| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 2 | Admitted-Fee/PreQual/Technical 05 AYODHYA NAGAR NEAR RAM MANDIR BEHIND HARIYA COLLEGE GOKUL NAGAR JAMNAGAR 361004 | JAMNAGAR | JAMNAGAR | GUJARAT | 361004 | Admitted-Fee/PreQual/Technical |
| 3 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
Tender Value
₹43.2 L
EMD Value
₹86,500
Closing Date
31 Aug 2026, 6:00 pmClosed
GE (I) (CG) Gandhinagar
GE (I) (CG) Gandhinagar, G-252, Sector-09, Gandhinagar-382007
PROVISION OF PQC ROAD FOR APPROACH TO EXISTING ROAD GATE NO 2 AT LEKHAWADA GANDHINAGAR UNDER GE(I) (CG) GANDHINAGAR
2026_MES_781000_1
8213/E8
Open Tender
Civil Works - Roads
Item Rate
180 days
Lekhawada Gandhinagar
As per NIT
7 documents required · 7 mandatory
₹500
GE (I) CG Gandhinagar
₹86,500
Yes
2 Sept 2026
27 Jul 2026
2 Sept 2026
27 Jul 2026
31 Aug 2026
11 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation over areas not exc 1.5 m deep and getting out in soft / loose soil complete all as specified and as directed. | 487.5 | CUBIC METRE | - | - |
| 2 | Excavating over areas,exc 1.5 m but n.exc 3.0 m deep and getting out in soft /loose soil complete all as specified and directed. | 37.5 | CUBIC METRE | - | - |
| 3 | Excavation in trenches in exc 1.5 m wide and not exc 1.5 M depth for foundation and getting out in soft and loose soil complete all as specified and as directed. | 18 | CUBIC METRE | - | - |
| 4 | Removing excavated material n.exc 50m & depositing where directed at a level n.exc 1.50m above the starting point in soil complete all as specified and as directed. | 400 | CUBIC METRE | - | - |
| 5 | Rolling and consolidating road formation surfaces in cutting with 8 to 12 tonne power roller complete all as specified and as directed. | 62.5 | TEN SQUARE METRE | - | - |
| 6 | M&L Laying and compacting 150 mm thick (compacted thickness) Granular Sub Base Course (GSB) grading as per Grade I as specified Table 400-1 of MoRTH specifications for Road and Bridge works, 2013, in asingle layer over compacted subgrade with natural sand, crushed gravel, crushed stone, crushed slag or combination thereof as per the grading required. The materials are mechanically mixed, spread andleveling on the subgrade by using motor grader ofadequate capacity, and rolling with vibratory roller of capacity 80-1 00 KN static weight for achieving required compaction density of atleast 98% of theMaximum Dry Density. Consolidating to required gradient and camber complete all as specified and directed with finished surface tolerances as per Table 900-1 of MaRTH specifications for Road and Bridge works, 2013 complete all as specified and as directed. | 62.5 | TEN SQUARE METRE | - | - |
| 7 | SLaying and compacting 150 mm thick (compacted thickness) Wet Mix Macadam (WMM) laid in two layers of 75 mm each grading as per table 400-13 of MoRTH specifications for Road and Bridge works 2013 manufactured in WMM plant material comprising of clean, crushed, graded aggregate and granular material premixed with wate to a dense mass, spreading with sensor paver and rolling with vibratory roller of capacity 80-1 OOKN static weight and consolidating to required gradien and camber complete all as specified and directed The finished surface tolerances to be as per Table 900-1 of MaRTH specifications for Road and Bridge works,2013 complete all as specified and as directed. | 62.5 | TEN SQUARE METRE | - | - |
| 8 | Providing and Laying Dry lean Concrete (DLC) 100 mm thick of aggregate gradation as per Table 1 of SP 49:2014 having 7 day average compressive
strength not less than 7 MPa Minimum cement content not less than 140 Kg/Cum DLC mixed in Batching Plant, transported to site and laid by
electron ic sensor paver including spreading and compacting usign high amplitude tamping bars of paver (initial compaction) further by double drum
smooth wheeled vibratory rollers with 80-100 KN static weight to achieve minimum dry density not less than 98% of maximum Dry Density, necessary
finishing etc complete all as specified and tolerances to be as per Table 900-1 of MaRTH specifications for Road and Bridge work 2013 complete all as specified and as directed. | 62.5 | TEN SQUARE METRE | - | - |
| 9 | M&L for 10 mm thick sand cushion with clean river sand duly clear of residual , organic and deleterious materials spread evenly to uniform thickness laid over DLC layer complete all as specified and as directed.
Note: No additional amount to be paid for overlap. | 6.25 | CUBIC METRE | - | - |
| 10 | Supplying and laying 400 micron thick HOPE shee (Virgin Quality) water proof, wrinkle free without puncture having minimum weight 390 gm/Sqm over tack coat/sand cushion as specified in the design with overlap between adjacent strips and transverse joints as minimum 300mm complete as specified and directed. | 625 | SQUARE METRE | - | - |
stage.html
html • 0.02 MB
tech_bid_open.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.32 MB
8213ps.pdf
Tender Documents • 1.04 MB
BOQ_874893.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .