2026
7 Mar 2025
15 Mar 2025
7 Mar 2025
14 Mar 2025
7 Mar 2025
7 Mar 2025 - 13 Mar 2025
Amount
CONSTRUCTION OF TOILET
2.9.1:Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinary rock
OD269194/2024-2025:Laterate masonry with neatly dressed laterate stone of size 35x20x20 cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. (Modified 50.6.7.1)
OD269192/2024-2025:Laterate masonry with neatly dressed laterate stone of size 35x20x20 cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for: Edges of slabs and breaks in floors and wallsUnder 20 cm wide
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.44.1:Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
13.62.1:Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade:Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture .
11.37:Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with white cement and matching pigment etc., complete.
11.36:Providing and fixing I st quality ceramic glazed wall tiles conforming to IS : 15622 (thickness to be specified by the manufacturer), of approved make, in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer -in-Charge, in skirting, risers of steps and dados, over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and jointing with grey cement slurry @ 3.3 kg per sqm, including pointing in white cement mixed with pigment of matching shade complete.
11.19.1:Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand):Light shade pigment using white cement
18.54.4:Providing and fixing PTMT bib cock of approved quality and colour.15 mm nominal bore, 90 mm long, weighing not less than 93 gms
50.18.7.2.2:Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer -in-Charge 20 mm dia 10 Kgf/cm2- Internal work - Exposed on wall
50.18.7.6.2:Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing . This includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 50 mm dia 6 Kgf/cm2 - Internal work- Exposed on wall
50.18.9.9.1:Providing and fixing PVC pipes includings jointing of pipes with one step PVC solvent cement, trenching, refilling & testing of Joints complete as per direction of engineer in charge.110 mm dia 6Kgf/cm2
50.18.9.15.2:Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 40 mm dia 6 Kgf/cm2 - External work - Exposed on wall
50.18.9.22.1:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes, including jointing with PVC solvent cement - 110 mm dia Elbow
50.18.9.22.4:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes, including jointing with PVC solvent cement- 110 mm dia Bend
50.18.9.22.5:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes including jointing with PVC solvent cement 110x110x110 mm dia Tee
50.18.9.22.8:Providing and fixing PVC moulded fittings /accessories for Rigid PVC pipes, including jointing with PVC solvent cement -110 mm dia Vent cowl
17.1.1:Providing and fixing water closet squatting pan (Indian type W.C. pan) with 100 mm Sand Cast Iron P or S trap, 10 litter low level white P.V.C.flushing cistern, including flush pipe, manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever require:White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests
OD269195/2024-2025:supplying and fixing good quality PVC door shutters including cost and conveyance of materials and all labour charges etc complete
OD269193/2024-2025: Hollow PVC Door Frame
13.71:Lettering with black Japan pint of approved brand and manufacture
Bidder Name
MOHAMMED ALI C H
stage.html
html • 0.03 MB
techsummary_1207452.pdf
finsummary_1207452.pdf
aoc.pdf
finance_1207452.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.37 MB
Tendernotice_2.pdf
PDF • 0.25 MB
Tendernotice_3.pdf
PDF • 0.25 MB
sbd.pdf
Tender Documents • 1.86 MB
BOQ_1207452.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid