Loading…
Loading…
Tender Value
₹48.6 L
EMD Value
₹48,627
Closing Date
30 Mar 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
The Chief Officer, Dahod Nagarpalika, Dahod
BID DOCUMENTS FOR CONSTRUCTION WORK OF PROPOSED COMPOUND WALL AT GODHARA ROAD KABRASTHAN (PHASE-01) OF DAHOD NAGARPALIKA UNDER: 15 TH FINANCE SCHEME (SECOND INSTALLMENT) GRANT YEAR: 2020-21.
288874
15th FCS/2020-21
Open
Civil Works - Buildings
Dahod
14 documents required · 14 mandatory
₹1,770
The Chief Officer, Dahod Municipality, Dahod
₹48,627
23 Mar 2026
23 Mar 2026
23 Mar 2026
30 Mar 2026
23 Mar 2026
Item Qty. Description Total Unit Amount
1 559.60 Excavation for foundation upto 1.5 m depth including sorting out and
Cu.m. stacking of useful materials and disposing off the excavated stuff
upto 50 Meter lead.(A) Loose or soft soil
2 101.70 Excavation for foundation for depth from 1.5 m to 3.0 m including
Cu.m. sorting out and stacking of useful materials and disposing off the
excavated stuff upto 50 Meter lead. (D) Soft rock not requiring
3 432.60 Filling available excavated earth (excluding rock) in trenches. plinth,
Cu.m. sides of foundations etc. in layers not exceeding 20 cm. in depth
consolidating each disposited layer by ramming and watering.
4 62.50 Providing and laying cement concrete (1:4:8) (1 Cement, 4 Coarse
Cu.m. sand, 8 Crushed stone agreegate 40 mm nominal) and curing
complete excluding cost of formwork in foundation and plinth.
5 116.50 Providing and Laying controlled cement concrete M-200 and curing
Cu.m. complete, including the cost of formwork but excluding the cost of
reinforcement for reinforced concrete work in Column footings.
6 19.00 Providing and laying controlled cement concrete M-200 and curing
Cu.m. complete including the cost of formwork But Excluding the cost of
reinforcement for reinforced concrete work in Column upto Plinth
Level having any cross section area.
7 26.60 Providing and Laying controlled cement concrete M-200 and curing
Cu.m. complete, including the cost of formwork but excluding the cost of
reinforcement for reinforced concrete work in Columns having any
cross section area upto floor two level.
8 31.50 Providing and laying controlled cement concrete M-200 and curing
Cu.m. complete including the cost of formwork but Excluding the cost of
reinforcement for reinforced concrete work in Ground Beam having
any cross section area.
SBD SECTION-7 BILL OF QUANTITIES-147
9 13.50 Providing and laying controlled cement concrete M-200 and curing
Cu.m. complete including the cost of formwork and excluding the cost of
reinforcement of reinforced concrete work in -- do -- for Coping
14130.00 Providing TMT Bar FE 500D reinforcement for R.C.C. work including
Kgs. bending, binding and placing in position complete upto floor two level
11 126.00 Brick work using common burnt building bricks having crushing
Cu.m. strngth not less than 35 Kg./cm2 in super structure for Ground Floor
in C.M. (1:6) (1 Cement, 6 fine sand) racking out joints curring etc.
complete directed by Engineer-in-charge.
12 1415.00 20mm thick sand faced cement plaster on walls upto height
Sqm. metres above ground level consisting of 12mm thick backing coat of
C.M. 1:3 (1-cement : 3-sand) and 8mm thick finishing coat of C.M.
1:1 (1-cement : 1-sand) etc. complete.
13 1414.54 Finishing wall with weather proof exterior emulsion paint on wall
Sqm. surface (two coats) to give an required shape even shade after
thoroughly brushing the surface to remove all dirt, and remains of
loose powdered materials.etc complete
14 11.50 Providing and laying and fixing 50 mm thick expansion joint by hydro
Sqm. cell semi rigid UV resistance with high performance laminated closed
cell polythene foam joint filler in sheet foam as directed, etc.
Providing and fixing M.S. grills of required pattern to wooden frames
of windows etc. with M.S. flats at required spacings and frame
alround, square or round bars with round headed bolts and nuts or by
screws (A) Plain Grill.
Kgs. FOR MAIN GATE
Painting two coats (excluding priming coat) on new steel and other
metal surface with enamel paint, brushing,interior to give an even
16 25.20 shade including cleaning the surface an even shade including 138.78 Sqm.
cleanicn the surface of all dirt, dust and other foreign matter.
17 7.43 Steel work, riveted in built up sections framed work including cutting,
Qtl. hoisting, fixing in position and applying a priming coat of red lead
paint. (A) In beams and joists, channels angles Tees, flats, with
connecting plates or angle cleats as in main and cross beams. Hip
and jack rafters, purlins conneted to common rafters and the like.
SBD SECTION-7 BILL OF QUANTITIES-148
16 1.34 16G Make Tata
Qtl. Double twisted barbed wire, gauge 16, barb spacing 4". four
horizontal lines and two diagonals of galvanised steel barbed wire
weighting 9.38 K.G. per 100 metre strained and fixed to posts with
G.I. staples, including fixing the posts in coping of compound wall.
Total Amount, Rs.
Total Amount, Rs.
Add :- 18% of GST, Rs.
Add :- 1% of Qaulity Controll Rs.
Add :- 2% of Contingency Charges Rs.
I / We am/are willing to carry out the work at _____________ % above / below (percent should be written in figure and
in words) of the estimated rates mentioned above. Amount of my/our tender works out as under.
( In words ) _________________________ percentage above / below the estimated rate.
Estimated Amount put to tender Rs.
Deduct _______ % below Rs. Rs.
Estimated Amount put to tender Rs.
Add _______ % above Rs. Rs.
Total Amount Rs.
Total Amount Rs.
Note :1 All work shall be carried out as per Public Works Department Hand Book and other specifications of
Division or as directed.
Note :2 Rates quoted include clearance of site (prior commencement of work and its close) in all respects and hold
good for work under.
Note :3 I/ We have read the conditions mentioned in this tender and agree to abide by the same.
Note :4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-
10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items
where there is a change as per actual mix design the cost of difference of cement consumption have been
deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Signature of Contractor President Chief Officer
Dahod Nagarpalika Dahod Nagarpalika
SBD SECTION-7 BILL OF QUANTITIES-149
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD.pdf
Notes.pdf
BOQ.pdf
OTHER IMPORTANT-1.pdf
OTHER IMPORTANT-2.pdf
OTHER IMPORTANT-3.pdf
Download all tender documents and submit your bid