| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.3 LAccepted-AOC | ₹6.3 L | L1 | Accepted-AOC L1 party |
| 2 | L2₹7.2 LRejected-AOC | ₹7.2 L | L2 | Rejected-AOC L2 party |
| 3 | L3₹8.1 LRejected-AOC ERNAKULAM KERALA 682301 INDIA | ERNAKULAM | KERALA | 682301 | ₹8.1 L | L3 | Rejected-AOC L3 party |
| Sl No | Description | Qty | Unit | VIJAYA ELE TECHS PRIVATE LTD. L2 | IDEAL DATACOM NETWORK AND ELECTRICAL SOLUTIONS PVT LTD L3 | GERESH ELECTRICALS PVT. LTD L1 |
|---|---|---|---|---|---|---|
| 1.01 | Erection, testing & commissioning of APFC panel at substation 3 as per the scope of work. Installation including transportation of APFC panel from C-Stores (Approx.: 250 mtrs), leading, mounting, levelling and assembly of APFC panel of dimension 2800 (L) X 800 (W) X 2000 (H) mm in substation 3, consisting of incomers ACB and outgoing MCCBs as per the GA details attached, including minor civil work as per the scope of work. Existing cables shall be terminated in the newly installed panels using the existing cable glands. However cables sockets (for 10 x 3.5 x 300 Sq.mm cable shall be supplied by the contractor) Panel shall be double earthed as per standards from the nearest earth grid. The APFC panel , required GI strips for earthling etc. shall be supplied by KMML. Necessary transportation facilities and material handling for positioning of APFC panel shall be arranged by the contractor. | 2 | Nos. | 80,000 ₹94,400 | 1,50,000 ₹1.8 L | 80,000 ₹94,400 |
| 2.01 | Dismantling the existing capacitor panels in PCC 1 & 3 of dimension 1070 x 950 x2230 mm and 3060 x 950 x 2250 mm respectively, which includes disconnection of existing AYFY power cables of 3.5x300sq. mm (14 nos) / 5/9 x 2.5 sq.mm YWY control cables(4 nos.). The cables after disconnection shall be properly tagged and the existing glands to be reused. The dismantled panels shall be transported to the respective substations after required civil works which shall include wall/door dismantling and creating openings in walls to facilitate smooth movement of panel as per scope of work. The transporting of dismantled panel to the substations shall be done with extreme care to prevent any damage to the capacitors/reactors mounted in panels. The movement of panels inside MCC room shall be such that it should not damage the dielectric flooring. Any damage to dielectric flooring shall be repaired at the cost and risk of the contractor. The cement and brick required for reinstating the wall shall be issued to contractor as free issue item from KMML.. | 4 | Nos. | 1,40,000 ₹1.7 L | 1,60,000 ₹1.9 L | 1,20,000 ₹1.4 L |
| 3.01 | Erection, testing and commissioning of dismantled APFC panels to the substations 1 and 5. Installation including leading, mounting, levelling and assembly of dismantled (as per 1.02) APFC panel in substation 1 & 5 including minor civil work as per the scope of work. The panels shall be erected on structural foundations, which is at 600 mm above the Finished Ground Level. Existing cables shall be terminated in the installed panels using the existing cable glands. However cables sockets (for 6 x 3.5 x 300 Sq.mm , 2 x 3.5 x 400 Sq.mm cable shall be supplied by the contractor) Panel shall be double earthed as per standards from the nearest earth grid. The APFC panel , required GI strips for earthling etc. shall be supplied by KMML. Necessary transportation facilities and material handling for positioning of APFC panel shall be arranged by the contractor. | 4 | Nos. | 1,60,000 ₹1.9 L | 1,60,000 ₹1.9 L | 1,20,000 ₹1.4 L |
| 4.01 | Laying, dressing and clamping of following cables through existing trays / structures / racks / columns etc. .Cable shall be supplied by KMML. All other materials required are under the scope of contractor. 3.5 x 300 sq.mm AYFY/XLPE power cable | 550 | Mtr | 96,250 ₹1.1 L | 77,000 ₹90,860 | 66,000 ₹77,880 |
| 4.02 | 4/5/7 sq. mm YWY control cable | 100 | Mtr | 8,000 ₹9,440 | 4,000 ₹4,720 | 5,000 ₹5,900 |
| 5.01 | Glanding and termination at panel side of AYFY cable using DC glands/ lugs including supply of cable glands, lugs, aluminium crimping sockets, nuts bolts etc. required for this work. Gland earthling as per standards shall be done by the contractor. 3.5 x 300 sq.mm AYFY/XLPE power cable | 24 | Nos. | 84,000 ₹99,120 | 96,000 ₹1.1 L | 1,20,000 ₹1.4 L |
| 5.02 | 4/5/7 sq. mm YWY control cable | 4 | Nos. | 5,000 ₹5,900 | 1,000 ₹1,180 | 10,000 ₹11,800 |
| 6.01 | Erection of new 600/300/200 mm GI ladder type cable tray on newly fabricated supports and replacing of existing corroded GI ladder type cable tray 600/300/200mm without damaging/deforming the cable on it with new one along the existing cable tray structure. Tray shall be jointed with GI side coupler with Bolts & Nuts. The cables shall be neatly dressed and clamped as per standards. Required qty of GI cable trays and coupling plates shall be supplied by KMML from the store. All other materials shall be supplied by contractor. | 30 | Mtrs | 9,000 ₹10,620 | 7,500 ₹8,850 | 4,500 ₹5,310 |
| 7.01 | Fabrication and erection of the supports for cable trays, panel foundations, earthling etc. without disturbing the existing cables/cable trays. Newly fabricated supports shall be painted with one coat of epoxy primer and two coats of epoxy grey paint. MS items shall be supplied by KMML. required paint ( make : Asian/Nerolac/Shalimar) shall be supplied by contractor | 1 | MT | 75,000 ₹88,500 | 80,000 ₹94,400 | 50,000 ₹59,000 |
| 8.01 | Re-routing and laying of existing cables of following sizes through cable trays/structures/trenches etc. Removal and rerouting shall be measured separately 3.5 x 300 sq.mm AYFY/XLPE power cable | 160 | Mtrs | 24,000 ₹28,320 | 19,200 ₹22,656 | 24,000 ₹28,320 |
Tender Value
₹10 L
EMD Value
₹25,000
Closing Date
29 Nov 2025, 12:00 pmClosed
JGM and HoU TP
TP Unit, Sankaramnagalam, Chavara, Kollam
Erection, Installation, Testing and Commissioning of APFC Panels at Substations of TP Unit
2025_KMML_814162_1
TP/MSDS/APFC/2025-26
Open Tender
Electrical Works
TP Unit, KMML
As per tender document
4 documents required · 4 mandatory
₹1,770
₹25,000
TP Unit KMML Kollam
9 Jan 2026
24 Oct 2025
1 Dec 2025
24 Oct 2025
29 Nov 2025
5 Nov 2025
24 Oct 2025 - 5 Nov 2025
5 Nov 2025
Erection, testing & commissioning of APFC panel at substation 3 as per the scope of work. Installation including transportation of APFC panel from C-Stores (Approx.: 250 mtrs), leading, mounting, levelling and assembly of APFC panel of dimension 2800 (L) X 800 (W) X 2000 (H) mm in substation 3, consisting of incomers ACB and outgoing MCCBs as per the GA details attached, including minor civil work as per the scope of work. Existing cables shall be terminated in the newly installed panels using the existing cable glands. However cables sockets (for 10 x 3.5 x 300 Sq.mm cable shall be supplied by the contractor) Panel shall be double earthed as per standards from the nearest earth grid. The APFC panel , required GI strips for earthling etc. shall be supplied by KMML. Necessary transportation facilities and material handling for positioning of APFC panel shall be arranged by the contractor.
Dismantling the existing capacitor panels in PCC 1 & 3 of dimension 1070 x 950 x2230 mm and 3060 x 950 x 2250 mm respectively, which includes disconnection of existing AYFY power cables of 3.5x300sq. mm (14 nos) / 5/9 x 2.5 sq.mm YWY control cables(4 nos.). The cables after disconnection shall be properly tagged and the existing glands to be reused. The dismantled panels shall be transported to the respective substations after required civil works which shall include wall/door dismantling and creating openings in walls to facilitate smooth movement of panel as per scope of work. The transporting of dismantled panel to the substations shall be done with extreme care to prevent any damage to the capacitors/reactors mounted in panels. The movement of panels inside MCC room shall be such that it should not damage the dielectric flooring. Any damage to dielectric flooring shall be repaired at the cost and risk of the contractor. The cement and brick required for reinstating the wall shall be issued to contractor as free issue item from KMML..
Erection, testing and commissioning of dismantled APFC panels to the substations 1 and 5. Installation including leading, mounting, levelling and assembly of dismantled (as per 1.02) APFC panel in substation 1 & 5 including minor civil work as per the scope of work. The panels shall be erected on structural foundations, which is at 600 mm above the Finished Ground Level. Existing cables shall be terminated in the installed panels using the existing cable glands. However cables sockets (for 6 x 3.5 x 300 Sq.mm , 2 x 3.5 x 400 Sq.mm cable shall be supplied by the contractor) Panel shall be double earthed as per standards from the nearest earth grid. The APFC panel , required GI strips for earthling etc. shall be supplied by KMML. Necessary transportation facilities and material handling for positioning of APFC panel shall be arranged by the contractor.
Laying, dressing and clamping of following cables through existing trays / structures / racks / columns etc. .Cable shall be supplied by KMML. All other materials required are under the scope of contractor. 3.5 x 300 sq.mm AYFY/XLPE power cable
4/5/7 sq. mm YWY control cable
Glanding and termination at panel side of AYFY cable using DC glands/ lugs including supply of cable glands, lugs, aluminium crimping sockets, nuts bolts etc. required for this work. Gland earthling as per standards shall be done by the contractor. 3.5 x 300 sq.mm AYFY/XLPE power cable
4/5/7 sq. mm YWY control cable
Erection of new 600/300/200 mm GI ladder type cable tray on newly fabricated supports and replacing of existing corroded GI ladder type cable tray 600/300/200mm without damaging/deforming the cable on it with new one along the existing cable tray structure. Tray shall be jointed with GI side coupler with Bolts & Nuts. The cables shall be neatly dressed and clamped as per standards. Required qty of GI cable trays and coupling plates shall be supplied by KMML from the store. All other materials shall be supplied by contractor.
Fabrication and erection of the supports for cable trays, panel foundations, earthling etc. without disturbing the existing cables/cable trays. Newly fabricated supports shall be painted with one coat of epoxy primer and two coats of epoxy grey paint. MS items shall be supplied by KMML. required paint ( make : Asian/Nerolac/Shalimar) shall be supplied by contractor
Re-routing and laying of existing cables of following sizes through cable trays/structures/trenches etc. Removal and rerouting shall be measured separately 3.5 x 300 sq.mm AYFY/XLPE power cable
31/2 x 400 sq.mm AYFY/XLPE cable
4/5/7 sq. mm YWY control cable
Preparation of electrical drawings and approval from electrical inspectorate for new installation including energisation sanction as per scope of work.
VIJAYA ELE TECHS PRIVATE LTD. (BID ID -2430951)
IDEAL DATACOM NETWORK AND ELECTRICAL SOLUTIONS PVT LTD (BID ID -2442752)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.11 MB
Tender_Document_Part1.pdf
Tender Documents • 0.34 MB
GA_APFC.pdf
Other Document • 3.14 MB
GCC_SR.pdf
Additional Documents • 0.07 MB
BOQ_1361730.xls
BOQ • 0.28 MB