The Executive Engineer, PMD,PHE.Dte
Office of the Executive Engineer Purulia Mechanical Division,PHE.Dte Ranchi Road,Purulia.
Operation, maintenance and guarding of all pumping machinery at intake and WTP site, 800kva substation, gaseous chlorination system at 2.4 mgd water treatment plant at Lakshmanpur, under Purulia Mechanical Division. P.H.E. Dte.
2026_PHED_1032570_1
10 /EE/PMD/PHED OF 2026-2027
Open Tender
MECHANICAL
Item Rate
365 days
Purulia
Please refer Tender documents.
6 documents required · 6 mandatory
₹1.6 L
Yes
17 Jul 2026
17 Jul 2026
12 Aug 2026
17 Jul 2026
10 Aug 2026
17 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Labour charges with Bonus(8.33%) for operation & upkeepment of 3(three) no 55KW capacity VT Pump Motor set at intake, 3(three) nos 160KW capacity Centrifugal Pump Motor set at CWPH, 2(two) nos 7.5 KW capacity VFD driven pump motor set for ESR, 2(two) nos. 3.7KW capacity VT recirculation pump motor set, 2(two) nos 3.7 KW capacity chlorination pump motor set, 1(one) no 3.7KW capacity fire fighting pump motor set, 1(one) no 1.75KW capacity De-sludgeing pump motor set, 1(one) no Sump Pump Set, 2(two) no 18.5KW capacity VFD Driven Pump Motor set, 3(three)no 15KW capacity Air Blower set at filter house, 2(two) nos 3.7KW capacity Air Blower set at chemical house, 2(two) no.1.5HP capacity flash mixture, 2(two) nos 1.5HP capacity End Carriage Drive, 4(four) no 1H.P. capacity floculator, 8(eight) no 1HP Capacity Agitator, 1(one) no 5H.P. exhaust for chlorinator room, 1(now)5HP capacity centrifugal pump set for fountain, 1(one) no 500KVA DG set, Chlorination system, 1(one)No 800KVA substation with 11KV/415V 800 KVA transformer, 11KV/ 11KV VCB panel, AVR, HT panel, LT. Panel, EOT crane, Electromechanical chemical dosing system, and other mechanical and electrical installation within WTP area, sweeping of individual treatment units and administrative building with switching On/Off of outdoor & indoor lighting etc for 16hr running of 160KW pumps and 22 hours running of remaining units as per direction of EIC Engaging -12nos | |||||
| 2Periodical inspection, twice in a Month by Electrical Supervisor having valid supervisors certificate of competency from Directorate of Electricity (Licensing Board), Govt. of W.B. Each visit should be recorded in the Log Book (with Date & Time) to be supplied by the agency and kept in the Pump House & Sub-Station Building. The Supervisor requires to have thorough / in depth inspection of all the Electrical appliances to ascertain the healthy/fault free operational condition of each equipment i.e. pumps, motors, valves, flow meters, pressure gauges, lightings, waistings arrangements, exhaust fans, HT & LT panel boards, cables, capacitors, transformers, battery & battery chargers along with in house lighting system. All other necessary requirement to execute the maintenance work including other necessary materials to be supplied as and when required by the agency. | |||||
| 3Calibration of all meters viz. Ammeter Voltmeter, Kilowatt meter etc. Test of all relays, Transformer Oil (Dielectric test) by agency and approved by Directorate of Electricity or any other Power Generating unit and submission of test report to Department as per direction of EIC. | |||||
| 4Cleaning of contacts by CRC 226 spray in both the HT< panel Board cleaning of all Terminal Sockets, Coils once in a month in present of Electrician and to be recorded in the Log Book with date as per direction of EIC. | |||||
| 5Checking of healthy condition of all Feeders by Electrician having ITI (Electrician) certificate and findings to be recorded in the Log Book as per direction of EIC. | |||||
| 6Day to day maintenance and upkeeping including replacement of HRC fuses, terminal blocks, lugs, ferrules, add on contacts, auxiliary contactors, indication lamps, gland packing, rubber bush but excluding major items like MCCB, MPCB, MCB, SFU, Power contactor, Overload Relay, SMPS etc of 3(three) no 55KW capacity VT Pump Motor set at intake, 3(three) no 160KW capacity Centrifugal Pump Motor set at CWPH, 2(two)No. 7.5 KW capacity VFD driven Pump Motor set for ESR, 2(two) No. 3.7KW capacity VT Re-circulating Pump Motor set, 2(two) no 3.7 KW capacity Chlorinating Pump motor set, 1(one) 3.7KW capacity Fire fighting Pump Motor set, 1(one) 1.75KW capacity De-sludgeing Pump Motor set, 1(one) no Sump Pump set, 2(two) no 18.5KW Capacity VFD Driven Pump Motor Set, 3(three) No 15KW capacity Air Blower set at filter house, 2(two) No. 3.7KW capacity Air Blower set at Chemical House, 2(two) No.1.5H.P. capacity Flash Mixer, 2(two) No.1.5H.P. Capacity End Carriage Drive, 4(four) No.1H.P. Capacity Floculator, 8(eight) no 1H.P. capacity Agitator, 1(one) no. 5H.P. exhaust for chlorinator room, 1(one) no. 5H.P. capacity centrifugal pump set for fountain, 1(one) no 500KVA DG set, Chlorination system, 1 No.800KVA Substation with 11KV/415V 800KVA transformer, 11KV/11KV VCB Panel, AVR , HT Panel, LT Panel, Indoor ,outdoor lighting system at WTP , Intake , I.B. & all Annex building and all street light within WTP , I.B. & Annex compounding area , Street light of Intake road and other road side street light related to Raghunathpur W.S. Project ,EOT Crane, Chemical Dosing system, actuator valves and other electrical installation ancillaries by engaging an Electrician and Mechanic as and when required engaged by the agency having ITI Certificate in Electrical Trade as per direction of EIC. (a) Intake | |||||
| 6.01 | (b) WTP | - | day | - | - |
| 7Beautification of existing Garden and the vacant place in side the compound by engaging 2nos mali and required no. labour including supplying of necessary seasonal flower plants, decorative plants and other fruit plants (if suggested by the Deptt.) Supplying necessary fertilizer, bio-chemical, manure, pesticide, Insecticides ,petrol etc. as and when necessary including regular curing, watering, nursing, uprooting, seasonal plants, propagation by cutting, turfing, pruning plantation of sapling in side the WTP complex as per direction of EIC. | |||||
| 8Inspection and calibration, cleaning for filter, washing of Flow meter in rising and distribution mains, Ultrasonic meter in parshall flume, raw water inlet line by authorised representative once in as per direction of EIC. The rate is inclusive of service charges of authorised experts, wages of mechanic and labors, hiring charges of vehicles tools and tackles and all type of incidental charges as may be required to complete the job in all respect. | |||||
| 9Recording of reading in Log Book of Bulk water meter installed in different places in rising mains and distribution mains by deploying appropriate personnel once in a month within the 2nd day of very month as per direction of EIC. | |||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.99 MB
Tendernotice_2.pdf
PDF • 0.53 MB
Tendernotice_3.pdf
PDF • 0.28 MB
BOQ_2535802.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].