| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.5 CrAccepted-Finance SEC 1 A 73 14 01 SULABH AVASH GOMTI NAGAR VISTRA LUCKNOW UTTAR PRADESH | LUCKNOW | UTTAR PRADESH | 226001 | ₹1.5 Cr | L1 | Accepted-Finance L1 Lower Rate Quoted |
| 2 | L2₹1.6 CrRejected-Finance 26 2 MUIR ROAD BELI PRAYAGRAJ | PRAYAGRAJ | UTTAR PRADESH | 211001 | ₹1.6 Cr | L2 | Rejected-Finance L2 Higher Rate Quoted |
| 3 | L3₹1.8 CrRejected-Finance 198 MUNSHIGANJ SHYAM NATH ROAD SITAPUR | SITAPUR | UTTAR PRADESH | 261001 | ₹1.8 Cr | L3 | Rejected-Finance L3 Higher Rate Quoted |
Tender Value
₹2.1 Cr
EMD Value
₹12.5 L
Closing Date
21 May 2026, 12:30 pmClosed
S.E., Azamgarh Circle, P.W.D., Azamgarh
S.E., Azamgarh Circle, P.W.D., Azamgarh
Construction of 04 Category-03 residential units in Sagri Tehsil, Azamgarh District
2026_CEUAZ_1148306_1
1512/SE Tender/Aazamgarh Circle/2026 Date.27-04-2026
Open Tender
Civil Works - Buildings
365 days
Azamgarh
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,590
₹12.5 L
26 May 2026
14 May 2026
21 May 2026
14 May 2026
21 May 2026
14 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation of Foundation- Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. | 1 | CUM | 172 | ₹171.83 |
| 2 | Sand Filling- Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 1 | CUM | 1,402 | ₹1,400.6 |
| 3 | PCC Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 1 | CUM | 4,495 | ₹4,490.51 |
| 4 | Providing and injecting chemical emulsion for preconstructional antitermite treatment and creating a chemical barrier under and around the column pits wall trenches basement excavation top surface if plinth filling junction of wall and floor, along the the external perimeter of binding expansion joints, surrounding of pipes and conduits etc, complete (plinth area of the building at ground floor only shall be measured as per I.S.6313(PartII 1981)Alderine emulsifiable concentrate or any other approved material such as Heptrachlor or Chlordane will be used. The rate of application of chemical emulsion shall be as follows : (1)Treatment for masonary & foundation 5 liters per sqm. (2) Back fill in immediate contact with foundation 7.5 liters/sqm (3) Treatment of top surface of plinth filling 5 liters/sqm (4) Treatment of soil along external perimeter of building 7.5 liters/sqm. (5) Treatment of soil under apron along external perimter 5 liters/sqm. | - | SQM | 205 | - |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Ground Floor UP TO PLINTH | 1 | CUM | 5,970 | ₹5,964.03 |
| 6 | ABOVE PLINTH | 1 | CUM | 7,593 | ₹7,585.41 |
| 7 | First floor | - | CUM | 7,593 | - |
| 8 | Mumty Floor | - | CUM | 7,593 | - |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Ground Floor | 1 | CUM | 7,593 | ₹7,585.41 |
| 10 | First floor | 1 | CUM | 7,593 | ₹7,585.41 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.55 MB
BOQ_2149337.xls
BOQ • 0.66 MB
T2.pdf
Tender Documents • 1.04 MB
Download all tender documents and submit your bid