Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.5 LAccepted-AOC CHENNAI CIRCLE CHENNAI 6 | L1 | Accepted-AOC Lowest Amount Quoted BY M/s. KVR and CO and called for negotiation amount Rs. 1949573.57 | |
| 2 | L2₹20.5 L+₹94,842.50 (4.85%)Rejected-Finance 3 24 SOUTH STREET ORAKKADU VILLAGE ORAKKADU POST ORAKKADU TAMIL NADU 607103 | ORAKKADU | CUDDALORE | TAMIL NADU | 607103 | L2 | Rejected-Finance 5.18 percentage above ER not accepted |
Tender Value
₹19.8 L
EMD Value
₹20,000
Closing Date
30 Jun 2023, 3:00 pmClosed
Additional Collector (Dev)
DRDA,Tiruvallur
Strengthening of BT Road in Koduveli to Karani Road at Koduveli Panchayat Km0/0 0/450 in Ellapuram Block
2023_RDTN_328531_1
755/2023/A7
Open Tender
Civil Works
Item Rate
180 days
Ellapuram
As per Documents
5 documents required · 5 mandatory
₹0
₹20,000
Yes
DRDA,Tiruvallur
28 Jul 2023
16 Jun 2023
30 Jun 2023
16 Jun 2023
30 Jun 2023
16 Jun 2023
20 Jun 2023
Amount
1.STRENTHENING OF BT ROAD IN KODUVELI TO KARANI ROAD @ KODUVELI PANCHAYAT
Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complete.
Clearing the Scrub jungle removing from away site including incidential charges and all labour charges with burning and ashes including all labour charges etc,..complete.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete
Applying PRIMECOAT over WBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete.
Applying TACK COAT over Primed WBM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,.
Provision for Road Marking with hot applied Thermoplastic Compound wuith Reflectorising Glass Beds on Bitiminous surface etc,..
Provision for HM Board charges etc,..
Provision for Sign Board
Provision for Name Board Citizen Information Board Charges with Painting
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
M/s. PCN CONSTRUCTIONS
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .