| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹84.4 LAdmitted-Finance | -21.77% | ₹84.4 L | L1 | Admitted-Finance |
| 2 | L2₹85.4 L+₹96,073.35 (1.14%)Admitted-Finance | -20.88% | ₹85.4 L+₹96,073.35 (1.14%) | L2 | Admitted-Finance |
| 3 | L3₹86.9 L+₹2.5 L (2.93%)Admitted-Finance | -19.48% | ₹86.9 L+₹2.5 L (2.93%) | L3 | Admitted-Finance |
| 4 | L4₹88.3 L+₹3.8 L (4.55%)Admitted-Finance | -18.21% | ₹88.3 L+₹3.8 L (4.55%) | L4 | Admitted-Finance |
| 5 | L5₹88.5 L+₹4.0 L (4.79%)Admitted-Finance | -18.02% | ₹88.5 L+₹4.0 L (4.79%) | L5 | Admitted-Finance |
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
1 Jun 2026, 6:00 pmClosed
SE RSAMB CIRCLE KOTA
SE RSAMB CIRCLE KOTA
Construction of C.C. Pavement on Existing Various Internal road around the convered shed at sub yard Kawai Under KUMS Atru
2026_RSAMB_559986_2
NIT NO. 04/2026-27 SE RSAMB CIRCLE KOTA
Open Tender
Civil Works
Percentage
150 days
BARAN
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,000
RTGS/NEFT/Any other money Transfer System
₹2.2 L
Yes
8 Jun 2026
16 May 2026
3 Jun 2026
16 May 2026
1 Jun 2026
16 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per MoRTH Specification Clause 202 | - | - | - | - |
| - | By Mechanical Means (A) Bituminous Courses & Granular Courses | 1,412 | Per Cum | 100 | ₹1,41,200 |
| - | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400-12 & 400-13 and MoRTH Specification Clause 406. | - | - | - | - |
| - | By Mechanical Means with all lead | 471 | Per Cum | 1,147 | ₹5,40,237 |
| - | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. | 471 | Per Cum | 2,715 | ₹12,78,765 |
| - | Construction of un-reinforced , plain cement concrete pavement M30 (Grade), thickness as per design, over a prepared sub base, with 43/53 grade cement as per Clause 602.2.2 , coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a in fully automatic Batching Plant and transported to site in transit mixer for having continous agitated mixer, manufactured as per approved mix design including pumping of R.M.C. from transit mixer to site of laying , with all lead and lift including cost of admixtures in recommended portion as per IS 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in charge laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using Fixed Form Paver and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 including vaccum dewatering process with all required equipments (Dowel Bars will be paid seprately). | 1,431 | Per Cum | 6,000 | ₹85,86,000 |
| - | Providing and Fixing of Dowel Bars of Mild Steel confirming to IS : 432 of specified length and diameters as per MoRTH Specification IRC 15 & 58 including cutting, placing in position across transverse joint with proper spacing, providing with PVC sleeve complete as per drawing, technical specification and as per direction of the Engineer-in-charge. | 3,228 | Per Kg | 77 | ₹2,48,556 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.04 MB
Tendernotice_2.pdf
PDF • 0.14 MB
Tendernotice_3.pdf
PDF • 0.87 MB
BOQ_996855.xls
BOQ • 0.33 MB
2_Agreement.pdf
Tender Documents • 0.85 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .