Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹98.0 LAdmitted-Finance | ₹98.0 L | L1 | Admitted-Finance |
| 2 | L2₹98.0 L+₹2,278.61 (0.02%)Admitted-Finance | ₹98.0 L+₹2,278.61 (0.02%) | L2 | Admitted-Finance |
| 3 | L3₹1.1 Cr+₹12.5 L (12.8%)Admitted-Finance | ₹1.1 Cr+₹12.5 L (12.8%) | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | GIMMY PAULOSE L1 | MATHA CONSTRUCTIONS L3 | Sreeram C L2 |
|---|---|---|---|---|---|---|
| 1.00Renovation of Common Toilets | ||||||
| 1.01 | 14.82:Dismantling W.C. Pan of all sizes including disposal of dismantled materials i/c malba all complete as per directions of Engineer-in-Charge | 119 | no | 135.38 ₹16,110.22 Lowest | 152 ₹18,088 | 138 ₹16,422 |
| 1.02 | 15.23.1:Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.For thickness of tiles 10 mm to 25 mm | 1,263.37 | sqm | 73.97 ₹93,451.77 Lowest | 83 ₹1,04,860.04 | 76 ₹96,016.42 |
| 1.03 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 21.48 | cum | 2,454.01 ₹52,721.95 Lowest | 2,768 ₹59,467.71 | 2,508 ₹53,881.87 |
| 1.04 | OD287159/2025-2026:Removal of soil/sand filled in the sunken portion of toilets up to floor level VII and disposal of unserviceable
material within 250 meters lead as per direction of Engineer in Charge | 85.93 | cum | 844.09 ₹72,534.34 | 952 ₹81,807.26 | 420 ₹36,091.44 Lowest |
| 1.05 | 22.5:Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/sqm. This layer will be allowed to air cure for 4 hours. b) Second layer of slurry of cement @ 0.242 kg /sqm mixed with water proofing cement compound @ 0.126 kg/ sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry. | 583.7 | sqm | 631.64 ₹3,68,685.11 Lowest | 712 ₹4,15,590.84 | 635 ₹3,70,646.33 |
| 1.06 | OD17337/2026-2027:Filling with broken hurudees tile obtained from roof top for filling including consolidating each deposited layer by ramming in all floors as per direction of site Engineer-in charge.
Ref item No. 2.27 | 85.93 | cum | 310.51 ₹26,682.75 Lowest | 350 ₹30,076.2 | 1,000 ₹85,932 |
| 1.07 | 4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | 21.48 | cum | 8,354.91 ₹1,79,496.89 Lowest | 9,426 ₹2,02,508.18 | 8,542 ₹1,83,516.33 |
| 1.08 | OD290429/2025-2026:Providing and laying vitrified anti skid Mat finish floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS : 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4(1 cement : 4 coarse sand), including grouting the joint of floor tiles having joints of 3 mm width, using epoxy grout mix 0.70 kg of organic coated filler of desired shade(0.10 kg of hardner and 0.20 kg of resin per kg)including filling/grouting and finishing complete as per direction of Engineer-In-Charge.Size of Tile 600 x 600 mm. | 265.33 | sqm | 1,843.97 ₹4,89,269.78 Lowest | 2,080 ₹5,51,896.8 | 1,856 ₹4,92,461.76 |
| 1.09 | OD422669/2025-2026:Providing and Laying vitrified wall tiles in different sizes ( thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 ( 1 cement: 4 coarse sand), including grouting the joints of wall tiles having joints of 3mm width using epoxy grout mix0.70 kg of organic filter of desired shade (10 kg of hardner and 0.20 kg of resin per kg) including filling/grouting and finishing complete as per direction of Engineer- in- charge size of tile 600x 1200 mm | 955.08 | sqm | 1,743.31 ₹16,65,000.51 | 1,966 ₹18,77,687.28 | 1,522 ₹14,53,631.76 Lowest |
Tender Value
₹1.0 Cr
EMD Value
₹50,000
Closing Date
20 Aug 2026, 5:00 pmClosed
Regional Engineer, Kochi Housing Unit
Office of Regional Engineer 5th Floor Revenue Tower, Ernakulam 682011
Civil works Renovation of Common Toilets, Maintenance work at Yard, roofing sheet maintenance, waterproofing, sump and overhead tank cleaning etc Electrical work Wiring and accessories, Panel Boards, CCTV, DG hauling, acoustic Enclosure etc
2026_KSHB_862988_2
02_RE_KSHB_KHU_2026_27
Open Tender
Civil Works - Others
Item Rate
180 days
Kattapana
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,900
Yes
₹50,000
Yes
1 Sept 2026
11 Aug 2026
22 Aug 2026
11 Aug 2026
20 Aug 2026
11 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Renovation of Common Toilets | |||||
| 1.01 | 14.82:Dismantling W.C. Pan of all sizes including disposal of dismantled materials i/c malba all complete as per directions of Engineer-in-Charge | - | no | - | - |
| 1.02 | 15.23.1:Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.For thickness of tiles 10 mm to 25 mm | 0.6 | sqm | - | - |
| 1.03 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | - | cum | - | - |
| 1.04 | OD287159/2025-2026:Removal of soil/sand filled in the sunken portion of toilets up to floor level VII and disposal of unserviceable
material within 250 meters lead as per direction of Engineer in Charge | 0.8 | cum | - | - |
| 1.05 | 22.5:Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/sqm. This layer will be allowed to air cure for 4 hours. b) Second layer of slurry of cement @ 0.242 kg /sqm mixed with water proofing cement compound @ 0.126 kg/ sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry. | - | sqm | - | - |
| 1.06 | OD17337/2026-2027:Filling with broken hurudees tile obtained from roof top for filling including consolidating each deposited layer by ramming in all floors as per direction of site Engineer-in charge.
Ref item No. 2.27 | 0.8 | cum | - | - |
| 1.07 | 4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - |
| 1.08 | OD290429/2025-2026:Providing and laying vitrified anti skid Mat finish floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS : 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4(1 cement : 4 coarse sand), including grouting the joint of floor tiles having joints of 3 mm width, using epoxy grout mix 0.70 kg of organic coated filler of desired shade(0.10 kg of hardner and 0.20 kg of resin per kg)including filling/grouting and finishing complete as per direction of Engineer-In-Charge.Size of Tile 600 x 600 mm. | 1 | sqm | - | - |
| 1.09 | OD422669/2025-2026:Providing and Laying vitrified wall tiles in different sizes ( thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 ( 1 cement: 4 coarse sand), including grouting the joints of wall tiles having joints of 3mm width using epoxy grout mix0.70 kg of organic filter of desired shade (10 kg of hardner and 0.20 kg of resin per kg) including filling/grouting and finishing complete as per direction of Engineer- in- charge size of tile 600x 1200 mm | - | sqm | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
BOQ_1463755.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .