EXECUTIVE ENGINEER BUILDING DIVISION MADHUBANI
EXECUTIVE ENGINEER
BUILDING DIVISION MADHUBANI
Superintending Engineer, BUILDING CIRCLE DARBHANGA
SE
Raising of perimeter wall (with fencing) of District Jail at Rampatti, Madhubani for the year-2026-27
134820
7/BCD/MADHUBANI/2026-27
Open Tender
CIVIL
Madhubani
• REGISTRATION WITH BCD BIHAR
GST REGISTRATION
PAN NO AND INCOME TAX RETURN
CHARACTER
ELECTRIC CERTIFICATE.
• Annual Financial Turnover for Last Three Financial years:- in Rupees (enter NUMERS only)
2023-24,
2024-25,
2025-26
• Maximum Contract amount for one work of similar nature completed during years:- in Rupees (enter NUMERS only)
2021-22,
2022-23,
2023-24,
2024-25
2025-26
• Enter Number of Engineers employed to prove Bidder's Engineering Establishment Available for This Project Type of Technical Staff
1. Civil Engg Degree holder
2. Civil Engg Diploma holder
3. Other Technical Staff / Supervisory Staff
• Name of Plants and Equipment owned by bidder in Working Condition Which will be available at This Work Site Type of Machine
1 Automatic batching plant+accessories
1 Mixer Machine With Weighing Facility
2 Steel shuttering Minimum 2000 Sft
3 Water Tanker
4 Vibrator (Needle and Surface)
• Bank credit and/or Self Declaration submitted / uploaded Particulars
1.Certificate of Bank for credit facility 10 %
2 Self declaration for investing 25 %
• Necessary undertakings submitted / uploaded UNDERTAKINGS
1. Not abandoned any project
2. Never been in Litigation
3. No relative or any person Working in Department
4. Not Debarred / Blacklisted from any Govt. , PSU Dept.
• Bidding Capacity in Rupees Amount of Existing commitments and ongoing works in Rupees
A= Maximum ATO in Rupees
BID CAPACITY
• Work Programme
CIVIL
PERCENTAGE
L1
1
11 documents required · 11 mandatory
₹10,000
Processing Fee: 3540
₹1.8 L
SE OFFICE DARBHANGA CIRCLE 02-07-2026 03:00 pm
25 Jun 2026
25 Jun 2026
21 Jul 2026
25 Jun 2026
20 Jul 2026
25 Jun 2026
2 Jul 2026
BILL OF QUANTITY
BUILDING DIVISION MADHUBANI
NAME OF WORK :- Raising of perimeter wall (with fencing) of District Jail at Rampatti, Madhubani for the year-2026-27
BOQ AMOUN :- 8789431.00
Earnest Money:- 175800.00
S.NO. S.O.R. CODE ITEM OF WORKS QTY. UNIT RATE AMOUNT
1 15.3 DEMOLISHING OF RCC.
Demolishing R.C.C. work including stacking of steel bars and disposal of unserviceable material withing 50 metres lead:
2 15.7.4 Demolishing brick work including stacking of serviceable material and disposal of unserviceable material within 50 meters lead:In cement mortar
3 5.2 Providing RCC (1:1.5:3) Work in Column
Reinforced cement concrete work in wall (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts, etc. upt floor five level excluding cost of centring, shuttering, finishin and reinforcement.
5.2.2 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20mm nominal size)
4 5.3 Providing RCC (1:1.5:3) Work in Band
Reinforced cement concrete work in band, floor beam, roof slab ect work.
5 5.33 Add or deduct for providing richer or leaner mixes respectively at all floor levels.
5.33.B.4 Providing M-15grade R.C.C instead of M-20 grade R.C.C.
6 5.9 SHUTTERING WORK
Centering and shuttering including strutting, propping etc. and removal of form for.
5.9.3 Suspended floors, roots, landings, balcnies and access platform.
5.9.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers.
5.9.6 Columns,Pillars, Piers, Abutments, Posts and Struts
7 5.22 REINFORCEMENT STEEL WORK
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.
5.22.7A Thermo-Mechanically Treated bars TMTC-500-8mm dia. 4238.85 Kg. 94.50 400,571
5.22.7B Thermo-Mechanically Treated bars TMTC-500-10mm dia. 2119.42 Kg. 92.60 196,258
5.22.7C Thermo-Mechanically Treated bars TMTC-500-12mm dia. 2119.42 Kg. 90.80 192,443
5.22.7D Thermo-Mechanically Treated bars TMTC-500-16mm dia6 2119.42 Kg. 91.70 194,351
8 6.1.14A BRICK WORK
Brick work with bricks of class designation 100A in foundations and plinth in :
9 6.3A Extra for Brick work in superstructure above plinth level upto floor V cum 295.20 Cum 842.20 248,617
10 13.12.4 EXTERNAL PLASTER
Providing and laying 15 mm thick cement plaster on wall of mix 1:6 (1 cement :6 coarse sand)
11 13.56 POINTING
Pointing on brick work with cement mortar 1:3(1 cement:3 coarse sand):
13.56.1 Flush pointing
12 10.33.6 Drilling 6mm Dia. In M.S. angle iron for fixing of staples etc. as per building specification and direction of E/l. 1818.000 Each. 9.00 16,362
13 10.33.7 Labour for cutting of M.S. angle iron post to required length, one end splitted as fish tailed in a length of 150mm complete as per building specification and direction of E/l. 303.000 Each. 28.20 8,545
14 10.43 concertina coil fencing
Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 metre openable length ( total length 90 m), having 50 nos rounds per 6 metre length, upto 3 m height of wall with existing angle iron ‘Y’ shaped placed 2.4 m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal, including necessary bolts or G.I. barbed wire tied to angle iron, all complete as per direction of Engineer-in-charge, with reinforced barbed tape(R.B.T.) / Spring core (2.5 mm thick) wire of high tensile strength of 165 kg/ sq mm with tape (0.52 mm thick) and weight 43.478 gm/ metre (cost of M.S. angle, C.C. blocks shall be paid separately)
15 13.78 APPLYING PRIMER
Applying one coat of cement primer of approved brand and manufacture on wall surface:
13.78.1 Cement prime
16 13.79 WATER PROOF PAINT
Finishing walls with water proofing cement paint of approved brand and manufacture and of required shade to give an even shade
13.79.1 New work (three or more coats)
13.79.2 OLD work (one or more coats)
17 13.82 READY MIXED PAINT
Painting with ready mixed paint of approved brand and manufacture in all shades to give an even shade:
13.82.1 New steel work (two or more coats)
18 13.82.3 Old Steel work (one more coats)
19 0L01 Supplying Labour for cleaning debries 100.00 Each. 355.42 35,542
20 10.1 STRUCURAL STEEL WORK
Structural steel work in singal section fixed without connecting plate including cutting.hoisting,fixing in position and applying a priming coat of approved steel primer all complete.
20 CARRIAGE OF MATERIALS
Coarse Sand @ 3867.49/Cum 232.82 Cum. 3867.49 900,410
Aggregate @ 2205.95/Cum 87.86 Cum. 2205.95 193,814
21 EXTRA COST OF MATERIALS
Cement @ 05.50/Bag 1701 Bag 5.50 9,356
22 1002 Mild steel round bar 12mm dia and below
Net Total- 8,789,431
Executive Engineer
Building Division,
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
LETTERFOREVALUATION1094.pdf
NIT • 3.92 MB
NIT 07.pdf
NIT • 3.59 MB
perimeter wall rampatti jail boq correct.xlsx
NIT • 0.45 MB
Download all tender documents and submit your bid