Tender Value
₹4.0 Cr
EMD Value
₹1 L
Closing Date
26 Apr 2023, 2:00 pmClosed
State Agricultural Engineer
Directorate of Agriculture Development and Farmers Welfare Department Vikas Bhavan Thiruvananthpuram
NABARD RIDF XXVIII Infrastructural development works at various padasekharams of Thalayazham and Kallara Krishi Bhavan in Vaikom LAC Kottayam District
2023_AGRI_571526_1
AGRI/DOA/EST/30/2022/S
Open Tender
Miscellaneous Works
Item Rate
540 days
Thalayazham Kallara Vaikam Kottayam
Please refer Tender documents.
10 documents required · 10 mandatory
₹8,270
Yes
₹1 L
16 Jun 2023
11 Apr 2023
28 Apr 2023
11 Apr 2023
26 Apr 2023
11 Apr 2023
11 Apr 2023 - 26 Apr 2023
Amount
1 Appendix I - CKN Pump house east side
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
2.16.1:Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth not exceeding 1.5m
OD166/2022-2023:Modified old data 60.64.1 Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete
OD136/2022-2023:Modified old 60.64.4 Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end Details for one post of 8m long
OD755/2022-2023:Dry rubble masonry with hard stone in foundation and plinth including packing to compactness to lines and levells cost and conveyance of all materal labor charges etc. boat load up to 3 km distance
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
OD139/2022-2023:Modified olf 50.2.26.1<br>Filling using excavated earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
11.5:62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufactures specification. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete.
50.6.2.2:Solid masonry using pre cast solid blocks (factory made) of size 30x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in : CM 1:6 ( 1 cement : 6 coarse sand) etc complete
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.45.1:Finishing walls with textured exterior pint of required shade:New work (Two or more coats applied @ 3.28 ltr/ 10 sqm ) over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm
50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
50.10.1:Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
10.1:Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
12.50:Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+0.05%), total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x55mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.
12.4.1:Providing ridges or hips width 60 cm overall width plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete.0.80 mm thick with zinc coating not less than 275 gm/m2
Appendix II . Construction of Sluice 3 nos (CKN-1 , Mundar5,Kalappurakkal kari -1)
OD142/2022-2023:Putting up ring bund to a bottom width of 3m, top width of 1m, height of 2m and side slopes 1/2:1 by driving down half split coconut posts 3m long to a depth of 1.5m below ground level at 0.75 C/C in two rows and fixing 1/4th split coconut wailing pieces in 3 rows and connecting the posts with 1/4th split cross ties, bamboo reepers for tying, screening and filling inside with clay maintain the bund till the completion of the work and removing the same after etc. complete (Boat load upto 3 km)
OD143/2022-2023:Modified old 60.2.3 Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
OD172/2022-2023:Modified old data 60.64.1 Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete
OD145/2022-2023:Modified old 60.64.4 Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end Details for one post of 8m long
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
2.26.1:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
OD149/2022-2023:Modified old 60.7.2 DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
OD150/2022-2023:Filling with Quarry Muck Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
OD152/2022-2023:Modified old data60.3 Supplying and fixing structural steel channel ISMC 75X40mm for holding shutter planks including cutting ,hoisting fixing in position with material and labour charges etc complete
OD153/2022-2023:Modofied 60.5 MS Rings - 100mm dia Length of ring and hook 1 Ring 100mm diameter- 0.314m One hook 0.25 m Total = [email protected]/m= 0.35kg Hence weight of one ring and hook =0.35kg Data for 100 set of hook and ring
OD154/2022-2023:Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete
10.2:Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
13.59:Coal tarring two coats on new work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively.
Appx III - outer bund protection
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD155/2022-2023:DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
OD156/2022-2023:Modified old data 60.7.8 DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
OD756/2022-2023:Dry rubble masonry with hard stone in foundation and plinth including packing to compactness to lines and levells cost and conveyance of all materal labor charges etc. boat load up to 3 km distance
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
13.33.1:Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand):Flush/ Ruled pointing
OD158/2022-2023::Supplying and filling hard stiff clay for bund formation by Earth work in excavation by mechanical means in or under water (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed. (2.6.1 modified)
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
OD160/2022-2023:Forming bund using excavated clay including sectioning and consolidation by layers etc. complete.
2.28.1:Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil
50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
APPX IV - Mundar -5 near moosara palm VCB
OD161/2022-2023:Putting up ring bund to a bottom width of 3m, top width of 1m, height of 2m and side slopes 1/2:1 by driving down half split coconut posts 3m long to a depth of 1.5m below ground level at 0.75 C/C in two rows and fixing 1/4th split coconut wailing pieces in 3 rows and connecting the posts with 1/4th split cross ties, bamboo reepers for tying, screening and filling inside with clay maintain the bund till the completion of the work and removing the same after etc. complete (Boat load upto 3 km)
OD162/2022-2023:Modified old 60.2.2 Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD165/2022-2023:Modified old data 60.64.1 Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete
OD164/2022-2023:Modified old 60.64.4 Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end Details for one post of 8m long
OD167/2022-2023:Modified old 60.7.2 DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
OD168/2022-2023:Modified old data60.3 Supplying and fixing structural steel channel ISMC 75X40mm for holding shutter planks including cutting ,hoisting fixing in position with material and labour charges etc complete
OD169/2022-2023:Modofied 60.5 MS Rings - 100mm dia Length of ring and hook 1 Ring 100mm diameter- 0.314m One hook 0.25 m Total = [email protected]/m= 0.35kg Hence weight of one ring and hook =0.35kg Data for 100 set of hook and ring
OD170/2022-2023:Modified Data 60.7.1 DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
13.33.1:Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand):Flush/ Ruled pointing
OD171/2022-2023:Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete
E M MADHU
Bidder Name
E M MADHU
M A JAMES, Mannasseril
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_843727.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .