EXECUTIVE ENGINEER ELECTRIC DIVISION SOPORE
EXECUTIVE ENGINEER ELECTRIC DIVISION SOPORE
R AND M of Distribution Substation (in ED Sopore) under UT Capex 2026-27
2026_PDD_315105_1
EMDS/25
Open Tender
Electrical Works
45 days
R AND M of Distribution Substation (in ED Sopore)
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
Yes
EXECUTIVE ENGINEER ELECTRIC DIVISION SOPORE
₹39,600
Yes
8 Jul 2026
8 Jul 2026
1 Aug 2026
8 Jul 2026
30 Jul 2026
9 Jul 2026
8 Jul 2026 - 9 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station (100kva sub station at Hospital Sopore) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,07,458 | ₹1,07,458 |
| 2 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 400kva sub station at Samad ) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,07,458 | ₹1,07,458 |
| 3 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 250kva sub station at Noorbagh Sopore) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,07,458 | ₹1,07,458 |
| 4 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station (250kva sub station at Samad ) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,07,458 | ₹1,07,458 |
| 5 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 250kva sub station at Wani Mohalla Sangrama ) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 88,171 | ₹88,171 |
| 6 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 400kva sub station at Kushal Colony) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,91,322 | ₹1,91,322 |
| 7 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station (250kva & 100kva sub station at Hatishah ) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 2,60,305 | ₹2,60,305 |
| 8 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 100kva sub station at Shalimar Colony Warpora) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 1,84,801 | ₹1,84,801 |
| 9 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 100kva sub station at Ashtan Mohalla Sagipora) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 2,08,475 | ₹2,08,475 |
| 10 | Supply, installation, testing and commissioning including carriage, loading & un-loading etc. of :
R&M of Distribution Sub-station ( 63kva sub station at Chopan Mohalla Dangerpora) under UT Capex 2026-27
(Complete Job)
(Detailed Estimate is in the SBD ) | 1 | Job | 2,02,506 | ₹2,02,506 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.48 MB
DrawingsCumSpecification.pdf
Additional Documents • 18.28 MB
BOQ_1021118.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid