| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.0 LAccepted-AOC | ₹6.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹8.1 LRejected-AOC | ₹8.1 L | L2 | Rejected-AOC L2 |
Tender Value
₹8.9 L
EMD Value
₹22,240
Closing Date
12 Feb 2026, 2:00 pmClosed
Assistant Executive Engineer
O/o Office of the Assistant Executive Engineer, Irrigation Sub Division III Chittoor
GENERAL WP DAMSAFETY 2025 26 Annual Maintenance Of Walayar Dam Camp Area Including Establishing Bench Mark Clearing Jungle Improvements To SRGS And Taking Level At Every 10 m Intervals Of Earthen Dam To Establish The Profile Of The Dam
2026_Irrig_833562_1
IRR/PI/TR/5086/2025_5_1_1/1
Open Tender
Civil Works - Others
270 days
Walayar Dam
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,965
Yes
₹22,240
Yes
26 Feb 2026
5 Feb 2026
13 Feb 2026
5 Feb 2026
12 Feb 2026
5 Feb 2026
Dam Maintenance Works
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
OD20757/2025-2026:Engaging Coolie For Removing Weeds Over The Turfing Area (D/S Of Earthen Dam) And The Dam Premises
Surveying To Verify The Profile Of Earthen Dam
56.12.c:Total station surveying and preparation of site plan - In hilly terrain
Fixing Bench Mark
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
6.1.1:Brick work with common burnt clay F.P.S (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
13.37.1:White washing with lime to give an even shade:New work (three or more coats)
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
OD31112/2025-2026:Supplying Stacking And Spreading 20 To 12.5 mm Crushed Stone Aggregate In ARGS And FWS To Avoid Growth Of Weeds In It
Please Enable Macros to View BoQ information
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1402062.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.07 MB
BOQ_1402062.xls
BOQ • 0.31 MB
viewsbd.pdf
Tender Documents • 2.08 MB
Download all tender documents and submit your bid